Lecture 7 Basements Single Level
Lecture 7 Basements Single Level
Lecture 7
Basement Construction
(Single level)
2
Case study
Precast concrete panels used for a single level basement, 2 temporary props per panel required 3
Case study
Steel shutters for worker safety and cast insitu concrete walls built in sections called “Drives” 4
Describe the drawing annotations
5
Single level precast concrete panel basement
precast concrete panel basement wall installation
1. Bulk excavation as per drawing in previous slide
3. Excavate for strip footing, place reinforcement and panel dowel bars into
footing and cast footing. Provide bent out bars from ends of footing to
enable lapping to adjoining footing.
2
Single level
precast concrete
3 panel basement
Overall Construction sequence
5
7
Single level precast
concrete panel basement
8
Single level precast
concrete panel basement
9
Single level precast
concrete panel basement
10
Image shows adjoining building brick wall, rendered,
The earth batter, footing poured with starter bars and
PVC packers, strip drain at base of wall, wilseal on
edge of RHS precast panel, overlapping edge of the
sheet drain at the back of the panel and precast panel
props.
Pin connections top and bottom of wall, therefor props
required.
11
All work by hand inside the steel shutter protection: Including footing excavation, reinforcement incl starter bars,
strip drain installation and protective cover and pouring concrete. This section of wall is cast insitu concrete. 12
precast concrete panel basement
Options?
13
precast concrete panel basement
14
Case study
Completed precast concrete panel installation. Note the internal pad footings have been poured with column starter
bars in place, the bulk of the basement slab has been poured prior to the first suspended slab. Why? 15
Drainage systems
Stripdrain
• Stripdrain is a geotextile filter fabric around a
deep formed plastic core
• available in widths of 100mm, 200mm, up to
900mm. Standard thickness 40mm.
• Stripdrain is lightweight, flexible and easy
to join simply by overlapping core and
taping geotextile
Coredrain at the back of the wall, no-fines concrete backfill as drainage, and partially completed panel to panel 19
corner connection. Wilseal on exterior, backing rod and sealant on inside face, grout infill still to be done.
Waterproofing Solutions:
Note the location of exterior and interior drains & pit locations
22
Single level basement drainage plan
Discuss:
External drains
Internal drains
Spoon drains
Pits and pumps
23
Cast insitu reinforced concrete basement
Torched on bituminous sheet tanking, overlapped at joints and protected with black corflute board to prevent
the sheet tanking being punctured during backfilling with crushed rock 24
Waterproofing
25
example cast insitu walls, joint layout
Floor Plan
• Corkjoint Waterstops
– Sure‐Stop PVC Waterstops
– Sure‐Stop Rubber Waterstop
– Sure‐Stop Copper Waterstop PVC waterstops
– SUPERSWELL
– HYDROTITE
– Waterproof injection system
• Geotextile Fabrics
• Bentonite Geotextile WP System
• Nylex Drainage Solutions
Hydrotite
– Stripdrain
– Cordrain
– Plazadeck Drain
– Root Barrier
Sure‐Stop PVC Waterstops
F
Sure‐Stop PVC Waterstops
Waterstops being used in joint between the tunnel base and the side walls, cruciforms prefabricated
in factory with heat plastic welding to ensure watertightness.
Sure‐Stop PVC Waterstops
31
Superswell/Waterstop‐RX
Hydrotite is less flexible than Waterstop RX so can only be used on flat surfaces 35
Hydrotite
• Hydrotite
• some leakage may occur before
hydrotite re-expands fully
• repeated wet and dry cycling of
this nature does not effect the
functioning of Hydrotite
• self adhesive backing which makes
installation easier and lower
construction time and cost
• suitable for low movement joints
36
Hydrotite
37
bituminous tanking
• Bitumen is a mixed substance made up of organic liquids that are highly
sticky, viscous, and waterproof.
• Bitumen tanking membranes are usually self bonding and can be used in
vertical or horizontal applications for tanking below ground structures,
subways, and retaining walls.
• Bitumen primer can also be sprayed or applied on a surface with a
brush/roller.
A roll of bitumen tanking membrane Bitumen primer applied to concrete blockwork, ready for
pressing onto surface and heat torching for adhesion
bituminous tanking
39
Bituminous tanking covered with black protective core flute board
bituminous tanking
40
Bituminous tanking can also be applied using a brush with 2-3 coats required, still requires coreflute boards
Bored pier and shotcrete infill panels
MSD building
Exposed bored piers, capping beam with strip drains, starter bars epoxied in and ground anchors installed
Bored pier and shotcrete infill panels
There are horizontal and vertical joints in the shotcrete infill panel walls. All have the potential to leak. 42
Joints can be sealed for example with Waterstop RX if required
Bored pier and shotcrete
infill panels
Leakage through:
43
Drainage pits
Cast insitu concrete pits including pump pit, future pit access is by lifting the open grate covers 44
Storm water drains and pits
Note subfloor drainage pipes and pits, strip drains in the centre of each infill panel and vertical joints 45
between piers and shotcrete panels
Strip drain connection
Connection of the strip drain behind wall connected to internal subfloor drainage system 46
MSD building
north west corner
showing strip drains
connected to storm
water drains
47
MSD building
North west corner
Submersible pump
48
MSD building
north west corner
Pump details
49