CBA Lecture 1
CBA Lecture 1
Levan Pavlenishvili
ISET
2021
CBA will show you how your knowledge in economics is applied in practice.
Assessment:
Main Textbook:
[BGVW] Boardman, Anthony E., David H. Greenberg, Aidan R. Vining,
and David L. Weimer. Cost-Benefit Analysis: Concepts and Practice. 5th
ed., (Upper Saddle River, NJ: Pearson Education, 2018).
Group Project:
Office Hours:
NB = B − C
where, B represents benefits, C represents costs;
Criticism
P.S. Some practitioners might disagree about ways to cheat, after all:
There are three main types of CBA analysis based on the time, when it is
conducted.
At this step analyst should state why analysis is being conducted. Some
of the questions, that should be answers are:
For example, a hydro power can be built at: different location, with
different size of the dam, different type of the dam, different installed
capacity, different number of generation units etc.
Levan Pavlenishvili (ISET) Lecture 1 - Introduction to CBA 2021 15 / 29
The Basic Steps of CBA
Sometimes, ’status quo’ could not be kept and an action must be taken.
In such situation common mistake is to think that ’status quo’ in not an
option.
Term impact is used to refer to both inputs (resources, costs) and outputs
(benefits, costs).
One could construct impact matrix to formalize all impacts that are
included in the analysis.
It is important to try to include all impact, however for some, data might
not be available, or it might be impossible, very hard, or morally wrong to
monetise impacts (for example life saved).
Many projects, or policies have impacts that accrue over years. For such
projects you need to have money representing same value over time, as
well as its own opportunity cost - calculate present value (PV).
n
X Bt
PV (B) =
(1 + r )t
t=0
n
X Ct
PV (C ) =
(1 + r )t
t=0
NPV = PV (B) − PV (C )
Make a recommendation
After calculating NPV you might have a situation when one alternative
has higher NPV and higher risk. In this case:
You could suggest preferred alternative by calculating expected NPV
(considering the probability of risk, use distribution of NPV to
calculate its expected value)
Point it out as a trade-off and let decision makers do their job
One could use internal rate of return (IRR) or benefit-cost ratio
indicators as a decision rule
But! Have we actually evaluated an optimal alternative i.e. maximised
NPV at all?
Origins of CBA starts from 17th century England, where argument was
about management of epidemic.