Material Schedule of Two Storey Building

Material scheduling is necessary in every constructions to determine the extents of materials needed in each development.

Uploaded by

Oreoluwa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
50% found this document useful (4 votes)
3K views

Material Schedule of Two Storey Building

Material scheduling is necessary in every constructions to determine the extents of materials needed in each development.

Uploaded by

Oreoluwa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT: PROPOSED RESIDENTIAL TWO STOREY BUILDING

SITE MANAGER: HOMES & SHELTER 360 LIMITED

PROJECT ADDRESS: FETUGA STREET, LADI-LAK, BARIGA LAGOS.

ITEM DESCRIPTION QTY UNIT TOTAL


AMOUNT
A. SETTING OUT
25 X 50 X 3600mm timber profile 22 600.00 13,200.00
50 x 50 x 900mm pegs 3 2500.00 7,500.00
Lines 4 300.00 1,200.00
Nails 0.13 14000.00 1,820.00

B. EARTHWORKS
Site Clearing and Excavations 1 Lot 11,100.00
Ground Leveling and Backfills 200 m3 60,000.00

C. STEEL AND REINFORCEMENT WORKS


Footings & Columns
10 - 12mm diameter 0.6 ton 430,000.00 258,000.00

Beams and Roof Beams


10 - 12mm diameter 0.6 tons 430,000.00 258,000.00

Slabs and Dovels


10 - 12mm diameter 1.7 tons 430,000.00 731,000.00
Binding Wires #16 3 Rolls 13,000.00 39,000.00

D. CONCRETE AND MASONRY WORKS


Cement 701 bags 4,200.00 2,944,200.00
Sand 40 tons 60,000.00 2,400,000.00
¾ Crushed Gravel 54m3 120,000.00 6,480,000.00
4” CHB 2932 pcs 10.00 29,320.00

E. FORMS AND FORMWORKS


2” X 3” Cocu Lumbers 31 pcs 2500 77,500.00
2” x 2” Cocu Lumbers 33 pcs 2500 82,500.00
Plywood Forms Paneling 15 780 11,700.00

F. ROOFING WORKS / CONSTRUCTION 2,578,750.00

G. FINISHES 4,796,450.00

TOTAL ESTIMATED COST N 20,781,240.00