CMT Section A&b Question Answers-1
CMT Section A&b Question Answers-1
Contract Costing is a special type of job costing where the unit of cost is a single contract.
Contract is executed under the customer’s specifications and costs are accumulated and
ascertained for each contract.
2
UNIT III OPERATING COSTING
Nature Jobs are done for a single job or Contracts are undertaken for large
manufacturing a few products Construction works like buildings,
roads, apartments, dams etc.
2.Size Job is small in size as compared to Contracts are large in size with huge
contracts and o less value compared to investment
contracts.
3.Place of work Jobs are performed in the company Contract work is done at the customer’s
workshop/ plant as per order site/ location
4.Time of A job usually takes less time for A Contract usually takes more time for
completion completion(less than year) completion (more than a year)and is of
high value
5.Payment of The selling price is paid in full as soon as In contracts, the payment is done in
price the job is completed instalments each year depending on
the completion level.(work certified)
6.Nature of Costs incurred may be direct and Almost all costs are directly charges to
expense indirect costs the contract
Transferability Jobs cannot be transferred from one o Contracts can be transferred(some jobs
another can be sub-contracted to 3rd parties)
4
➢ DIFFERENCES BETWEEN JOB COSTING AND PROCESS COSTING
Job Costing Process Costing
Cost is ascertained for every job Cost is ascertained for every process in the
department
Costs of the job can be calculated when the Cost of the product is calculated only at the end
job is completed or beforehand too of the process
Used in those firms where production is Used in those firms manufacturing mass
according to customer orders. production of homogeneous products.
There is no transfer of work from one job The cost of output of one process is transferred
to another to the next process as input and input cost
There may or may not be work-in-progress There is always some work-in-progress at the
at the end of the period beginning or at the end of the period
The time frame depends on the completion There is a time frame within which the processes
of job of production are completed
Job costing is used for very small Process costing is used for large production runs
production runs
Cost of each unit is separately identified The total cost of production is ascertained after
all the processes are completed, spread over the
number of units
For contracts which have just started: When value of WC is less than one fourth( 25% of contract
price) No profit is transferred to P&L Account. The entire amount is transferred to work-in-progress
account being reserve.
Contracts which have reached certain stage of completion: This includes contracts which have
sufficiently progressed and some part of the work is completed.
When value of WC is more than 25% but less than 50% of the contract price, One-third of the notional
profit, reduced in the ratio of cash received to work certified, should be transferred to profit and
Loss Account and the balance will remain in reserve to meet contingencies.
1 𝑐𝑎𝑠ℎ 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑
= 𝑁𝑜𝑡𝑖𝑜𝑛𝑎𝑙 𝑝𝑟𝑜𝑓𝑖𝑡 𝑋 3 𝑋 𝑤𝑜𝑟𝑘 𝑐𝑒𝑟𝑡𝑖𝑓𝑖𝑒𝑑
5
Contracts which have reached more than 50 % stage of completion: When value of WC is equal to
or more than 50% but less than 90 % of contract price, Two-thirds of the notional profit, reduced in
the ratio of cash received to work certified, should be transferred to profit and Loss Account
2 𝑐𝑎𝑠ℎ 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑
=𝑁𝑜𝑡𝑖𝑜𝑛𝑎𝑙 𝑝𝑟𝑜𝑓𝑖𝑡 𝑋 3 𝑋 𝑤𝑜𝑟𝑘 𝑐𝑒𝑟𝑡𝑖𝑓𝑖𝑒𝑑
Contracts which are almost complete: Value of work certified is more than 90 % of the contract
price, then it is possible to estimate profit which is then transferred to Profit and Loss Account in
the ratio of cash received to work certified and further reduced in the ratio that work certified bears
to the contract price.
𝑐𝑎𝑠ℎ 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑 𝑤𝑜𝑟𝑘 𝑐𝑒𝑟𝑡𝑖𝑓𝑖𝑒𝑑
=𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑓𝑖𝑡 𝑋 𝑤𝑜𝑟𝑘 𝑐𝑒𝑟𝑡𝑖𝑓𝑖𝑒𝑑
𝑋 𝑐𝑜𝑛𝑡𝑟𝑎𝑐𝑡 𝑝𝑟𝑖𝑐𝑒
Alternately, estimate profit can be transferred to Profit and Loss Account in the ratio that cost of
work done to date bears to the estimated total cost, further reduced in the ration of cash received
to work certified
𝐶𝑜𝑠𝑡 𝑜𝑓 𝑤𝑜𝑟𝑘 𝑑𝑜𝑛𝑒 𝑡𝑜 𝑑𝑎𝑡𝑒 𝐶𝑎𝑠ℎ 𝑟𝑒𝑐𝑒𝑖𝑣𝑒𝑑
=𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑝𝑟𝑜𝑓𝑖𝑡 𝑋 𝐸𝑠𝑡𝑖𝑚𝑎𝑡𝑒𝑑 𝑡𝑜𝑡𝑎𝑙 𝑐𝑜𝑠𝑡
𝑋
𝑊𝑜𝑟𝑘 𝑐𝑒𝑟𝑡𝑖𝑓𝑖𝑒𝑑
For Completed contracts: Work done is 100% of contract price, The entire profit is transferred to
P&L Account.
6
SECTION D (Anyone of the following) ( 6X1=6)
OR
Paper Mill: Method of costing used is Single costing is also known as unit costing or output
costing. Under single costing, the cost per unit of output or production is ascertained. Each
element constituting such a cost is determined separately. This costing method is suitable in
industries such as brick-making, paper mills, and flour mills.
Sugar Mill: The method of costing used is process costing. This method is used in mass
production industries, as the material passes through different processes up to the completion
stage (sugar cane to sugar).
Hospitals: The method of costing used is service costing. In this method, the indirect costs are
allocated based on the services rendered (services or units of a hospital) as per patient days .
7
Oil refinery: The method of costing used is process costing as the raw material undergoes
different stages of processing before being converted into oil (copra to coconut oil). Process
costing is suitable for industries that produce homogeneous products
Pickle manufacturing: The method of costing used is process costing. This method is used in
mass production industries like pickle making. The raw material passes through a number of
processes up to a completion of the final product-pickle.
KSRTC: The method of costing used is Transport costing/Operating costing. Transport Costing
is used or the determination of the cost per unit of services rendered by a vehicle run by KSRTC.
( Cost per unit may be cost per kilo meter or cost per passenger kilometer )
Hotel: The method of costing used is Service costing / Operating costing. This method is used
or the determination of the cost per unit of services rendered by the hotel for maintaining and
running he hotel ( cost per room day).
OR
BREAK EVEN CHART