Project 1

This document outlines the tasks and timeline for an underground pipe work project. It includes 9 total tasks: 1) Layout over 3 days from April 10-12, 2) Excavation for 5 days from April 13-18, 3) Pipe Procurement over 9 days from April 10-19, 4) Pipe Lay from May 7-23, 5) Back filling and compaction from May 18-June 4, 6) Surface construction from May 24-June 14, with the 7) PROJECT START on April 10, and 8) PROJECT FINISH on June 15. The overall duration of the project is 44 days from April 10 to June 15.

Uploaded by

Md. Abdun Nayeem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views1 page

Project 1

This document outlines the tasks and timeline for an underground pipe work project. It includes 9 total tasks: 1) Layout over 3 days from April 10-12, 2) Excavation for 5 days from April 13-18, 3) Pipe Procurement over 9 days from April 10-19, 4) Pipe Lay from May 7-23, 5) Back filling and compaction from May 18-June 4, 6) Surface construction from May 24-June 14, with the 7) PROJECT START on April 10, and 8) PROJECT FINISH on June 15. The overall duration of the project is 44 days from April 10 to June 15.

Uploaded by

Md. Abdun Nayeem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Mode Task Name Duration Start 02 Apr '23 16 Apr '23 30 Apr '23 14 May '23 28 May

;23 16 Apr '23 30 Apr '23 14 May '23 28 May '23 11 Jun '23
W S T M F T S W S T M F T S W S T M F
1 Underground pipe work 44 days Mon Underground pipe work
10-04-23 10-04

2 PROJECT START 44 days Mon PROJECT START


10-04-23 10-04

3 Layout 3 days Mon


10-04-23 10-04 12-04
Layout
4 Excavation 5 days Thu 13-04-23
13-04 18-04
Excavation
5 Pipe Procurement 9 days Mon
10-04-23 10-04 19-04
Pipe Procurement
6 Pipe Lay 15 days Sun 07-05-23
07-05 23-05
Pipe Lay
7 Back filling & 15 days Thu 18-05-23
compaction 18-05 04-06
Back filling & compaction
8 Surface construction 20 days Wed
24-05-23 24-05
Surface construction
9 PROJECT FINISH 0 days Thu 15-06-23

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: Project1
Milestone Inactive Summary Start-only Critical
Date: Fri 22-07-22
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1