Rebar IPC 1 Agreement 2
Rebar IPC 1 Agreement 2
PAYMENT CERTIFICATE 1
አባሪ በሆነው የክፍያ ሰነድ ጥያቄ መሰረት እስከ ዛሬ ድረስ ተቋራጩ የሰራው ሥራና/ያቀረበው ዕቃ
As per the attached statement the value of work executed and/or materials supplied to-date የገንዘቡ ልክ /ብር/
before VAT is Birr 91,903.39 Amount (Birr)
Main Contract 91,903.39
Price adjustment
VAT Payments
Details Deduction Payables
VAT on Amount of
Work Executed 13,785.51
VAT on Retention -
VAT on Advance
Sub-total - - - Repayment -
VAT on Previous
ADVANCE REPAYMENT payments -
Description Before VAT VAT Total Total Deduction -
Amount of advance taken - -
Advance repaid - - - VAT Payable in this payment 13,785.51
Outstanding adv. - - - Total Payable to the Contractor including
101,093.73
VAT
አባሪ በሆነው የክፍያ ሰነድ ጥያቄ መሰረት እስከ ዛሬ ድረስ ተቋራጩ የሰራው ሥራና/ያቀረበው ዕቃ
We certify that the Contractor is now entitled to the sum of Birr 101,093.73 (One Hundred One Thousand Ninety Three birr and 93/100)
.
5
B5, On axis 5 b/n A-G 0.00
Top bar 20 4.00 2.00 1 2.00 8
20 12.00 2.00 1 2.00 24
20 11.20 2.00 1 2.00 22
20 3.00 2.00 1 2.00 6
Negative Bar 20 2.55 3.00 1 3.00 8
20 3.69 3.00 1 3.00 11
20 3.87 3.00 1 3.00 12
20 3.87 3.00 1 3.00 12
20 3.14 3.00 1 3.00 9
20 2.00 3.00 1 3.00 6
Bottom bar 20 11.70 3.00 1 3.00 35
20 12.00 3.00 1 3.00 36
20 4.35 3.00 1 3.00 13
Stirrups 8 1.40 173.85 1 173.85 243
Stair beam B5, On axis 5 b/n C-
6
D 0.00
Top bar 20 7.45 2.00 1 2.00 15
Negative Bar 20 2.78 3.00 1 3.00 8
20 2.78 3.00 1 3.00 8
Bottom bar 20 6.65 3.00 1 3.00 20
Stirrups 8 1.40 41.00 1 41.00 57
Enterance Stair
ON AXIS 1/B-C 14 9.28 54 1 54.00 501.12
14 1.26 49 1 49.00 61.79
14 2.71 49 1 49.00 132.89
14 1.27 49 1 49.00 62.38
RISER 14 1.27 73 1 73.00 92.71
10 4.80 52 1 52.00 249.60
SB1, On axis1 b/n B-C 1 0.00
Top bar 20 5.66 7 1 7.00 39.62
Bottom bar 20 4.76 6 1 6.00 28.56
Stirrups 8 1.10 48 1 48.00 52.80
SB2, On axis1 b/n B-C 1 0.00
Top bar 20 6.66 7 1 7.00 46.62
Bottom bar 20 5.86 6 1 6.00 35.16
Stirrups 8 1.10 57 1 57.00 62.70
SB3, On axis1 b/n B 1 0.00
Top bar 20 7.16 7 1 7.00 50.12
Bottom bar 20 5.86 6 1 6.00 35.16
Stirrups 8 1.10 57 1 57.00 62.70
SB4, On axis1 b/n C 1 0.00
Top bar 20 7.16 7 1 7.00 50.12
Bottom bar 20 4.76 6 1 6.00 28.56
Stirrups 8 1.10 48 1 48.00 52.80
SHEAR WALL ON AXIS 1,b/n axis B-C
Linear weight Kg/m 0.395 0.617 0.888 1.208 1.578 2.466 3.551
Total weight(Kg) 93.46 213.24 133.20 1027.87 0.00 774.13 0.00
Project : 4B+G+14 Mixed Use Appartment
Contractor: Hambra Plc.
Sub-Contractor:Ameneshewa Solomon & friends Small Building Contractors p/s