PMP Practice Exam Question Bank - Feb 2023
PMP Practice Exam Question Bank - Feb 2023
840664 I.6 A project manager joins a project team, replacing a manager who C Forming Storming Norming Performing During the norming phase, team members begin to work
left. During initial meetings, the project manager realized that the together and adjust their work habits and behaviors to
team members have differing opinions about how to address support the team. The team members learn to trust each
technical decisions. Team members did NOT respect each other's other.
ideas, and the environment was becoming counterproductive.
However, now with the new manager’s leadership, the team has
begun to communicate more effectively and develop some
processes and procedures for working together.
2
840679 I.6 A project is comprised of three highly dependent parts, each being A Identify potential conflicts and then Decide which team’s work should be Document conflicts as they occur and Continue to let all three teams work Consistent communication is important for ensuring a
completed by its own project team. The team leader, worried that arrange for a weekly joint meeting prioritized, then delay the work from take action to remedy any problems simultaneously, recognizing that lower probability of issues and successfully addressing
conflicts might arise when the outputs from the three teams are with the members of the three the other two teams to ensure there that arise. conflicts can be addressed at the existing risks.
combined, asks for advice. teams to review each other’s work. are NO conflicts. testing phase.
What guidance should the project manager offer to the team lead?
11
X00003 I.6 A project manager has assembled a project team. During initial C Storming Norming Forming Performing The Forming phase is when the team members meet and
meetings, the project manager observes that team members are learn about the project and their formal roles and
getting to know each other, feeling excited and positive about the responsibilities. Team members tend to be solitary and
project, and have NOT been told the specific details of the project. independent in this phase.
17
840760 I.12 A project team is small, and the team members have known each B Review the current stakeholder Schedule a team meeting to discuss Hold a team morale-building event to Speak to the team members A team meeting is the best solution because it encourages
other for a long time. The team's project is in the execution stage. engagement plan to identify how to the current team charter and ground improve team culture. individually and ask them how they every team member to participate and results in a clear set
Recently, a team member told the new project manager that resolve this difficulty. rules, especially around would like to deal with the situation. of guidelines for the team.
another team member has been complaining about how the communication and teamwork
project is being managed. expectations.
33
840756 I.8 A cross-functional team on Project B reports a delay in developing B,C,D Ask the team leader to recommend Identify required skills and organize Make a list of required, specific skills Outsource the task to a skilled Identify the skill deficiency as a Developing the team and proactively strengthening
a prototype. The project manager believes that the cause is lack of a solution. the team based on the strength of for the project. expert. project risk. individual team members’ skills is an important part of
knowledge in a specific, required skill on the team. those skills. servant leadership. This means that the project manager
needs to know the required strengths and skill sets needed
In which three ways can the project manager prevent this situation for a project and recruit or be able to outsource the work
on future projects? (Choose THREE.) to a resource with that skill.
34
840765 I.8 A project manager notices that team member A seems more B Reassure team member A about Meet with team member A to Enroll team member A in targeted Reassign team member A to a more Meeting with team member A to find out if they are
unhappy after every team meeting. After looking into the their abilities by reminding them discuss where they can contribute, training to acquire the needed skills appropriate role in another project. correctly placed in a project role is the best response. The
situation, the project manager finds out that team member A is that they were chosen for a reason. based on their strengths. for their assigned role. individual may be right. As a servant leader, you can help
not making progress on a key activity. This has an impact on the them find the correct role. The other responses may be
critical path. Team member A also feels that they are NOT in the helpful, but they miss addressing the team member’s
correct role within the project team. concern.
35 What should the project manager do?
840768 I.8 A customer requests a change in the technical approach for a B Work with team members to Let the team decide on the Discuss the pros and cons of the In order to obtain sponsor buy-in, As this is a technical issue, the project manager should
product in development. The project manager learns about this immediately implement the new appropriate approach, giving them proposed approach with stakeholders, allow the team to benchmark the discuss the request with the team and empower them to
request during a recurring project review. approach. authority to implement and validate then select the approach that is best approach. assess and select the best options to solve the customer's
their decision in talks with for the team and notify team request and communicate it with them.
How should the project manager respond? stakeholders. members.
36
A B C D E F G H I J K L M N
841276 I.8 A project manager receives complaints from a project sponsor B Create training sessions at the start List required skills for the project and Consult with the project sponsor to Empower team members to problem Develop the resource management plan by defining the
because of a delay in developing a prototype. The project manager of the project, so all necessary skills organize the project team based on add training once the lack of a specific solve where skills may be lacking, roles and responsibilities of the project team members to
consults the resource management plan and responds that the are learned. those skills. skill becomes apparent. using the skills they do have. create a project organizational structure and provide
delay was due to a lack of knowledge in a specific skill that was guidance regarding how resources will be assigned and
needed by the cross-functional project team. managed.
How can the project manager perform this task better in the
37 future?
A00041 I.8 Most of an agile team’s members are away for a month, but the C Engage an interpreter to translate all Assign all the usability stories to the Reprioritize the backlog to match the Find another remote team with The project manager should notice that the remote team
project needs to make progress. The project manager outsources the requirements remaining local team member remote team's skills better linguistic skills. has a higher specialist skill level and seek to leverage their
the work to overseas contractors to work remotely on the stories. talent. This action fills the skill gaps of the local team.
In their first sprint, the overseas team did NOT understand certain
usability requirements, but still managed to complete five (5)
stories that were previously blocked because the original team
could NOT handle the algorithmic complexity of the work.
46
840759 I.4 A project team has been efficiently delivering results. The product A Meet the new demand by adding Recommend suspending the project Discuss options with the project Challenge the request and initiate In situations with time constraints, the most efficient
upgrade they are working on must be released in three months or new resources with the required until a firm decision can be made. sponsor and choose the best one. customer research to determine option is expanding the team to include skilled resources.
else a competitor’s new product will make theirs obsolete. Citing skills. whether the new feature is desirable. Training is also an option if resources have the capability to
this reason, the product owner makes a sudden request for a learn within the timeframe. The project sponsor has
feature revision. However, no one on the project team is capable already made their request, so it is up to the project
of doing the work. The project sponsor is willing to extend the manager to realize it. Agile projects are designed to
budget but CANNOT extend the schedule. function in highly complex and unpredictable
environments, so suspending or cancelling the project
47 What should the project manager do? hardly ever is an option.
A B C D E F G H I J K L M N
840780 I.4 Some agile approaches have recently been added to an A,D Provide team training, so the team Speed up the project by reducing the Gain the needed time for story point Use burndown and burnup charts to Training can be a great way to empower team members to
infrastructure company's predictive processes. The team is NOT can do a better job of estimating backlog. completion by adding more iterations evaluate team performance and grow their skillsets. This would also create consistency in
completing the planned story points, and they are becoming story points. to the project. show story points completion. story point estimation techniques. Burndown charts show
passive. The project manager is concerned and wants to improve the remaining story points and burnup charts show story
productivity. point completion.
Which two actions should the project manager take? (Choose
48 TWO.)
841275 I.4 An agile approach is required during the final phase in a team’s D File a change request that addresses Escalate this as an issue to the Ask the team members who have Identify and provide the most cost- Providing training to project team members can result in
project. As the team discusses the phase, some team members the agile training that members lack. project sponsor, as it is a company- worked with agile to mentor the effective agile training for team added skills that can be useful for future phases or
disclose that they have NOT worked with agile before. The wide issue and a blocker for this others. members. projects. Training lessons and related costs could be
deadline is approaching soon. project. evaluated to be included in the resource management and
cost management plans. Mentoring is a good idea, but with
How should the project manager respond? a firm schedule, you may NOT have enough time to
transfer skills while getting project work done. Finally, this
is the project manager’s issue to deal with, NOT the project
sponsors.
49
844625 I.4 A project has the following characteristics: C,E Meet with the team leader to discuss Implement a whole-team training Work collaboratively with the team to Design a checklist for all team Set up mentoring sessions within Project managers should attempt to resolve issues using
the situation and decide if escalation program to address efficient working design training and a checklist for task members. the team so that the experienced the tools and techniques available to them prior to
- Schedule performance issues occur due to low expertise levels of to the project sponsor is necessary. and task completion. completion aligned with project goals. resources can coach the junior changing the plan or escalating the issue. Providing training
project resources. resources and work to those who need it will improve team performance and
- Junior-level resources are NOT completing tasks in a timely collaboratively. implementing a checklist ensures each team member is
manner. checking only what needs to be checked.
- Highly-experienced resources report that their junior colleagues
are performing unnecessary tasks.
68
840644 I.9 A project manager is preparing the charter for a project. The A,C Have a meeting with the test Request for the project sponsor to Present data-driven, cost-benefit Raise the risk that the senior testing Work with the project sponsor to In this scenario, the project manager’s first action is to
project aims to automate 30 percent of the company’s product department manager to discuss provide a rationale for test evidence of test automation to the engineers will NOT be available for create a project charter that the attempt to make the stakeholder cooperative with the
testing. The project sponsor advises the project manager to assign mutual expectations. automation. test department manager. the testing. test department manager will project. One way of doing this is presenting the data that
senior test engineers to identify the tests that can be automated. NOT perceive as threatening. supports the business decision.
The test department manager, however, is NOT cooperative
because they believe that the project will lead to downsizing in
their department.
Which two actions are suitable in this scenario? (Choose TWO.)
69
840668 I.9 Project manager A identifies three critical risks with probability of D The project team members – to The project sponsor – to request The three resources – to convince Project manager B – to negotiate Project manager B has the authority to reschedule or
a high impact on the schedule and budget of project A—this assist in training the new team more funding for the budget in order them to join the team or, at least, reallocation or sharing of the three reallocate the resources, once it will NOT jeopardize
project is producing critical deliverables for the company. members quickly so they can to hire contractors agree to coach the existing team required resources project B. Going directly to the resources themselves
complete work on time undermines the functional manager, so this is unethical.
The team meets to devise a solution for the risks and decides that The resources have been identified as the solution to the
three specific resources will be required to address the risks. problem, so it is best to attempt to make this solution work
However, these resources are already committed to a separate first. The other options of the project sponsor and working
project, which is managed by project manager B. with project team members would be secondary and
tertiary options which would probably NOT work as well.
Which party should the project manager work with first to find a
70 solution?
840758 I.9 A customer is NOT satisfied with the delivered product, saying that C Required team sign off for each of Set aside more resources for product Ensured that the customer was aware Ensured that the development team The customer was NOT engaged enough in the project. The
it was NOT what they expected. The project manager is surprised, the changes to the requirements testing after making changes of the value of demos and the fully participated in the iteration iteration review is the best mechanism for the team to
because the agile development team delivered the product several approval process for the deliverable review, by explaining and answering demonstrate the product and for the customer to give
iterations early. questions feedback to ensure that expectations are met and that
final stakeholder approval will be given.
What is one way that the project manager could have avoided this
71 result?
840764 I.9 A key stakeholder voices a concern during the planning stage C,E Review the bounds of the Determine the project's ultimate Engage in negotiations for more Ensure that the impact of the Re-evaluate the project In this case, the stakeholder’s concern should be
about whether the available resources are adequate to meet the negotiations for stakeholder objectives after carefully evaluating resources. shortage of required resources is objectives, review the planned researched before any action is taken. Once the project
objectives of the project. After further discussion about the agreement. project priorities. fully documented. activities, and recalculate the manager has determined the correct number and type of
requirements and the number of resources identified, the project resource needs. resources for the project, then they should use negotiation
manager is hesitant about the original plan. skills to achieve the proper support for the work of the
project and its outcome.
Which two steps should the project manager take next? (Choose
72 TWO.)
840783 I.9 A contractor has sent an email request for urgent payment of their C Negotiate payment terms through a Authorize the payment by notifying Act according to the agreed-upon Authorize payment only after Even an inexperienced project manager should understand
last invoice on a project that is going through a long execution meeting with procurement and the accounts payable and follow up to commitments in the procurement reviewing forecast spend versus that terms and conditions should be agreed before
stage with multiple contractors. contractor. ensure it was made. management plan and the signed actual spend to see if the actual engaging a contractor to actually do project work. The
agreement/contract. status allows it.
procurement plan and the agreement/contract hold all
How should the project manager respond to this contractor's data reference contracts and are the sources to guide
73 request? payment activities.
844613 I.9 The sales and marketing director at company A reports a 40% drop B Remind them that they were Review the customer and market Let them know that you also are Ask the team to perform the final The director is understandably concerned, given the
in revenue and significant increase in returns for Widget version consulted about the agreed product research—both qualitative and disappointed, but this risk was demo for version 6.0 again for the negative performance of version 6.0 in the customer
6.0. Customers are complaining directly to customer service and requirements for versions 6.0 and quantitative—that supported the documented and listed as a probable director’s information. market. Base your interactions in a shared sense of
the social media teams report a high rate of negative feedback. 6.1; also remind the stakeholder and business case for the 6.0 project. customer/market reaction for a major responsibility for the failure, whether it is a real failure,
that the responsible and accountable Begin by discussing the stakeholder’s version release.
whether it was predicted or probable, or whether it is a
The project team is already working on Widget version 6.1., which stakeholders approved version 6.0 role in the research. temporary or unexpected event. Avoid performing actions
is a small set of upgrades and bug fixes. The director gets in touch before release. again that your team already made; likewise, avoid being
with the team, requesting a full disclosure of the version 6.0 and defensive by reminding them that they had a role in
6.1 requirements. approving a failed product. Neither of these will help the
company achieve its strategic goals—which is what both
How should the project manager interact with this stakeholder? parties are supposed to be committed to doing.
74
844615 I.9 A project has a quality management plan in place. A Generate a cause-and-effect Rewrite relevant portions of the Inquire regarding the feasibility of an Contact the project sponsor and Cause-and-effect diagrams break down the causes of the
diagram for analysis. quality management plan. internal audit of the project. request advice.
problem into discrete branches, helping to identify the
This plan states that project deliverables must be reviewed for main or root cause.
quality at least five (5) business days before the deadline. Four
deliverables have failed the quality requirement.
75 What should the project manager do?
H00013 I.9 The project sponsor is NOT convinced that an agile track should be B,C,D A product roadmap can provide a Requirement priorities are confirmed Incremental development reduces risk Impact mapping can be used to Stories can be broken down into Valid agile methods to secure on-time delivery include
used in a new R&D project because the company needs to be detailed breakdown at each iteration of quality delays group related stories granular epics backlog reprioritization at every sprint, impact mapping for
certain that specific features will be ready for mass production by feature-level view, and incremental testing to secure
a specific date. progressive development. Roadmaps and epics are high-
level, NOT detailed views—so these will NOT work.
Which three agile methods can ensure that the sponsor's needs
76 can be fulfilled in a hybrid project approach? (Choose THREE.)
A B C D E F G H I J K L M N
840609 I.2 A project manager observes that team members are in a low mood C Meet with the stakeholders and find Verify that the project requirements Coach the team to be more confident Consult the stakeholder matrix and Leading the team means understanding how they can best
after demos. Feedback from stakeholders is constantly causing out the root cause of their feedback. are suitable and that the team in their work and communicate identify whether any of these people be successful. In this case, they are NOT communicating
concern for the team. As a result, the team rushes through product Work with the stakeholders to members can do the work. properly with the stakeholders. are known to be difficult. well with project stakeholders and risk becoming
demos, and the interaction between the team and stakeholders is rectify the problems. demoralized. You should perceive this behavior as a risk to
minimal. the project, caused by poor communication. You will
already have verified the requirements and determined
Which action should the project manager take? that your resources are adequate. Whether or not a
stakeholder is difficult, your team needs to be able to
perform. If you choose to work directly with the
stakeholders, then you are undermining your team. Coach
the team members on how to work better with the
stakeholders.
77
A00036 I.2 The IT department of a glassware manufacturer enthusiastically D Contract directly with the customer Ensure that all software releases Create a realistic simulation of end- Plan for end users to test prototypes Requirements and feedback from actual end users
approved the agile team's mid-project demo of quality-checking department that defines the product include adjustable accessibility user conditions for developers testing and incremental releases in their CANNOT be replaced by organizational structures,
software for assembly line workers. However, the final product requirements. features. the software. production environments. simulations, or generalized feature sets (accessibility).
was considered UNUSABLE because the workers’ gloves are too Contracting with the end-user department would NOT be
thick to press the machinery’s small buttons. appropriate either, as they would NOT have expertise,
norms, and assets relating to how the software integrates
What should the project manager do to avoid this kind of failure in into the larger IT environment.
the future?
78
A00044 I.2 The agile team sometimes has idle periods while awaiting a B Plan team training events to coincide Run market research spikes to Eliminate slack by reducing the team Run team brainstorming sessions on Running market research spikes supports the product
product director to inform the product owner on new goals. The with the anticipated idle periods. update the director after clearing the size to smooth the output curve. new goals to suggest to the director. director and helps build and diversify team skills. If the
decisions depend on analysis of market research. backlog. team is idle, it means they are NOT working on
stories/features in the backlog. Reducing output means
Which measure could reconcile the needs of the director and the negative productivity, and the team's ideas would NOT
agile team? provide market facts needed to make informed product
79 development decisions.
A00029 I.7 An agile development team changes a design element in a project. C Set out all decision path conditions in Request additional funding from the Ensure regular engagement with the As servant leader, help the team to The product owner has ultimate authority on the scope of
Testing results improve dramatically over the next two iterations. the ground rules and correct any product owner for re-work due to product owner and run catch-up focus by removing all impediments. the product. Thus, product owner engagement is critical
At the third iteration retrospective, the product owner is unhappy deviations as early as possible. lack of collaboration with the team. meetings if necessary. when considering scope changes or any changes that may
to learn about the change to the original design and asks the team have an impact on the scope.
to redo the work based on the original design.
84
844590 I.3 A project manager with limited experience managing globally C Read books about cultural sensitivity Hire a professional coach to learn Request a different assignment, citing Enroll in language and culture lessons Great leaders have a growth mindset. Always aim to
distributed team members is appointed to a project with team in leadership. how to be a more successful leader. the language barrier as an obstacle. to learn about this country.
capitalize on cultural differences, focus on developing and
members who are all from another country and speak a different sustaining the project team throughout the project life
native language. cycle, and promote working together interdependently in a
climate of mutual trust. In this case, you can NOT assume
To successfully manage this project, the project manager needs to that there is a language barrier, as the team members may
have cultural sensitivity. be bilingual. This answer also does NOT demonstrate a
growth mindset.
What of the following actions should the project manager NOT
85 take?
A B C D E F G H I J K L M N
A00046 I.3 A governmental anti-money laundering software project needs a D Information radiator monitors On-demand video conferencing Workstation screen mirroring Always-on fishbowl windows
This is a project where confidentiality and security are
solution to collaborate with a remote agile team of four (4) people critical—thus, permanent monitoring of remote resources
in another country. Spontaneous verbal communication between is necessary. Only the fishbowl window solution would
the teams must be supported. All the remote team's workstations have the required field of view on a permanent basis.
and Kanban boards must be visible at all times. Radiators only display content, on-demand video
conferencing would NOT be a permanent video feed, and
Which virtual team collaboration solution is most appropriate? mirroring only displays one (1) computer screen, NOT the
86 environment.
A00070 I.3 A financial software company serves stock markets worldwide. An B Conduct Scrum-of-Scrum meetings Run fishbowl windows during the Conduct Scrum-of-Scrum meetings Run fishbowl windows during the The fishbowl window solution allows teams to interact in
experimental quality assurance project has agile teams working in daily in order: overlapping shifts: daily in order: overlapping shifts: real time, thus allowing faster coordination and handling of
three company offices: Seattle, Tokyo, and London. The teams 1 Tokyo Shift 2 with London Shift 1 - London Shift 1 with Tokyo Shift 2 1 Seattle Shift 2 with London Shift 1 - Tokyo Shift 2 with Seattle Shift 1 issues. The shifts overlap in follow-the-sun order: Tokyo 2-
work in two shifts in each location at the following times in each 2 London Shift 2 with Seattle Shift 1 - Seattle Shift 1 with London Shift 2 2 London Shift 2 -Tokyo Shift 1 - London Shift 1 with Seattle Shift 2 London 1, London 2-Seattle 1, Seattle 2-Tokyo 1
time zone: 3 Seattle Shift 2 with Tokyo Shift 1 - Tokyo Shift 1 with Seattle Shift 2 3 Tokyo Shift 2 -Seattle Shift 1 - Tokyo Shift 1 with London Shift 2
116
A B C D E F G H I J K L M N
H00051 II.2 A smart grid project combines predictive and agile tracks. The B Run the same unit tests in the agile Send project-wide issue log updates Ensure that retrospectives are shared Replan the software track into the The root problem is that impactful information in the agile
agile team detected a major software defect after its release and lab and in the field sites. via instant messaging. with the predictive team. predictive schedule team was NOT passed to the predictive team quickly
began working on a correction. But the defective release was enough to prevent the test failure. Instant messaging of
deployed by the predictive track, and this caused a field test to fail. issue log updates can reach the full project immediately
after the issue is logged, and act as an alert.
Which measure would be most effective to prevent similar
problems in the future?
117
840611 II.3 A project is at the planning stage. The project manager realizes A Mitigate Transfer Accept Avoid The risk to the project was posed by insufficient resources.
that producing a complex, multi-functional application is NOT The risk was mitigated by hiring additional resources.
feasible with the current number of resources and decides to hire
more resources for the production of the application. The project
manager identifies and contracts temporary resources.
The project manager decides the best way to manage this risk is to
deliver all heavy equipment themselves, despite the significant
added expense.
124 Where can the project manager look to evaluate these risks?
840675 II.3 Although the sponsor and project team say that the new project A Engage in identification of project Ask the project sponsor for Schedule a meeting with the Execute the project as planned and The project manager needs to be proactive and familiar
has an adequate budget and realistic schedule, the project risks, then assess those risks. additional funding to cover project functional manager to address the handle any risks as they arise. with as many project risks as possible. The risk assessment
manager worries that unplanned events could threaten the planning. potential impact of unplanned risks. needs to occur before the risk is encountered.
project’s success.
125 What should the project manager do first?
840678 II.3 A company wants to reduce future operating costs by installing D Loss of energy efficiency rating Loss of funding for the project Increase in scope Increased total cost The risk described here is a loss of potential subsidy that
solar panels on the facility being built by using a local government would reduce the cost of the project. So, this risk amounts
subsidy for energy-efficient projects. They have NOT yet applied to the project requiring much more in future operating
for the subsidy. costs.
Before the project starts, the project manager is describing project
risks.
149
840775 II.4 A company is struggling to define the scope of a new project that B Contract with a third-party Work with project stakeholders to Review the project management plan Move forward with the project but A corrective action, such as the iterative approach, is
has multiple phases with a high level of dependency between the consultant that specializes in helping recommend an iterative approach to ensure that it provides extra time keep a daily check on the schedule to required here. Introducing adaptive steps in a heavily
phases. businesses define scope of work on that will then help to define the within the schedule, then revise the prioritize the dependency issues. predictive environment is never easy and the stakeholders
large projects. project's scope. scope of work. should be involved in this process.
150 How should the project manager approach this challenge?
A00073 II.4 A product owner in an agile project complains of too many C,D Sprint retrospectives Product SME consultations Daily standup meetings Team performance reviews End-user feedback sessions In agile projects, the customer is the highest priority,
meetings in their monthly schedule. There is NOT enough time for because this leads to end-user satisfaction and focus on
project work. They instruct the project manager to prioritize some delivery; administrative processes such as performance
meetings and decrease the frequency of others. reviews are a lower priority. The product owner is NOT
needed at every daily meeting.
Which two of the product owner’s meetings could the project
manager deprioritize so that they attend less frequently? (Choose
151 TWO).
840648 II.5 A deliverable on the project's critical path is behind schedule. A,C,D Activities will be performed in Project scope will be revised. Associated risks will increase. Costs will increase. The team should expect rework. The cost performance index (CPI) is above 1; therefore, the
parallel. project is spending money at a rate lower than planned.
The cost performance index (CPI) is 1.3. The project manager is Since the project is behind schedule, its schedule
able to put the project back on schedule. performance index (SPI) is less than 1. In order to increase
the SPI to 1, there will most likely be an increase in costs,
Which three results are the most likely for this project? (Choose perhaps from crashing activities on the critical path that
THREE). will lower the CPI towards 1. This will most likely increase
risks associated with the project when trying to do more in
152 a shorter time.
840649 II.5 A project that should have been 90% complete by now is only 65% A The SPI is 0.72, and the CPI is 0.98. The SPI is 1.38, and the CPI is 1.2. The SPI is 0.94, and the CPI is 1.04. The SPI is 0.80, and the CPI is 0.91.
EV = % complete * budget: 65% * $120,000 = $78,000,
complete. The total project budget is US$120,000 and the actual AC = $80,000.
cost spent to date (AC) is US$80,000. CPI = EV/AC = $78,000/80,000 = 0.975 or 0.98
A CPI less than 1 means the project is over budget.
What is the scheduled performance index (SPI) and cost
performance index (CPI) of this project? PV = % complete * budget: 90% * $120,000 = $108,000,
SPI = EV/PV = $78,000/108,000 = 0.72
153 An SPI less than 1 means the project is behind schedule.
840652 II.5 A project is 7 months into execution. The project manager A Issue a change request to redo the Ask for additional resources. Crash the project schedule. Utilize the management reserve.
Since the project is over budget and the trend analysis
determines that the cost performance index (CPI) is .80. cost baseline. shows that this will continue, the best course of action is to
redo the cost baseline of the project and manage it.
According to a trend analysis, the CPI has a downward trend.
154 What should the project manager do next?
840654 II.5 A project has the following characteristics: B The project is ahead of schedule and The project is behind schedule and The project is ahead of schedule and The project is behind schedule and CV = EV - AC: 540 - 650 = -110 (negative cost variance)
under budget. over budget. over budget. under budget. SV = EV - PV: 540 - 630 = -90 (negative schedule variance)
- US$3 million budget
- Planned value of US$630,000 Negative cost variance means the project is over budget.
- Actual cost of US$650,000 Negative schedule variance means project is behind
- Earned value of US$540,000 schedule.
155 Which statement is true about the current status of the project?
840685 II.5 The project manager learns that one team member needs to A Meet with the team member’s Ask the team member to focus on Send a report to the project sponsor, Tell the team member’s manger to The resource management plan is used to help determine
complete a critical task that is outside of the project, resulting in a manager and negotiate for an the critical task and obtain an documenting noncompliance from the release the team member from how resources allocated to agreed-upon risk responses will
scheduling risk for the project. alternative time to complete the additional resource from another member’s manager. outside activities until the scheduled be coordinated with other project resources. This will
other task. department. project activity is complete. provide guidance as to how the project manager can
How can the project manager eliminate this risk? negotiate with the resource’s manager.
156
844452 II.5 A project that should have been 70% complete by now is only 55% A The SPI is 0.79, and the CPI is 0.71. The SPI is 1.27, and the CPI is 0.98. The SPI is 0.82, and the CPI is 1.05. The SPI is 0.99, and the CPI is 0.96. EV = Actual% * BAC = 0.55*$210,000 = $115,500
complete. The total project budget is US$210,000, and the actual PV = Plan% * BAC = 0.70*$210,000 = $147,000
cost spent to date is US$162,000. AC = $162,000 (given)
What is the scheduled performance index (SPI) and cost SPI = EV/PV = $115,500/$147,000 = 0.785 or 0.79
157 performance index (CPI) of this project? CPI = EV/AC = $115,500/$162,000 = 0.71
A B C D E F G H I J K L M N
844455 II.5 A project that should have been 90% complete by now is only 84% A The SPI is 0.93, and the CPI is 1.13. The SPI is 1.07, and the CPI is 0.99. The SPI is 1.15, and the CPI of 0.93. The SPI is 0.96, and the CPI is 1.18. EV = Actual% * BAC = 0.84*$110,000 = $92,400
complete. The total project budget is US$110,000 and the actual PV = Plan% * BAC = 0.90*$110,000 = $99,000
cost to date is US$82,000. AC = $82,000 (given)
What is the schedule performance index (SPI) and cost SPI = EV/PV = $92,400/$99,000 = 0.93
158 performance index (CPI) for this project? CPI = EV/AC = $92,400/$82,000 = 1.126 or 1.13
A00055 II.5 Over the past six months, the cost per story in agile project A has B The head of business control The product owner The procurement manager The project manager
The product owner acts as the sponsor in agile projects and
risen by more than 250% due to a faulty platform which is no therefore has the authority to decide if conditions warrant
longer supported. The project will exceed the budget increment termination of a project.
threshold at the next iteration.
How can the project manager forecast the completion date with
more accuracy and certainty?
169
A00078 II.6 A - Agile An ongoing agile project is measured as follows: B,D SPI = 0.98 CPI = 1.05 CPI = 1.30 SPI = 1.01 CPI = 0.95 SPI is calculated as stories completed/stories planned
(78/77 = 1.01) and CPI as earned value /actual cost
2-week Stories Stories Actual Earned (3090K/2950K = 1.05).
Sprint Planned Completed Cost Value
1 15 10 450K 300K
2 20 18 600K 540K
3 20 25 800K 1000K
4 22 25 1100K 1250K
_____________________________________________________
Totals 77 78 2950K 3090K
=====================================================
According to the table, which two of the following are the project's
170 metrics? (Choose TWO).
A00095 II.6 A - Agile A start-up has grown quickly, and there are now four (4) agile C Eliminate dependencies between Favor collaboration tools over Implement a Scrum of Scrums layer. Merge into two large teams to Scrum of Scrums is the most effective way to coordinate
teams working on interrelated products. All teams have begun to teams. meetings. reduce issues. work between teams working on interrelated products.
experience impediments and gaps related to work in other teams.
179
A00100 II.7 A - Agile During sprint planning, some new backlog items are prioritized but C Use analogous estimating based on The product owner defines a new Add the relevant acceptance criteria The product owner should provide Specific acceptance criteria should be defined and checked
NOT estimated. The product owner requires a new set of tests to similar tests on similar stories. epic to allow testing in the next in the Definition of Ready before the initial estimate to be refined by in the Definition of Ready of any impacted item before
verify the unique properties of the items. sprint. estimating. the team. estimation to ensure all effort is accounted for.
In which two ways can the project manager help the agile teams
improve their work? (Choose TWO).
182
A00089 II.7 A - Agile The agile team surpassed the planned number of stories in the last B Ask the product owner if results are Check results against the Definition Ask the team to cross-check other Check the results of all the tests The Definition of Done lists all criteria that must be met to
three agile iterations. satisfactory. of Done. members' work. performed. consider a task/story completed.
How can the project manager be sure all the work performed is
183 truly complete?
840620 II.8 P - Predictive A medium-sized company is expanding into a new market. A,B Prototypes Expert judgment Product analysis Create requirements traceability Experts are a source of experience and knowledge. Given
However, the company does NOT have previous experience in that matrix the increased risks of a new and potentially complex
market. market, using expert judgement is recommended.
Prototypes are an excellent way to gain a better
A project manager needs to collect requirements. understanding of the product and to gather requirements.
Which two tools or techniques should the project manager use?
184 (Choose TWO).
840632 II.8 P - Predictive A client brings a project manager into a project during the project's C Verify with the stakeholders to see if Ask that the project management Include the work in the WBS, per the Determine whether these The 100% rule states that any work package in the WBS
execution stage. these missed deliverables should be office (PMO) approve additional 100% rule, and recalculate the total deliverables are necessary by should consist of 100% of all work for that work package.
added. funds for this work. project cost. verifying with experts in the field. Since the WBS is a work package itself (the project), and
The project manager reviews the project scope for cost estimating since the WBS should contain only work packages that are
purposes and notices that some deliverables were missed in the in-scope, any missing work packages should be added to
work breakdown structure (WBS). the WBS and recalculated.
185 Which step should the manager take next?
840634 II.8 P - Predictive Review the following project characteristics: C Milestone list Work breakdown structure (WBS) Scope management plan Requirements management plan The scope management plan is a component of the project
dictionary management plan that describes how the scope will be
- A sponsor approves a project. defined, developed, monitored, controlled, and validated.
- The project manager invites selected team members, key
stakeholders, and the sponsor to a meeting.
- The primary purpose of the meeting is to create a document that
will guide the team in defining the main project deliverables.
What will be the final output of this meeting?
186
840651 II.8 P - Predictive A project manager is working with a customer who repeatedly D Hold a meeting with the product Define project boundaries Organize a meeting with the Analyze the scope management plan The scope management plan documents how the project
submits requests for new requirements for an existing software manager to request that the number immediately with the sponsor. stakeholders to set expectations. to see how changes in scope are and product scope will be defined, developed, monitored,
product. of new requests be reduced. handled. controlled, and validated. The key benefit of this document
is that it provides guidance and direction on how scope will
The project manager has already provided the completed scope be managed throughout the project.
definition for the product's next version release to stakeholders.
187 Which step is appropriate for the project manager to take next?
844480 II.8 P - Predictive A project manager is working on a software development project. D Ask to meet with the product Meet with the sponsor immediately Meet face-to-face with stakeholders Assess the scope management plan The scope management plan provides details on how
manager, and discuss reducing the to discuss project boundaries. to set expectations. to see how changes in scope are project and product scope will be defined, validated, and
Two customers are repeatedly submitting new feature requests. number of new requests. managed. controlled. It is needed to help control the scope of the
The completed scope definition for the product's next version project.
release has already been provided to stakeholders.
191 How can the project manager best resolve the problem?
840631 II.9 AG - Agnostic A marketing team is developing a new website for an existing A Focus groups Brainstorming Product analysis Benchmarking
Focus groups bring together prequalified stakeholders and
product range. The team reads through some customer comments subject matter experts to learn about their expectations
submitted on the current website: and attitudes about a proposed product, service, or result.
What next step should the project manager take in this scenario?
213
840746 II.13 H - Hybrid Company P’s IT transformation project has three (3) deliverables, D Select a fully agile project model, Select a waterfall project model for Select a hybrid project model; Select a hybrid project model; In this project, two (2) deliverables have unknown
and they have the following characteristics, according to the with a common user story and three- deliverables, with firm milestones position deliverable 2 as a single agile position deliverable 2 as a single durations or changing requirement sets—both of which are
project team: week sprints. and change control procedures. sprint embedded in an overall waterfall phase embedded in an appropriate conditions for use of the agile life cycle.
waterfall project. overall agile project. Deliverable 2 requires strict schedule control and external
- Deliverable 2 has strictly scheduled milestones, with no expected dependencies, which require a traditional or waterfall
variation in the timeline. project life cycle.
- Requirements for deliverables 1 and 3 will change quickly during
development.
Which project life cycle should the project manager use for this
214 project?
A00099 II.13 A - Agile A consultant has advised an IT director to use a development and B, E Virtualization of all systems and Early collaboration between Machine Learning-based development Development testing at deployment Automation of operations and Development and operations collaboration (early and
operations (DevOps) approach to a migration project. The IT software containers operations and development and deployment sites before operations development constant) and automation of both domains is at the heart
director wants to understand how the necessary speed can be of DevOps. Virtualization and machine learning are
achieved in a safe way. enablers of efficiency but NOT DevOps methods.
Development testing on deployment sites is impractical
Which two examples could demonstrate how DevOps can reduce and inefficient.
incidents and speed up deployment at the same time? {Choose
215 TWO.)
A00031 II.13 A - Agile An innovative product fails to satisfy targeted consumers despite A Run continuous consumer usability Align objectives between the product Broaden the persona type definition Add more features and tests to the Continuous user testing and feedback is the most effective
significant investments in quality control and marketing testing on product releases. owner and marketing. of the target consumer. minimum viable product (MVP). way to align requirements to user needs and integrate
campaigns. them incrementally into product releases.
What could the agile team have done to prevent the current
malfunction?
220
H00014 II.13 H - Hybrid A medical equipment vendor is running a hybrid project which C Invite the customer to send Work out an arrangement with the Propose new terms for team Allow the team to progress at their Agile seeks to maximize transparency between supplier
includes some custom software development by an agile team. representatives to witness the customer to defer as many tests as members to work aside the customer pace while the customer continues to and customer as well as optimizing to remove unnecessary
The team progress is good, but slow customer approval causes team's testing to pre-approve the possible to the final release. testers to run tests in their test and approve earlier builds. work. Combining teams to remove work duplication is the
unnecessary delays. The customer insists that approval can only be tests. environment. best option.
given after repeating all the test cases in the target environment.
Witnessing only would NOT remove duplicated work;
How can the project manager accelerate the approvals and build deferring tests is always bad practice because defects are
customer trust at the same time? NOT detected at the earliest possible point; and
unsynchronized progression between the teams would
221 potentially cause rework if defects are found.
H00038 II.13 H - Hybrid An organizational change program has met with internal D Work with the program sponsor to re- Request that the sponsor escalate Perform root-cause analysis on the Review the risk register and Stakeholder resistance was anticipated and multiple risk
resistance, a risk which was previously identified. A logistics prioritize the program backlog the strategic issue to the executive key factors causing the manager's implement the relevant risk response responses are likely to exist, so reviewing the risk register
manager is particularly affected, due to reduction of the team size sequence. committee. resistance. for the case. is the correct response. Agile planning would enable
and the rate of change driven by an agile planning of the predictive frequent retrospectives to refine the risk responses, which
implementation. The manager's supervisor formally requests the could be more flexible than a fully predictive response.
change program to delay implementation for the logistics team.
231 What is the first action the project manager should take?
840662 II.17 P - Predictive After a project ends, the project manager and project team A Complete the hand-off of the Review the acceptance criteria and Formally disband the project team Continue to fulfil the requests as the Project closure and hand-off will ensure knowledge
members are still being asked to do the following: project. get acceptance. and find a new project. product is still being developed. transfer to production and/or operations.
Which three (3) documents should the project manager use for
this decision?
233
A B C D E F G H I J K L M N
844595 II.17 P - Predictive A project is completed, but the project manager and project team D Since the product is still under Procure project acceptance. Contact the project team, dismiss Execute the project hand-off. In the Close Project or Phase process, the project team
members are being asked to do the following: development, continue to fulfil the them from the project, and find a new formally transitions the final product, service, or result to
requests. project. the production support team. The receiving group signs
- Troubleshoot and resolve technical issues documentation, agreeing to accept the final product,
- Evaluate new requirements service, or result. Once signed, the owner is responsible for
- Make minor adjustments changes, adjustments and resolving technical issues.
How can the project manager ensure that the deliverables are
248 realistic?
844631 III.2 P - Predictive A key project resource is discussing the complexity of project A Implement a feasibility study, and Hold a meeting with the project Ensure that the concerns are Start to identify threats and The feasibility study will support the business case to begin
deliverables with the project manager 2 weeks before the kickoff then assess and review the results. sponsor to discuss the resource's documented in the issue log for later preventive actions by performing a a new project.
call. The resource expresses nervousness and concern regarding concerns and revise the project review. risk assessment.
the deliverables. charter.
Which two actions should the project manager take to adapt the
258 project to these new conditions? (Choose TWO).
H00052 III.3 H - Hybrid A pharmaceutical project includes an agile team of doctors who B Record the risk in the register and Work with the team to plan how to Anticipate a negative response from Ask the team to produce a SWOT The project owner works for the business and supports the
analyze human tissue scans from drug trial patients. The CEO plan for discussing a response in the use the ML resources and produce a the team and be ready to persuade analysis supporting human-based CEO decision. ML is an accelerative tool, NOT a
wants to leverage Machine Learning (ML) technology, because it is retrospective. business case. them that their time and skill will be validation. replacement for experts. Working with the team to plan
proven to be faster and more accurate than doctors in scan better spent elsewhere. their new ways of working and using a business case to
analysis. support the decision is in the company's and team's best
interests. Though you should use emotional intelligence to
How should the product owner proceed in response to the CEO's help the team realize the next step, focus on how the team
wish? can be involved, NOT on another, unknown future.
259
A00071 III.4 A - Agile As part of an organizational change program, an experienced C,E Ensure that the MoSCoW method is Analyze all planned projects to pick Show stakeholders how agile can Train project teams to be more self- Identify opportunities for Agile adoption is enabled through communicating and
project manager with agile experience and certification is hired by used to write all project the appropriate agile model. increase quality and decrease risk. reliant and cross-functional. incremental business value demonstrating its benefits.
a company with a strong predictive culture. requirements. delivery.
Which two actions can the project manager take to start helping
the company adopt agile methodologies? (Choose TWO.)
260
A00097 III.4 A - Agile An agile team needs to decide who should represent them in the B Scrum DevOps eXtreme Programming CI/CD
DevOps is designed to eliminate the potential impediments
Scrum of Scrums. and gaps that cause incidents in the cycle of development,
deployment and use of software and IT resources. CI/CD is
Which option should be used to select the best-suited team included within DevOps and therefore CI/CD alone would
member? NOT address as many problems. XP and Scrum would NOT
address coordination with operations.
261
A00208 I.5 A – Agile User testing on the last product release revealed low user B Team can brainstorm how to Scrum master can coach the Team lead can arrange a training Team lead can perform The product was released without sufficient user input
interest in certain features that required a significant effort to better understand the product product owner on prioritizing the session for everyone to learn about stakeholder analysis to find or prioritization to ensure it has appeal and delivers
develop. The team feels demoralized, and they want to make vision. desired end-user features and the benefits of a growth mindset. subject matter experts (SMEs) business value. SME input (for example from
sure their future efforts are worthwhile. Success in the next engaging stakeholders. who can guide the backlog value marketing or market researchers) can help with
iteration is critical as the competitor product is gaining market ranking process. ranking the features appropriately, but the deficiency
share. points to the product manager. The person in this role
needs to understand how to work with stakeholders in
How should the team respond? a more effective way so that the team is spending time
and effort developing features that are relevant and
262 represent value.
A00210 I.9 A – Agile A product owner has created a lot of epics and has started D The team lead should draft the The iteration planning ends after The product owner should present The team should decompose the The team should continue where the product owner
breaking them down into user stories. These high-priority user remaining acceptance criteria the estimate and team the committed user stories with the user stories into tasks. stopped and complete this activity that began as a
stories fulfill the definition of ready. At the iteration planning before starting the iteration. commitment. key stakeholders before the collaborative exercise with the product owner. The
meeting, the product owner leaves after 2 hours. iteration starts. team can decompose the user stories into tasks, then
estimate them before putting them on the board. They
What should happen next? can continue this work for the rest of the iteration
263 planning meeting.
A00212 I.14 A – Agile While the team coordinates delivering the latest version of a B Ask the client to replace this Ask the stakeholder to express Express empathy directly to the Tell the stakeholder that their Transparency and active listening are key elements to
machine-learning product, a client stakeholder shows signs of stakeholder to avoid project their concerns and ensure full stakeholder to gain cooperation. cooperation and patience are gain trust. Lack of trust is often the root cause of
resistance. The team lead suspects this is because the delays. transparency. appreciated. resistance. While empathy and appreciation help gain
stakeholder feels their job is threatened by the automation in trust, they do NOT necessarily promote better
the product. communication, as active listening would. Swapping
out the stakeholder based on an assumption would be
Which approach should the team lead take to effectively unprofessional and damage trust with the client.
264 reduce the stakeholder’s resistance?
A00213 I.2 H - Hybrid A project is more than halfway finished. The project manager C Respect the decision of the self- Explain to the team that Encourage the team to conduct Agree with the team that there is The purpose of the retrospective is to discuss
noticed that the teams have not been conducting organized team. retrospectives are required in retrospectives more frequently than little benefit in doing retrospectives performance as they experience it—on a “trial and
retrospectives at the end of every sprint. Instead, they are agile teams. twice a year because this is a after every sprint. error” basis—and for the team to incorporate
conducting them after the release, which is every 6 months. chance to talk about what works continuous improvement. Not every action item will
When the project manager addresses this problem during the and what doesn’t. result in a best practice or be an improvement.
all-hands meeting, the team responds that retrospectives are However, it is essential that the team continues to try.
a waste of time because nothing changes. As the leader, it is the project manager's role to
encourage and reinforce good practice.
What should the project manager do in this situation?
265
A00215 I.12 A – Agile A collocated agile team is updating the ground rules based on D Tell the truth and address any There shall be no email or surfing Ask for clarification if you are There shall be no swearing during Politeness and attendance at leisure activities are
the last iteration and retrospective. issues to the correct party (at the the web during team meetings and confused and do not interrupt one team meetings and participation in typically NOT part of the ground rules.
right time). be present on-site between 9:00 another. chess club on Monday evenings is
Which option should be excluded from the new ground rules? am and 4:00 pm. mandatory.
266
A B C D E F G H I J K L M N
A00216 I.14 A – Agile In a product demo meeting, an engineering specialist presents A Intervene and state that the cost Stop the meeting. Firmly tell Take the opportunity to address Allow the team to work through the As an effective team lead, you need to know when
the latest test-driven development prototype and asks for query will be considered but everyone to calm down and team member Y’s concern during disruption and the problem on their people are behaving in ways that will have a negative
team feedback. Team member Y interrupts the demo to remind everyone that this demo is control the rest of the meeting. the meeting. own. effect on the team. In this case, Y is behaving like a
protest about the high cost of the prototype. Members of the for product development bully and the behavior threatens the stated purpose of
engineering team immediately become defensive and begin feedback. the meeting. You should NOT respond by behaving
answering all at once. like an authoritarian. Leaving the team to work out a
problem might take a very long time and uncover even
What action should the project leader take in this situation? more emotional responses. If you can get the meeting
back on track with a quick reminder, this is the best
267 option.
A00217 I.14 A – Agile A project team is completing a sprint. This team normally B Assume everything is fine and let Think about any other recent Ask everyone to give a quick report Tell the team you are feeling If the data shows positive signs that work is on track
performs well under time pressure. But this time, something the team continue working. changes or reasons that could be of how they think the sprint is going anxious about their work. and you are feeling anxious or unsure, then it's a good
seems different. The workrooms are quiet, and people are the cause of these anxious at the next standup. idea to trust your instinct. Something could be
having conversations that seem secretive. A check of the feelings. happening outside of the project, and your awareness
scrum board shows that work is on schedule and quality of it might be causing concern. Try to identify the
checks are met, yet the team lead feels anxious. cause of your anxiety on your own without spreading
worry or alerting the team about it. Assuming
What should the team lead do? everything is fine would be alright, but without some
introspection to analyze the context of the project, your
268 anxiety might affect the team.
A00218 I.3 A – Agile A project team member is having an extremely difficult and A Coach the team member. Replace the team member. Discipline the team member. Consult the team member’s Team performance is the focus of an agile team. If a
busy personal life. The team is NOT aware. They only see functional manager. team member is underperforming, then the team lead
mistakes and missed deadlines. The team is in the middle of should coach them as much as possible to improve
an iteration and this team member’s latest mistake has performance.
caused a major issue.
How should the project team leader support the growth and
270 development of this group?
A00221 I.14 A-Agile A project team is being sent overseas to lead an integration A Host team is very unwilling to Scheduling problems because Heatwave during site visit, so Equipment is at risk from poor It is possible to understand why another team would be
project at a subsidiary factory. To prepare, they review a partner in training exercises. host teams have dedicated non- outdoor practical training was quality maintenance because of unwilling to do something and then seek a resolution.
transcript from the retrospective from a previous trip to identify working hours at different times of replaced by simulations. ineffective training Use empathy and active listening to try to understand,
the main problems. the day due to shift work. but also inspire the host team with the use of servant
leadership. Scheduling problems, adverse weather,
Which problem listed below can the team approach and and incomplete training need practical, technical
potentially solve using servant leadership and active listening solutions.
271 during the next iteration?
A00222 I.14 AG - Agnostic The team lead is having a coaching session with a team C,E Self-control Self-discovery Self-assessment Self-definition Self-management This team member has just completed an accurate self-
member. Read the scenario and answer the question. assessment, thanks to the coaching session. This is
the step when the team member declares that “I
Lead: We've noticed that your work is a few days late again. realize. . .” The next step is self-management, which
happens when we accept responsibility for our actions.
Team Member C: It is. I took extra time to fine-tune settings When the team member admitted they wrongly blamed
before handing off to the release team. something else in sprint 3, they accepted responsibility
and demonstrated self-managing behavior.
Lead: OK. We have been through this for the last four
sprints, and we need to resolve it. After sprint 3, you blamed a
faulty technical setup for the delay, but we found out that was
not accurate. Do you think you can give us more realistic
estimates next time?
How can the project manager avoid scope creep and keep
the team focused on delivering a product that meets
282 requirements during planning?
A B C D E F G H I J K L M N
H00247 II.10 H - Hybrid A client is making a lot of small, minor change requests, A Log each change request in the Reject the minor changes. Escalate the client's behavior to the Put the requests into the iteration Even though a client is making very minor change
indicating that they are urgent and critical. log. sponsor because it is annoying the backlog. requests, every single one needs to be processed.
team. Frequent, minor requests are not a cause for
Which action should the project manager take? escalation. Project managers cannot reject change
requests from stakeholders and clients. Finally, putting
the requests into the iteration backlog is not the correct
283 response to a change.
A00249 II.11 A - Agile An agile team is in dire need of additional resources, so the C Existing agile team Team lead Management Product owner Hiring and firing are management tasks. The other
department decides to add another agile team. A few teams roles may take part during the test and work with the
are possible candidates, so management decides on using a acquired team, but the hiring decision is up to
performance test to decide which team to add for 10 management.
iterations.
Which action should the team take to assist the product owner
291 with validating business value?
X00266 II.7 P - Predictive A team was assigned a project to build a new insurance policy A,C Defect count A risk metric Issue log Changes Technical debt You need to obtain data and report on quality and any
administration system. After 6 months of project work, the obstacles affecting the project to explain problems to
project sponsor expresses concern. A colleague in an the project sponsor. A defect count will indicate the
unrelated company division claims the policy administration quality of the product being built as well as which areas
system has bugs and the team is unable to solve critical of the product require more attention. The issue log will
problems. provide information about the obstacles. An issue log
is a reporting tool that tracks errors in the project and
Which two options should the project manager use to prepare organizes the current issues by type and severity to
a response to the project sponsor? (Choose two) prioritize issues. A risk metric tool can identify threats
to your project and put them in order of priority, while
changes and technical debt will have to be considered,
but only after you solve these critical issues.
292
A B C D E F G H I J K L M N
X00267 II.7 P - Predictive A project team lead has challenged the team to minimize C Review the requirements Check the ISO.org website. Investigate the project quality Interview the person who Quality metrics describe project or product attributes
defects and waste in project teamwork. As an initial step, the management plan. metrics. manages quality compliance. and provide details about how the team measures
team proposes to assess the relevant quality standards and quality. The requirements management plan will give
framework. information and project requirements, NOT necessarily
the details about the standards and frameworks about
How can the team do this? the project that is needed. The compliance manager
and ISO.org will have more general information about
293 quality standards.
H00284 II.13 H - Hybrid A project team is set to deliver a project in 12 months. The C The project sponsor would have Less paperwork and The desire for innovation and high Agile does not require acceptance The benefit of agile to this project would have been the
sponsor encourages innovation, and the project has a high been the product owner. documentation are required. risk tolerance are ideal for agile criteria. prioritization of innovation. With a high risk tolerance
risk tolerance. However, 8 months into the project, it is practices. from the start, this is an ideal condition for use of the
plagued with incomplete and failing prototypes. The highly agile life cycle. While it’s true that “acceptance criteria”
capable team is feeling demoralized, and the project manager is not an agile concept, there is a definition of done,
worries whether the deliverable will ever meet the stated which is a similar premise. Whether the owner of the
acceptance criteria. project is called a sponsor or a product owner would
not indicate a greater level of involvement—both roles
are still stakeholders who are focused on value.
How would an adaptive life cycle have helped this project? Though it could be considered a benefit, less
paperwork is not a true benefit to realizing this project’s
294 vision.
A00202 I.10 A – Agile A newly assembled project team is holding a kickoff meeting C Create breakout sessions and Nominate someone to the role of Ask the product owner to lead the The team lead should arrange the This team is in the storming phase, so arguments may
over a weekend. About half of the project team already works assign team members to specific project manager and adopt a session and explain to the team team and contractors in working be normal. However, they need to refocus and come
together; the other team members are contractors. work based on their expertise. hierarchical team structure. what to do. pairs. together sooner rather than later. The team should
collaborate, and at this stage the product owner is best
The company already uses lean and agile approaches. qualified to offer some cohesion.
However, during the meeting, the team members openly
argued about everything—from project goals to the smallest
details.
298
A00211 I.2 A – Agile An agile team welcomes a new team member who is B, D The product owner should Allow the team members to figure Hold a team meeting to find out The team lead should reiterate the Facilitate a face-to-face Agile teams are self-organizing and need to negotiate
unfamiliar with the agile approach. At the weekly demo approach the team member later out their own relationships since from the other team members what ground rules at the next meeting between the new team healthy relationships. The team lead, as an important
meeting, this team member becomes visibly nervous when an in the day to find out the history of this is a self-organizing team. they know about this situation. retrospective meeting, especially member and the operations member of the scrum team, has a key role to play in
operations engineer, who often criticized their previous work, the problem. the engagement protocols and engineer maintaining the team's decorum and maintaining
appears unexpectedly and gives very direct feedback about communication standards. healthy relationships. Given this scenario, it is far too
the prototype. After the meeting, the new team member early to force an intervention. Self-organization is a
leaves the room quickly. process of finding agreeable working relationships.
317
H00320 II.3 H A project team is working in a A Seek expert judgment on the matter and revise the risk Focus on Cancel the Escalate to
remote location, and its operability response maintaining project an
is threatened due to severe supply team organizatio
chain disruption. This risk was coherence nal
listed in the risk register, but the resource
severity of the disruption was not that can
accounted for, so guidance on the help
response is minimal.
318
A00321 II.11 A A project team relies on work with B Do the work themselves Suggest Switch Renegotiat
an overseas contractor. For years, using a vendors e the
this contractor accepted payment fixed price contract
in the team’s currency, but have with rate,
now notified the team’s company economic including a
that after next month, future price percentage
payments must be made in the adjustment contingenc
contractor’s local currency. s contract y for
fluctuating
How can the team deal with this exchange
problem with the least disruption to rates
the team?
319
A B C D E F G H I J K L M N
A00322 II.1 A An agile team is deployed to B Research the market and make a list of available Work with Determine Find out
create a workable solution for technologies. the local the cost of how many
helping a region with contaminated stakeholder a few people are
water supply. They are working s to find out solutions. affected.
with the government, contractors, how much
and local residents to find the right they are
technology to solve the problem. affected.
The product owner is trying to
determine the urgency of the
problem.
320
H00323 III.3 H A project in a university to create a D Create a temporary wiki site for stakeholders to Review all Send a Conduct a
seed bank is complete. It was the provide anonymous feedback. the lessons satisfaction product
first project used in the learned to survey and review
organization to use an agile evaluate then set up meeting
approach. The deliverables were strategic a focus with the
identified by the product owner. alignment. group. concerned
Some of the stakeholders are stakeholder
concerned about quality and have s.
not signed off on the deliverables.
321
A00324 I.8 A A project team has just A Research the risk associated with the low budget for Explore Create a Include a
II.1 successfully completed this work and present this to the stakeholders. with the story map feature that
development of an underwater stakeholder for the addresses
exploration device, which has cost s less risky proposed the risk
more than $US3 billion to deliver. ways to developme approach
The company immediately orders gain nt with the to this
five more units to be delivered, but financial risks clearly work.
with a budget of $US1 billion. The value from accounted
stakeholders' reason for the the first for in the
reduced budget was since the project. work items.
technology has been developed,
the project can be funded for
building costs primarily, with a
small amount for troubleshooting
or development work. The
stakeholders’ priority is to recoup
some financial value from the first
project.
322
A B C D E F G H I J K L M N
A00326 III.2 A A project team is worried about C Look through the customer’s social media accounts Investigate Revise the Find better
product packaging and and perform a qualitative analysis of customer changes in definition of options for
presentation. They receive a lot of attitudes towards packaging. the done packaging.
negative feedback about this external (DoD) with
during iteration demos. business the
environme customer.
How can the team improve their nt related
chances of customer acceptance? to
consumer
attitudes
about
packaging.
323
H00327 I.13 H A company executive who is not a C Ask the product owner to intervene in the conflict. Add this Discuss Use Speed
I.9 key project stakeholder of a executive what B Leas
project has expressed continued to the team should conflict
interest and opinions directly to the as a key happen at manageme
project team. The key stakeholder the next nt
stakeholders are becoming . retrospectiv techniques.
annoyed and perceive the e.
executive to be interfering and
causing unwanted noise, but the
project team finds the executive’s
inputs helpful.
324
H00328 II.3 H An executive in the company who B,D An intractable/war situation, in the Leas conflict model A potential Escalation An
I.9 is not a key project stakeholder of conflict required opportunity
a project has expressed continued
interest in the project and
frequently gives their opinions
directly to the project team. The
key stakeholders are becoming
annoyed and perceive the
executive to be interfering, but the
project team finds the executive’s
inputs helpful.
325
A B C D E F G H I J K L M N
A00329 I.1 A The executives, managers and A Meet with the stakeholders to brainstorm, allow Interview Hold a Since the
I.4 coaches of a professional sports stakeholders to give their opinions and use active the kickoff stakeholder
team often disagree. On a current listening and expert judgment to note areas of stakeholder meeting s can’t
project to create a VIP perks agreement for use in creating user stories. s with all agree,
program, the product owner gets separately stakeholder send them
wildly conflicting inputs from the and then s, present individual
stakeholders ––9 executives, the team the surveys to
managers and coaches. The and conflicting collect
product owner who is new to the product points of data, then
organization asks the team for owner can view and write user
help on making decisions to create make the take notes stories and
the initial product backlog. decisions. on the use voting
whiteboard. techniques
What should the team do? These will to prioritize
become them.
user
stories.
326
A00330 II.3 A An agile project team is working A Project risk is everyone’s responsibility, and the team The risk If the team Risk
on improvements to the user should not have skipped the risk assessment. assessmen is correct, assessmen
experience (UX) for an online t will be the product t is the
newspaper. The team thinks this is completed, owner is product
a fairly low-risk project, so they so wasting owner’s
forgo a risk assessment and start everything time and responsibili
working. The product owner is fine. resources. ty.
disagrees and commissions a risk
assessment.
327
A00331 I.6 A A company initiates a project to B,C,E Benefits management plan Business Initial risk Benefit-
I.8 replace aging infrastructure by case assessmen cost
I.10 adopting an emerging green t analysis
technology. The team is forming
and having initial conversations
about how to approach the project.
328
A B C D E F G H I J K L M N
A00332 II.7 A A tech startup has four projects B All of these projects contain the same risk and are These The project The quality
II.3 authorized and running: subject to the same quality standards because they projects all using requiremen
are in the same organization. contain experiment ts for
1. Customer experience (CX) app inherent al technology
development with executive risk and technology depend on
stakeholders require has the external
2. Third-party app development unique highest regulations.
with new vendors quality level of risk So the
3. Project with global team metrics. and quality multilingual
members who speak six standards. project
languages team
4. Game development using presents
experimental technology the lowest
risk.
Which statement about risk and
quality is correct?
329