Concrete Test Report
Concrete Test Report
*Project DESIGN AND BUILD AND NEGOTIATED - MEMBINA JAMBATAN NG. LASI, JULAU
Date Issued 08/09/2023
Date Tested 08/09/2023
Request Form No. 2023/CRL/CC/01251
Name of person making cubes Romeano
11/08/2023 21:00 Condition of
#Date, time and place of
Test Report Ref. 2023/CRL/CC/01251/CT/01-2 PM, Sarikei, specimen when Satisfactory
sampling
Julau received
*Number and norminal size of 6 units, Date of receipt of
*Client Frasser Anak George Michael 14/08/2023
specimens (mm) 150x150x150 specimen
*Method of compaction (hand or
Avg. lab
vibration) including type of Hand 27
*Sample Covering temperature, °C
PWD/CRL/LAB/04/2023/PT.03/56 equipment used
Ref.
Avg. lab
*Condition of curing and storage Water 71.5
humidity, %
Remarks : -
Page 1 of 2
APPROVED SIGNATORY
(MUHAMAD AQMAL HAZIZI BIN HILL
JUNAIDI)
This Test Report remains the property of the JKR Laboratory; no corrections / amendments are to be made and it shall not be reproduced in part without prior
Note
written consent from the Lab Management
The Lab is not responsible for the correctness of sampling/ preparation and curing of cubes. Cubes information (including grade and casting date) are provided by
customer. This test results applies the the sample as received only
Disclaimer
i) * This information is provided by the customer
ii) # This information is provided by the customer and can have an significant effect on the test results
Page 2 of 2