Schedule For Retail Tariff Rate and Terms & Condition of Supply For FY 2010 11
Schedule For Retail Tariff Rate and Terms & Condition of Supply For FY 2010 11
PATNA
TARIFF
SCHEDULE
The tariffs are applicable for supply of electricity to L.T consumers with a connected
load upto 60 kW for domestic and non-domestic category, upto 99 HP for industrial
(LTIS) and for public water works (PWS) category and upto 100 HP for irrigation
category.
Applicability
Applicable for supply of electricity to domestic purposes such as lights, fans, radios,
televisions, heaters, air-conditioners, washing machines, air-coolers, geysers,
refrigerators, ovens, mixers and other domestic appliances including motor pumps for
lifting water for domestic purposes. This is also applicable to the common facilities in
the multistoried, purely residential apartments, buildings.
This will be applicable to (i) all huts (Kutir) and dwelling houses of rural and urban
poor Below the Poverty Line (BPL) (ii) houses built under schemes like Indira Awas
Yojana and similar such schemes.
i) Hut (Kutir) is meant a living place with mud wall and thatched roof or house built
under Indira Awas Yojana and other similar schemes which shall not exceed
200 Sq ft area.
Applicable to domestic premises in rural areas for a load upto 2 kW not covered by
areas indicated under DS-II and not being fed from urban / town feeders.
Applicable for domestic premises in urban areas covered by Notified area committee
/ Municipality / Municipal Corporation / Development Authority / All District and Sub
divisional towns / Block Head Quarters / Industrial areas /Contiguous Sub urban
areas and also areas getting power from Urban / Town feeders for single phase
supply for load upto 5 kW and three phase supply for load of 5 kW and above. Rural
consumers having sanctioned load above 2 kW will come under this category.
Consumer has the option to take 1-phase or 3-phase supply connection for a load of
5KW.
Applicable for registered societies, for their residential colonies, having not less than
15 houses / flats in the colony. Residential colonies / multistoried residential
complexes taking load in bulk at a single point with a minimum load of 2 kW per flat /
house and maximum total load upto 60 kW.
x 150 Ps/unit
Metered only
subject to Monthly
Minimum Charge of
Rs.35 per connection
per month.
Fuel and Power Purchase Cost Adjustment (FPPCA) charges as applicable will be
charged extra.
OPTIONAL
All those consumer under DS-II category with 3 phase meter connection with contract
demand between 5 kW and 60 kW opting for demand based tariff shall be required to
pay at the rates indicated below:
Applicable for supply of electrical energy for non domestic consumers having
sanctioned load upto 60 kW, using electrical energy for light, fan and power loads for
non – domestic purposes like shops, hospitals, nursing homes, clinics, dispensaries,
restaurants, hotels, clubs, guest houses, marriage houses, public halls, show rooms,
centrally air-conditioning units, offices, commercial establishments, cinemas, X-ray
plants, Non – Government schools, colleges, libraries and research institutes,
boarding / lodging houses, libraries, railway stations, fuel – oil stations, service
stations, All India Radio / T.V. installations, printing presses, commercial trusts,
societies, banks, theatres, circus, coaching institutes, common facilities in
multistoried commercial office / buildings Government and Semi – Government
Offices, Public Museums and other installations not covered under any other tariff
schedule.
Places of worship like temples, mosques, gurudwaras, churches etc. and burial /
crematorium grounds.
Applicable to loads upto 2 kW in rural areas not covered by areas indicated under
NDS – II and not being fed from urban / town feeders.
Consumption Rate
in a month P/unit
(Units)
Unmetered
Connected Load Rs.115/connection/ x x
Upto 500 W (0.5kW) per month
Above 0.5 kW upto1 Rs.135/connection x x
kW per month
Above 1 kW upto 2 Rs.175/connection/ x x
kW per month
Metered x 1-100 units 145
x 101-200 units 165
x Above 200 205
units
x Subject to monthly
minimum charge for Load
upto 500 watts – 30 units
Above 0.5 kW and
upto 1 kW – 50 units
Above 1 kW – 70 units
Rural consumers having sanctioned load above 2 kW will also come under this
category.
Three Phase
Rs.170/kW or part thereof
for loads 5 kW and above
Subject to a monthly minimum charge of 50 units/kW
or part thereof
OPTIONAL
All those consumers under NDS-II with 3 phase supply and contract demand
between 5 kW and 60 kW opting for demand based tariff shall be required to pay at
the rates indicated below:
Subject to
(i) Monthly minimum charge of 70 units per month/kW on recorded demand or
contract demand, whichever is higher.
(ii) If in any month the recorded maximum demand exceeds 110% of contract
demand, that portion of the demand in excess of the contract demand will be
billed at twice the normal rate.
Fuel and Power Purchase Cost Adjustment (FPPCA) charges as applicable will be
charged extra.
Applicable for places of worship like temples, mosques, gurudwaras, churches etc.
and burial / crematorium grounds. If any portion of the premises is used for
commercial purposes, a separate connection shall be taken for that portion and NDS-
II tariff schedule shall be applicable for that service.
Tariff Rates-NDS-III
Fixed charge (Rs.) Energy charges
Consumption in a month Rate P/unit
(Units)
Rs.45 /kW with minimum 1-100 units 215
of Rs.165 per connection 101-200 units 280
/ month Above 200 units 335
For load upto 30 KW. Subject to monthly minimum charge of 50 units/kW
or part thereof.
OPTIONAL
2.3.1 Non-Domestic Service - NDS – III (A) – Demand Based
All those consumers under NDS-III category with 3 phase supply and with contract
demand between 5 kW and 30 kW opting for demand based tariff shall be required to
pay at the rates indicated below:
Fuel and Power Purchase Cost Adjustment (FPPCA) charges as applicable will be
charged extra.
Applicability
Applicable for supply of electrical energy for bonafide use for Agricultural purposes
including Processing of Agricultural Produce, confined to Chaff - Cutter, Thrasher,
Cane crusher and Rice Hauler when operated by the agriculturist in the field or farm
and does not include rice mills, flour mills, oil mills, dal mills or expellers. This is also
applicable to hatcheries, poultries (with more than 1000 birds) and fisheries (Fish
ponds).
3.1 IAS - I
Applicable for all purposes indicated above including Private Tube wells.
Tariff Rates
Unmetered Supply
Rural feeder - Rs.100 / HP per month
Urban feeder - Rs.120 /HP per month
Note: Hatcheries, poultries and fisheries are not covered under unmetered
supply they have to be metered only.
Metered supply
All units
Rural feeder – 80 Ps/unit
Urban feeder – 130 Ps/unit
Subject to monthly minimum energy charges of –
Rural feeder - Rs. 75/HP per month
Urban feeder - Rs.120/HP per month
No FPPCA charges applicable.
3.2 IAS – II
Applicable to State Tube Wells / State lift irrigation pumps / State Irrigation pumps
upto 100 HP.
Unmetered Supply
Rural feeders - Rs.450 /HP per month
Urban feeders - Rs.480/HP per month
Subject to a monthly minimum energy charge of 225 units /HP per month.
Applicability
The tariff is applicable for supply of electricity to low tension industrial consumers
with a connected load upto 99 HP and below including incidental lighting for industrial
processing or Agro – industries purposes, Arc welding sets, Flour Mills, Oil Mills, Rice
Mills, Dal Mills, Atta Chakki, Hauler. Expellers etc.
Tariff Rates
All those consumers under LTS-I category with 3 phase supply and with contract
demand 5 kW to 15 kW opting for demand based tariff shall be required to pay at the
rates indicated below:
Fuel and Power Purchase Cost Adjustment (FPPCA) charges as applicable will be
charged extra.
Consumers with a connected load above 79 HP and upto 99 HP have option to avail
power under LTIS / HTS category.
4.2.1 LTIS-II (A) (Contract demand above 15 kW and upto 60 kW – Demand Based
Tariff)
All those consumers under LTS-II category with 3 phase supply and with contract
demand above 15 kW and upto 60 kW opting for demand based tariff shall be
required to pay at the rates indicated below:
Fuel and Power Purchase Cost Adjustment (FPPCA) charges as applicable will be
charged extra.
The tariff is applicable to Public water works, Sewerage treatment plant and
Sewerage pumping stations functioning under State Government and State
Government Under takings and local bodies.
Energy charges
Fixed charge (Rs.)
Consumption in a month Rate
(Units) (Ps/unit)
Rs. 100/HP or part All units 330
thereof per month
Subject to monthly minimum charge of 165 units /
HP or part thereof.
Applicability
Applicable for supply of electricity for street light system, including signal system in
Corporation, Municipality, Notified area, Committees, Panchayats etc. and also in
areas not covered by Municipality and Notified Area Committee provided the number
of lamps from a point of supply is not less than five. Also applicable for Traffic Lights,
Mast lights / Blinkers etc.
Tariff Rates
ii) For Nagar Palika / NAC / Municipality – 220 units / kW or part thereof.
Fixed Charges
Sl. Light Point Gram Panchayat Nagar Palika / Municipal
No. Wattage NAC / Municipality Corporation
(i) Upto 100 W Rs.60/month Rs.100/month Rs.110/ month
Above 500 watts the rates shall be on pro-rata basis of the rates indicated for 100
Watts.
FPPCA charges as applicable will be charged extra.
The due date for making payment of energy bills or other charges shall be 15 days
from the date of issue of the bill. Rebate will be allowed for making payment of
energy bills on or before due date specified in the bill as given below:
i. Kutir Jyoti (Unmetered) Rs.2/- per connection per month.
ii. DS-I and NDS-I (Unmetered) Rs.3/- per connection per month.
iii. Agricultural and Irrigation pumpsets Rs.5/- per HP/month
(Unmetered)
iv. Street Lights (Unmetered) Rs.3/- per connection/month
v. All metered categories 10 paise per unit, on units billed
In case a consumer makes full payment after due date but within 10 days after the
due date, no DPS shall be leviable for this period but rebate for prompt payment will
not be admissible.
In case a consumer does not pay energy bills in full within 10 days grace period after
due date specified in the bill, a delayed payment surcharge of one and half (1.5)
percent per month or part thereof on the principal amount of bill will be levied from
the due date for payment until the payment is made in full without prejudice to right of
the licensee to disconnect the supply in accordance with Section 56 of the Electricity
Act, 2003. The licensee shall clearly indicate in the bill itself the total amount,
including DPS, payable for different dates after the due date after allowing for the
grace period of 10 days. No DPS shall be charged on DPS arrear. The bill shall
indicate the energy charges for the month, arrears of energy charges and DPS
separately.
Other statutory levies like electricity duty or any other taxes, duties etc., imposed by
the State Government / Central Government or any other competent authority, shall
be extra and shall not be part of the tariff as determined under this order.
In case of meter being defective / damaged / burnt the Board or the consumer as the
case may be shall replace it within the specified period prescribed in “Standards of
Performance for Distribution Licensee”, Regulations issued by the Commission.
Till defective / damaged / burnt meter is replaced the consumption will be assessed
and billed on an average consumption of last 12 months from the date of meter being
out of order. Such consumption shall be treated as actual consumption for all
practical purposes including calculation of electricity duty until the meter is
replaced/rectified.
(i) The billing demand shall be the maximum demand recorded during the month
or 85% of the contract demand whichever is higher.
(ii) Minimum base energy charge will be billed on the basis of energy
consumption at a load factor of 30% and power factor of 90% on contract
demand payable at 423 Ps/unit, monthly.
(iii) Surcharge of 7.5% will be levied on the demand and energy charges for
supply at 6.6 kV.
(iv) If in any month the recorded maximum demand exceeds 110% of contract
demand, that portion of the demand in excess of the contract demand will be
billed at twice the normal charges.
(i) The billing demand shall be the maximum demand recorded during the month or
85% of the contract demand whichever is higher.
(ii) Minimum base energy charge will be billed on the basis of energy consumption
at a load factor of 35% and PF of 90% on contract demand payable at
415 Ps/unit monthly.
The capacity of induction furnace shall be 600 kVA per metric tonne as existing for
determining the contract demand of induction furnace in the existing HTSS service
connections. However, for new connection and if the furnace is replaced with a new
one for the existing connections, the contract demand shall be based on total
capacity of the furnace and equipment as per manufacturer technical specifications,
and in case of difference of opinion, the provisions of clause Nos. 6.39 and 6.40 of
the Bihar Electricity Supply Code shall apply.
Those consumers who are having rolling/re-rolling mill in the same premises will take
additional contract demand for the rolling/re-rolling mill over and above the contract
demand required for induction furnace. The consumer will have the option to
segregate the rolling/re-rolling mill and take separate new connection following all
(i) Minimum monthly charges at Rs. 1233 per kVA of contract demand per month
shall be payable on monthly basis. Minimum hours of supply will be 630 hours
per month. If for any particular month the hours of supply are less than the
minimum assured hours of supply as shown above then the minimum monthly
charges for the month will be –
(ii) The billing demand shall be the maximum demand recorded during the month or
the contract demand whichever is higher.
(iii) If in any month the recorded maximum demand of the consumer exceeds 110%
of contract demand that portion of the demand in excess of the contract demand
will be charged at twice the normal charges.
(iv) If the power is availed at 11 kV a surcharge of five (5)% will be charged extra
on demand and energy charges.
(i) 10 Ps/unit of surcharge, is to be billed for availing supply at lower voltages than
132 kV.
All HT consumers other than Railway traction have the option to take TOD tariff
instead of the normal tariff given in the schedule.
Under the Time of Day (TOD) Tariff, electricity consumption and maximum demand
in respect of HT consumers for different periods of the day, i.e. normal period, peak
load period and off-peak load period, shall be recorded by installing a TOD meter.
The maximum demand and consumption recorded in different periods shall be billed
at the following rates on the tariff applicable to the consumer.
(i) TOD tariff will be optional for all HT consumers having contract demand below
200 kVA. TOD tariff will be mandatory for all HT consumers having contracted
demand of 200 kVA and above. BSEB shall implement this condition within 3
months from the date of this order.
(ii) The facility of aforesaid TOD tariff shall not be available to HT consumers
having captive power plants and/or availing supply from other sources through
wheeling of power.
(iii) The HT industrial consumers who have installed standby generating plants
shall also be eligible for the aforesaid TOD tariff.
(iv) After electing TOD tariff, if any industrial HT consumer on account of some
reasons wants to go back to the earlier tariff according to the agreement, this
facility shall be available to him only once in two years.
All HT consumers except Railway Traction shall be given rebate for higher
consumption as noted below only on excess units consumed.
Rebate on energy
Category Load Factor charge (only on excess
units consumed)
(i) HTS-I Above 50% 3%
(MMC-30% LF) Above 60% 4%
Above 70% 5%
Above 80% 6%
(ii) HTS-II Above 60% 4%
(MMC-40% LF) and Above 70% 5%
(iii) HTSS Above 80% 6%
(MMC-40% LF) Above 90% 7%
(iv) HTS-III Above 70% 5%
(MMC-50% LF) Above 80% 6%
Above 90% 7%
The tariff rates are subject to prompt payment rebate of 1 (one) paise per unit on
units billed provided the bill is paid by due date specified therein. If the consumer
makes full payment after due date but within 10 days after due date, no DPS shall be
leviable for this period but rebate for prompt payment will not be admissible.
Other statutory levies like electricity duty or any other taxes, duties etc., imposed by
the State Government / Central Government or any other competitive authority, shall
be extra and shall not form part of the tariff as determined under this order.
If the monthly average power factor falls below 90% (0.9) he shall pay a surcharge in
addition to his normal tariff at the following rates:
(i). For each fall of 0.01 in power factor One percent on demand and energy
upto 0.80 charge
(ii). For each fall of 0.01 in power factor 1.5 (one and half) percent on demand
below 0.80 and energy charge (Actual Recorded)
For each increase of 0.01 in power 0.5 (half) percent on demand and
factor above 0.90 upto 0.95 energy charge (Actual Recorded)
For each increase of 0.01 in power 1.0 (one) percent on demand and
factor above 0.95 energy charges. (Actual Recorded)
6 Transformer Capacity
The transformer capacity of HT consumer shall not be more than 150% of the
contract demand, consumer found to be utilizing transformer of higher capacity than
admissible for his contracted load, will fall under malpractice.
All HT/EHT consumers having contract demand of 200 kVA and above may be
allowed to have a stand by transformer, whose capacity shall not be more than the
main transformer. The technical/physical arrangement shall be approved by the
Board’s officer before it is installed. If any consumer violates the condition, then line
will be disconnected and standby facility shall be withdrawn.
Considering the special need of the Railway, the RTS consumer may be allowed to
have 100% extra i.e. 200% of the contract demand. Stand by transformer may also
be allowed, which should not be more than the capacity of the main transformer.
In case of meter being defective / damaged / burnt the Board or the consumer as the
case may be shall replace the same within the period specified in “Standards of
Performance for Distribution Licensee” Regulations issued by the Commission. Till
defective meter is replaced the consumption will be assessed and billed on an
average consumption of last 12 months from the date of meter being out of order.
Such consumption shall be treated as actual consumption for all practical purposes
including calculation of electricity duty until the meter is replaced/rectified.
9. The prevailing practice will continue for determining the contract demand of induction
furnaces in the existing services connections. However, for new connections and
where the furnaces are replaced in existing connections, contract demand shall be
based on the total capacity of the furnace and equipment as per manufacturer
technical specifications and in case of difference of opinion, the provisions of clause
No.6.39 and 6.40 of Bihar Electricity Supply Code shall apply.
10. The Government of Bihar had issued “Industrial Incentive Policy Bihar-2006” in order
to create favourable environment and accelerated industrial growth of the State.
The Board shall comply with the Industrial Policy of Government of Bihar. Such
Industrial Policy shall be extended to other eligible consumers who comes under
the Policy.
9.2 Tariff
Fixed charge and energy charge shall be chargeable at one and half times the
normal tariff as applicable to the corresponding appropriate tariff category.
(a) Temporary supply under any category of service may be given for a period
not exceeding 30 days in the first instance. The duration of which, however
may be extended on month-to-month basis subject to maximum of one year.
(b) In addition to the charges mentioned above, the consumer shall have to
deposit the following charges before commencement of the temporary supply:
(i) Estimated cost of erection of temporary service line and dismantling.
(ii) Cost of irretrievable materials which cannot be taken back to service.
(iii) Meter rent for the full period of temporary connection as per appropriate
Tariff Schedule and miscellaneous charges.
(iv) Rental on the cost of materials as per estimate framed but not payable
by the consumer shall be payable at the rate of Rs. 15/- per month on
every Rs. 100/- or part thereof.
(v) Ten per cent on the total cost of the estimate for the temporary service
connection to cover as security for loss of materials and contingencies.
In case such loss is not noticed, the amount will be refunded.
(c) The applicants for temporary supply shall be required to make a deposit in
advance of the cost as detailed above including the energy consumption
charges estimated for full period on the basis of connected load. This will
however, be adjusted against the final bill that will be rendered on
disconnection of supply month to month basis.
1. Seasonal supply shall be given to any consumer on written request to the Board
subject to the following conditions.
2. The meter rent and other charges as provided in the appropriate tariff are
applicable to seasonal loads and would be charged extra for the entire period of
supply.
3. The supply would be disconnected after the end of the period unless the
consumer wants the supply to be continued.
Any reconnection charges have to be borne by the consumer.
4. Consumer proposing to avail seasonal supply shall sign an agreement with the
Board to avail power supply for a minimum period of 3 years in the case of HT,
and 2 years in the case of LT category of supply.
5. The consumers must avail supply in terms of whole calendar month
continuously.
6. The consumer is required to apply for seasonal supply and pay initial cost and
security deposit as an applicant for normal electricity supply.
7. The consumer shall ensure payment of monthly energy bills within 7 days of its
receipt. The supply will be disconnected if payment is not made on due date.
11.0 The Miscellaneous and General charges are approved by the Commission as below:
11.2 Application fee for new connection / reduction of load / enhancement of load /
request for permanent disconnection:
No. Category / class Rate
(i) Kutir Jyoti Exempted
(ii) LT Single phase Rs. 30.00
(iii) LT Three phase Rs. 60.00
(iv) LT Industrial Rs. 100.00
(v) HT Connection Rs. 200.00
If the meter is tested at third party testing laboratory at the request of the consumer
then the fees charged by the testing laboratory will be payable by the consumer.
(a) The consumer (except Kutir Jyoti rural and Kutir Jyoti urban) shall pay initial
security deposit equivalent to the estimated energy charges including fixed /
demand charges for a period of two months or as per the provisions of Bihar
Electricity Supply Code notified by the Commission.
(b) All Central Government and State Government departments are exempted from
payment of security deposit. However all public sector undertakings and local
bodies shall pay security deposit, as applicable.
12.0 The other terms and conditions of supply of electricity not specially provided in this
tariff order will continue to be regulated by the provisions specified in the Bihar
Electricity Supply Code notified by the Commission.
Where,
Qc = Quantity of coal consumed during the adjustment period (in M.T)
=
(SHR x QPg) (1+TSL)x1000 / GCV
RC1 = Weighted average rate of coal supplied ex-power station coal yard as
approved by the Commission for the adjustment period in Rs. / M.T
RC2 = Weighted average rate of the coal supplied ex-power station coal yard as
per actual for the adjustment period in Rs. / M.T
Qo = Quantity of oil (in KL) consumed during the adjustment period
= Generation (in MU) X Specific oil consumption approved by the
Commission (ml. / kWh)
RO1 = Weighted average rate of oil ex-power station (in Rs./KL) approved by
the Commission for the adjustment period
RO2 = Weighted average actual rate of oil ex-power station supplied (in Rs. /
KL) during the adjustment period
QPp = Power purchased from different sources and fed into Board’s system
(in MUs)
Rpp1 = Average rate of power purchase as approved by the Commission
(in Rs. / kWh)
Rpp2 = Average rate of power purchased during the adjustment period
(in Rs. / kWh)
QPg = Board’s own power generation (in MUs) at generator terminal – approved
auxiliary consumption
L = T & D loss as approved by the Commission or actual, whichever is lower.
PSE = Power sold to exempted categories (agriculture (private) and BPL
consumers only)
SHR = Station Heat Rate as approved by the Commission.
TSL = Transit and Stacking Loss as approved by the Commission.
GCV = Weighted average gross calorific value of coal fired at boiler front during
the adjustment period (in Kcal / Kg)
(x) The approved formula is subject to review, as the Commission may deem fit.