0% found this document useful (0 votes)
14 views

Lecture 7 Basements Single Level

This document discusses different methods of basement construction, including precast concrete panel systems and cast in-situ reinforced concrete walls. It provides details on installing precast concrete basement walls using a panel system and hit-and-miss excavation approach. It also discusses waterproofing and drainage considerations, including the use of strip drains, cord drains, no-fines concrete, and waterstops at construction joints.

Uploaded by

kriti shukla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views

Lecture 7 Basements Single Level

This document discusses different methods of basement construction, including precast concrete panel systems and cast in-situ reinforced concrete walls. It provides details on installing precast concrete basement walls using a panel system and hit-and-miss excavation approach. It also discusses waterproofing and drainage considerations, including the use of strip drains, cord drains, no-fines concrete, and waterstops at construction joints.

Uploaded by

kriti shukla
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 49

Semester 2

ABPL 90393 Steel and Composite


Construction Systems

Lecture 7
Basement Construction
(Single level)

All construction site images UNO Source: Peter Ashford 1


• precast concrete panel • Technical information
basement case study extracted from the following
• reinforced concrete wall manufacturer’s catalogues:
basement •
• Bored pier and shotcrete infill – Corkjoint www.corkjoint.com
panels – Parchem www.parchem.com.au
– CETCO www.cetco.com
• waterproofing solutions
– Nylex
• drainage

2
Case study

Precast concrete panels used for a single level basement, 2 temporary props per panel required 3
Case study

Steel shutters for worker safety and cast insitu concrete walls built in sections called “Drives” 4
Describe the drawing annotations
5
Single level precast concrete panel basement
precast concrete panel basement wall installation
1. Bulk excavation as per drawing in previous slide

2. Excavate vertical slots at locations marked 1 for a length equal to the


precast panel width (1.5 or 3.0m)

3. Excavate for strip footing, place reinforcement and panel dowel bars into
footing and cast footing. Provide bent out bars from ends of footing to
enable lapping to adjoining footing.

4. Place precast panels at locations marked 1, connect props from panel to


temporary footings. Precast panels to have the cordrain and the strip
drain adhered to the back of the panel prior to removal of the angle
restraint.

5. Grout in panel dowels

6. Pour no-fines concrete behind the wall

7. Repeat 1 to 7 for locations marked 2, then 3 then 4. 6


1

2
Single level
precast concrete
3 panel basement
Overall Construction sequence

5
7
Single level precast
concrete panel basement

Example of Drive No.1


on a hit and miss basis

Note how closely spaced the


Drives are in the top RHS due to
the adjoining building on the
boundary line.

8
Single level precast
concrete panel basement

Example of Drive No.1


on a hit and miss basis

Once these precast walls are


Installed, the soil is retained
from collapse and Drive No.2
can be commenced.

9
Single level precast
concrete panel basement

Example of Drive No.1


on a hit and miss basis

Once these precast walls are


Installed, the soil is retained
from collapse and Drive No.2
can be commenced.

Once No. 2 walls are installed


Drive No.3 can be commenced

10
Image shows adjoining building brick wall, rendered,
The earth batter, footing poured with starter bars and
PVC packers, strip drain at base of wall, wilseal on
edge of RHS precast panel, overlapping edge of the
sheet drain at the back of the panel and precast panel
props.
Pin connections top and bottom of wall, therefor props
required.

11
All work by hand inside the steel shutter protection: Including footing excavation, reinforcement incl starter bars,
strip drain installation and protective cover and pouring concrete. This section of wall is cast insitu concrete. 12
precast concrete panel basement

Options?

13
precast concrete panel basement

14
Case study

Completed precast concrete panel installation. Note the internal pad footings have been poured with column starter
bars in place, the bulk of the basement slab has been poured prior to the first suspended slab. Why? 15
Drainage systems
Stripdrain
• Stripdrain is a geotextile filter fabric around a
deep formed plastic core
• available in widths of 100mm, 200mm, up to
900mm. Standard thickness 40mm.
• Stripdrain is lightweight, flexible and easy
to join simply by overlapping core and
taping geotextile

The width of the strip drain and the number required


depend on the expected volume of water behind the wall,
which is determined by a geotechnical report
Cordrain
Coredrain is a geocomposite vertical
drainage blanket, which consists of a
plastic cuspated inner core, fitted with a
heat bonded, non woven geotextile filter
fabric bonded on one side only.
• Cordrain effectively reduces hydrostatic
pressure behind walls
• Cordrain typically eliminates the need
for aggregate or sand backfill

Cordrain sheets attached to the back of the


precastwalls prior to erection and no-fines
concrete backfill (example next 2 slides)
Waterproofing and panel joint detailing

Coredrain at the back of the wall, no-fines concrete backfill as drainage, and partially completed panel to panel 19
corner connection. Wilseal on exterior, backing rod and sealant on inside face, grout infill still to be done.
Waterproofing Solutions:

Example image of No-fines concrete


as drainage filter behind the back of a wall

What is no-fines concrete?


Concrete without any fines, that is NO SAND.
Contains cement and aggregate only, therefore
very porous and acts like a drain but is still strong enough
to provide lateral support to the retained soil.
precast concrete panel basement
Sealing the joints between
the precast panels

If the “Wilseal” is compressed


from 30mm to 15mm, it is
nearly waterproof
21
5 barriers to prevent water entry
Single level basement drainage plan

Note the location of exterior and interior drains & pit locations
22
Single level basement drainage plan

Discuss:

External drains
Internal drains
Spoon drains
Pits and pumps

23
Cast insitu reinforced concrete basement

• reinforced concrete basement walls require pour joints either vertical or


horizontal that must be sealed to limit/prevent water penetration when the
concrete shrinks.

Torched on bituminous sheet tanking, overlapped at joints and protected with black corflute board to prevent
the sheet tanking being punctured during backfilling with crushed rock 24
Waterproofing

Why Consider Waterproofing?

• Leakage is the most common problem


and waterproofing should not be
overlooked.

• The concrete substructure cannot


be constructed in one piece and
therefore contains construction
joints which can act as a water
path. (see next slide)

• What about different levels of


water‐ resistance? Does the
basement need to be water
resistant OR waterproof?

25
example cast insitu walls, joint layout

Floor Plan

It is not possible to cast all the wall perimeter at once


Careful compaction and good quality concrete essential
to achieve any level of water tightness.
All joints need some level of waterproofing
26
Cast insitu waterproofing solutions:

• Corkjoint Waterstops
– Sure‐Stop PVC Waterstops
– Sure‐Stop Rubber Waterstop
– Sure‐Stop Copper Waterstop PVC waterstops

– SUPERSWELL
– HYDROTITE
– Waterproof injection system
• Geotextile Fabrics
• Bentonite Geotextile WP System
• Nylex Drainage Solutions
Hydrotite
– Stripdrain
– Cordrain
– Plazadeck Drain
– Root Barrier
Sure‐Stop PVC Waterstops

• They are specially designed for use


throughout the construction industry in
water retaining and water excluding
structures where a positive seal is
required for poured in‐situ concrete
expansion, construction and contraction
joints.

• Waterstops are designed to allow for


expansion and other movements that
can cause joints to open and close.

• The efficiency of any waterstop is very


dependent on good workmanship and
on full compaction of the concrete!
Versatility of Sure‐Stop waterstops

For walls or basement slabs

F
Sure‐Stop PVC Waterstops

Waterstops being used in joint between the tunnel base and the side walls, cruciforms prefabricated
in factory with heat plastic welding to ensure watertightness.
Sure‐Stop PVC Waterstops

These waterstops are flat on one side for fixing


directly on to the formwork

31
Superswell/Waterstop‐RX

• Both products are sealing compounds which


expand in a controlled fashion when exposed to
moisture, forming a positive seal in concrete joints
• The key is their 75% sodium bentonite
content which provides superior expansion to
seal and fill small voids.
• Allows concrete to gain strength before expansion
• Unaffected by repeated wet and dry cycles
• Seals cracks and around penetrations

All images sourced


from the manufacturer
Superswell/Waterstop‐RX
• They are ideal for use in horizontal and
vertical construction joints
• Needs 50mm clear cover to the face of
the concrete
• Recommended for use in non‐movement joints
(reinforcement is continuous)

All images sourced


from the manufacturer
Superswell/Waterstop‐RX
Hydrotite
• Hydrotite expands as it absorbs
water and fills up concrete joint
gaps conforming to the gap
variation, ensuring excellent sealing
• Unique combination of expanding
hydrophilic material and non-
expanding chloroprene rubber
• expands in a controlled fashion by
approximately eight times by
volume in the presence of moisture
to create a compression seal within
joints which shuts out the water
path
• seals horizontal and vertical
construction joints
• returns to its original size if there is
no more water or moisture present

Hydrotite is less flexible than Waterstop RX so can only be used on flat surfaces 35
Hydrotite

• Hydrotite
• some leakage may occur before
hydrotite re-expands fully
• repeated wet and dry cycling of
this nature does not effect the
functioning of Hydrotite
• self adhesive backing which makes
installation easier and lower
construction time and cost
• suitable for low movement joints

e.g.: Vertical Thru Pipe


Construction tie penetrations Horizontal and vertical joints
joint holes

36
Hydrotite

37
bituminous tanking
• Bitumen is a mixed substance made up of organic liquids that are highly
sticky, viscous, and waterproof.
• Bitumen tanking membranes are usually self bonding and can be used in
vertical or horizontal applications for tanking below ground structures,
subways, and retaining walls.
• Bitumen primer can also be sprayed or applied on a surface with a
brush/roller.

A roll of bitumen tanking membrane Bitumen primer applied to concrete blockwork, ready for
pressing onto surface and heat torching for adhesion
bituminous tanking

39
Bituminous tanking covered with black protective core flute board
bituminous tanking

40
Bituminous tanking can also be applied using a brush with 2-3 coats required, still requires coreflute boards
Bored pier and shotcrete infill panels
MSD building

Exposed bored piers, capping beam with strip drains, starter bars epoxied in and ground anchors installed
Bored pier and shotcrete infill panels

There are horizontal and vertical joints in the shotcrete infill panel walls. All have the potential to leak. 42
Joints can be sealed for example with Waterstop RX if required
Bored pier and shotcrete
infill panels

Leakage through:

Horizontal joints in the shotcrete


between the capping beam and the
shotcrete infill panel

Vertical joint between the shotcrete and


the bored pier

Possible cracks in the shotcrete infill panel

Note spoon drain that is connected to the


SWD and pits

43
Drainage pits

Cast insitu concrete pits including pump pit, future pit access is by lifting the open grate covers 44
Storm water drains and pits

Note subfloor drainage pipes and pits, strip drains in the centre of each infill panel and vertical joints 45
between piers and shotcrete panels
Strip drain connection

Connection of the strip drain behind wall connected to internal subfloor drainage system 46
MSD building
north west corner
showing strip drains
connected to storm
water drains

47
MSD building
North west corner
Submersible pump

48
MSD building
north west corner
Pump details

49

You might also like