Chapter 7 Benefit Cost Ratio and Other Analysis Techniques
Chapter 7 Benefit Cost Ratio and Other Analysis Techniques
Chapter 7
Supplemental Reading, Chapter 8
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 1
Example 1
Benefit-Cost Ratio Analysis
• At a given MARR, alternative would be acceptable when:
➢PW of benefits - PW of costs ≥ 0, or
➢EUAB - EUAC ≥ 0
• Could also be stated as ratio, called the Benefit-Cost
Ratio
• Alternative would be acceptable when:
➢ PW of benefits/ PW of costs ≥ 1 Invest!
▪ Otherwise don't.
• EUAB/ EUAC ≥ 1
➢ IF very close to 1: use sensitivity analysis technique
Benefit-Cost Ratio Analysis
• In benefit-cost ratio analysis, two alternatives are compared
using incremental benefit-cost ratio (B/C)
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 2
Example 2
Example 3
Problem:
Consider the following six mutually exclusive alternatives.
They have 20 year useful lives and no salvage value. If the
minimum attractive rate of return is 6%, which alternative
should be selected?
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 3
Problem:
Consider the following six mutually exclusive alternatives.
They have 20 year useful lives and no salvage value. If the
minimum attractive rate of return is 6%, which alternative
should be selected?
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 3
Example 3
Payback Period
• Remember:
➢Only an approximate calculation
➢All costs/benefits/savings are included with no
consideration of time value of money
➢All economic consequences beyond payback
are ignored
➢Due to approximate nature, may not select
correct alternative
Payback Period
• A firm is trying to
decide which of two
scales it should
install to check a
package-filling
operation in the
plant. If both scales
have a six-year life,
which one should be
selected (using
payback period
analysis)?
• Assume an 8%
interest rate.
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Payback Period Example
You may assume that the benefits occur throughout the year rather
than just at the end of the year.
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 4
Example 4
Sensitivity Analysis
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 5
Problem:
Consider a project that may be constructed to full capacity
now or may be constructed in two stages. Both alternatives
have a 40 year useful life. Assuming an 8% interest rate,
what is the sensitivity of the decision to go with second-
stage construction when “n” is 16 or more years in the
future?
• Plot “Age When Second
Stage Is Constructed”
versus “Costs for Both
Alternatives.”
• Mark the break even
point on your graph.
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 5
Example 5
Example 5
Solution:
• The decision about how to construct the project is sensitive to the
age at which the second stage is needed only if the range of
estimates includes 15 years.
➢ For example, if one estimated that the second-stage capacity would
be needed between five and 10 years hence, the decision would be
insensitive to that estimate. For any value within that range, the
decision would not change. But if the second-stage capacity were to
be needed some time between 12 and 18 years, the decision would
be sensitive to the estimate of when the full capacity would be
needed.
• One question posed by this example is how sensitive the decision is
to the need for the second stage at 16 years or beyond. The graph
shows that the decision is insensitive.
• In all cases for construction at or after 16 years, two-stage
construction has a lower PW of cost.
Example 6
Problem:
Three mutually exclusive alternatives are given below, each
with a 20-year life and no salvage value. The minimum
attractive rate of return is 6%.
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.
Example 6
Example 6
Example 6
Sensitivity analysis:
• Here the rule is to
maximize NPW; as a
result, the graph shows
that B is preferred if its
initial cost is less than
$4,300.
• At an initial cost above
$4,300, C is preferred.
We have a break-even
point at $4,300.
• When B has an initial
cost of $4,300, B and C
are equally desirable.
Benefit-cost ratio
and other analysis techniques
Chapter 7
Supplemental Reading, Chapter 8
Newnan, D., Whittaker, J., Eschenbach, T., and Lavelle, J. (2018). Engineering Economic
Analysis (4th Canadian edition). Oxford University Press.