0% found this document useful (0 votes)
27 views

Ch-2project Cycle

The document discusses various models of the project cycle or life cycle. It begins by defining the project cycle as the different stages a project passes through from inception to implementation. It then describes several common project cycle models including the Baum Cycle adopted by the World Bank and the UNIDO model. The Baum Cycle involves 6 stages: identification, preparation, appraisal and selection, implementation and supervision, and evaluation. The UNIDO model involves 3 phases divided into various stages covering pre-investment, investment, and operational phases of a project.

Uploaded by

melkamu gemeda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views

Ch-2project Cycle

The document discusses various models of the project cycle or life cycle. It begins by defining the project cycle as the different stages a project passes through from inception to implementation. It then describes several common project cycle models including the Baum Cycle adopted by the World Bank and the UNIDO model. The Baum Cycle involves 6 stages: identification, preparation, appraisal and selection, implementation and supervision, and evaluation. The UNIDO model involves 3 phases divided into various stages covering pre-investment, investment, and operational phases of a project.

Uploaded by

melkamu gemeda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

Chapter Two: Project Cycle

The different stages/phases through which a project passes is called the project life cycle.

The main features and elements of this process are information gathering, analysis and decision
making. The project cycle consist of various stages in which each stage, not only is grown out of
the preceding ones, but also leads into the subsequent ones.

What is project cycle?

Project Cycle: Is the various stage through which project proceed from inception to
implementation.

1. It is a stage which project advance from inception to maturity stage.

2. The Project Analysis or appraisal is done in stage (Cycle) and should provide information
on:

Administrative feasibility, marketing, and technical appraisal;


Financial capability;
Expected economic contributions,
Social objectives .
Each stage follows the proceeding one and leads to the next.

 These different phases are identified by different institutions and authors. Some of the
phases as identified by different authors are the following.

The Baum Cycle (World Bank Procedures) (World Bank Project Cycle)

 Baum (1970) model is the first basic model of a project cycle which has been adopted by
the World Bank.

 According to this model a project cycle consists of the following six stages.

 Identification

 Preparation

 Appraisal and Selection

 Implementation and supervision

 Evaluation

1|Page
What does the World Bank do?

 Lending for development projects.

 The Bank's main business is to lend for specific projects, carefully selected and prepared,
thoroughly appraised, closely supervised, and systematically evaluated.

A. IDENTIFICATION

 The first phase of the cycle is concerned with identifying projects that have a high
priority, that appear suitable for Bank support, and that the Bank, the government, and the
borrower are interested in considering earlier years, project identification as done,
largely in response to proposals by governments and borrowers.

 Over the years, the Bank has encouraged and helped borrowing countries to develop their
own planning capabilities and has also strengthened its own methods of project
generation.

 Economic and sector analyses carried out by the Bank provide a framework for
evaluating national and sectoral policies and problems and an understanding of the
development potential of the country.

 They also assess a country's "creditworthiness“ for Bank

 This analysis provides the basis for a continuing dialogue between the Bank and a
country on an appropriate development strategy, including policy and institutional
changes for the economy as a whole and for its major sectors.

 It is then possible to identify projects that fit into and support a coherent development
strategy, that meet sectoral objectives, and that both the government and the Bank
consider suitable.

B. PREPARATION

 After a project has been incorporated into the lending program, it enters the project
pipeline, and an extensive period - normally one or two years - of close collaboration
between the Bank and the eventual borrower begins.

 A "project brief” is prepared for each project, describing its objectives, identifying
principal issues, and establishing the timetable for its further processing.

 It is difficult to generalize about the preparation phase because of the variables that
abound: the nature of the project, the experience and capability of the borrower, the
knowledge currently available, the sources and availability of financing for preparation,

2|Page
and the nature of the relationships between the Bank, the government, co-financers, and
other donors that may be involved in the sector or project.

TECHNICAL ANALYSIS

 The Bank has to ensure that projects are soundly designed, appropriately engineered, and
follow accepted agronomic, educational, or other standards.

 The appraisal mission looks into technical alternatives considered, solutions proposed,
and expected results.

INSTITUTIONAL ANALYSIS

 “Institution building" has become perhaps the most important purpose of Bank lending.

 The creation of a sound and viable local "institution”,

 It covers the borrowing entity itself, its organization, management, staffing, policies, and
procedures, and also the whole array of government policies that conditions the
environment in which the institution operates.

ECONOMIC ANALYSIS

 Through cost-benefit analysis of alternative, project designs, the one that contributes
most to the development objectives of the country may be selected.

 This analysis is normally done in successive stages during project preparation, but
appraisal is the point at which the final review and assessment are made.

 Through cost-benefit analysis of alternative, project designs, the one that contributes
most to the development objectives of the country may be selected.

 This analysis is normally done in successive stages during project preparation, but
appraisal is the point at which the final review and assessment are made.

FINANCIAL ANALYSIS

 Financial appraisal has several purposes. One is to ensure that there are sufficient funds
to cover the costs of implementing the project.

 The Bank does not normally lend for all project costs; typically, it finances foreign
exchange In addition, other co-financers, such as the European Development Fund, the
several Arab funds, the regional development banks, bilateral aid agencies, and a growing
number of commercial banks, are joining to an increasing extent in co-financing projects
that, in many instances, are appraised and supervised by the Bank.

3|Page
Therefore, an important aspect of appraisal is to ensure that there is a financing plan that will
make funds available to implement the project on schedule.

 costs and expects the borrower or the government to meet some or all of the local costs.

C. IMPLEMENTATION AND SUPERVISION

 The next stage in the life of a project is its actual implementation over the period of
construction and subsequent operation.

 Implementation, of course, is the responsibility of the borrower, with whatever assistance


has been agreed upon with the Bank in such forms as organizational studies, training of
staff, expatriate managers, or consultants to help supervise construction.

The Bank's role is to supervise the project as it is implemented.

EVALUATION

 While supervision is, in part, a process of learning through experience, it is primarily


concerned with that period in the project's life when physical components are being
constructed, equipment purchased and installed, and new institutions, programs, and
policies put in place.

 Once these stages are complete, and Bank funds fully disbursed, the level of supervision
declines sharply. During the period of active supervision, attention tends to be focused on
the problems of the moment.

 The bank’s independent operations evaluation department prepare an audit report and
evaluate the project.

 In 1970, an evaluation system was established as the final stage in the project cycle.

The UNIDO model of project life cycle


 The United Nations Industrial Development organization (UNIDO)is the most devoted
institution towards the development and the standardization of the concept, context and
content(CCC)of industrial project management system. According to the UNIDO
approach documented in the UNIDO manual, the project development cycle comprises
 Each of these three phases is divided into several stages, some of which constitute
important consultancy, engineering and industrial activities as shown below:
1. Pre- investment phase
 Opportunity study( identification of project ideas)
 Pre-feasibility study (preliminary project formulation , selection of alternatives)

4|Page
 Feasibility study (techno-economical project back ground, final project formulation
stage)
 Evaluation report ( decision making about project availability)
 2. Investment phase
 Project design stage
 Construction stage
 Pre-production marketing stage
 Training
 Start-up stage
 3. Operational phase
 Replacement of equipment
 Development, invasion or liquidation
 Before dealing with pre –investment phase, the various stages of the investment and
operational phases are considered since these impacts on the nature and scope of pre-
investment studies. The project investment or implementation phase for a large industrial
business project will be different as compared to that of a small non- industrial project.
 Assuming that a projected industrial activity involves the construction of a factory and
the installation of machinery and equipment, the project investment phase could be
divided in to the following stages:
 Project engineering designs
 Negotiations and contracting
 Construction and training and
 Plant start up
 An adequate importance should be given to the pre investment phase, because the success
or failure of an industrial project ultimately depends upon the marketing, technical,
financial and economic feasibility study findings and their interpretation. To reduce
wastage of scarce resources, a clear comprehension of the sequence of events is required
when developing an investment proposal from the conceptual stage by way of active
promotional efforts to the operational stage.

5|Page
Pre-investment stage
 It is a usual practice, project ideas must be elaborated in a more detailed study. However,
formulation of the detail techno-economic feasibility study, that enables a definite
decision to be made on the project, is a costly and time consuming task. Therefore, before
assigning large funds for such a study, a preliminary assessment of the project idea must
be made in a pre-feasibility study. This is just seeing that whether:
 All possible project alternatives are examined
 The project concept justifies the detail study
 All aspects are critical and need in-depth investigation
 The project idea is viable and attractive or not
 According to the UNIDO manual, the main stages of the pre-investment phase are as
follows:
 Identification of investment opportunities (opportunity studies)
 Analysis of project alternatives and preliminary project selection
 Project preparation( pre-feasibility and feasibility studies ) and
 Project appraisal and investment decision (appraisal report)
 These stages assist a potential investor in the decision making process and provide the
base for project decision and implementation.

a. opportunities studies

 Identification of investment opportunities is the starting point in a series of investment


related activities when potential investors (private or public) are interested in obtaining
information on newly identified viable investment opportunities. The main instrument
used to quantify the parameters, information and data required to develop a project idea
into a proposal is the opportunity study. An opportunity study should identify investment
opportunities or project ideas by analyzing the following factors in detail:
 Natural resources with high potential for processing and manufacture:
 Existing agricultural pattern that serves as a basis for agro-based industries:
 The future demand for certain consumer goods or for newly developed goods:
 Imports in order to identify areas for import substitution:
 Cost and availability of production factors:

6|Page
 Possible expansion of existing industrial capacity to attain economies of scale and
 Export possibilities.
b. Pre-feasibility studies
 A Pre-feasibility study should be viewed as an intermediate stage between a project
opportunity study and a detailed feasibility study. c and the intensity with which project
alternatives are examined. The structure of a prefeasibility study should be the same as
that of the detailed feasibility study. These two studies basically compile the information
on the justification of the project. In a practical sense, the main components of the project
feasibility report are:

 Executive summary  Factory, administrative and sale


 Project back ground and history overheads
 Market and plant capacity  Man power
 Location and site  Project implementation
 Project engineering works  Financial analysis and
 Project risk analysis

 The Objectives of conducting a prefeasibility study are:


 Conduct Preliminary project assessment
 Identify project alternatives
 Identify critical aspects that require special support studies such as project's design -
product, technology, marketing and distribution, capital structure.
 Characteristics of the study:-
 Intermediate level of detail based primarily on secondary data between project
opportunity study and a detailed feasibility study
 The difference being in the degree of detail of the information obtained and the
intensity with which project alternatives are discussed.
 The structure of a pre-feasibility study should be the same as that of a detailed
feasibility study.
C. feasibility studies
 A feasibility study should provide all data necessary for making the investment decision.

7|Page
 The commercial, technical, financial, economic and environment prerequisites for an
investment project should therefore be defined and critically examined on the basis of
alternative solutions already reviewed in the pre-feasibility study. The results of these
efforts strengthen a project whose back ground conditions and aims have been clearly
defined, in terms of its control objective and possible marketing strategies, the possible
market share that can be achieved, the corresponding production capacities, the plant
location existing raw materials, appropriate technology and mechanical equipment and,
location, existing raw materials, appropriate technology and mechanical equipment and if
required an environmental impact assessment.
 The financial part of the study covers the scope of the investment, including the net
working capital, the production and marketing costs, sales revenue and the return on
capital invested. The final estimates on investment and production costs and its
subsequent calculations of financial and economic profitability are only meaningful if the
scope of the project is defined in order not to omit any essential part and its related cost.
However, there is no uniform approach or pattern to cover all industrial projects of
whatever type, size or category. The emphasis on the components varies from project to
project. For most industrial projects, however, there is a broad format of general
application-bearing in mind the larger the project the more complex will be the
information required.
 The Objectives of conducting a feasibility study is to provide commercial, technical,
financial, and economic information needed for investment decision making.
 Characteristics of the study:-
 Clear project concepts and criteria
 Comprehensive project design
 Reliable information often primary data
 Quantified prediction of performance
 Detail analysis with high confidence level
 Consistent and defensible conclusions
 Selection criteria
d. Appraisal Report

8|Page
 When a feasibility study is completed, the various parties will carry out their own
appraisal of the investment project in accordance with their individual objectives and
evaluation of expected risks, costs and gain. Large investment and development finance
institutions usually have formalized project appraisal procedures and usually prepare an
appraisal report. This is the reason why project appraisal should be considered an
independent stage of the pre-investment phase, marked by the final investment and
financing decisions taken by the project promoters.
 The appraisal report will prove whether the pre production expenditures spent since the
initiation of the project idea were well spent or not. Project appraisal, as carried out by
financial institutions concentrates on the health of the company to be financed, the returns
to be obtained by equity holders and the protection of its creditors. The techniques
applied to appraise projects in line with these criteria center around technical,
commercial, market, managerial, organizational, financial and if possible economic
aspects of project.
Investment (implementation) phase
 The investment or implementation phase of a project provides a wide scope for
consultancy and engineering work, first and foremost, in the field of project management.
The investment phase can be divided into the following stages:
 Technological acquisition and transfer
 Detailed engineering design and contract, including tendering, evaluation of bids and
negotiations
 Acquisition of land, construction work and installation
 Pre-production marketing, including the securing of suppliers and setting up the
administration of the firm
 Recruitment and training of personnel and
 Plant commissioning and start-up
 Detailed engineering design comprises preparatory work for site preparation, the final
selection of construction planning and time scheduling of factory construction, as well as
the preparation of flow charts, scale drawing and a wide variety of layouts. During the
stage of tendering and evaluation of bids, it is chiefly important to receive comprehensive

9|Page
tenders for goods and services for the project from a sufficiently large number of national
and international supplies of proven efficiency and with good delivery capacity.
 This stage covers the signing of contracts between the investor on the one hand, and the
financing institutions, consultants, architects and supplies of raw materials and required
inputs on the other.
 The construction stage involves site preparation, construction of buildings and other civil
works, together with the erection and installation of equipment in accordance with proper
programming and scheduling. The personnel recruitment and training stage, which should
proceed simultaneously with the construction stage, may prove very crucial for the
expected growth of productivity and efficiency in plant operations. Plant commissioning
and start up is usually a brief, but technically critical span in project implementation.
Operational Phase
 The problem of the operational phase needs to be considered from both short and long
term view points. The short term view relates to the initial or commencement of
production when a number of problems may arise concerning such matters as the
application of production techniques, operation of equipment or inadequate labor
productivity owing to lack of qualified staff and labor. Most of the problems have their
origin in the implementation phase. The long term view relates to chosen strategies and
the associated production and marketing costs as well as sales revenues. These have a
direct relationship with the productions made at the pre-investment phase. If such
strategies and projections prove faulty and remedial measures will not only be difficult,
but may prove highly expensive.

10 | P a g e

You might also like