Zojila and Z-Morh Tunnel
Zojila and Z-Morh Tunnel
INTRODUCTION
1
CHAPTER 2
ZOJILA TUNNEL
2
CHAPTER 3
3
3.1 ZOJILA TUNNEL PROJECT: ZOJILA PASS SMART
TUNNEL FEATURES
The project is being developed as a smart tunnel (SCADA system) based on
the New Austrian tunnelling method. It will be equipped with modern safety
features, including a fully transverse ventilation system, CCTV monitoring,
uninterrupted power supply, emergency lighting, variable message signs, traffic
logging equipment and a tunnel radio system.
The Zojila tunnel, with length 14.15 km, is the first-of-its-kind tunnel project
in the Himalayas, given the challenging geographical conditions. It will be the
highest tunnel, built at an altitude of 11,578 ft (around 3,500 metres). As per the
proposed project plan, there will be provision for pedestrian cross passages at every
250 metres, emergency telephones and fire-fighting cabinets at every 125 metres,
and motorable cross passages and lay-bys at every 750 metres.
The halfway mark of the Zojila tunnel excavation work has been successfully
completed, accomplishing a major milestone.
Fig 3.3 Zojila Tunnel Project: Zojila Pass Smart Tunnel Features.
4
3.2 ZOJILA TUNNEL PROJECT ROUTE
The two-lane, bi-directional, single tube tunnel will link Baltal to Minamarg
(in Ladakh) on the Srinagar-Leh section. It will bypass the Zojila Pass and link
Sonmarg (in Jammu and Kashmir) with Ladakh. The government is also
constructing a 6.5-km Z-Morh tunnel from Gagangir to Sonmarg, a resort town.
This will ensure connectivity in all weather conditions between Srinagar (in Jammu
and Kashmir) and Kargil (in Ladakh). For the first time, it will give easy access to
Sonmarg, even during the winters.
The completion of this tunnel will reduce the travel time from Leh to
Sonmarg. It will cut down the distance between Gagangiri and Sonawal from 11 km
to 6.5 km.
5
3.3 ZOJILA TUNNEL PROJECT COST
According to the Ministry of Road Transport and Highways, the project
construction cost was initially budgeted at Rs 6,575.85 crores. The overall project
cost is estimated to be Rs 8,308 crores by the National Highways & Infrastructure
Development Corporation Limited (NHIDCL), after considering escalation at 5%
per annum. The total integrated cost, including Zojila tunnel and approaches up to
Z- Morh tunnel, is pegged at Rs 10,643 crores.The government is considering
design changes in the project to prevent cost escalation. The Z-Morh tunnel work,
which is expected to be completed by December 2023, is being constructed at a cost
of Rs 2,378 crores.
Union minister, Nitin Gadkari, recently said that while the cost of the Zojila
tunnel in the tender was projected at around Rs 11,000 crores, the government has
taken efforts to lower the cost by Rs 5,000 crores. The Zojila Tunnel project in India
was estimated to cost around ₹6,800 crores (approximately $930 million USD).
However, please note that construction costs for large infrastructure projects like
tunnels can change over time due to various factors, including inflation, changes in
design or scope, and other economic factors.To get the most accurate and up-to-date
information on the cost of the Zojila Tunnel project
The Zojila Tunnel project in India had been in the planning and construction
stages for several years. The project aimed to construct a tunnel through the Zojila
Pass in Jammu and Kashmir to provide year-round connectivity between Srinagar
and Leh. The Zojila Tunnel was expected to have a significant impact on
transportation and connectivity in the region, especially during the harsh winter
months when the pass becomes inaccessible due to heavy snowfall.The project’s
timeline can change due to various factors such as weather conditions, funding, and
logistical challenges. Therefore, for the most accurate and up-to-date information on
the Zojila Tunnel project's timeline and progress, I recommend checking official
government sources, recent news articles, or contacting the relevant authorities or
agencies involved in the project. They should be able to provide you with the latest
information regarding its status and expected completion date.
6
2005: Connecting Srinagar and Leh, the tunnel project was first planned, and a
detailed project report (DPR) was prepared by the Border Roads Organisation
(BRO) in 2013 on BOT (Annuity) mode.
July 2016: The project was given to NHIDCL for implementation on the EPC
mode.
January 2018: The Zojila tunnel project received approval from the union
cabinet.
May 2018: The foundation stone was laid by prime minister Narendra Modi.
February 2020: The project was reviewed by the Ministry for Road Transport
and Highways.
May 2020: An expert group submitted its report that was approved by the
Ministry of Road Transport and Highways
October 15, 2020: Work on the Zojila tunnel began with the first ceremonial
blasting initiated by Minister of Highways, Nitin Gadkari.
November 2021: The excavation work of tunnel 1 of the Zojila Tunnel was
completed by Megha Engineering and Infrastructures Ltd (MEIL).
7
3.5 ZOJILA TUNNEL BENEFITS
The Zojila Pass is closed during snowfall in the winter months, thus, cutting
off Ladakh from Kashmir and other parts of the country. The tunnel will make the
Srinagar-Kargil-Leh section on NH 1 free from avalanches, augment safety in the
region and significantly reduce the travel time by more than three hours, to a mere
15 minutes. The distance between Baltal and Minamarg will be reduced to about 13
kilometres from the existing route of 40 kilometres. Apart from providing safe
connectivity to Srinagar, Dras, Kargil and Leh, the construction of this tunnel will
lead to all-around economic and socio-cultural integration of these areas.
The infrastructure project also holds strategic importance for the country, as
Ladakh shares de-facto borders with Pakistan and China and depends on air
supplies for around six months in a year. It will provide logistical flexibility to the
military.
Once completed, the project is also expected to give a push to tourism, local
business activities and employment opportunities in the region.The Zojila Tunnel
project in India is expected to bring several significant benefits to the region and the
country as a whole. Some of the key benefits of the Zojila Tunnel project include:
8
Year-Round Connectivity: One of the primary goals of the Zojila Tunnel is to
provide year-round connectivity between Srinagar and Leh. Currently, the
region remains cut off from the rest of the country during the winter months due
to heavy snowfall and avalanches. The tunnel will ensure that essential supplies,
medical services, and connectivity are maintained throughout the year.
Economic Development: Improved connectivity is expected to boost economic
development in the region. It will facilitate the movement of goods and people,
which can lead to increased trade and tourism opportunities. This, in turn,
can stimulate economic growth and job creation.
Strategic Importance: The Zojila Pass is strategically important for India due
to its proximity to the Line of Control with Pakistan and its location on the route
to Leh and Ladakh. The tunnel will enhance the country's ability to quickly
deploy military forces to this region in case of any security concerns.
Reduction in Travel Time: The tunnel will significantly reduce travel time
between Srinagar and Leh, making transportation more efficient. Currently, the
journey through the mountainous Zojila Pass can be treacherous and time-
consuming.
All-Weather Access: The tunnel will provide a safe and reliable alternative to
the Zojila Pass, which often becomes impassable during harsh winter
conditions. This will help prevent disruptions in essential services and
transportation.
Environmental Benefits: The tunnel is designed to minimize the
environmental impact by incorporating various eco-friendly features. This
includes the use of modern technology to prevent pollution and maintain the
fragile ecosystem of the region.
Tourism Development: The improved accessibility is expected to boost
tourism in the region, attracting tourists to the picturesque landscapes and
cultural sites of Ladakh and the surrounding areas.
Safety: The Zojila Pass is known for its challenging terrain and weather
conditions, leading to accidents and loss of lives. The tunnel will provide a safer
alternative for travelers and transportation of goods.
9
CHAPTER 4
Z-MORH TUNNEL
10
Location: The Z-Morh Tunnel is situated in the Z-Morh area, which is part of
the Srinagar-Leh highway (National Highway 1D). It is located in the
Ganderbal district of Jammu and Kashmir.
Objective: Similar to the Zojila Tunnel, the primary objective of the Z-Morh
Tunnel project is to provide all-weather connectivity between Srinagar and
Kargil. The region experiences extreme weather conditions, especially during
winter, when the mountain passes are often closed due to heavy snowfall
and avalanches. The tunnel is intended to ensure year-round access.
Length: The exact length of the Z-Morh Tunnel may vary depending on the
final design and construction, but it is expected to be several kilometers long to
traverse the mountainous terrain.
Benefits: The tunnel is expected to bring several benefits, including improved
transportation, economic development, and enhanced access to the region. It
will reduce travel time and make the journey safer and more reliable for both
passengers and the movement of goods.
Status: As of my last update, the Z-Morh Tunnel project was under
construction. Please note that the status and progress of infrastructure projects
can change over time, and it's advisable to check with official government
sources or recent news reports for the most up-to-date information on the
project's status and completion timeline.
11
Situated in Jammu and Kashmir’s Ganderbal district, the Z-Morh Project
includes a 6.412 km Main Tunnel, a parallel Escape Tunnel spanning 6.426 km,
and approach roads totalling 5.568 km on both sides. This ambitious project
involves constructing challenging structures like bridges and underpasses to
address the issue of seasonal road closures effectively.
12
4.1 GEOLOGICAL CHALLENGES IN TUNNELLING IN
THE HIMALAYAS
Mountain belts, which are created by continent-continent collisions,
represent the most dominant and unique geologic features on the surface of the
Earth. Some of the best examples of such continent-continent collisions that lead
to orogenesis are the Rockies and the Appalachian belt in North America, the
Andes in South America, the Ural Mountains in central Eurasia, the Alps of
Europe, and the Himalayas in Asia. The Himalayan orogeny is the youngest and
most impressive of all the continent-continent collisional belts on Earth. The
Himalayan Mountain Ranges are the product of the collision between the Indian
and Eurasian plates and are a living example of a collision mountain belt as the
process of mountain building is still active, forming the highest range and plateau
in the world.
Tunnelling through the weak, fragile, jointed rock masses of the Himalayas
throws many surprises to planners and engineers. Almost in all the tunnelling
projects of the Himalayas some or other type of tunnelling problems have been
encountered and are still being faced; like Fault/thrust/shear zones, running
ground conditions, heaving, squeezing and swelling, rock bursting, groundwater
inflow, hot temperature conditions and gases in rock, wedge/block failures,
etc. Though it is a non-welcoming situation, still it gives lessons to learn.
13
Fig 4.4 Collision of Indian and Eurasian plates led to the formation of the
Himalayas.
The tunnelling method used for Z-Morh and Zojila Tunnels is the New
Austrian Tunnelling Method (NATM). As the name suggests, the method was
first used in Austria (Salzburg) by Mr. Rabcewicz in 1962, and it gained
worldwide recognition in 1964. In India, NATM is mostly used while tunnelling
in the Himalayas.
14
4.3 THE BASIC PRINCIPLE OF NATM
15
4.4 EXCAVATION
The drill and blast method is usually preferred for excavation in hard rocks,
whereas for soft rocks, excavation is done through breaking. Before the blasting, the
profile is marked using a Total Station. All the coordinates of the alignment are first
fed to the Total Station. After the profile marking, when blasting is used, excavation
is carried out in two parts: Heading and Benching. The heading is the top 65-70% of
the tunnel section, whereas the remaining is the benching. Such a method is adopted
considering the accessibility of the booms on the boomer machine. In Z-Morh and
Zojila tunnels, excavation was done through blasting using an industrial-grade
explosive, ANFO (Ammonium Nitrate + Fuel Oil). ANFO usually detonates
through electronic detonators (EDs). Sequential blasting is used for the effective
creation of free surfaces so that blasting is done up to the required length and
desired fragmentation of rocks. The process of blasting is highlighted in the
following figures:
Drilling: Usually, drilling in the tunnel is carried out using a boomer. The
length of holes is kept around 3-3.5 m, which indicates that in a single blast,
around 3 m of excavation pull is achieved.
Charging: The explosive used for the tunnel blasting is an industrial grade,
commonly known as ANFO (Ammonium Nitrate + Fuel Oil). After the holes
are drilled, the explosive is charged inside the hole. When the trigger is pressed,
a current is generated in the ED, which initiates a spark, and the blast takes
place.
16
Fig 4.8 Charging of explosives is done manually.
In addition to the above, for effective blasting and to get the desired
fragmentation of rocks, different blasting patterns are used such as wedge-cut, burn-
cut, ring configuration, etc. In Z-Morh and Zojila Tunnels, a wedge-cut blasting
pattern is used.
17
Fig 4.10 Burn-cut blasting pattern.
The numbers in both pictures indicate the sequence of blasting.
4.5 INSTALLATION OF SUPPORT SYSTEM
The primary support in the tunnel after excavation is decided based on the
quality of the rock mass which is usually decided by various rock mass
classification methods. Some of the classifications used generally to design the rock
support systems are:
Terzaghi’s rock mass classification or rock load classification method.
Stand-up time classification.
Rock Quality Designation (RQD).
Rock Structure Rating (RSR).
Rock Mass Rating (RMR).
Q-system.
CSIR classification of the jointed rock mass.
In the Indian context, for the tunnels in the Himalayan region, usually, two
main classifications are preferred by the design consultants, which are the RMR
method and Q-value. RMR is a rating for the rock mass which is usually decided
based on the six different parameters, involving rock mass strength, joint
conditions, presence of water, etc., whereas the Q-system is a classification system
for rock masses concerning the stability of underground openings. Based on the
estimation of six rock mass parameters, a Q-value for a rock mass can be calculated.
This value describes the rock mass quality.
18
4.6 DEFORMATION MONITORING OF THE TUNNELS
Geotechnical Instrumentation and 3D monitoring have a vital role in
evaluating the performance of the underground structure. The Natural ground or
rock mass tends to deform and de-stress when subjected to excavation or another
loading such as overburden above the tunnel. For calculating that deformation,
stress, etc. Instrumentation and 3D monitoring are required. The long-term
performance of an underground structure is monitored by installing structural
instruments to predict and evaluate the safety of excavated opening. The
instruments used for measuring different parameters are:
Bi reflex targets/Prism targets: used to measure convergence and
Deformation in the rock mass.
Load cells: Used to measure load or stress in rock bolts or anchors.
Strain gauge: Used to measure deformation or strain/load in LG or rib.
Multi-point borehole extensometer (MPBX): Measures deformation inside
rock mass.
Shotcrete/Concrete pressure cell: Measures total increase in pressure due to
redistribution of stresses in the rock mass after excavation.
Inclinometer: Used to measure lateral movements.
19
4.7 AFTER THE CONSTRUCTION PERIOD
Before moving further, mentioning that both the Z-Morh and Zojila
tunnels are currently under construction is pertinent. Hence, the information
shared in the article is purely based on the designs of the proposed systems (such
as ventilation systems, E&M, fire-fighting systems, and SCADA).
CCTV cameras will be strategically placed inside the tunnel and along the
project, alignment to monitor daily activities and ensure effective surveillance.
20
For ventilation, a semi-transverse ventilation system is proposed for the Z-
Morh Tunnel. This system involves introducing fresh air through the tunnel
portals and extracting exhaust air through equally spaced smoke extraction
dampers along the length of the tunnel. The extracted air will flow outside the
tunnel via an overhead duct.
The ventilation system will utilise a combination of jet and axial flow fans,
maintaining a maximum longitudinal airflow velocity of 10m/s. In a fire, the smoke
extraction dampers will open fully in the fire area while other dampers will close,
ensuring efficient smoke evacuation.
4.8 Z-MORH TUNNEL STRUCTURE
Sonamarg, which has places to visit like the Thajiwas Glacier and sports like
whitewater rafting on the Sind River, will see a rise in tourism due to the tunnel,
which will also contribute to the region's overall economic and social growth.
21
4.9 Z-MORH TUNNEL HISTORY
The tunnel can be found at 2,637 meters (8,652 feet) above sea level. In July
2012, during the 53rd PPPAC Conference, the site's overall capital cost was
approved at 2,717 crores. This sum comprises the land cost, relocation,
rehabilitation, and other pre-construction works, which total Rs. 36.48 crore.
22
4.11 CONTRACTOR DETAILS
August 2019: APCO Infratech receives the ₹2,378 crore project and will
build the tunnel (Balance Work) under BOT (annuity) mode. By December 2023,
the tunnel should be finished after 3.5 years of construction. It is essential for India
that Kashmir and Ladakh are connected. Infrastructure along the border had been
ignored for many years. It is essential to the advancement and development of the
local populace from a strategic standpoint.
2012 saw the laying of the project's foundation stone. It was once controlled
by the Border Roads Organization (BRO), which hired Srinagar-Sonamarg
Tunnelway Ltd, an IL&FS-owned business, to build the civil portion of the road.
The project was retendered in 2019, and NHIDCL granted the contract to APCO
Infratech, which is carrying it out on behalf of Apco Shri Amarnathji Tunnelway
Private Limited (ASATPL).
23
CHAPTER 5
Z-MORH TUNNEL CONSTRUCTION
The work on the Z-Morh Tunnel was halted for two years between 2017 and
2019 due to financial constraints faced by the then main executing agency IL&FS
which later abandoned the work.
24
Fig 5.3 Internal Work Like Lining, Lighting, Finishing, and Ventilation
Fig 5.4 Internal Work Like Lining, Lighting, Finishing, and Ventilation
25
Fig 5.5 Construction Work
26
Fig 5.7 Construction Work
27
CHAPTER 6
CONCLUSION
28
CHAPTER 7
REFERENCE
8. Strategic Zojila tunnel to see defence forces crossing into Ladakh 2 years
ahead of deadline, The Hindu, 28 March 2022.
29