Plumbing - Testing-and-Commissioning
Plumbing - Testing-and-Commissioning
#3 INSPECTION, TESTING,
AND COMMISSIONING
Testing and Commissioning (T&C) is a diligent process of planning and performing all
necessary quality controls that encompass the complex PLUMBING SYSTEM of
infrastructures or building with their multiple and complex lines and interconnections.
Significance of Inspection, testing, and commissioning.
a. Anticipate dangers to life and limb before the actual persons use.
b. Necessary Repair or Replacement can be done.
c. In contracts final billing or retention maybe held for the benefit of the
owner or entity.
Floor drain shall be considered as a plumbing fixture and each drain shall
be provided with approved type and hinged strainer plate having the sum
of areas of small holes or gross waterway equal to cross sectional area of
the tailpiece. (NPCP 409.1)
Advanced Notice – RMP authorized by the permit to notify the Administrative Authority that
said work is ready for inspection 3 days notification before the work is inspected.
Responsibility – It shall be the duty of the holder of a permit to make sure that the work will
stand the test prescribed before giving notification and provide all the testing equipment's
and facilities required.
Covering or use – No plumbing or drainage system, building sewer, private sewer disposal
system or part thereof, shall be covered, concealed or put into use until it has been
inspected, tested, and approved as prescribed in the code.
Media – The piping of the plumbing, drainage, and venting system shall be tested with
water-hydrostatic or air-pneumatic.
Pneumatic tests are potentially more dangerous than hydrostatic because of the higher
level of potential energy. Pneumatic tests may be performed only when at least one of the
following conditions exists:
1. When pressure systems are so designed that they cannot be filled with water.
2. When pressure systems are to be used in services where traces of the testing medium
cannot be tolerated.
2. Performing
Mechanic – Check site, plugs, gauges, operate tools/ equipment.
- Pressurize the system gradually until the designated pressure is
achieved. (Gradually means 1/10 of the desired pressure at a time,
on air test gradually to 50% of the desired pressure, inspect for
leaks then gradually 1/10 of the desired pressure at a time)
- Ensure the piping materials does not exceed 50 degrees Celsius.
- Check the pressure gauge for indication of leaks, locate the leak
and repair
3. Recording
Mechanic – Complete the form
Inspector/ Supervisor/ Owners Representative – Counter-sign the
test results
Note:
1. On Extreme weather conditions the test result may show increased or
decreased pressure after 24 hours, that is due to temperature changes that
may expand or constrict the piping system, temperature changes should be
considered on long lines of piping especially on main pipe lines outdoor.
3. When a very small pressure drop was noted, a retest should be performed
with a lower pressure.
Third Party Inspection and Testing Team:
Independent – Hired to ensure that all installations are up to needed quality
standard
Water Storage tanks and pipelines should be cleaned and disinfected upon commissioning
and a minimum of once a year. Where the water supply has high levels of sediments at
certain times of the year, cleaning more often is recommended. If water tastes, looks or
smells unusual - the tank and pipelines needs cleaning. Also to remove algae (plant growth
which produces bad tastes and odors), silt, and bacteria which may be harmful to occupant’s
health.
Procedures:
1. Shut off the valve to the water lines. Drain all water from the tank. If the tank is non-
accessible, proceed directly to Step 5, otherwise continue to Step 2
2. Wash and remove dirt from inside surfaces of tank by means of a high pressure hose or
clean with a disinfected mop.
3. Remove wash water by draining the wash water and sediment from the bottom of the
tank.
4. Rinse the inside surfaces of the water tank with clean drinking water. Again
remove wash/rinse water.
5. Disinfect the inside surfaces of the tank and distribution lines as follows:
a) Fill the tank with clean drinking water (volume enough to flush all pipelines).
b) Add 5 ml of liquid household bleach for every liter of water inside the tank holds. For
example, a 1000L tank content will require 5 L of bleach.
c) Open the valve to the distribution lines.
6. Run water out of all water taps and faucets in the water lines, until the smell of chlorine is
detected in the water.
7. Hold for at least one (1) hour, drain the tank and taps. Purge/ clean for at least fifteen (15)
minutes with the potable water.
Testing Procedure:
Master Plumbers believe we can DO IT!