0% found this document useful (0 votes)
60 views4 pages

Defect List PMI Lombok Office

The document is a defect list check for a construction project of a PMI Lombok Tengah office building in Central Lombok, Indonesia in 2021. It lists the status (approved or not approved) of over 100 line items across 12 sections covering preparation work, land work, foundations, concrete work, brick walls, ceilings, roofing, doors/windows, flooring, painting, sanitation, electrical work, electronic work, and CCTV work. The defect list is intended to track the approval status of various construction elements and ensure all work meets standards before completion.

Uploaded by

Corleone
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views4 pages

Defect List PMI Lombok Office

The document is a defect list check for a construction project of a PMI Lombok Tengah office building in Central Lombok, Indonesia in 2021. It lists the status (approved or not approved) of over 100 line items across 12 sections covering preparation work, land work, foundations, concrete work, brick walls, ceilings, roofing, doors/windows, flooring, painting, sanitation, electrical work, electronic work, and CCTV work. The defect list is intended to track the approval status of various construction elements and ensure all work meets standards before completion.

Uploaded by

Corleone
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

DEFECT LIST CHECK

PROJECT : CONSTRUCTION OF PMI LOMBOK TENGAH OFFICE


LOCATION : CENTRAL LOMBOK
YEAR : 2021

STATUS REPORT
NO REMARK
APPROVED NOT APPROVED
I PREPARATION WORK
1 Setting out/stake out
2 Site Office Rent
3 Administration and Documentation
4 Assistive Work Tools
5 Security Fence
6 Application of Occupational Health and Safety
7 Land Clearing and the Remnants of Demolition
II LAND WORK
1 Foot Plate Foundation Soil Excavation
2 Split Stone Foundation Soil Excavation
3 Foot Plate Foundation Re-Embankments
4 Split Stone Foundation Re-Embankments
5 Sand Embankment Under the Foundation of Split Stone
6 Sand Embankment Under Foot Plate Foundation
7 Embankment Elevation 20 cm 1st Floor Building
III SPLIT STONE FOUNDATION WORK
1 Aanstamping
2 Split Stone foundation
3 Split Stone Rolag
IV REINFORCED CONCRETE WORK
1 Quality of Concrete Structure K250
2 Quality of Non-Structural Concrete K175
FIRST FLOOR STRUCTURE
a FOUNDATION
1 Lean Concrete K100
2 Foot Plate Foundation P1
Concrete K250
Formwork
Reinforcement
3 Foot Plate Foundation P2
Concrete K250
Formwork
Reinforcement
b. TIE-BEAM
1 Practical Tie Beam 12x20
2 Structural Tie Beam 15x35
Concrete K250
Formwork
Reinforcement
c. COLUMN
1 Practical Column KP 12x12
2 Structural Column Type K1 25x25
Concrete K250
Formwork
Reinforcement
3 CONCRETE TABLE (Homogeneous tile finishing)
Concrete K175
Formwork
Reinforcement
SECOND FLOOR CONCRETE STRUCTURE
Coloumn anchorage
1 Structural Coloumn Type K1 30x30
Concrete K250
Formwork
Reinforcement
2 Structural Coloumn Type KS 30x30
Concrete K175
Formwork
Reinforcement
BEAMS
1 Practical Ring Balk and Lintel Beams
2 Beam Structure Type B1 25x30
Concrete K250
Formwork
Reinforcement
3 Beam Structure Type BK1 25x30
Concrete K250
Formwork
Reinforcement
4 Listplank beam LPB
Concrete K250
Formwork
Reinforcement
PLATE
1 Concrete Roof Plate thickness = 12 cm
Concrete K250
Formwork
Reinforcement
V BRICKWALL AND PLASTERING WORK
First floor
1 Brickwall Instalation
2 Plastering
3 Trassram (Impermable) Brickwall instalation
4 Acian (smooth surface coating)
# Internal
STATUS REPORT
NO REMARK
APPROVED NOT APPROVED
VI CEILLING WORK
1 Gypsumboard Ceiling 9mm rk Hollow Galvanis 4/4 & 2/4 (0,4mm)
2 Kalsiboard Ceiling 4,5mm rk Hollow Galvanis 4/4 & 2/4 (0,4mm)
3 Drop Ciliing; Gypsumboard Ceiling 9mm rk Hollow Galvanis 4/4 & 2/4 (0,4mm)
4 Steel coating for steeldeck
5 U-shape alumium List (shadow line)
VII ROOF AND ROOF FRAME WORK
Frame work
1 Light gauge steel framing system
Roof covering
2 Galvalume BMT 0,35 metal deck
3 Galvalume Rooftop Ridge
4 Kalsiplank for Lisplank of roof Edge
VIII DOOR WINDOW AND PARTITION WALL WORK
1 Door frame, Door, and window
Type :
PU
PJ1
PJ2
P1
P2
P3
P4
P5
P6
P7
P7'
J1
J2
J2'
BV1
BV2
BV3
2 Partition wall
Type :
PR1
PR2
PR3
PR4
PR5
PR6
PR7
PR8
PR9
PR10
PR11
PR12
PR13
PR14
IX FLOOR AND WALL COATING WORK
1 Sand Embankment Under the lean concrete, thicness 5cm
2 Lean concrete thicness 5cm under finishing cover
3 Homogeneous Tile 60x60 polished for Floor cover finshing (inc. Concrete table)
4 Homogeneous Tile 60x60 Unpolished
5 Homogeneous Tile 30x60 Unpolished with stepnosing grid
6 Ceramic tile 30x30 cm unpolished for restroom
7 Lean concrete thicness 10cm around the building
8 Acian for top surface lean conrete
9 Wall ceramic tile 30x60 cm for rest room
10 Alumium hairline Plint, height = 10 cm
11 Homogeneous Tile Plint 10x60
12 Alumium Composte Panel PVDF Type, Th 4mm material for cutting laser ornamen
included suporting frame
13 Finishing stone slabs material
X PAINTING WORK
1 Interior Wall Paint Work
2 Weathershield Exterior Wall Paint Work
3 Ceilling Paint Work
4 Waterproofing coating on lisplank
XI SANITATION WORK
1 Stainless steel water faucet ex TOTO T23BQ13N
2 Washing faucet ex TOTO TX609K
3 Stainless steel Floor drain ex.TOTO TX1CV2
4 Jet Flush ex TOTO (JW) tipe TX403SMCRB inc stop faucet
5 Close Coupled Toilet + Accessories Installed
6 Squating Toilet
7 Counter lavatory / Wastafel ex TOTO (inc. Acesories )
8 Kitchen zink stainless steel material
9 Tissue Holder (TH) tipe TX703M3AV1
10 Wall mirror thckn 5mm dimension 80x100cm, bevel edge
11 Stainless steel handgrip for diffable
XII OTHER WORK
1 Ramp Railling; Stainless steel pipe and Acrylic Panel materials
2 Ground Water Tank
3 Water tower Structure
4 Yard environment and entrance pavement
5 Decker plate work
6 Drainage Channel
7 Infiltration well (as point XII.9 )
8 Septic Tank
# Internal
STATUS REPORT
NO REMARK
APPROVED NOT APPROVED
9 Infiltration well (concrete pipe material dia 100cm)
10 The Building Marks (Top facade )
11 Signage
12 Flagpole instalation
13 Hand washing basin
Trash can
A ELECTRICAL WORK
a Feeder cable and cable tray instalation
1 NYY 4x16mm2 + BCC 6mm2 cables fromi MDP Panel to KWH Meter PLN
2 NYY 3x4mm2 cables in conduit PVC AW 20 mm pipe from MDP Panel
To Control Panel of well pump
3 Provision and Installation of Grounding System
includedds Grounding Wells, Grounding Connectors and Other Assistive Materials
a. SDB Grounding BCC Cable 10 mm2
4 Cable Tray instalation, dimension 20 x 10 cm
5 Addition Electric Power PLN suply
b Low Voltage Panel Work
1 MDP Panel
2 DeepWeel Pump and Transfer Pump Control Panel
c Lighting Installation and Electric Socket Work
1 LED lamp Bulb type 19 Watt, E27 + fitting
2 LED lamp Bulb type 14,5 Watt, E27 + fitting
3 LED lamp Bulb type 12 Watt, E27 + fitting
4 LED lamp Bulb type 8 Watt, E27 + fitting
5 LED lamp Strip Type on Drop Ceiling 3,6 w/m
6 LED lamp Strip type in Signage 3,6 w/m (2 unit)
7 Electric Wall Socket, General +40
8 Electric Wall Socket, General +150
9 Electric Ceiling Socket General
10 Electric Wall Socket,UPS+40
11 Electric Wall Socket,UPS+150
12 Floor Sochet (Electric Socket+ Telephone outlet + data outlet )
13 Single Switch
14 Double Switch
15 Electrical Installation; with NYM Cable Point 2x2.5mm2 in 20mm conduit pipe
17 Instalation of electrical socket; NYM 3x2,5mm2 cable in conduit pipe 20mm
18 Instalation of exhaust fan ; NYM 3x2,5mm2 cable in conduit pipe 20mm
d Lightning Rod Instalation
1 Lightning rod of ef type, non radioaktif R.85 m+ pole 3 m+ suporting material
2 Cable type NYA 50mm2
3 Earthing Pit & Grounding Electrode
4 Permits to Disnaker
5 Assistive Equipments
B ELECTRONICAL WORK
a Telephone Work
Main Equipment
1 TDA PABX/STLO capacity:
4 Channel PT. Telkom
16 Extension channel
2 Operator Console
3 Surge Aresster
4 Jelly Fillet armoured cable from PT. telkom
5 Permits to Related agencies
6 MDF 20 Pair
Telephone instalation
1 Telephone wall outlet
2 Instalation of telephone wiring, Cable ITC 2x2x0,6 mm2
b Data Work
Main Equipment
1 Server
2 Switch Hub 16 Port
3 Surge Aresster
4 Router 8 Port
Data Installation
1 Data Outlet
2 Wifi Ceiling Type
3 Data wiring Instalation Cable UTP cat 6
c CCTV Work
Main Equipment
1 DVR 16 Channel with HDD 4 TB
2 Monitor LED 32"
CCTV Installation
1 CCTV IP Type Dome, HD Quality, 1080P, POE
2 Instalation of CCTV wiring, coaxial cable RG 11
3 Instalation of CCTV power, NYM 2 x 2,5 in Conduit High Impact 20 mm
d Fire Extinguiser Installation
C MECHANICAL AND PLUMBING WORK
a AIR CONDITION (AC) INSTALATION
1 Electrical socket
2 AC Wiring instalation Cable NYM 3x2,5mm2 in conduite pipe dia 20mm
3 Drain Pipe, PVC ø 3/4"
4 Ceiling Exhaust Fan 100 CFM
5 Wall Fan 200 CFM
6 PVC pipe dia. 4" AW + assesories for cooper tube conduit sparing
7 Exhaust Grill 6"x8"
8 Instalasi Wall Fan kabel NYM 3x2,5mm2 dalam pipa konduite 20mm
b Clean Water Instalation
- Clean Water Installation Source from PDAM
1 Clean Water Installation Source from PDAM outlet to ground water tank
2 Clean water pipe installation for emergency tank fillers
3 Soil excavation for pipe line; Widht 40cm depth 60cm and re embankment
# Internal
STATUS REPORT
NO REMARK
APPROVED NOT APPROVED
4 Valves
5 Permit for installation of PDAM clean water source
- Clean water instalation by shallow wells source (depth 40m)
1 Making shallow wells inc. Submersible pump, Pump panel, piping, power cable etc ,
Piping Instalation
1 Ground Water Tank cap. 4 M3
2 Tansfer pump distribute clean water from Ground Water Tank To Water Tower Tank :
3 Header pipe for Transfer pump
4 Piping instalation from transfer pump to water tower tank
5 Valves
Water tower tank instalation
1 Instalation services for Profil Tank 2000 liter (tanki by user) + pedestal + acc
2 Header Pipe PPR-PN 10 dia Ø 4"
3 Accessories + Fitting
4 Gate Valve Ø 1"
5 Drain Pipe PVC AW Ø 1"
6 Accessories and Assistive Equipments
Clean Water Instalation
In Building
1 Clean water piping, PPR-PN 10 pipe type:
2 Gate valve
Garden Faucet
1 Clean water piping, PPR-PN 10 pipe type:
c Dirty Water, Used Water Piping Installation Work
1 Septic Tank 2m3
2 Infiltration well (as point XII.9 )
Dirty water, Used water, and ventilation piping instalation, PVC class AW (10 kg/cm2)
3
type
4 Floor Drain 2"

Prepared by, Acknowlwdge by,

Donny Pansa ____________________


IFRC Sr. Shelter Officer PT IFOS Satria Mahkota