Single Point Interchanges Planning-Operarion and Design Guidelines
Single Point Interchanges Planning-Operarion and Design Guidelines
INTRODUCTION
The SPI is an interchange configuration that combines the two separate diamond ramp
intersections into a single large at-grade intersection. The SPI, sometimes referred to as an
"urban interchange", has been known to most highway agencies for many years, but was
seldom used because of its cost, difficulty in constructing and unknown performance
characteristics. In recent years, however, the SPI has become increasingly popular in a few
states and local agencies. SPIs should be used under specific situations and should not be
selected because the interchange is considered “state of the art” or a "gateway" concept.
06/15/01 Page 1 of 25
1-200 GEOMETRIC CONSIDERATIONS
Any SPI proposal must be compared to other conventional interchange types. Consistent with
the philosophy of the PDPM, several interchange alternatives should be evaluated. The SPI
alternative should be compared in particular to spread diamonds, L-9 partial cloverleaves
(parclo) and tight diamonds. The type of interchange selected should be based on the
discussions in these guidelines in order to select the best overall interchange configuration.
SPI intersections are larger than other intersections. Many existing SPI intersections are 90
meters in length or longer. Most SPI intersections operate with a three-phase signal. A
significant distance separates the right turn lanes at exit ramps from the left turn lanes.
Because of its unique design, certain geometric features are more critical to the SPIs operation
than to other types of interchanges. Among those features are crest vertical curvature, skew
angles, intersection length, and large radius sweeping left turn moves. See Section 2,
“Geometric Design” for detailed discussion of these design items.
California drivers are relatively unfamiliar with the SPI geometric and operational
characteristics. Therefore the selection of an interchange type should consider the number of
non-repeat drivers who may not be familiar with the SPI. These locations should include, but
are not limited to, airports, hospitals, sports stadiums and resort areas. Additional
consideration should be provided to locations where visibility may be reduced by weather
conditions.
1-400 CAPACITY
When the SPI configuration is unconstrained by the local road system, it has the capability of
handling larger volumes of traffic than the tight diamond. However, in urban situations the
local road system is often the controlling factor for overall system capacity. The following
constraints influence the selection of an SPI:
Intersection Size
The size of SPI intersections necessitates a long traffic signal clearance interval for all
moves. The all-red clearance interval represents dead time to the signal timing cycle,
which reduces capacity and efficiency. This needs to be considered during the planning
stage of the SPI design.
06/15/01 Page 2 of 25
Adjacent Intersections
The proximity of adjacent intersections and driveways to ramp termini is a critical
factor in the operation of any interchange. Under moderate to heavy traffic demands,
SPIs require longer signal cycle lengths to maximize operations. When an SPI
configuration is used, intersection spacing becomes even more critical because all
stopped traffic must be stored between the near stop bar and the adjacent intersection.
Often free right turn moves at exit ramps can not be provided due to close proximity of
adjacent intersections. See Section 2-300, Right Turns at Exit Ramps” and HDM Index
504.3(2), “Location and Design of Ramp Intersections on the Crossroads”, and 504.8
“Access Control” for more information.
Bicycles
The presence of bicycles can affect the decision to choose a SPI. Due to their slower
speeds, bicycles may adversely affect the capacity and operation of motor vehicles at
SPI intersections, thereby negating the benefits of choosing a SPI over another
interchange alternative. The required green and all-red clearance intervals necessary
for a bicycle to clear most SPI intersections are substantially longer than what is
needed for a motor vehicle. The required extended signal timing increases delay for
motorists. Accommodation of bicyclists through the SPI intersection is an important
consideration. Section 2–800, “Pedestrians and Bicycles” discusses how to accommodate
bicyclists through SPI intersections.
Pedestrians
Because signals at SPI intersections are timed to move motorists efficiently through the
intersection, pedestrians normally can only cross a portion of the intersection in a single
cycle. It may take a pedestrian as many as four cycles to cross the separate ramps
connections along the local street as opposed to typically two to four crossings at
conventional tight diamonds and partial cloverleaf interchanges. Pedestrians shall be
prohibited from crossing the local street within the interchange.
06/15/01 Page 3 of 25
SPIs with incorporated Frontage Roads
SPIs incorporating frontage roads should be avoided.
This configuration requires that the frontage roads be one-way and in the direction of
ramp traffic. A slip ramp from the mainline to the frontage road provides access to and
from the intersection. An SPI incorporating frontage roads by combining the ramps and
frontage road is shown in the 1994 AASHTO “Green Book”, Figure X-25.
A fourth signal phase is required with this configuration to allow through moves on the
frontage roads. This layout typically requires at least 90 m between stop bars, thus
diminishing operational efficiency. The fourth signal phase and additional intersection
size required to accommodate frontage roads reduces the available green time.
Normally bicycles are allowed to use the traffic lanes or shoulders and can legally turn
left at an intersection. In order to accommodate a left turning bicycle in an SPI, longer
signal timing is required. This longer signal timing makes the intersection operate
inefficiently. At three-phase SPI intersections, bicyclists will normally not be turning
left onto the freeways but will be proceeding as through traffic along the local cross
streets.
06/15/01 Page 4 of 25
position of the entering vehicles complicate the required “stop and proceed in order of arrival”
rule. Manually directing traffic will be difficult on an SPI intersection without signal control.
Plans for operation of the SPI intersection during power outages should be developed
cooperatively between California Department of Transportation and the appropriate local
agency.
Staging for SPIs can be more difficult than other interchange types and may result in local
street closures. It is important that proposed SPIs receive a constructability review in
accordance with current procedures.
06/15/01 Page 5 of 25
drivers be able to see and understand their destination and path through the
intersection. Decision Sight Distance per Table 2-101.1 shall be provided
through the SPI intersection along the local street extending 50 m beyond the
stop bars. Decision sight distance is measured from a driver’s eye height of 1070
mm to an object height of 150 mm.
Table 2-101.1
Sight Distance
To verify the driver’s ability to see the pavement, signing, delineation, signals,
and curbs within the intersection, the designer should plot the vertical
alignment of each move through the intersection. As would be expected, curbs
and raised markers can be seen and understood from further distances because
they are raised above the pavement. Based upon field observations, the striping
and pavement can be understood by drivers at approximately half of the sight
distance on longer crest vertical curves. Table 2-101.2 shows the relationship
between sight distance* and the distance that markings on the pavement are
visible.
06/15/01 Page 6 of 25
Table 2-101.2
* Sight Distance is measured from the driver’s eye (1070 mm) to a 150 mm
object.
** Distance is from the driver’s eye to limits of perceivable pavement
delineation. The basis for this measurement is field observation.
Where compound curves are utilized for a left turn alignment through the SPI
intersection, the smaller curve radius should be at least half that of the larger
06/15/01 Page 7 of 25
curve radius. Broken back curves for left turn moves through the intersection
should be avoided.
The exit ramps terminus should be designed to avoid aligning headlights into
the eyes of drivers on the opposite exit ramp. Exit ramps on ascending grades
are particularly prone to directing headlights into opposing exit ramp driver’s
eyes.
Geometrics for left turn moves provide for higher speeds at SPIs than at typical
ramp intersections, therefore stopping sight distance shall be provided along the off-
ramp left turn segment. This shall match or exceed the design speed provided by
the ramp’s horizontal alignment in accordance with Table 203.2 of the Highway
Design Manual and be at least 40 km/hr; Index 504.3(1)(a) not withstanding.
Corner sight distance should be provided from a point 12m before the exit ramp
left turn stop bar. Where restrictive situations exist, the minimum corner sight
distance shall be equal to the stopping sight distance provided from the same
point.
06/15/01 Page 8 of 25
driver's ability to identify and understand the intersection layout, thereby reducing driver
confusion and the potential for wrong way moves. Larger intersections also complicate
movements for bicyclists. Bicycle issues are covered in more detail in Sections 1-400,
“Capacity” and 2-800, “Pedestrians and Bicycles”.
Signal operation has a direct relationship to intersection size. The amount of red
clearance time increases with intersection size, thus increasing the overall signal timing
cycle length, requiring more storage for waiting traffic and reducing the efficiency of the
intersection. In addition, larger intersections expose vehicles to conflicts for longer periods
of time.
If an SPI is proposed without a separate bicycle facility, it shall be a Compact SPI. Where a
separate bicycle facility is provided in conjunction with an SPI, the following intersection size
criteria applies. Where an SPI intersection is located on a crest vertical curve, the distance
between opposing stop bars on the local street should not be greater than 50 meters, but shall
not be greater than 60 meters. Where an SPI intersection is located on a sag vertical curve or
at a constant grade, the distance between opposing stop bars on the local street should not be
greater than 60 meters, but shall not be greater than 70 meters.
The following geometric features can reduce the size of a SPI intersection:
1. Increasing the median width of the local street allows the local street stop bars to be
placed near the center of the intersection. This aspect can be difficult to visualize but is
easily understood if the designer draws and compares the effects of different median
widths.
2. Field observations noted that vehicles frequently stop beyond the stop bar and idle
within the intersection. A wider median width includes space between the through move
stop bars and left turn moves which may compensate for driver error.
3. At undercrossings, signals should be hung beneath the bridge soffit. The vertical
clearance should be sufficient to hang signal heads vertically, thus allowing local street
stop bars to be located nearer the center of the intersection. See Section 6-200,
“Undercrossings” for additional information on signal placement at undercrossings.
The free right turn lane, as shown in Item 2-300(1) in Figure 1, is a typical feature of SPIs
and should be used when the right turning vehicles enter the local street in their own
lane, and adequate weave and merge lengths can be provided downstream. If volumes are
06/15/01 Page 9 of 25
too high for a single lane it is sometimes reasonable to add and signalize the #1 right turn
lane as shown in Figure 1, Item 2-300(2). The signalized #1 right turn lane allows vehicles
in this lane a protected movement to the local street. In some situations this configuration
of a combination free right/signalized right turn layout can mitigate short weaves and
merges related to close spacing of the ramp and adjacent local intersections. Where
spacing between exit ramps and adjacent intersections is short and/or a large volume of
vehicles weave across the local street to turn left at the adjacent intersection,
consideration should be given to signalizing the right turn move at the ramp terminus as
shown in Figure 1, Item 2-300(3).
Per Index 504.3(2) of the HDM, “Where a separate right turn lane is provided at ramp
terminals, the turn lane should not continue as a free right unless pedestrian volumes are
low, the right turn lane continues as a separate full width lane for at least 60 m prior to
merging and access control is maintained for at least 60 m past the ramp intersection.
Provision of the free right should also be precluded if left turn movements of any kind are
allowed within 125 m of the ramp intersection.” In addition, an analysis should be
performed to verify that adequate merge and/or weave distance is provided. If the analysis
indicates that additional lane length is required for merge and/or weave, the access control
should be correspondingly extended.
Where a turn lane converts into an HOV lane on the entrance ramps, adequate weaving
distance should be provided to ensure vehicles entering the ramp can weave out of the
HOV lane to a mixed flow lane. To avoid this weave, it may be feasible to begin an
exclusive HOV lane on the local street leading to the ramp’s HOV lane. Where this occurs,
advance overhead signing should be installed to prepare drivers for the weave. When an
exclusive HOV lane does not begin on the local street, an overhead sign should be placed
at the ramp entrance stating “HOV ONLY AHEAD”.
06/15/01 Page 10 of 25
Where entrance ramps include an HOV bypass lane, adequate distance for merging from
the far lane to the HOV lane should be provided.. A fourth lane on the entrance ramp
should typically be avoided. Figure 1 illustrates the above concepts.
Figure 6 shows a Compact SPI designed to accommodate bicyclists, and minimize the
intersection size thus improve overall operations. An SPI with a 25 m maximum distance
from the stop bar to the conflict point is considered a Compact SPI. The conflict point is
defined as the middle of the far lane for turning vehicles that bicyclists must cross under a
single signal phase. Single free right turn lanes are an integral part of the Compact SPI
design, and are considered independent of the signalization. The Compact SPI design utilizes
a single lane free right turn lane so bicyclists need to cross only one lane of uncontrolled
traffic. However in order to be able to provide free right turn lanes, adequate weave and
merge distance from the free right turn to the adjacent intersection must be provided. See
Section 300, “Right Turns at Exit Ramps” and the HDM for discussions regarding free right
turn movements. In some situations the right turn move can be handled with stop control and
thus adequately accommodate bicyclists.
To accommodate bicyclists through SPI intersections, all SPI alternatives shall be Compact
SPI except as discussed in the following. If an SPI alternative other than a Compact SPI is
chosen, a separate bicycle facility shall be constructed in conjunction with the SPI. The
06/15/01 Page 11 of 25
separate bicycle facility would typically be a bicycle overcrossing or undercrossing and should
be located in the immediate vicinity of the SPI to minimize out of direction travel by bicyclists.
It should be noted that where the right turn movement is signalized, the conflict point is the
middle of the far right turn lane. If it is anticipated that in the future the right turn move at a
Compact SPI will be signalized, a separate bicycle facility should be incorporated into the
current project.
Bicycle push buttons to extend the next through-move green phase for bicyclists have been
installed in California. The push button is located at the limit line and near the curb facing
the street for easy bicyclist access. This allows the bicyclist to cross the SPI with minimum
conflict. The longer green phase however increases the delay to motor vehicles at the
intersection and thus reducing its efficiency. This concept may be applicable at other existing
SPIs. Where bicycle push buttons are installed at SPIs, a sign advising bicyclists that pushing
the button will provide an extended green light on the next cycle shall be installed. The sign
should be white on green, have a bicycle symbol and say: "Push button for more time on next
green.”
Signals at SPIs are timed to move motorists efficiently through the intersection; pedestrians
are normally allowed to proceed as far across the intersection as they can in a single phase.
Due to the substantial length across the intersection it may take a pedestrian as many as four
cycles to cross the interchange as shown in Figure 1.
06/15/01 Page 12 of 25
3-300 LEFT TURN CHANNELIZATION OF LOCAL STREET
On local streets, a striped channelization island to separate left turning vehicles from through
vehicles may be provided as shown on Figure 2. If used, the island should consist of 200 mm
white thermoplastic striping. The island should be at least 1.5 m wide at the widest point.
The island should direct the left turning vehicles towards the freeway on-ramps. A striped
divisional island or “pork chop” island (see Figure 6) shall be provided beyond the left turn
lane stop bar.
The HQ Traffic Liaison shall approve all final signing, striping and signalization plans for
SPIs.
Proper striping and delineation are valuable tools to provide guidance through the
intersection. A dark colored deck is beneficial to increase visibility of pavement markings,
curbs and other interchange features. Some recommended treatments are dyed PCC, open
graded AC, iron oxide-epoxy seal, or a slurry-seal coated PCC. Consult Structures
Maintenance and District Maintenance prior to choosing a surface treatment.
100mm thermoplastic striping material of appropriate color shall be applied around all raised
medians and islands, and surround center islands with a 200mm white thermoplastic stripe.
06/15/01 Page 13 of 25
4-300 LANE LINE EXTENSIONS (SWINGLINES)
In an effort to help guide drivers through SPI intersections, swinglines (Detail 40 plus
reflective markers at approximately 6.4 m on center) shall be provided for all left turn
movements. This will usually be the centerline between double left turn movements. In some
instances a second swingline may be appropriate at the left edge of the left lane. Left edge
swinglines consisting of Type AY markers or Type H markers spaced no closer than 1.2 m on
center for motorists in the number 1 lane may be considered for vehicles turning left from the
exit ramp to the local road on larger intersections and/or through crest vertical curves.
SECTION 5 - SIGNS
The HQ Traffic Liaison shall approve all final signing, striping and signalization plans for
SPIs.
06/22/01 Page 14 of 25
5-300 CENTER/MEDIAN ISLAND SIGNAGE
The center island should be signed with W57 and type N markers placed back-to-back facing
each exit ramp, and type K markers at the noses as shown in Figure 3. Signs should be placed
for maximum visibility to approaching traffic and to reduce the chance for driver confusion
that may be caused by opposing headlights and geometry as discussed in 2-103, “Horizontal
alignment”. Signs in the center island shall be mounted on break away posts.
Median island noses must be signed with R7 signs mounted on break away posts and type K
markers.
5-400 U-TURNS
U-turns are prohibited on the local roads when exit ramp right turns are signalized due to the
overlap of traffic signal phasing. Proper signage must be placed prohibiting this U-turn
movement. R34 (No U-turn) signs may be placed on the traffic signal bridge or adjacent to the
traffic signal heads. U-turns may be allowed at SPIs as long as the U-turn does not conflict
with other movements.
Pedestrian signals must be timed only with the local street through move because of conflicts
with U-turns from exit ramps.
In instances where right turn on red is allowed, a sign indicating that right turn on red is
allowed should be placed. Where right turn on red is not allowed, a sign indicating that right
turn on red is prohibited (R13) shall be placed.
This sign will reduce the risk of driver confusion on the nature of this movement and in
enforcement.
06/15/01 Page 15 of 25
SECTION 6 - TRAFFIC SIGNALS
The HQ Traffic Liaison shall approve all final signing, striping and signalization plans for
SPIs.
Additionally, as is consistent with good design practices and intersection safety, lighting
should not be located where direct or scatter light could possibly reduce the visibility of the
signal indications.
6-200 UNDERCROSSINGS
On SPI undercrossings, traffic signals should be mounted under the structure, to minimize
intersection width. Oversized back plates are recommended to reduce backlight. If
intersection width standards and signal set back requirements can be met, signals may be
placed on the face of the SPI structure.
06/15/01 Page 16 of 25
There shall be no signal heads located at the far side of the intersection facing through traffic
on the local street.
Lighting should be provided at each on ramp entrance. All areas bounded by the crosswalks
should have minimum maintained 1.6 horizontal lux.
For an undercrossing intersection, 70 watts or 100 watts HPS flush mount soffit lighting
should be used. The intersecting point of the centerlines should have the minimum
maintained 6.5 horizontal lux. All areas bounded by the crosswalks should be lit by either
soffit lighting under the structure or by Type 15 electroliers outside the structure area.
The intersection safety lighting should be maintained by the agency responsible for
maintaining the signal, as it is an integral part of the traffic signal.
06/15/01 Page 17 of 25
06/15/01
Figure 1
Typical SPI Layout
Page 18 of 25
06/15/01
Page 19 of 25
Figure 2
Typical Pavement Marking Plan
06/15/01
Figure 3
Page 20 of 25
Partial Signing Plan
06/15/01
Figure 4A
Page 21 of 25
Typical Signal Layout
(Overcrossing)
06/15/01
Figure 4B
Page 22 of 25
Typical Signal Layout
(Undercrossing)
06/15/01
Figure 5A
Typical Lighting Plan
Page 23 of 25
(Undercrossing)
06/15/01
Figure 5B
Typical Lighting Plan
Page 24 of 25
(Overcrossing)
Compact SPI
Figure 6
06/15/01 Page 25 of 25