0% found this document useful (0 votes)
58 views

Guide EG 1MW and Larger Working Version January 2023 4

1. This guide provides municipalities with a step-by-step process for assessing generator applications that are 1 MW or larger from initial application through commissioning and compliance. 2. The key steps in the process are: application submission, application evaluation, providing a budget quote, completing legal and authorization requirements, design, construction, commissioning, ensuring grid code compliance, and closing out the authorization. 3. The guide includes information on regulatory requirements, technical considerations, indicative equipment costs, connection configurations, and checklists to help municipalities efficiently process large embedded generator applications.

Uploaded by

Dave C
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views

Guide EG 1MW and Larger Working Version January 2023 4

1. This guide provides municipalities with a step-by-step process for assessing generator applications that are 1 MW or larger from initial application through commissioning and compliance. 2. The key steps in the process are: application submission, application evaluation, providing a budget quote, completing legal and authorization requirements, design, construction, commissioning, ensuring grid code compliance, and closing out the authorization. 3. The guide includes information on regulatory requirements, technical considerations, indicative equipment costs, connection configurations, and checklists to help municipalities efficiently process large embedded generator applications.

Uploaded by

Dave C
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 70

Guide for Municipalities on Processing

Embedded Generator Applications 1 MW


and Larger
Revision 1.2

January 2023

Developed under the Municipal Embedded Generation Support Programme

Partners: SALGA, DMRE, GIZ, AMEU

Programme implemented by:

Sustainable Energy Africa NPC, Solar Training Centre, Power System Dynamics, Digsilent Buyisa
2

Document Type: Guide Status: Revision 1.2: Working Version (open


circulation)
Compiled by: Dr Gerhard Botha (technical specialist)
Revision history: Version Date Comments
First internal 23 September 2022
draft
Revision 1 14 October 2022 Initial internal comments addressed
Initial comments from AMEU Grid Code Subcom
addressed
Revision 1.1 9 November 2022 2nd Comments by AMEU Grid Code Subcom
addressed
External reviewer comments addressed
Revision 1.2 20 January 2023 Additional external reviewer comments addressed
Schedule 2 (17Jan2023) regulatory changes included

Acknowledgements
The development of the document was supported and guided by the AMEU Grid Code Subcommittee:

• Vally Padayachee (AMEU Strategic Advisor)


• Bernhardt Lamour (Nelson Mandela Bay Metro)
• Shane Prins (City of Cape Town)
• Marlyn Hendricks (City of Cape Town)

The following people reviewed and contributed to the document:

• Ryno van der Riet (City of Cape Town)


• Ismail Jeffreys (City of Cape Town)
• Sanjeeth Sewchurran (eThekwini Metro)
• Zoë Lincoln (TNEI)
• Nicola Cencelli (independent)
• Philipp Vanicek (GIZ)
• Basetsana Molefyane (GIZ)
• Babalwa Mbobo (GIZ)
• Peter Lilje (MPE Engineering)
• Eleni Papantoniou (MPE Engineering)
• Jonathan Horne (MPE Engineering)
• Geeven Moodley (Digsilent Buyisa)
• Josh Dippenaar (SEA)

Disclaimer: This Guide is intended to help Distributors in processing generator applications. Guide users are
responsible for ensuring all relevant legislation, regulations and other compliances have been adhered to. Neither
the authors or contributors, nor any organisation associated with the development of this Guide are liable for any
loss or damages that may occur as a result of using this Guide.

Comments on the document are welcomed, and should be submitted to:

[email protected] and [email protected] (please include both emails)

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


3

How to use this document


This is a reference document, and is not designed to be read cover-to-cover. The below graphic helps
readers locate sections of relevance more easily.

Section 1
GENERAL and REGULATORY
•INFORMATION PURPOSES: look at for
Background information
context or for information on the regulatory
Overview of the process environment governing EG >1MW
Regulatory context - Electricity sector
Regulatory context - Municipal
Authorisations required

Section 2 •PRACTICAL GUIDANCE: This is the heart


of the document - actions, responsibilities
MUNICIPAL PROCESSES and outputs for both municipal
Step by step guide for assessing generator Distributors and Customers are provided
applications right through to commissioning, for each step of the process
Grid Code compliance and close-out

Section 3
•INFORMATION PURPOSES: look at for
FINANCIAL and BILLING general information on these topics
Background information on tariffs, billing,
metering etc

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


4

Table of Contents
Definitions............................................................................................................................................... 6
General Definitions .............................................................................................................................. 6
Definitions of Parties Involved ............................................................................................................. 7
Acronyms ................................................................................................................................................ 9
1 Introduction .................................................................................................................................. 11
1.1 Purpose of this document ...................................................................................................... 11
1.2 Regulatory overview .............................................................................................................. 12
1.3 Size categories ....................................................................................................................... 15
1.4 Overview of the process: From application to compliance sign-off ......................................... 16
1.5 Municipal own procurement processes .................................................................................. 17
1.6 Other considerations .............................................................................................................. 18
1.7 Life cycle costing considerations ............................................................................................. 21
1.8 Assumptions regarding Distributor capabilities....................................................................... 21
2 Municipal Processes ...................................................................................................................... 22
2.1 Step 1: Application ................................................................................................................. 22
2.2 Step 2: Evaluate Application ................................................................................................... 24
2.3 Step 3: Budget Quote (Grid Strengthening Studies) ................................................................ 33
2.4 Step 4 – Contracting/ Legal compliance and authorisations .................................................... 35
2.5 Step 5: Design ........................................................................................................................ 40
2.6 Step 6: Construction ............................................................................................................... 42
2.7 Step7: Commissioning ............................................................................................................ 44
2.8 Step 8: Grid Code Compliance ................................................................................................ 47
2.9 Step 9: Authorisation Close-Out ............................................................................................. 50
3 Financial and billing considerations ................................................................................................ 51
3.1 Tariffs..................................................................................................................................... 51
3.2 Metering and billing ............................................................................................................... 51
3.3 Budgets and quotes ............................................................................................................... 51
4 References..................................................................................................................................... 52
Appendix A Indicative Cost of Equipment .......................................................................................... 53
Appendix B Connection Configurations and Agreement Options ....................................................... 55

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


5

Appendix C Checklist for Processing Embedded Generator Applications ............................................ 57


Appendix D Summary of Aspects Related to the Grid Impact Study and Grid Strengthening Study ..... 61
D.1 Data Requirements for grid studies ........................................................................................ 61
D.2 Network Study Simulation and Permutations ......................................................................... 61
Appendix E - Grid Code Compliance Tests and Process ..................................................................... 64
E.1 GCC simulations ..................................................................................................................... 64
E.2 Testing of Grid Code Compliance (During Commissioning) ...................................................... 64
E.3 Dry Run .................................................................................................................................. 65
E.4 Compliance testing................................................................................................................. 65
E.5 RMS models ........................................................................................................................... 66
E.6 EMT models ........................................................................................................................... 66
E.7 Power Quality ........................................................................................................................ 66
Appendix F - NERSA Requirements for Generators and Distributors .................................................. 68
F.1 Requirements for generators ................................................................................................. 68
F.2 Requirements of the Distributor (Network Service Provider) .................................................. 69

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


6

Definitions
General Definitions
After Diversity Maximum Statistical value that is used to design networks taking into account
Demand that there is diversity in the demand from customers in the network.
Embedded Generation A legal entity that operates one or more unit(s) that is connected to
the Distribution System.
Alternatively, a legal entity that desires to connect one or more unit(s)
to the Distribution System.
Distribution Code Legal set of documents compiled to establish the reciprocal
obligations of industry participants around the
use of the DS and operation thereof.
EMT Simulations EMT simulations are used to evaluate stability of the network and
results are provided as waveforms.
Grid Code Legal set of documents compiled to establish the reciprocal
obligations of industry participants around the
use of the TS and operation of the interconnected power system (IPS).
May also include reference to the Distribution Code.
Grid Code Compliance Process or status of complying with all relevant requirements from
the South African Grid Code.
Grid Impact Study Simulation study to evaluate the impact of a generator on the
network – may be limited to impact at the Point of Connection, or on
broader network beyond the PoC.
Hosting Capacity Capacity of the grid (Transmission level) or network (Distribution
level) to accommodate generators, i.e. how much generation can be
connected without the need to upgrade any grid components.
Network Study General term for simulation studies to evaluate the impact of a
generator on the Distributor network (sometimes used
interchangeably with ‘Grid Impact Study’.
Network Hosting Study Simulation study to determine the generation hosting capacity of the
network.
Operational Notification Written permission granted by the Distributor for the Customer to
commence with commissioning, or commercial operation.
RMS Simulations RMS simulations are phasor-type simulations, where only the
magnitude and phase of the network variables are evaluated. These
are dynamic simulations to evaluate the stability of the network, but
at a slower time scale than EMT simulations.
Point of connection The electrical node(s) on the Network Service Provider’s network
where the embedded generator‘s electrical equipment is physically
connected to the Network Service Provider‘s electrical equipment.
(Eskom definition in document 240-61268576).
The electrical node on a distribution system where a customer’s
assets are physically connected to the Distributor’s assets (SAGC).
Point of supply Physical point on the electrical network where electricity is supplied
to a customer.
Small Scale Embedded Embedded generator in category A (up to 1 MW).
Generation

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


7

Definitions of Parties Involved


The following parties have relevance to Customer/Generator applications for connection as referred to in
this document:

Entity Definition Role


Customer A customer of the Distributor, i.e. a traditional load Initiate request to connect
or generator. Drive the process
In this document, Customer (capitalized) refers to Ensure continued adherence to the
the customer applying to connect a generator. supply agreement
Consumer A customer that consumes electricity only. None in terms of this document

Prosumer A customer that both consumes and generates Same as customer


electricity.
Generally a net consumer, i.e. over a specific billing
period they consume more electricity than they
generate. Net consumption is not a pre-requisite.
Battery energy storage facilities are also
considered to be prosumers.
Generator 1. A Customer who connects a unit or group of Same as customer
(capitalized) units that generate electricity. The electricity
may be consumed by a customer on-site, or
wheeled to another customer elsewhere on
the network, or sold directly to the Distributor
or Eskom.
2. Generator may refer to a Prosumer or a pure
generator, i.e. that only generates electricity
for export.
generator A unit of group of units that generate electricity.
(not capitalized)
Developer A natural person or a juristic person, whether in Drive the process
the public sector or the private sector, that carries
out building and engineering operations to
establish a development.
Distributor A municipal licensee or its appointed Manage, maintain, operate and expand
representative that constructs, operates and the network.
maintains the distribution network. Approve connection requests.
Informs Eskom.
Installer The installer is the entity that does the physical Install the equipment
installation work. Ensure adherence to the Grid Code
Financier This refers to the entity that provides funding for Fund the process
the development and construction costs of the Conduct due diligence
generator.
Municipality / Owner and licensee of the distribution network in Manage, maintain, operate and expand
Municipal the municipal area. May also be referred to as the the network.
Distributor Distributor or Network Service Provider (NSP). Approve connection requests.
Informs Eskom.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


8

Network Service A legal entity that is licensed to provide network Manage, maintain, operate and expand
Provider services through the ownership and maintenance network.
of an electricity network. Approve connection requests
Informs Eskom.
Eskom State Owned Enterprise and main supplier of Main supplier and owner of national grid
electricity in South Africa. It is (at the time of
publication) a vertically integrated utility
comprising of generation, the system operator,
transmission and distribution.
System The legal entity licensed to be responsible for Control and operate the TS
Operator short-term reliability of the integrated power Dispatch generation
system (IPS), and is in charge of controlling and Balance supply and demand
operating the transmission system (TS) and
dispatching generation (or balancing the supply
and demand) in real time. The SO requires
information on embedded generators connected
to the network for appropriate forecasting and
scheduling of power production. Aspects such as
frequency control are the responsibility of the SO.
Distribution The Distribution Network Operator (DNO) Control and operate the distribution
Network manages the operational aspects of their network. network
Operator This mostly involves voltage regulation and
thermal management of equipment.
Transmission A legal entity that is licensed to own and maintain
Network Service a network on the TS.
Provider
Other municipal Interaction as required by wheeling
Distributors agreements
Traders A legal entity licensed or registered to engage in Comply to licensing conditions
the buying and selling of electricity as a commercial
activity.
Retailer A legal entity licensed to engage in the retail buying Comply to licensing conditions
and selling of electricity as a commercial activity,
whether for the account of the person involved
therein, or on behalf of someone else.

Resellers See Retailer


NERSA A legal entity established in terms of the National Regulate the electricity supply industry
Energy Regulation Act (Act 40 of 2004) in South Africa

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


9

Acronyms
AC Alternating Current
ADMD After Diversity Maximum Demand
AGUP Allowable Grid Unavailability Period
AMEU Association of Municipal Electricity Utilities
B-BBEE Broad-based Black Economic Empowerment
BESF Battery Energy Storage Facility (alternative to BESS)
BESFCC Battery Energy Storage Facility Connection Code
BESS Battery Energy Storage System (alternative to BESF)
CUOSA Connection and Use of System Agreement
DC Direct Current
DMRE Department of Mineral Resources and Energy
DOE Department of Energy
DNO Distribution Network Operator
DS Distribution System
DSO Distribution System Operator
ECSA Engineering Council of South Africa
EG Embedded Generator
EIA Environmental Impact Assessment
ERA Electricity Regulation Act (Act No. 4 of 2006) as amended
EMT Electromagnetic Transient
ERA Electricity Regulation Act
FAT Factory Acceptance Testing
GCAC Grid Code Advisory Committee
GCS Grid Code Secretariat
ha hectare
IDP Integrated Development Plan
IPP Independent Power Producer
IPS Interconnected Power System
IRP Integrated Resource Plan
kV kilovolt
kW kilowatt
LV Low Voltage
MFMA Municipal Finance Management Act
MW Megawatt
MV MegaVolt
MVA MegaVolt-Amperes
MVar MegaVolt-Amperes reactive power
NMD Notified Maximum Demand
NERSA National Energy Regulator of South Africa
NSP Network Service Provider
REIPPPP Renewable Energy Independent Power Producer Procurement Program
REDZ Renewable Energy Development Zone

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


10

RETEC Renewable Energy Technical Evaluation Committee


RMS Root Mean Square
RPP Renewable Power Plant
RPPGC South African Grid Code for Renewable Power Plants
PoC Point of Connection
PoD Point of Delivery
PoS Point of Supply
PPA Power Purchase Agreement
PPP Public-Private Partnership
PQ Power Quality
PV Photovoltaic
SAGC South African Grid Code
SALGA South African Local Government Association
SAT Site Acceptance Testing
SIT Site Integration Testing
SO System Operator
SSEG Small-scale Embedded Generator
ToU Time of Use
TS Transmission System
UoS Use of System

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


11

1 Introduction
Municipalities are experiencing a sharp rise in applications to connect generators to distribution systems.
The size of generation applications has until recently been largely within the Small Scale Embedded
Generator (SSEG) < 1 MW range. However, recent amendments to the Electricity Regulation Act Schedule
2 (reduced licensing requirements) has resulted in many more larger generator connection applications.

In terms of the clause 4(1) of the Distribution Code, Distribution Network Code (NERSA, 2022), Distributors
are obliged to consider connection applications from such generators, whether they have processes and
policies in place for this or not 1. While many of these Distributors have processes to enable Small Scale
Embedded Generators (SSEG) – i.e. below 1 MW - to connect, this is often not the case for larger
generators, and the regulatory and technical environment is substantially different for such generators.
This guide provides support to municipal Distributors in this regard. The focus is on the electrical aspects
of (renewable) generators2 connecting to municipal networks. However, non-electrical compliances and
considerations are also noted, and further references provided.

1.1 Purpose of this document


The document is primarily intended to support municipal Distributors with assessing applications for the
connection of generators 1MW and larger. However, it also provides useful information to prospective
Generators/Customers (or Developers and IPPs) regarding what is permissible and various criteria and
processes that are involved in considering generator connection applications.

The following is covered for the relevant parties:

1. Distributor
a. The process to be followed to enable generator applications
b. Proposed steps to follow to assess the application
c. Assessing the network capacity
d. Role in the evaluation of Grid Code compliance
e. Overview of regulatory processes
2. Generator/Customer
a. Understand the process that the Distributor will follow
b. Checklist of the Distributor requirements
c. Grid/network and Grid Code compliance studies overview
d. Overview of regulatory processes

Note that the document remains a guide. As such, Distributors may modify, add, or remove steps and
requirements as is necessary according to their operational requirements. The intent is to cover all

1
Legal Framework Applicable to Embedded Generation in South African Municipalities. Pinsent Masons for
Sustainable Energy Africa, September 2022. Available at www.sseg.org.za
2 At the time of publication, non-renewable generators have to follow the SAGC – Transmission Code. Some aspects
for licensing etc. may differ from this document. It is, however, unlikely that large non-renewable generators will
require connection to the municipal network. It is anticipated that a new code under development will address all
generator aspects in one document.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


12

processes to be followed, but some aspects may not be covered in detail since they may already be in
place or covered elsewhere, e.g. regulatory approvals for Rights-of-Way, etc.

It remains the responsibility of prospective Generators/Customers to make sure all regulatory, technical,
procedural and other aspects are suitably adhered to in terms of national and municipal frameworks and
requirements.

This document does not cover off-grid applications and/or installations.

1.2 Regulatory overview


This section provides a brief overview of the relevant regulatory aspects. It is not exhaustive since many
aspects are already covered in the standard operation of the Distributor business. Generators need to
comply to these regulatory requirements as applicable. More detail of the non-technical regulations is
provided in section 2.4 (specifically 2.4.12 and 2.4.13).

Note that the current RPP Grid Code does not make a distinction between Generators who sell energy, and
embedded generators largely for self-consumption. Where unclear, Grid Code requirements are to be
applied at the Generator point of connection, not at the Customer point of connection.

1.2.1 General rights and obligations of Distributors and Generators/Customers3


In terms of the ERA and Grid Code, licensed Distributors have an obligation to allow access to generators
in connecting to the network and may not refuse to permit an EG facility to connect provided such access
would not violate any technical and safety requirements as set out in the relevant Grid Codes, license
conditions and tariff schedules.

If the licensed Distributor is unable to provide access to the network at the point of connection applied
for, it must provide reasons and advise the customer of alternative options available, which includes
increasing the capacity of an existing connection.

Each Distributor is required in terms of paragraph 4(2) of the Distribution Code to make available to the
customers the 'Customer Connection Information Guide' which shall cover as a minimum:-

• the process to follow when applying for supply at the specific Distributor;
• information requirements of the Distributor from the customer to effect an appropriate
connection; and
• the process and related timeframes which follow the application.

Municipal Distributors have the duty to develop electricity services policies relating to, inter alia, the
connection of generation systems to the distribution system and to pass and implement by-laws with
respect to the electricity distribution functions.

If there is no policy document or by-law issued by a municipal Distributor governing the application
process for generation systems, the application for connection should be dealt with in accordance with
the Distribution Network Code, the RPP Code, the BESF Code and the ERA, as amended.

3
This section is largely informed by Legal Framework applicable to Embedded Generation In South African
Municipalities. September 2022. Pinsent Masons, for the Municipal Embedded Generation Support Programme,
available at www.sseg.org.za.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


13

The absence of a policy document regulating the application process for connection of an EG facility 1
MW or larger is insufficient grounds for the municipal Distributor to refuse to consider the connection to
the municipality's distribution system. An application for connection can be submitted in accordance with
the provisions of the Distribution Code.

Paragraph 4.4 of the Distribution Code states that the Generator/Customer must enter into a Connection
Agreement with the licensed Distributor before any actual connection to the distribution system can take
place. This will require that Generators/Customers comply with all municipal requirements, including
application and assessment processes. This also implies that, amongst other activities, appropriate
studies are done to ascertain whether Customers, including Generators, can be connected

1.2.2 NERSA licensing / registration


According to the latest Schedule 2 of the ERA4 the following registration and licensing exemptions exist
for EG:

• Exempt from NERSA registration and licensing:


o EG of any size which are primarily for self-consumption (not for wheeling/export)
o EG for wheeling/export up to 100kW
• Require NERSA registration but exempt from licensing:
o EG for wheeling/export over 100kW

EG of any size are exempt from NERSA licensing. The above applies whether the EG has storage or not.

All EG, irrespective of size, need to comply with the Codes and Distributor requirements, and the
Distributor needs to keep a record of these systems.

Although registration is a simpler and quicker process than licensing, there are still requirements to be
complied with and the process can take time5.

More details on NERSA’s registration process and requirements for Generators/Customers and
Distributors are provided in Appendix F.

Note: Although the regulations are not clear on licensing and registration of BESF, it is understood that
stand-alone BESF should be treated as a generator and should comply with registration requirements
based on their output in kW and self-consumption characteristics, as indicated above.

1.2.3 Feasibility of the project


At the time of publication of this document, NERSA will consider the feasibility when assessing the
registration application as per Clause 9.2(b) of the application for registration procedure. It is not clear
what is involved in this assessment by NERSA.

4
First released on 15 December 2022 with a re-release on 17 January 2023 with a minor correction. Available here:
Electricity Regulation Act: Amendment: Licensing Exemption and Registration Notice. Govt Gazette No 47877, 17
January 2023)
5
Note that the recent Energy Action Plan Update, January 2023 released by the South African Government states
that NERSA registration timeframes have now been reduced from 4 months to 19 days.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


14

1.2.4 ERA Section 34 determination 6


The determinations deal with the procurement of new generation capacity by organs of state and ensures
all procurement is in line with the Integrated Resource Plan (IRP). When NERSA considers an application
for a generation license, a primary measure is to check for evidence of compliance with the national
Integrated Resource Plan (IRP). However, with the amendment to Schedule 2 all EG for self-consumption
are exempt from licensing.

For municipal own-procurement (municipal owned or via an IPP), legal analyses indicate that a Section 34
Ministerial Determination is not required for generators > 1MW7 (as long as individual generators are
below any licensing threshold that is set in Schedule 2 of the ERA), but note that DMRE still considers it
necessary (in terms of Regulation 5 of the New Generation Regulations). Such application to the Minister
should be in accordance with Regulation 5 of the New Generation Regulations, including feasibility
studies, proof of compliance with the MFMA and other municipal regulations, and proof of alignment with
the municipal IDP.

1.2.5 Other regulatory requirements


Municipal Distributors should be aware that requirements additional to the Grid Code are implied by the
Distributor’s license conditions, such as safety of staff and the general public.

Installation safety remains the responsibility of the Distributor, delegated to the owner or tenant via
responsibility for the Certificate of Compliance. To this effect, compliance to the relevant documents from
the SANS 10142-series are required, including SANS 10142-2 for larger installations.

6
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022)
7
For example Constitutional and Legislative Competence and Authority of Municipalities to Procure or Buy New
Generation Capacity - Part B: Overview Legal Framework. Western Cape provincial Government MER Programme –
Energy Projects Report, November 2021, and Legal Framework Applicable to Embedded Generation in South African
Municipalities. Pinsent Masons for Sustainable Energy Africa, September 2022.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


15

1.3 Size categories


In terms of the RPPGC and BESFCC, Table 1 lists the following size categories to apply to renewable power
plants and battery energy storage facilities:
Table 1: Generator size categories according to SAGC.

Category Subcategory Size


A1 Up to and including
13.8 kW
A2 Greater than 13.8 and
A Up to 1000 kW
less than 100 kW
A3 Greater than 100 and
less than 1000 kW
B1 From 1 up to and
excluding 5 MW
B8 1-20 MW
B2 From 5 up to and
excluding 20 MW
C Anything above and including 20 MW

These size categories are important since some Grid Code requirements differ between the categories.

The size referred to in Table 1 refers to the rated AC capacity of the generator installation, and not the
anticipated net export capacity.

The term ‘small-scale embedded generation’ (SSEG), refers to category A generators.

Note that while some regulatory documents classify generators according to their apparent power rating
(in kVA or MVA), others classify them only based on their active power output (in kW or MW). In many
instances the two can be used interchangeably, however, it is recommended for consistency that
municipalities communicate with prospective Generators/Customers based on the active power (MW)
output of the generator, with the understanding that reactive power (MVar) range shall meet the
applicable requirements of the Grid Code and apparent power (MVA) shall remain within the rating of all
associated equipment and applicable Grid Code category requirements.

8
Category B is subdivided at 5 MW in the BESFCC only (at the time of publication), but certain requirements, e.g.
power quality, follows the same categorisation in the RPPGC.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


16

1.4 Overview of the process: From application to compliance sign-off


At a high level, the process comprises nine steps as shown below:

•SUBMIT APPLICATION
•Distributor provides information pack
•Customer fills in application form
STEP 1: •Customer pays application fee

•EVALUATE APPLICATION
•Distributor (or developer) undertakes Grid Impact Studies
•Distributor identifies any grid strengthening requirements
STEP 2 •Distributor provides Cost Estimate Letter

•BUDGET QUOTE
•Customer pays Budget Quote fee
•Distributor (or developer) undertakes detailed grid strengthening studies (if needed)
STEP 3 •Distributor costs strengthening etc
•Distributor provides Budget Quote (typically 85% accurate)

•CONTRACTING/LEGAL
•Parties negotatiate relevant agreements, such as the Connection Agreement, Use of System
STEP 4 Agreement, Self-Build Agreement.
•All permitting/authorisation secured

•DESIGN
•Distributor design undertaken (as needed)
STEP 5 •Customer completes design of plant, regulatory approvals

•CONSTRUCTION
•Distributor constructs infrastructure (as applicable, indicated by Grid Impact and Strengthening studies)
•Customer constructs plant
STEP 6 •Distributor monitors & approves connection works

•COMMISSIONING
•Generator Plant Commissioning
STEP 7

•GRID CODE
•Grid Code Compliance verification
STEP 8

•AUTHORISATION CLOSE-OUT
•Distributor checks all documentation, agreements, specifications etc in place
STEP 9 •Formal close-out

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


17

Figure 1: High-Level overview of process (showing progression and relevant party for different steps)

1.5 Municipal own procurement processes9


For municipal own procurement (municipal-owned or IPP power purchase) a competitive process is
required as per the MFMA. Criteria for considering unsolicited bids are articulated in section 113 of the
MFMA and Regulation 37 of Municipal Supply Chain Management Regulations. Power purchase is unlikely
to meet these criteria, and the procurement process should uphold fair, equitable, transparent,
competitive and cost-effective principles.

Any PPA with a duration longer than 3 years needs to comply with MFMA Section 33 processes, including
requirements around public notices and consulting relevant national and provincial government
departments (specific Distributor supply chain policies may also include other conditions in this regard).

Expenditure by municipalities must not only be according to sound procedures but must be included in
council approved budgets, considering both capital costs and operational costs.

Specific Distributor Supply Chain Management Policies may also have relevant provisions regarding such
procurement.

Procurement should be in terms of the Preferential Procurement Policy Framework Act, 2000, and
associated Regulations, including B-BBEE and local content provisions. Exemptions may be applied for
from Department of Trade, Industry and Competition, although in the past these have seldom been
granted. Local content requirements are being revised with a view to facilitating generation
development10.

9
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022).
10
Address by President Cyril Ramaphosa on actions to address the electricity crisis, 25 July 2022.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


18

1.5.1 Public Private Partnership (PPP)


Where the performance of a municipal function by a private party takes place, this may be considered a
PPP and the MFMA and Treasury Guidelines in this regard should be followed. Where the municipal
Distributor is an offtaker of power generated, this is unlikely to be considered a PPP. Similarly, the use of
municipal land for an IPP where the Distributor is an offtaker does not on its own classify this arrangement
as a PPP.

The difference between PPPs and traditional government infrastructure projects

A PPP is defined as a contract between a public‐sector institution and a private party, where the
private party performs a function that is usually provided by the public sector and/or uses state
property by agreement. Most of the project risk (technical, financial and operational) is transferred
to the private party. The public sector pays for a full set of services, including new infrastructure,
maintenance and facilities management, through monthly or annual payments. In a traditional
(non PPP) government project, the public sector pays for the capital and operating costs, and
carries the risks of cost overruns and late delivery. (Source: National Treasury PPP Manual and
Practice Notes).

1.6 Other considerations


This section contains a brief discussion on other issues related to EG on municipal networks.

1.6.1 Self-consumption
Self-consumption generation refers to the condition where the generator is sized mainly to support the
existing load and export to the network is secondary – if it takes place at all. Customers with such
characteristics are also called prosumers. The generator may typically be sized for the customer’s
expected base load (during peak generation). It would typically be installed to reduce the electricity bill.
In the South African context, this may also include the use of storage to allow stand-by operation during
interruptions (such as load-shedding).

Customers should note that self-consumption will potentially have less impact on the network and enable
a simpler assessment process than for generators exporting all of their power. The network impact is
reduced since the maximum instantaneous rejection is limited to relatively small values in line with the
load size, i.e. if the network is adequate for the load it should be able to accommodate the generator.
Note that a grid impact study will still be required – even where customers do not export onto the network
(e.g. to assess generator rejection impact etc).

Self-consumption is not a requirement for customers to connect.

Four-quadrant metering should be installed. For Distributors that do not have any four-quadrant meters
available, an export block device may be applicable as an interim measure. Export may be allowed at a
later stage only when a four-quadrant meter can be installed. It is recommended that the Distributor
monitors the meter for possible reverse feed, even in the presence of reverse block devices.

Note on export/reverse blocking: Note that while EG with reverse blocking can have reduced impact on
the grid, the Grid Code still applies and grid impact studies are still needed.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


19

1.6.2 Peak-load capacity


Peak-load in a power system context refers to the load during peak demand. Thermal generators (e.g.
coal, gas, biomass) can be dispatched during peak load conditions and support the grid during these
periods. Similarly, storage facilities may be able to support peak load.

Therefore, dispatchable, and partially dispatchable embedded generation should be encouraged as this
could potentially support the network and alleviate the impact of loadshedding. This could include
generators having some form of storage.

1.6.3 Upgrading of existing SSEG to >1 MW


Where an existing generator of up to 1MW (i.e. an SSEG) wishes to upgrade output capacity to greater
than 1 MW, the total size of the generator needs to be considered in assessing the application – not just
that of the additional capacity. The full application process therefore needs to be followed for the
Customer’s total generation capacity. This refers to grid impacts, agreements, regulatory authorisations
etc.

1.6.4 Ancillary Services


Ancillary services refer to any function provided by grid-connected generators11 that assists the network
in some way, e.g. voltage control or frequency control. Voltage control is usually implemented via reactive
power control or transformer tap-changer control and can be managed by the Distribution Network
Operator (DNO) or the System Operator (SO). Frequency control is a system-wide phenomenon and
typically managed by the SO.

Apart from reactive power control and frequency response control, both the risk mitigation and recent
government procurement programmes require that the generators provide additional ancillary services,
namely instantaneous reserve and regulating reserve.

These requirements are in the RPP Grid Code but have not been enforced operationally before. The
appropriateness of EG installed for self-consumption to comply with these requirements is under debate,
and future regulatory revisions may modify such requirements. Any Customer wishing to install such a
generator should enquire with the SO and/or NERSA about these requirements as part of their process.
In the interim, should ancillary services be required beyond standard generator capability requirements
listed in the Grid Code, these will be contracted specifically by the SO.

All battery storage facilities of category B2 and up must have the capability to provide ancillary services
by default.

11
Ancillary services may also refer to the grid stability support provided by e.g. large industrial loads, etc. This is
however, not applicable in the current context.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


20

Institutional Capacity / Human Resources


Initial implications for municipal institutional capacity of dealing with increased applications for large generators
to connect can be significant. Potential areas requiring attention in different municipal departments are noted
below:

1. Technical (Evaluation of Application):


a. Planning
Staff capacity will be needed to undertake the following:
i. Network data capture and quality checking
ii. Evaluation of grid impact studies
Should the Distributor wish to do the studies themselves, they will also require staff as follows:
iii. Network studies, including loadflow and fault analysis
b. Protection and SCADA requirements
c. Quality of Supply: Capture, analyse and interpret data. Additional power quality monitors will
also be required.
d. Network control: Give effect to DNO/DSO requirements in terms of the Grid Codes.
e. Maintenance: It is not anticipated that significant additional infrastructure will be required;
therefore staff capacity issues are unlikely, at least in the short term.
However, ensuring adequate training for maintenance in the presence of EG is essential.
2. Finance:
a. Tariffs: extra demands are likely to be limited, although additional tariff structures may be
required as a once-off design. A wheeling tariff will be required where wheeling is allowed.
b. Metering and billing: Small increases in workload are likely. However, with appropriate
database and smart system setup, this increase should remain manageable.
c. Budgets and quotes: Issuing more quotes will be necessary. This will require cooperation with
the electricity planning department.
d. If the municipal Distributor intends to enter into PPAs with Customers installing generators, a
competitive procurement process will be needed in accordance with the MFMA, which will
place additional demands on staff resources.
e. Wheeling: allowing wheeling may result in additional workload; at least a wheeling agreement
will be required in addition to other agreements. Apart from the tariff, additional data
management will be required.
3. Legal:
There may a significant increase in the number of agreements required over and above the standard
Connection Agreement. This may have implications for staff capacity over time as more generators are
connected.

Municipal own generation or IPP procurement:

This is a significant endeavor and typically will require substantial allocation of staff capacity, often need external
expert support, and require staff training to manage such processes.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


21

1.7 Life cycle costing considerations


The Customer should consider life-cycle costing in their feasibility assessment. The purpose of life-cycle
planning is to ensure that the total cost of ownership of an installation is considered. Often, the capital
costs are included and most other aspects are overlooked, e.g. maintenance. An important aspect often
omitted is the decommissioning, removal and site restoration costs.

Aspects such as decommissioning, waste management and site restoration, including financial provisions
for these tasks, would typically be included in the environmental management plan. It is the Distributor’s
prerogative to request these details.

1.8 Assumptions regarding Distributor capabilities


It is assumed that the relevant Distributor already has a suitable process in place to deal with SSEG 12,
based mainly the NRS097-2-suite of documents (NRS, 2020) (NRS, 2014). This guide focusses on the
additional aspects when dealing with generator applications larger than 1 MW.

12
Where a Distributor does not have a process in place for SSEG, contact the SSEG support team for assistance:
[email protected].

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


22

2 Municipal Processes
This section contains the steps to be followed by a Distributor from the time a Customer intending to
install a generator (hereinafter referred to as the ‘Customer’) applies for a connection point, up to the
time of Commercial Operation. High-level descriptions of the Customer processes that may occur in
parallel to the Distributor processes are also provided. No proposed timelines are provided at this stage
and may be added in a future revision of this document.

The processes assumes that no hosting capacity study has been done, i.e. the Distributor does not know
how much generation can be accommodated at various levels in the network. This means that each
application is reviewed on its own, taking other installed and approved generator installations into
account. A hosting capacity study should ideally be done along with the periodic network development
planning exercises, as it will allow for more rapid generator application assessment.

This steps in this section may form the basis for a customised internal municipal guideline.

2.1 Step 1: Application

APPLICATION STAGE SUMMARY:


The Distributor provides the customer with necessary forms and information, and the customer
completes the application form enabling the assessment to proceed.

Distributor:
• Provides information pack to customer, including the application form
• Invoices the customer for the application fee (as applicable)
Customer:
• Completes the application form for generator
• Submits the completed application form
• Pays the application fee

Initial interactions with the Customer should be handled by the Customer Care department (or equivalent
section), who will communicate internally with the Network Planning Department. Future interactions
may be between the Network Planning Department and the Customer directly. The process starts when
a Customer applies for a generator connection point. This application is required in all cases:

1. New generator application – Customer has no supply point yet

2. New generator application – the Customer only has a load supply point (Point of Supply)

3. Amended generator application – the existing generator capacity is increased (or decreased)

Grid stability and network interference is likely to change at the point of connection, hence grid impact
studies are required.

The Distributor should ensure that the Customer understands the process via the provision of an
information pack.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


23

Once the application fee has been paid, the application will be processed, generally by the Distributor’s
Network Planning Department. The customer will receive a Cost Estimate Letter after the evaluation of
the application (Step 2).

NOTE: Other departments / sections will also need to be advised, e.g. quality of supply, protection, legal,
metering and billing. It is important that the relevant people be informed of the generator application as
soon as possible to prevent delays later in the project. It is useful to include these sections and timeline
for the process in an internal municipal guideline.

2.1.1 Application Pack


The base set of documents that the customer should receive are the following:

1. Connection application form


No application can be processed without a certain minimum set of information, as specified
in the application form for larger generators. Critical information includes location/address,
generation technology, intended/preferred point of connection to existing infrastructure (if
known), capacity of generator, intended maximum export capacity, whether storage will be
installed as part of the generation facility and whether charging will be required from the grid.
A template application form can be found here.
2. Invoice for the application fee13
The Distributor should apply an appropriate application fee, which would:
a. Cover the costs incurred by the Distributor in assessing the application and providing a
Cost Estimate Letter (see Step 2)
b. Act as a guarantee that the customer is serious about the application
3. Information pack
This document pack should include a guideline regarding the processes and technical
requirements that the customer needs to meet to connect successfully (e.g. extracts of this
document). It should also contain a set of generic legal agreements which will be applicable.
See Section 2.4 for a list of possible agreements.

The information pack provided should include:

a. Guideline for Municipalities on Processing Embedded Generator Applications Larger than


1 MW (e.g. this document)
b. Connection and Use of System Agreement (CUOSA) (template here)
c. Self-Build Agreement (should the Customer be required to build infrastructure within a
Municipal substation)
d. Wheeling agreement (if applicable - this may be embedded into the CUOSA)
e. Distribution Network Code (NERSA, 2022)
f. Other applicable technical, legal, financial and operational agreements (unique to each
Distributor)
g. Applicable tariff structures

13
As an example, Eskom’s 2022/23 fees on application to produce a Cost Estimate Letter are shown here:

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


24

h. Grid impact study information/specification and requirements


i. Grid Code Compliance Requirements (NERSA, 2022)
j. Policy regarding the allocation or reservation of hosting capacity space on the network

2.2 Step 2: Evaluate Application

EVALUATION STAGE SUMMARY:


This step undertakes studies to determine if the generator can connect to the network or if grid
strengthening is required, as well as assessing protection, power quality and maintenance
implications. A key output is a Cost Estimate Letter (non-binding) to enable the customer to
estimate project financial feasibility.

Distributor (many of these may also be outsourced to the Customer):


• Undertakes Grid Impact Study
• Undertakes short-circuit studies
• Evaluates protection coordination
• Undertakes quality of supply apportioning and expected resonance screening
• Assesses maintenance implications
• Assesses metering implications
• Issues Cost Estimate Letter to Customer
Customer:
• Accepts Cost Estimate Letter (or explores/discusses other options)
• Acknowledgement of protection and power quality parameters/implications

Aspects included in the evaluation are summarised in Figure 2.

Figure 2: Distributor evaluation process and components (‘D’ refers to Appendix D, numbers to section numbers in the document)

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


25

2.2.1 Grid Impact Study


For all generators >1MW simulation studies need to be done to evaluate the impact on the network in
the area. This requires sufficiently detailed information of the surrounding network. This is called the Grid
Impact Study14. High-level guidance is provided in Appendix D.

The Grid Impact Study should:

1. Check for impact on the network in the area to see if the generator can be connected without grid
strengthening, or if such strengthening is necessary
2. Deliver basic information on grid strengthening to enable an indicative Cost Estimate Letter so
Customers can assess financial feasibility of the project.

Note that existing generators are considered during this phase of the evaluation, but other applications
that are not at Budget Quote fee payment stage (Step 3) are typically not considered.

NRS097-2-3 Simplified Connection Criteria for generators <1MW

Small-scale embedded generators (i.e. <1MW) may be evaluated by following a simplified connection
criteria assessment as per the NRS097-2-315 instead of doing grid impact studies. The NRS097-2-3 covers
generator impact at the PoC but also considers the cumulative grid impact (i.e. hosting capacity) of all
other embedded generators on that section of the network, including on the relevant MV feeder.

One of the outputs of a hosting capacity study would be to determine internal, network-specific, simplified
connection criteria for generators larger than 1 MW.

If the proposed connection point and/or surrounding network does not have sufficient capacity for the
generator to connect, the customer should be advised that (a) the process will take longer and (b) the
cost to connect may be significantly higher as network upgrades are needed. An indication of such costs
will be given in the Cost Estimate Letter.

14
Note on terminology: Grid Impact Studies can also be termed Network Studies, or Network Impact Studies – there
appears to be no standard way of using these terms – either locally or internationally. In this document ‘Grid Impact
Studies’ will be used since this is the term familiar to many Distributors.
15
The NRS 097-2-3 criteria may be adapted for local Distributor conditions. Note that the use of the NRS097-2-3 in
evaluating generator connections should be documented in a municipal policy document, which should also clarify
any adaptations to the NRS097-2-3 criteria.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


26

The customer should also be given options to reduce their impact on the network (e.g. by installing a
smaller system) to potentially avoid the need for upgrades.

Fair share of hosting capacity: Municipalities may elect to allocate network capacity for generation
connections on a “first-come, first-served” basis, or to apportion quantities of network capacity to
customers such that the total available capacity can be fairly shared amongst many or all customers,
should they wish to connect a generator at a later stage. Assessments should also consider how much
of other customers’ fair share of the network generator hosting capacity is used, since this affects the
potential cost of connection for future customers. Currently there are no guidelines in place for
sharing of hosting capacity or network upgrade costs, and no legal requirements exist in this regard.

An overview of the network study evaluation process is provided in Figure 2. This figure also indicates
Data requirements, Simulation Permutations and Acceptable Grid Impact, as well as relevant departments
that need to be consulted during the evaluation process, i.e. Protection, Power Quality, Network Control
and Maintenance.

2.2.2 Who should undertake the Grid Impact Studies?


While some municipal distributors will undertake all aspects of impact studies in-house, many do not have
the necessary staff capability or software. Three options are identified:

1. Grid Impact Studies done in-house: provided the Distributor has sufficient staff with appropriate
training and experience using a suitable software package. Associated costs are covered by the
application fee.
2. Outsource to specialist company: the Distributor may outsource the Grid Impact Study to a
specialist company. Associated costs are covered by the application fee.
NOTE: This may imply a more costly application fee, since external consultants may be more
expensive than internal staff. This should be a pass-through cost to the Customer.
3. The Customer’s engineering team does the Grid Impact Study:
a. The Distributor will provide the customer with the Grid Impact Study Specification
Guideline16 which sets out the work to be undertaken.
b. The Distributor’s planning department will provide the necessary network information for
the studies to be done. Network information may need to cover additional parts of the
network up to the Eskom point of delivery to evaluate changes in the agreement with
Eskom as well.
c. The Distributor will evaluate the study to determine if the generator can connect without
adverse impact on the grid.

It is noted that there may be conflict of interest when Customers have their own specialists
to conduct the Grid Impact or Strengthening Studies. For this reason, sign-off by an
independent ECSA registered professional17 is required for these studies – paid for by the

16
Available at https://www.sseg.org.za/grid-impact-study-specification-guide/
17
Ideally, the independent professionally registered person should be procured by the Distributor to reduce conflict
of interest. However, the code of conduct for professionally registered persons mitigates the risk.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


27

Customer - along with any internal reviews that the Distributor conducts (e.g. technical and
financial evaluation committee reviews).

Note: In the case that the Customer does the Grid Impact Study, it is possible that the Grid Strengthening
Study (Step 3) is included to make it a combined study. The proposed solution will still have to be evaluated
by the Distributor and be accepted at the relevant technical and commercial committees.

2.2.3 Protection
Protection aspects include monitoring fault levels as well as to ensure protection coordination. The
Distributor need to evaluate the requirements for updated protection settings or even protection
upgrades during the Grid Impact Study. This should be included in the scope of work of the party
undertaking the study.

Fault Levels
As part of the Grid Impact Studies, fault levels are calculated under all conditions to ensure they remain
within existing equipment specifications. These results provide an input into the protection settings and
selection of protection equipment. Fault current withstand and breaker rupturing values should be
considered to ensure that the system may be operated safely.

Protection Coordination
Protection coordination studies need to be done separately to ensure correct operation of protection for
the various network conditions as well as prevent nuisance tripping where possible.

Auto-reclosers
If there are reclosers upstream of the generator, the speed of closing should be coordinated with the anti-
islanding requirement of the generator. The standard anti-islanding requirement is that generators
disconnect from an islanded network within 2 s. Therefore, reclosing times should be longer than 2 s.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


28

Figure 3: Grid (network) impact study process.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


29

2.2.4 Quality of supply (power quality)


The RPP Grid Code stipulates specific requirements from the Distributor in terms of power quality. Non-
renewable generators should be managed in a similar manner, since these requirements are well
described in the RPP Grid Code. The Connection Agreement allows for appropriate collaboration between
the different parties even in the absence of specific Grid Code requirements (e.g. for non-renewable
generators). The three key aspects are:

1. Background power quality levels

2. Recording power quality going forward

3. Allocating appropriate emission limits to the customer (apportioning)

Figure 4: Power Quality aspects.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


30

Background Levels
The Distribution System Operator (DSO) should supply background power quality information (i.e.
historical information), including reliability of the network. This may be at the closest node in the network
where a PQ recorder is available. If no suitable power quality data is available, the Customer is referred
to the NRS 048-2 compatibility levels. Note that all generators must be designed to withstand the
NRS 048-2 compatibility levels, including appropriate response when these levels are exceeded, e.g.
disconnect from the system to protect themselves.
The background levels should be provided to the Customer along with the Cost Estimate Letter.

Monitoring
It is required that generators larger than 5 MW all have PQ recorders installed at the PoC 18. This may also
be at the customer’s cost, and should be included in the Budget Quote (see Step 3). In line with Grid Code
and legal requirements, these instruments must be compliant to IEC 61000-4-30.
Such installation should be undertaken with or before generator installation.

Note that it is the Customer’s responsibility to monitor power quality at the PoC (monitoring may be
periodic or ongoing/permanent – the latter is suggested for EG>5MW) and they should be informed of this
responsibility. This requirement should also be included in the relevant Distributor policy documents.

Apportioning
The RPP Grid Code requires that apportioning for power quality parameters be done for all generators
larger than 5 MW following the IEC 61000-3-6/7/13 (or as simplified in NRS 048-4) documents.
Apportioning shall be done for voltage harmonics, voltage flicker and voltage unbalance. Other
parameters may be added to a Connection Agreement based on particular local network performance,
such as inter-harmonics, rapid voltage changes etc.
The quality of supply parameters and emission limits needs to be included in the Connection and Use of
System agreement with the Customer. Apportioned power quality emissions levels should be provided
along with the Cost Estimate Letter.

Note: Where the Distributor’s PoD with Eskom may be affected, e.g. reverse power flow to Eskom, it may
be required to update the Connection and Use of System agreement between the Distributor and Eskom.
In this case, the power quality emission limits from the Distributor may change. This needs to be taken into
account when calculating the emission limits for the generator.

2.2.5 Maintenance
The impact of network extensions and/or strengthening on maintenance requirements should be
assessed. The following impacts should be considered:

• additional equipment that requires more personnel to maintain


• additional spares requirements (new network equipment should be the same as existing
equipment as far as possible so that existing spares will be sufficient)

18
The Distributor may also require this of smaller generators should they consider this necessary (in which case it
should be specified in their policy and by-law). As per clause 9(3) of the RPPGC, the RPP shall monitor and report the
power quality. In view of the simplified power quality requirements for units smaller than 5 MW, it is recommended
to require the permanent PQ recorder only for larger units.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


31

Note: appropriate policies to prevent continuation of outdated equipment should be in place.

New equipment may also have special maintenance requirements, e.g. if new breakers are SF6 insulated.
This should be discussed and agreed with the maintenance/operational department, as well as
operational philosophies.

For a network point that may not have high enough reliability, the potential improvement of network
interruption and dip performance should be considered, which may be addressed via improved
maintenance philosophies.

2.2.6 Other considerations


Loadshedding

Where a generator should preferably not be subjected to loadshedding, the connection point may need
to change to ensure that loads may be disconnected while the generator remains connected (if there is
sufficient export capacity). This can be dealt with on a case-by-case basis.

Grid availability

It is good practice to agree on the expected availability of the grid connection point. This is often referred
to as the allowed grid unavailability period (AGUP) per year. Penalties for less availability may be
appropriate in some circumstances e.g. in the Power Purchase Agreement (PPA).

Since loadshedding is outside the control of the Distributor, it should be excluded from AGUP.

Ramp rate(s)

Although the voltage changes are evaluated during the Grid Impact Study, it is better to prevent such
voltage changes. Therefore, appropriate ramp rates should be set where the generator can control this,
e.g. for wind generation tripping off during overspeed conditions, or PV during partially cloudy days.

Battery charging

The potential impact of generators with battery storage, especially after a long interruption, needs to be
evaluated. In general the charging rate should be limited to the ADMD value.

Note that a smaller value than the ADMD may be appropriate in congested networks.

2.2.7 Network operations


The Network Operations Department need to consider the impact of the generator under normal and
contingency scenarios. The following list provides guidance on the key aspects (not an exhaustive list):

1. The daily voltage variations - This may require updating tap-changer settings, or control voltage
levels upstream in the network.
2. Change in power flow - This is evaluated during the Grid Impact Study and some network
contingencies may require specific operating procedures, e.g. requesting a reduction in power
output or changing the reactive power control of the generator.
3. Loadshedding impacts - Generators will reduce the load that is switched out per block during
loadshedding. It may also be desirable to exclude generators from loadshedding schedules to
rather assist the Grid.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


32

2.2.8 Cost Estimate Letter


The cost estimate to the customer should take the following into account:

1. Connection equipment required for construction of the point of connection.


2. Indicative grid strengthening costs19 (if applicable)
3. Protection & control equipment.
4. Design and project management time required from the Distributor to develop and supervise the
connection works.
5. The new meter (if applicable): A four-quadrant meter is required to monitor active and reactive
power in both directions each. Note that time of use for each of these quadrants is also required
(where Time of Use tariffs is a requirement from NERSA).
6. Administrative charges to change the customer to a new tariff (if applicable).
7. Anticipated reduction in equipment lifespan (if deemed necessary) e.g. due to possible DC current
injection and additional harmonic current injection.
8. The Distributor may ask each customer to pay towards future network upgrades, i.e. the
connection fee could include a proportional cost of e.g. future transformer replacements, and/or
conductor upgrades. Ring-fencing on the municipal financial system is a possible option to support
this.

The letter should clarify power quality emissions level apportionment, and should clearly state that the
cost estimate is non-binding. Should the Customer accept the Cost Estimate Letter and choose to proceed
and where strengthening is required, a Grid Strengthening Study will need to be undertaken (see Step 3).

Reserving capacity: The Cost Estimate Letter does not guarantee that the generator will be able to
connect at the proposed point of connection. For example, should another generator apply to connect
to the same network, the available capacity is allocated to the generator who accepts the Budget
Quotation first, i.e. pays the Budget Quote fee.

This will depend on the pricing philosophy, i.e. where the Distributor can fund most of the network
upgrades with a long-term cost-recovery plan, they may not wait for Budget Quote acceptance before
allocating network capacity.

2.2.9 Deliverables and Outputs from Step 2


A report detailing the results of the Grid Impact Study should be compiled and provided to the Distributor
and Customer.

Outputs:

1. Internal outputs (for Distributor):


a. Grid Impact Study and recommendations
b. Indicative grid strengthening options (if relevant)

19
A table with costs is provided in Error! Reference source not found. to assist with the calculation of indicative strengthening c
osts (Appendix A costs need to be adjusted for inflation etc).

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


33

c. Power Quality information and apportioned emission levels


d. Protection impacts and expected upgrades / adjustments required
e. Any potential maintenance impacts
f. Metering changes/implications
g. Details of the calculation of the Cost Estimate for future reference
h. All internal departments/sections sign-off on proposed Cost Estimate
i. Any issues/concerns raised by other Distributor departments/sections
2. External outputs (for Customer):
a. Cost Estimate Letter, including indicative grid strengthening options and costs (if relevant)
b. Protection settings that may be required
c. Background power quality and reliability levels at the PoC
d. Apportioned power quality emission levels

2.3 Step 3: Budget Quote (Grid Strengthening Studies)

BUDGET QUOTE EVALUATION STAGE SUMMARY:


The key component of this step is undertaking the Grid Strengthening Study (only if strengthening
was shown to be necessary in Step 2). If no strengthening is necessary, the Budget Quote can be
prepared for the customer with little additional work. The Budget Quote can then be issued, which,
upon acceptance by the Customer, enables the detailed contracting, design and construction work
to proceed (Steps 4 onwards).

Distributor:
• Issues Budget Quote fee invoice to Customer
• Undertakes (or outsources) detailed Grid Strengthening Study (as relevant)
• Issues Budget Quote to Customer
Customer:
• Pays Budget Quote fee
• Accepts Budget Quote in writing

When the Customer accepts the Cost Estimate Letter, the municipal Distributor invoices for the Budget
Quote fee20 to cover the work involved in undertaking any detailed studies necessary to enable the Budget
Quote to be issued. This quote should have a high certainty level21 to allow the customer to secure
funding.

The Budget Quote fee should reflect the work needed in preparation of the Budget Quote: if no grid
strengthening study is required (as determined in Step 2) the fee should be reduced as the Distributor has

20
Note that the Cost Estimate Letter is a non-binding estimate of the cost implications for the Customer/Generator,
including initial estimate of grid strengthening cost if applicable. The Budget Quote fee covers the work involved in
establishing costs with adequate certainty – including grid strengthening study costs if relevant – such strengthening
costs are then presented in the Budget Quote.
21
Eskom typically issues this quote with an 85% confidence level.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


34

minimal work to do in preparing the Budget Quote. If grid strengthening study is required, the fee should
be adequate to cover this.

Once the Budget Quote fee is paid:

• network capacity allocation can be reserved for the Customer (with a time validity limit, aligned
with NERSA registration timeframes if applicable)
• any grid strengthening studies can commence

Grid strengthening studies should build on the indicative strengthening findings from the Step 2 study,
reviewing different options to select the best one, and establishing adequately detailed equipment
characteristics to enable accurate costing.

A Note on Who Pays for the Infrastructure Upgrades

As explained in NRS 069:2018 section 6.4.3 Table 1, assets paid for by the customer and transferred to
the municipal Distributor cannot be included in the asset base on which the Distributor makes a
financial return. Over time this will erode the municipal asset base and can have an impact on recovery
of refurbishment or maintenance costs.

Although NRS 069 specifically states that it is not applicable to generators, it is recommended that the
legal principle of not making revenue on assets that the customer paid for should be applied regarding
generators too.

Ideally the asset is paid for by the Distributor, and the cost of grid expansion is recovered over time
through tariff charges, or if the Customer pays, they are compensated over time (based on connection
charges).

The NRS 069 speaks of cost apportionment of grid expansions that could benefit future Customers and
also highlights refunds to initial Customers (including reference to the distribution code).

Also refer to the note on Reserving Capacity on p32.

If any department (protection, power quality, maintenance) has not yet given their inputs, it needs to be
covered in this Step. Ensure that inputs given, or concerns raised previously by these
departments/sections are adequately addressed during this stage.

2.3.1 Deliverables and Outputs from Step 3


Outputs:

1. Internal outputs (for Distributor):


a. Compile detailed planning outputs from Grid Impact Study (Step 2), power quality,
protection and maintenance assessments, i.e. all equipment requirements as well as
voltage, current ratings of the equipment, fault levels
b. Detailed outputs of the Grid Strengthening Study (if relevant) including equipment
requirements, ratings and characteristics to enable accurate costing
c. Record of the calculations behind the Budget Quote provided to the customer, including:
i. Details of strengthening equipment costs

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


35

ii. Construction and management costs


iii. PQ metering
iv. All other costs covered by the Cost Estimate Letter, to the necessary level of
accuracy
d. Internal departments/sections sign-off on Budget Quote or future work.
2. External outputs (for Customer):
a. Budget Quote
b. Copies of Network Studies

2.4 Step 4 – Contracting/ Legal compliance and authorisations

CONTRACTING STAGE SUMMARY:


Various agreements need to be in place (depending on the specific situation) between the
Distributor and Customer, and other existing agreements may need amending. In addition,
environmental and land-use authorisations need to be obtained by the Customer.

Distributor:
• Issues relevant generic agreements to Customer
• Issues Letter of Consent to Connect for customer’s NERSA registration/licensing application
(if required)
• Checks environmental and necessary land-use authorisations obtained by customer
Customer:
• Signs relevant agreements
• Applies to NERSA for registration/licensing (if required)
• Obtains necessary environmental and land-use authorisations

The various agreements and authorisations that need to be considered and complied with amongst the
involved parties are discussed below.

Permutations of connection options and agreement requirements are provided in Appendix B.

2.4.1 Implementation Agreement (Distributor-Customer)


In some cases an implementation agreement between the Distributor and Customer/developer may be
applicable to establish the process and timelines for construction, commissioning etc. This is particularly
important where coordination between municipal network upgrading and generator construction is
needed.

2.4.2 Letter of Consent for NERSA application


A letter of consent to connect from the Distributor is required for both license and registration
applications to NERSA by the Customer – if these are needed (note that this is not the Cost Estimate Letter
or Budget Quote). This would normally be issued by the Distributor upon the Customer’s acceptance of
the Budget Quote.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


36

2.4.3 PPA (generator-customer)


A power purchase agreement (PPA) may be in place between two independent parties – a generator and
their customer. The Distributor is not involved in such agreements (unless they are the offtaker), but they
(and/or Eskom) would have a wheeling agreement with these parties. In this case, the Distributor should
include appropriate clauses in the Connection Agreement and/or wheeling agreement, including having
no obligation to purchase energy if a PPA should lapse.

2.4.4 Connection Agreement (Distributor-Customer)


The purpose of such a Connection Agreement is to govern the performance of both parties at the point
of connection. This was previously called the Supply Agreement. Clause 3.2 of the Distribution Network
Code specifically requires a Connection Agreement with Customers, which shall include at least the
following:

1. Project planning data,


2. Inspection, testing and commissioning programs,
3. Electrical diagrams and
4. Any other information the Distributor may deem necessary to proceed with the processing of the
application for connection

Note that point 4 infers that the processing of the Customer application and finalising the
Connection Agreement have interdependencies. Final approvals cannot be given until all required
agreements have been signed off, irrespective of physical installation and/or commissioning
progress.

In addition, the following aspects should also be included in the generator Connection Agreement:

1. Power factor/reactive power requirements


2. Power quality requirements
3. Applicable tariffs for use of the system, including for example reliability fees
4. Legal responsibilities

Distributor-wheeling customer Connection Agreement

A customer that purchases the electricity from a generator via wheeling also needs an updated
Connection (and Use of System) agreement, since the relationship between the Distributor and this
customer changes significantly.

2.4.5 Supply Agreement


See Connection Agreement in section 2.4.4.

2.4.6 Use of System Agreement (UoS)


Previously, the Connection Agreement and Use of System Agreement was combined. However, in some
cases ‘use of system’ aspects may be extracted into a separate agreement for specific
Generator/Customer combinations for practical reasons. It is recommended to have a single combined
Connection and Use of System Agreement for Customers.

An example for a separate UoS could be when a third-party installs a generator onto a privately owned
network, e.g. large factory or residential estate.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


37

2.4.7 Operations Agreement (Distributor-Customer)


An Operations Agreement is required to ensure all parties understand each other’s responsibilities,
especially during the operational phase. Alternatively, operational responsibilities may be included in the
Connection Agreement.

2.4.8 Wheeling Agreement (Generator-Distributor-Customer)


A Wheeling Agreement will include the fees and costs for using the DSO network for all parties involved,
i.e. the generator, the DSO as well as the end customer(s). Note that this may include power quality
parameters and reliability requirements or information as well.

2.4.9 Trading Agreement


The trader acts as a middleman between Generators and Customers. This means the trader will manage
all relevant agreements for their listed Generators and Customers, i.e. power purchase agreements,
selling (tariff) agreements. This arrangement can have significant advantages for Distributors since the
trader can have a single agreement with the Distributor that relates to many Generators and Customers.

To date NERSA has issued few trading licenses.

A trading agreement indicates a reseller (“middleman”) in the distribution of the electricity. Where
applicable, a separate agreement needs to be entered into over and above the PPA. Currently, the
electricity regulation act prohibits that a trader sells electricity at a higher tariff than the Distributor in
whose area they are located.

2.4.10 PPP (Public Private Partnership)


(To be added in further editions of this document)

2.4.11 Potential amendment of Distributor-Eskom agreement


Due to the potential impact at higher voltage levels (higher up in the network) of additional embedded
generation capacity, it may be necessary to review or amend the Connection Agreement with Eskom. This
would typically occur if the Customer/Generator connects at the Distributor’s Point of Delivery (from
Eskom) or if the power flow is changed significantly in the network.

In such cases where reverse feed will occur into the Eskom grid, a similar process will need to be followed
for an amended connection point with Eskom. Note that these costs need to be taken into account in the
Budget Quote, i.e. costs may be passed-through to the Customer.

2.4.12 Environmental and other authorisations22


Environmental authorisations required by Customers are clarified in the National Environmental
Management Act No. 107 of 1998 and Environmental Impact Assessment Regulations Listings Notices.
Such authorisations are necessary before construction. Authorisations may involve a Basic Assessment or
comprehensive assessment (i.e. Scoping and Environmental Impact Reporting Process), depending on
various conditions such as generator size, land requirement, whether it utilises existing infrastructure or

22
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022).

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


38

not, whether it is in an urban area or not, and whether it falls within a Renewable Energy Development
Zone23. As a general guide, the following apply24:

• No environmental assessment required: generators under 10MW, on land <1ha, and involves
distribution/transmission infrastructure below 33kV outside an urban area, or below 275kV in
an urban area
• Basic environmental assessment required: generators between 10 and 20MW, or that cover
>1ha, or involve infrastructure over 33kV outside an urban area or over 275kV in an urban area
• Comprehensive environmental impact assessment required: generators over 20MW, or that
involve infrastructure over 275kV

Based on the above, rooftop solar PV projects are unlikely to require an environmental assessment. Multi-
MW ground-mounted solar generators are likely to take enough land area to trigger an environmental
assessment (~1.6 MW per ha of land). Greenfield sites/ vacant land usually requires a comprehensive
assessment.

There is a national focus on reducing the environmental regulatory requirements for solar projects in
areas of low and medium environmental sensitivity25. Normally, a Basic Environmental Assessment
process can take around 8 months for final approval by a Competent Authority (including a public
participation process) and a Comprehensive Environmental Assessment 16 months. However the January
2023 Energy Action Plan update states that “Embedded Generation projects have been gazetted as
Strategic Integrated Projects, reducing timeframes for environmental authorisations to 57 days” 26.

The Competent Authority is normally the province (although in certain circumstances it may be the
Minister).

Other authorisations that may apply include:

• Water use license (assessment included in the EIA) – associated with significant use of water,
storage of water, discharge into water resources and altering of watercourses, amongst other
criteria. Should this authorisation be necessary, specialist studies will need to be undertaken,
and approval will take at least 90 days. It should be noted that solar and wind projects generally
do not require large amounts of water.
• Biodiversity permit (this need is identified during the EIA) – associated with threatened or
protected species. The permit should be applied for before construction, and can take 20-30
working days.
• National Heritage Resources Permit (this is part of the EIA) – associated with impact on a
national heritage resource. Where applicable, authorisation is required before developing the
project, and approval is part of the environmental authorisation.

23
Due to an in-depth Strategic Environmental Assessments conducted in determining the Renewable Energy
Development Zones (REDZ), the decision-making timeframes are significantly reduced for such zones.
24
See EIA GUIDELINE FOR RENEWABLE ENERGY PROJECTS, Dept of Environmental Affairs, 2013, and associated
Activity Listings GNR 544, GNR545 and GNR546 for a more complete set of criteria.
25
Address by President Cyril Ramaphosa on actions to address the electricity crisis, Union Buildings, Tshwane, 25
July 2022
26
Energy Action Plan Update, January 2023 (page 9). South African Government.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


39

• Approval in terms of the Astronomy Geographic Act – where the site may affect areas declared
uniquely suited to optical or radio astronomy.
• Civil aviation approval – where the plant may impact a runway or airport, a Glint and Glare
Assessment may be needed.
• Mineral and Petroleum Resources Development Regulations - where the use of land may impact
on petroleum resource development. Approval is not required outside of mining areas.
Approval is required prior to using the land, and timeframes are uncertain but the process may
take 6 months.
• Electronic communications approvals – in terms of the Electronic Communications Act 36 of
2005, these may be applicable where ‘electronic communications network facilities’ pass over
private property or interfere with buildings to be erected.
• Atmospheric emissions, waste management, and community hazard management
authorisations may be needed in the case of generators with harmful atmospheric emissions,
utilise waste as a feedstock (biogas or biomass generators), or store hazardous material such as
fuel, respectively27.

As a part of the process of obtaining necessary approvals, required specialist studies may also include
traffic impact, decommissioning and disposal, groundwater, tourism, noise, visual, agricultural potential,
and socio-economic assessments.

Where projects include batteries, a battery energy storage system assessment must be conducted, and
it must be flagged in the environmental assessment.

2.4.13 Land use authorisations


Land zoning and subdivision

A change in zoning may be necessary to establish a generator on a piece of land, such as to a suitable
‘Utility’ zoning. Any such changes need to be consistent with the municipal or provincial Spatial
Development Framework. Typically a rooftop solar PV system (e.g. on a mall) will not require a zoning
change as the principle site activity has not changed. A solar generator developed on vacant land will
typically require rezoning. Depending on the original zoning, an environmental impact assessment may
be triggered.

Subdivision of agricultural land is subject to more stringent approvals in terms of the Subdivision of
Agricultural Land Act 70 of 1970. This normally take 3 to 6 months.

Note that the Energy Action Plan update of January 2023 states that land use authorisations for energy
projects have been priorioritised, and timeframes reduced to 30 days 28.

Depending on the site location, servitudes may also need to be registered by the Customer.

Note that land use is often regarded as one of the more problematic aspects, unless the Customer already
owns the land. Long-term lease and use of land permissions may also be registered at the Deeds office.

National Building Regulations

27
Goldblatt M. Mapping of authorisation processes for renewable energy projects, 2015. PDG
28
Energy Action Plan Update, January 2023 (page 9). South African Government.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


40

Building plan approvals are necessary for site development, which may take between 30 and 60 days.

The built structure needs to be signed off by a suitably qualified person, e.g. ECSA registered civil engineer.
The requirements should be set or confirmed in terms of the National Building Regulations and Standards
Act.

Wind load can play a significant role, even for PV systems, and should not be disregarded.

Municipal land29

Leasing or otherwise using municipal land is regulated by the MFMA and associated Regulations, and
relevant municipal by-laws where established. Depending on the value and length of a land lease,
different conditions for approval apply, ranging from simple Council approval to more complex processes
involving public participation.

2.5 Step 5: Design


2.5.1 Step 5A: Distributor Network Design

NETWORK DESIGN STAGE SUMMARY:


If grid strengthening or upgrades are necessary for the generator to connect, detailed design can
commence once the Budget Quote is accepted. This Step is skipped if no such changes are required.
Interconnection equipment design also takes place in this step.

Distributor:
• Select and specify equipment to be procured and installed
• Provide necessary guidance to customer to design and install interconnection equipment
• Proceed with procurement

Where grid strengthening or upgrades are necessary for the generator to connect, detailed design can
commence once the Budget Quote is accepted. The Grid Strengthening Study provides key parameters
to inform detailed design. The design department process is no different to any other network upgrade
process.

In addition to strengthening design work, interconnection equipment needs to be designed.


Municipalities may elect to perform the design and upgrade work for any interconnection equipment
which will be owned and operated by themselves, but it is recommended that they require customers to
perform this work in accordance with the Distributor’s specification. In this case it may be necessary to
prepare instructions, procedures and specifications for the customer’s team to take this forward.

29
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022).

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


41

During the design stage, all equipment requirements are converted to specifications, e.g. insulation
coordination, protection selection and coordination, transformer specifications etc.

Should a dedicated transformer be selected for a customer, this transformer may be specified for
harmonics and small DC current injection. This may allow for a higher embedded generator penetration
capacity for the same transformer capital costs.

Protection coordination may include that the relays and breakers cannot be unidirectional and should
operate for a fault in any direction.

Design also includes revised Single Line Diagrams, layouts (if necessary), external services, and civil works,
particularly if network reinforcement is needed.

These outputs will allow procurement to proceed.

2.5.2 Step 5B: Generator Planning and Design (Including Grid Code Compliance Studies)

GENERATOR PLANNING AND DESIGN STAGE SUMMARY:


The Customer undertakes all necessary design work, including generator and collector network,
and performs simulations to check Grid Code compliance of designs. Equipment is also specified in
this step.

Customer:
• Undertake the necessary studies for PoC impact (Grid Impact)
• Undertake impact assessments for generator collector network and infrastructure
• Undertake interconnection equipment design if required (see Step 5A)
• Undertake Grid Code Compliance Simulations
• Design generator and related infrastructure
• Specify equipment

2.5.2.1 Grid Impact Study


This Grid Impact Study is limited to evaluating the effect of the generator at the proposed point of
connection (PoC). The studies will evaluate the expected voltage regulation and rapid voltage changes at
the point of connection, assuming a Thevenin equivalent circuit for the upstream network. This study can
be seen, and undertaken, as a subset of the Grid Impact Study that is required by the Distributor (see
section 2.2), although such a PoC impact study is a default requirement for the Customer.

2.5.2.2 Generator Planning and Design


Generator design should comply with Eskom standard 240-61268576, (Standard for the Interconnection
of Embedded Generation) (Eskom, 2018) until NRS097-1 is published.

Part of the generator planning and design is to ensure that all associated equipment that is selected is
appropriately sized. This process is similar to the Grid Impact Study, except here the focus is on the new
generator collector network and infrastructure. Note that transformers should be specified appropriately
for the increased harmonic loading on the transformers.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


42

This design work is entirely the responsibility of the Customer, and the Distributor is not required or
advised to review, approve or accept designs for equipment beyond the Customer PoC.

Simulations

The following simulation studies should be done by the Customer to check that designs align with Grid
Code compliance:

1. Loadflow studies to confirm the following:


a. Voltage levels in the Customer /Generator plant remain within acceptable levels,
b. Loading on all relevant feeders, cables, and transformers to ensure no equipment is
overloaded.
2. Loss evaluation to ensure optimal collector network design and equipment selection.
3. Short-circuit study to evaluate the capabilities of existing equipment (including circuit breakers).

Based on the design and simulation work, equipment should be specified so procurement can proceed.
2.6 Step 6: Construction

Construction of municipal assets (grid strengthening and interconnection equipment) as well as


generator equipment is undertaken in this step.

DISTRIBUTOR NETWORK CONSTRUCTION SUMMARY:


Distributor:
• Procure and install new metering equipment
• If strengthening required:
o Upgrade and/or update protection
o Procure and install new equipment
• If strengthening required and Self-Build selected:
o Review type-test certificates
o Review/attend acceptance testing (FAT, SAT, SIT etc).
o Quality assurance of construction works

GENERATOR PLANT CONSTRUCTION SUMMARY:


Distributor:
• Allow access to connection point for Customer equipment connection
• Review integration equipment installation
• Witness key points during construction
Customer:
• Procure equipment and construct
• Quality assurance during construction (acceptance testing)
• If strengthening required and Self-Build selected:
o Provide all relevant type-test certificates
o Invite and arrange viewing / attendance of acceptance testing (FAT, SAT, SIT etc)

Once designs are complete and appropriate approvals have been given, the construction can commence.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


43

2.6.1 Acceptance testing


During the construction phase, there are tests and quality assurance processes which prove that the
equipment is fit for purpose. Depending on the size of the installation and some specific equipment items,
different tests may be required. It is the responsibility of the Customer to identify and specify which are
applicable. Examples of these tests are:

• Factory Acceptance Testing (FAT) is the testing that’s conducted by the manufacturer in the factory
prior to shipping to site.
• Site Acceptance Testing (SAT) is the testing that’s conducted in the field either by the vendor or by
the on-site commissioning team. These are the standalone tests of the equipment to confirm no
damage during shipping or installation.
• Site Integration Testing (SIT) is the testing conducted on-site to confirm equipment functions as a
subsystem or system.
• Type Testing is the testing that is done on one piece of equipment, for example in an accredited test
laboratory, and accepted as representative of other equipment that are manufactured in the same
way and to the same specifications.

Some tests may form part of the pre-commissioning or commissioning tests.

2.6.2 Construction of municipal network assets


The construction phase will follow the same procedure as any other Distributor construction project, e.g.
new lines or transformers. Many Distributors will outsource this work. In the case of Self-Build
arrangement – where the customer constructs network components that will become part of the
Distributor’s network - the Distributor remains responsible for all quality assurance and
attending/witnessing relevant tests. The Distributor will be required to approve equipment installation
according to the Distributor’s own standards. Key aspects of such standards should be included in the
Connection Agreement.

Internal quality checks, e.g. Clerk of Works inspections, remain the responsibility of the Distributor.

Part of the construction phase includes installing the necessary municipal metering, and potentially
upgrading or updating protection equipment in the case of grid strengthening.

Once the municipal network construction is complete, the Customer should be notified in writing.

2.6.3 Generator construction


The customer will procure and install the necessary generation equipment and undertake quality
assurance during construction. The Distributor will review integration equipment installation as well as
participate in key milestones during the process.

The municipal Distributor should allow access to their substation for cabling termination to the outgoing
feeder to the Customer PoC.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


44

2.7 Step7: Commissioning

COMMISSIONING STAGE SUMMARY:


This step covers all of the checks involved in delivering a fully commissioned generator. These are
largely the responsibility of the Customer, but the Distributor will want to witness key checks and
receive the necessary commissioning documentation.

Distributor:
• Provide Customer with written permission to enable commissioning to proceed
• Attend aspects of generator commissioning (e.g. anti-islanding)
• Check commissioning documentation submitted (commissioning report, anti-islanding
certification)
• Provide Customer written permission for Commercial Operation
Customer:
• Pre-commissioning checklist (internal)
• Pre-commissioning tests (internal)
• Commissioning tests (internal)
• Commissioning checks with Distributor present (e.g. anti-islanding)
• Provide documentation to Distributor (commissioning report, anti-islanding certification)

Commissioning is the process of bringing the newly installed generator and associated equipment into
service and confirming that all operational requirements are met.

2.7.1 Pre-commissioning
Pre-commissioning is done by the Customer to verify that each piece of equipment meets the technical
requirements of the project. Pre-commissioning activities test equipment as standalone items. Tests
during pre-commissioning don’t necessarily operate the equipment as a system yet. Each piece of
equipment is individually confirmed to be ready for further commissioning tests.

The set and sequence of tests depends on the installation, i.e. the type and number of equipment items
installed. A pre-commissioning procedure and checklist should be compiled to ensure that everybody
knows what will happen, as well as what to do should tests go wrong. The safety aspects during pre-
commissioning are extremely important, especially since some protection aspects have not yet been fully
tested and commissioned.

During pre-commissioning, the entire installation is checked to ensure that everything is installed correctly
and is able to operate individually as expected. The following list contains examples of typical electrical
tests:

• Grounding and bonding checks- confirm the integrity of the earthing system that sufficient bonding
between metallic parts is done; by measuring the resistance of bonds.
• Cold loop checks- confirm that all cable and conductors are terminated to the correct terminal blocks.
• Megger checks- apply a voltage across the cable conductor and insulation to confirm that the cable
has not been damaged or punctured to degrade the dielectric properties of the cable.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


45

• Test DC voltage and polarity- confirm that the DC voltage is of the correct magnitude and polarity at
the inverter input, or battery connection points.
• Hot loop checks- confirm calibration settings and ranges of control loops. This confirms that ranges
and setpoints are correct for each control point.
• AC phase checks- verify the installation of each electrical phase in the correct order using a phase
rotation meter.
• Transformer checks-
o Take oil samples before and after energization. The samples are compared to see if any
differences could indicate an internal problem within the transformer.
o Winding resistance measurements are taken as well to measure insulation resistance.
o Transformer ratios are measured once tap changes are set to confirm that the primary and
secondary windings are correct.
o Open circuit tests- conducted to measure the no-load current losses.
o Short-circuit tests performed with reduced voltage to the primary winding to measure full-load
current losses.
• During protection relay testing, primary and secondary injections are performed on CTs and VTs to
verify relay settings are correct.
• Interlock verification (where installed)- interlocks are verified by operating equipment with no bus
voltage applied. Different operating configurations are selected to verify that interlocks are
functioning correctly before applying any bus power to the system.
• Battery discharge tests– confirm how many hours of rated voltage and current can be supplied during
charge and discharge cycles.

The Distributor may require submission of all test reports and certificates prior to commissioning.

2.7.2 Commissioning tests


Once pre-commissioning is complete, commissioning can commence where multiple pieces of equipment
are tested together to function as one system.

Written permission (Operational Notification for Commissioning) should be provided by the Distributor
before synchronisation of the generator with the distribution system is attempted, and the Customer
should ensure that such permission has been obtained.

The set and sequence of tests depends on the installation. A commissioning procedure and checklist
should be compiled, as well as to provide clarity on what to do if things do go wrong.

It is also at this point that certain safety aspects may be tested in the presence of Distributor staff, such
as the anti-islanding function. Note that the SANS 10142 Certificate of Compliance (electrical installation)
should check this as well.

2.7.3 Grid Code Compliance testing coordination


Practical verification of Grid Code compliance takes place after commissioning. More details are provided
in section 2.8.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


46

2.7.4 Documentation
IEC 62446 provides the full set of documentation required for a PV installation. The main items are listed
below. In the absence of similar documentation for other technologies, the below is the recommended
minimum list of documentation to be provided by the Installer to the Customer:

• System data
o Basic system information
o System designer information
o System installer information
• Wiring diagrams
o General
o Array – general specifications (PV-only)
o PV string information (PV-only)
o Array electrical details (PV-only)
o AC system
o Earthing and overvoltage protection
• String layout (PV-only)
• Datasheets
• Mechanical design information
• Emergency systems
• Operation and maintenance information
• Test results and commissioning data

The Distributor will require relevant test results and commissioning data, and proof that anti-islanding
operates correctly.

2.7.5 Commercial Operation


Once the Distributor has received all required documentation and successful commissioning has been
demonstrated, written permission to begin Commercial Operation may be given (Operational Notification
for Commercial Operation).

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


47

2.8 Step 8: Grid Code Compliance

GRID CODE COMPLIANCE (GCC) STAGE SUMMARY:


This step undertakes all checks to achieve compliance with the Grid Code, including the necessary
simulation models, on-site tests and longer-term measurements.

Customer:
• Pre-Construction:
o Compile model of the generator for Grid Code Compliance simulations
o Confirm Grid Code Compliance via simulations
• Post-Construction:
o Submit test procedure to Distributor/RETEC
o Conduct compliance testing dry run
o Conduct compliance tests with Distributor/RETEC
o Submit compliance reports to Distributor/RETEC
• Post-Commercial Operation Date (when commissioning is complete):
o Undertake RMS and EMT modelling
o Submit RMS and EMT modelling reports to Distributor/RETEC
o Undertake power quality compliance assessment
o Submit power quality compliance reports to Distributor/RETEC
Distributor:
• Allocate power quality emissions limits to generators (if >5 MW)
• Confirm that Grid Code compliance is achieved (with RETEC)
• Sign off on power quality assessment

The Grid Code is a set of documents that govern the access to the transmission system (TS) or the
distribution system (DS) and operation of the interconnected power system (IPS). All parties need to
comply to the provisions of the relevant Grid Code(s); this section deals with the requirements for the
renewable embedded power plants.

Compliance to the Grid Code refers to the entire facility and not individual units or turbines. Amendments
to ERA Schedule 2 do not relax any Grid Code requirements.

Note: The RPP Grid Code was written with large generators in mind – typically over 20 MVA. The
appropriateness of requiring grid support and SCADA functionality, for example, for generators of under 5
or 10 MW as is currently required in the Code is under consideration. Should a 2 MW self-consumption PV
installation on a mall be required to support the network in a similar manner to a 100 MW plant? Why
include SCADA capabilities when the municipal Distributor is unlikely to ever have such functionality in
place? Nevertheless, the Grid Code in its current form is legally binding, which is reflected in this document.

Exemptions may be applied for in terms of the relevant governance codes. Note that permanent
exemption requests are seldom approved.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


48

Responsibility for compliance

Responsibility for Grid Code compliance lies with the Customer. The Renewable Energy Technical
Evaluation Committee (RETEC) undertakes compliance assessments and submit results to NERSA who
then certify compliance. The role of the Distributor in the compliance verification process is limited.

Compliance tests every 6 years

In terms of the RPP Grid Code Appendix 9, the compliance assessment tests need to be repeated every 6
years. The results are submitted by the Customer to RETEC and the relevant Distributor for approval in
each cycle.

It is recommended that the Distributor has an internal process to continuously monitor compliance in
terms of impact on the network, e.g. protection coordination, power quality etc.

2.8.1 Control/support requirements of different size generators


Larger units have significantly more requirements in terms of grid support and grid stability than the
smaller generator units. These are shown in Table 2. In Section 13 of the RPP Grid Code, RPP Availability,
Forecast, and SCADA only applies to units larger than 1 MW.
Table 2: Control functions required of RPPs (Table 4 of the RPP Grid Code).

Control function Category A3 Category B Category C


Frequency control X
Absolute production constraint X X X
Delta production constraint X
Power gradient constant X X X
Q control X X
Power factor control X X
Voltage control X X

2.8.2 Renewable Energy Technical Evaluation Committee (RETEC)


Grid Code compliance is evaluated by RETEC, previously consisting of members from Eskom, NERSA and
municipal Distributors. It is done in phases in conjunction with the Distributor: starting with a set of
simulations and measured field data taken during commissioning.

Note that NERSA has accountability to approve the Grid Code compliance status, based on RETEC advice.
RETEC remains responsible for reviewing all Grid Code compliance aspects. The Distributor’s inputs are
often requested, e.g. for power quality.

2.8.3 Grid Code compliance aspects and process


There are several different aspects to Grid Code compliance. An important guide in this regard is the Grid
Code Secretariat document titled Renewable Power Plant Grid Code Compliance Test Guideline - Version
3.0 (GCS, undated), which includes reporting formats. Appendix E provides more information, and key
aspects are summarised below for convenience.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


49

Note that the Customer is responsible and accountable for Grid Code compliance. All steps are to be done
by the Customer to the satisfaction of RETEC. The Distributor may assist in reviewing the results when
requested by RETEC.

GCC simulation

A simulation model of the generator is compiled and a range of simulations performed, including around
frequency tolerance and support, reactive power capabilities, voltage ride-through and harmonic
resonance screening.

Testing of compliance during commissioning

Some commissioning tests also form part of Grid Code compliance (see Step7: Commissioning).

Dry run

This is an internal customer process where all compliance requirements tests are pre-checked in
preparation for formal RETEC evaluation.

Compliance testing

Testing is undertaken in the presence of RETEC delegates, including active power constraint, power
curtailment during frequency variations, reactive power control, power factor control and voltage control
function.

In addition, voltage ride-through and power quality tests are undertaken over a longer time period.

Voltage ride-through requirements are deemed compliant based on the simulation results. However,
should any non-compliance be detected by the Distributor or the Customer, this shall be addressed and
corrected. The timeline for corrections should be agreed between both parties, including NERSA (via
RETEC/GCAC).

For units up to 5 MW, Grid Code compliance can be confirmed by way of type test certificates, i.e. NRS
097-2-1 for harmonic emissions and SANS/IEC61000-3-3/5 for voltage flicker emissions.

For units of 5 MW and larger, the power quality compliance must be measured within 6 months. The
Customer must show, by analysis of the power quality measurements, that the plant complies with the
emission limits. Appendix 13 of the RPPGC provides more guidance on the power quality compliance
aspects.

RMS (phasor type) and EMT models

These models need to be compiled and run to replicate a range of relevant generator performance
characteristics.

Power quality

It is the Distributor’s responsibility to allocate power quality emissions limits to generators larger than
1MW. For smaller generators (less than 1 MVA) NRS097-2-1 may be used. At least one weeks’ worth of
measured power quality data is needed for compliance verification. The current practice is that the

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


50

Distributor needs to sign-off on the power quality assessment before Grid Code compliance will be verified
by RETEC.

2.9 Step 9: Authorisation Close-Out

AUTHORISATIONS SUMMARY:
The Distributor checks that all the necessary authorisations, agreements and compliances are in
place before close-out.
Customer:
• Provides all related information (as per previous sections)
Distributor:
• Checks documentation received
• Formal close-out and informs customer

In this step the Distributor checks all aspects relating to the compliance of the Customer. It includes
confirming the following:

• Network assets have been constructed to their standards, and that they have the necessary
certificates and specifications in their possession.
• Necessary agreements are in place (connection, wheeling etc).
• NERSA registration or licensing completed if relevant.
• Commissioning report complete.
• Grid Code compliance report submitted to RETEC.
• Letter provided by the Grid Code Secretariat that they are satisfied that all Grid Code
requirements have been met.
• Environmental, land use and other authorisations are in place and validated by the necessary
authorities.
• Written permission for Commercial Operation has been issued.

Appendix C provides a checklist which supports this close-out process.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


51

3 Financial and billing considerations


Embedded Generators have an impact on the Distributor financial situation. The two key aspects to
consider are developing distribution Use of System charges for generators, as well as recovering the costs
for additional infrastructure that may be required to connect larger generators to the distribution
network. These impacts are briefly discussed in terms of the tariffs, metering and billing, and budgets and
quotes.

3.1 Tariffs
Managing the integration of several large generators is not a historical competency of most Distributors
and they typically will require additional capacity to manage these operations. Protection and quality of
supply require dedicated staff and sections that cooperate closely with the planning section. Costs for
additional staff members will need to be included in budgets and recovered through cost-reflective tariffs.

Most Distributors do not have NERSA-approved Use of System tariffs for generators and wheeling
customers. Distributors need to determine Use of System tariffs and submit them for approved by NERSA
in order to connect generators to the network.

For prosumers (i.e. customers with generators for the primary purpose of self-consumption), cost-
reflective basic charges are critical to ensure cost recovery despite reduced consumption. Export credits
are also an important element of a prosumer tariff to compensate customers for feeding electricity into
the network. Many Distributors are already implementing export credits in line with the principle of
avoided costs (i.e. export credit compensation should align with the value of what the Distributor would
have paid for that unit of energy from the wholesale market). The principle of export cost compensation
in line with avoided cost is suitable for larger than 1 MW generators.

3.2 Metering and billing


Large customers are often already on an appropriate metering and billing system, including appropriate
“smart” meters (4-quadrant meters) that can both monitor the import and export as well as implement
ToU tariffs. Should the Customer not have an appropriate meter installed, this should be installed as part
of the application before the generator commissioning can take place. Distributor billing systems are often
a hindrance to the implementation of export credits. Upgrading billing systems to accommodate exported
power can be challenging but remains a critical task which should be prioritized.

3.3 Budgets and quotes


Budgeting for future network requirements, e.g. extension, refurbishment, etc. also needs to consider the
impact of more generators on the network. Internal policies and procedures need to be developed to
determine how such capital projects are funded by new Generators30. These types of studies are typically
done as part of network development plans.

The methodology used to calculate connection charges must be approved by NERSA, in line with NRS 069.
If the Transmission System requires modifications to connect the generator, any changes in such charges
to the Distributor should be passed through to that Customer.

30
Infrastructure development capital cost recovery policies of Cape Town and George can be referred to for
examples of such approaches.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


52

4 References
Eskom. (2018). Standard for the Interconnection of Embedded Generation. Eskom.

GCS. (undated). Renewable Power Plant Grid Code Compliance Test Guideline - Version 3.0. RSA Grid Code
Secretariat.

MPE. (2021). Recommended Practice for Grid Code Compliance Studies for Renewable Energy Power Plants
and Hybrid Power Plants (P13906). MPE.

NERSA. (2020). NERSA. Retrieved from https://www.nersa.org.za/wp-content/uploads/bsk-pdf-


manager/2020/09/Generation-Licensing-and-registration-frequently-asked-questions.pdf

NERSA. (2022). NERSA. Retrieved 12 12, 2022, from https://www.nersa.org.za/wp-content/uploads/bsk-


pdf-manager/2022/03/Registration-application-form-2022.doc

NERSA. (2022). NERSA. Retrieved 12 12, 2022, from https://www.nersa.org.za/wp-content/uploads/bsk-


pdf-manager/2021/11/Registration-Application-Procedure.pdf

NERSA. (2022). NERSA. Retrieved from https://www.nersa.org.za/electricity-overview/electricity-grid-


code/

NERSA. (2022). RSA Distribution Code, Distribution Network Code. Pretoria: NERSA.

NERSA. (2022). The South African Grid Code: The Information Exchange Code.

NERSA. (2022). The South African Grid Code: The Network Code.

NRS. (2014). NRS 097 Grid Interconnection of Embedded Generation, Part 2: Small Scale Embedded
Generation, Section 3: Simplified utility connection criteria for low-voltage connected generators.
Johannesburg: NRS.

NRS. (2020). NRS 097 Grid Interconnection of Embedded Generation, Part 2: Small Scale Embedded
Generation, Section 1: Utility Interface (Amendment 2.1 ed.). Johannesburg: NRS.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


53

Appendix A Indicative Cost of Equipment


The following list provides indicative costs of equipment in 2022 that can support cost estimate
determination.

Major summarized item (for detailed cost calculation,


refer to detailed costing sheet for substation works or UoM Cost per unit
MV/LV reticulation works

HV Incomer bays - Outdoor each R 3 440 000

HV outdoor Busbar, bussectionalizers & related shared Lot R 13 490 000


infrastructure

HV Outdoor Feeder breakers each R 4 290 000

HV cable feeder length km R 7 346 640

HV line feeder length km R 2 840 000

HV/33kV transformers each R 13 270 000

HV/11kV transformers each R 13 270 000

33 kV incomer bays (Main sub) each R 1 690 000

33 kV busbar (Main sub) (incl. all building works & Lot R 9 070 000
common services)

33 kV outdoor feeders (Main sub) each R 1 580 000

33kV cables km R 4 500 000

33KV OHL km R 468 445

33/11kV transformers each R 9 050 000

11kV incomers - main sub each R 860 000

11kV busbars - main sub (incl. all building works & Lot R 6 460 000
common services)

11kV Feeders - main sub each R 760 000

11kV primary feeder ring km R 1 090 000

11kV incomers - switching sub each R 571 000

11kV busbars - switching sub (incl. all building works & Lot R 3 349 000
common services)

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


54

11kV Feeders - switching sub each R 500 000

11kV secondary feeder ring km R 720 000

Ring main unit with CT/VT unit each R 394 000

11kV/400V minisub each R 541 000

4-core LV feeder km R 610 000

LV Kiosk each R 13 100

11kV Overhead line km R 360 342

Pole transformer each R 101 921

LV overhead line km R 609 222

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


55

Appendix B Connection Configurations and Agreement Options


Permutations of connection options and associated agreement requirements are provided here.

Customer/Generator selling power to the municipal Distributor

The Customer/Generator sells power to


the municipal Distributor:

• Connection Agreement
(Distributor-Customer/Generator)
• PPA (generator-municipality)

If the generator size is significant, the


Connection Agreement between the
municipal Distributor and Eskom may
require amendment.

Customer/Generator in a municipal network wheeling to a customer in the same network

Generator wheels to a customer –


both in the same municipal
distribution network:

• Connection Agreement
(Distributor-Generator)
• PPA (Generator-customer)
• Wheeling agreement (Generator-
Distributor-customer)

The existing Connection Agreement


between the municipal Distributor and
the customer is amended.

If the generator size is significant, the


Connection Agreement between the
municipal Distributor and Eskom may
require amendment.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


56

Customer/Generator in a municipal network wheeling to a trader in the same network

Customer/Generator wheels to trader –


both on same distribution network:

• Connection Agreement
(Distributor-Generator)
• PPA (Generator-trader)
• Wheeling agreement (Generator-
Distributor-trader)
• Trading agreement (trader-
Distributor)

If the generator size is significant, the


Connection Agreement between the
municipal Distributor and Eskom may
require amendment.

Customer/Generator in a municipal network wheeling across the Eskom network to a customer in


another distributor’s network

Customer/Generator in municipal
network wheels across Eskom network
to a trader on a different Distributor’s
network:

• Connection Agreement (Distributor


1 -Generator)
• PPA (Generator-trader)
• Wheeling agreements:
o Generator-Distributor 1
o Generator-Eskom
o Generator-Distributor 2
• Connection Agreement (Distributor
2 – trader)
• Trading agreement (trader-
Distributor)

Connection Agreement between Eskom


and each municipal Distributor will need
amendment.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


57

Appendix C Checklist for Processing Embedded Generator


Applications
This appendix contains template Checklists for processing embedded generators applications larger than
1 MW. By stepping through the items in each list the Distributor will cover necessary areas in the
assessment of the application.

Distributor Processes
This section covers the Distributor process.

Application Yes N/A Comments/notes


Customer sent fill information pack, forms and
application fee invoice
Application received and complete
Application fee paid
Evaluate Application
Grid Impact Study
Other necessary studies undertaken (short-circuit,
protection coordination, QoS background and
apportioning etc)
Cost Estimate Letter issued
Cost Estimate Letter accepted
Grid strengthening study
Internal Departments sign-off
Planning
Protection
Power Quality
Maintenance
(other)
Budget Quote issued
Budget Quote accepted
NERSA letter of consent
Letter of consent issued (for
registration/license)

Agreements / Contractual Yes N/A Comments/notes


Implementation Agreement
Letter of Consent for use of Distribution network
PPA
Connection
Supply (amended)
Use of System Agreement (UoS)
Operations Agreement

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


58

Wheeling
Trading
PPP (Public Private Partnership)
(other)

Environmental, land use and other approvals Yes N/A Comments/notes


ENVIRONMENTAL APPROVALS AND OTHER AUTHORISATIONS
Environmental authorisation and environmental
management plan
Water Use License / Entitlements
Biodiversity Permit for a restricted activity
Heritage Resources Assessment and Permits
National Forests Act 84 of 1988.
(other)

LAND AND SITE RELATED AUTHORISATIONS AND CONSENTS


Subdivision of Agricultural Land Act 70 of 1970
National Building Regulations and Standards Act 103 of
1977
Municipal site-specific land authorisations (i.e. zoning)
(other)

OTHER AUTHORISATIONS
Astronomy Geographic Advantage Act 21 of 2007, (AGA
Act) permit
Civil Aviation Act 13 of 2009 approval for a wind facility
Mineral Petroleum Resources Development Act 28 of
2002 (MPRDA)- Section 53 approval
Electronic Communications Act 36 of 2005 (ECA)
DMRE ERA Section 34 Ministerial Determination
(other)

Design – Distributor network Yes N/A Comments/notes


Technical specification and approval - Distributor assets
and integration assets
Capital approval
Procurement
Guidance, specs etc provided to customer regarding
interconnection equipment

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


59

Construction – Distributor network Yes N/A Comments/notes


Metering equipment
Strengthening – upgrade protection
Strengthening – equipment installation
Construction – Customer plant/equipment
Type test certificates provided
Acceptance testing attendance

Commissioning Yes N/A Comments/notes


Permission to synchronise generator for commissioning
purposes issued
Attendance at commissioning (e.g. anti-islanding)
Documentation received (commissioning report, anti-
islanding certificate, CoC, engineering sign-off of electrical,
civil, mechanical designs etc)
Permission for Commercial Operation issued

Grid Code Compliance


Grid Code compliance is the Customer/Generator responsibility to prove. RETEC will evaluate and finally
recommend to NERSA to issue the compliance status.

Grid Code Compliance – Distributor responsibilities Yes N/A Comments/notes


Allocate power quality emissions limits
Grid Code compliance achieved (with RETEC)
Sign off on power quality assessment

The below checklist is primarily for use by the Customer.

See also the Grid Code Secretariat document titled Renewable Power Plant Grid Code Compliance Test
Guideline - Version 3.0 (GCS, undated).

Grid Code Compliance - Customer Yes N/A Comments/notes


Simulations
LVRT and HVRT
Active and Reactive Power Capabilities
Active, Reactive and Voltage Control Capabilities
Dynamic Reactive Current Support
Rapid Voltage Fluctuations
Tolerance of Frequency and Frequency support
Short-circuit studies
Protection coordination

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


60

Islanding
Ancillary Services
Instantaneous Reserve
Regulating Reserve
Ramp Rates
Testing
Power Assessment:
Absolute Active Power Constraint
Active Power Gradient Constraint
Active Power Curtailment during Frequency Deviations
Reactive Power (Q) Full Capability of the Plant
(𝑃𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 above 50%)
Reactive power Full Capability of the Plant at 20%
Pmax)
Power Plant Control Modes
Reactive Power (Q) Control at 𝑃𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒
Power Factor Control
Voltage Control
SCADA Testing
Power Quality
Meets emission limits
Filter required and installed
RMS model (usually Digsilent PowerFactory)
EMT model (usually PSCAD)
RETEC
RETEC approval

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


61

Appendix D Summary of Aspects Related to the Grid Impact Study


and Grid Strengthening Study
This section provides an overview of key aspects of relevant grid studies. More comprehensive
information is provided in the Grid Impact Study Specification Guideline31 which enables the specification
of such studies to be undertaken by the customer or consultant, as well as assisting with the evaluation
of such studies.

D.1 Data Requirements for grid studies


Information required for such studies should cover the surrounding network to at least one voltage level
above the PoC. Data shall be accompanied by appropriate single line drawings.

Relevant network data:

• The surrounding network data, at least up to one voltage level above the proposed point of
connection:

o Fault level at the infeed of the equivalent network.

o X/R ratio at the infeed of the equivalent network.

o All cable and conductor parameters, including impedance per length, length of cable or
conductor, topology with dimensions, thermal limits.

o Relevant transformer parameters, including percentage impedance, winding and core losses,
tap changer settings (transformer test sheets).

o Network loading profiles.

o Lumped loads in relevant network areas.

o Other generation in the relevant network (generic information per generation type).

o A list of network contingencies that the Distributor deems realistic (as planned).

D.2 Network Study Simulation and Permutations


A suitable selection of cases needs to be simulated in the network studies, taking the following into
account:

1. Load conditions (at least high and low load)


2. Generation conditions (maximum and minimum generation)
3. Network contingencies

The network operational conditions (voltage levels, loading of equipment etc) need to be within
acceptable levels for all these cases.

D.2.1 Acceptable Grid Impact


The following conditions need to be confirmed to ensure the impact on the network is manageable:

31
Available at https://www.sseg.org.za/grid-impact-study-specification-guide/

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


62

1. Steady-state network conditions:


a. Voltage regulation
b. Thermal loading
2. Fault levels:
a. Impact on network protection and equipment ratings
b. Impact on neighbouring customers’ protection and ratings
c. Maximum fault level withstand capabilities of all equipment
3. Voltage changes (at all nodes in the network):
The requirements can differ. Based on e.g. VDE-AR-N-4105 (2018) recommendations, the voltage
change due to all EG connected on an LV network should be limited to 3%. As the generators
become larger at higher voltage levels (and further apart), this could be increased to 3% or even
5% per generator.
The recommendation is as follows for 100% generation rejection during network normal
conditions:
a. On LV networks, ≤1% per generator
b. On short MV networks with large numbers of customers (high density networks), <1% per
generator
c. On longer MV networks with lower numbers of customers (low density networks), <3%
per generator
d. On higher voltages, <3% per generator
e. On higher voltages and if the generator is dispatchable, the voltage change at unity power
factor can increase to 5%, as long as the voltage change at 0.95 pf (absorbing) remains
<3%
The recommendation is as follows for 100% generation rejection during any credible network
contingency:
a. On LV networks, ≤1% per generator (no change)
b. On short MV networks with large numbers of customers (high density networks), <1% per
generator (no change)
c. On longer MV networks with lower numbers of customers (low density networks), <5%
per generator
d. On higher voltages, <5% per generator
e. On higher voltages and if the generator is dispatchable, the voltage change at unity power
factor can increase to 6%, as long as the voltage change at 0.95 pf (absorbing) remains
<5%
4. Feedback into network:
The maximum energy fed back from the LV to the MV network should be limited to 75% of the
transformer rating to protect the Distributor’s distribution transformers.
• Note that this is for possible DC injection from inverters and does not take harmonic
loading into account. Municipalities are advised to discuss the harmonic impact with the
suppliers of their transformers.
• At higher voltage levels (MV), the generator should have its own transformer connecting
to the network and the impact of feeding back into the network is evaluated using points
1 to 3.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


63

D.2.2 Undertaking the Grid Impact and Strengthening Studies


The typical aspects to be taken into account for a detailed Grid Impact Study are the following:

1. Select an appropriate node on the network where the installation can connect.
In practice this will be a node closest to the planned installation that can successfully transfer the
energy generated.
2. Select an appropriate voltage level for the point of connection:
a. SSEG (up to 1 MW) generally connect at LV
b. Generators >1MW and < 20 MW generally connect at MV
c. Generators larger than 20 MW generally at HV
3. Evaluate network capacity:
a. Voltage levels in surrounding network and one voltage level up
b. Thermal capacity of lines and transformers in surrounding network and one voltage level
up
c. Voltage changes at all nodes in the surrounding network and one voltage level up
4. Evaluate fault levels for all study cases
a. The recommended short-circuit calculation method is according to IEC60909.
5. Adjust generation power factor for maximum leading and lagging and review point 3.
6. Evaluate appropriate network contingencies and review points 3 and 4.
7. Consider alternative point of connection and / or different voltage level.
8. Consider the reliability of the point of connection, i.e. the frequency and duration of interruptions
of this network point. Improved reliability may be required by the Customer/Generator and may
be funded via a special reliability charge as part of the tariff. (Also see AGUP in section 2.2.4).
9. Consider possible change in demand at Eskom Point(s) of Delivery (inform Eskom if relevant,
including consideration of Connection Agreement amendments).

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


64

Appendix E - Grid Code Compliance Tests and Process


This appendix deals with different aspects of Grid Code Compliance from the RPP and BESF Grid Code
Perspective. In the absence of specific guidance for other generation types (i.e. non-renewable
generators), these requirements should be applied. Also see the SAGC, Network Code.

E.1 GCC simulations


A suitable simulation model of the generator plant needs to be compiled. This is usually done as part of
the design stage (see section 2.5.2). To do the Grid Code compliance simulations, all control functions that
will be included in the plant need to be added to the base model used for design. The following key
simulations are then done and presented in report format:

• Tolerance of Frequency and Frequency support


• Active and Reactive Power Capabilities
• Active and Reactive Power, and Voltage Control Capabilities
• Dynamic Reactive Current Support
• Low Voltage Ride Through and High Voltage Ride Through Capabilities
• Harmonic resonance screening (needs to be done in conjunction with the Distributor)

The following studies, which form part of the design of the generator plant phase, are also included during
this phase of simulation studies.

• Short-circuit studies
• Rapid Voltage Fluctuations
• Protection coordination

Apart from the 3 times resonance screening, the latest version of the Grid Code does not require power
quality simulation to prove Grid Code Compliance, and such compliance is proven by using on-site
measurements of all steady-state power quality parameters:

• Voltage and current harmonics,


• Voltage unbalance,
• Voltage flicker.

Note that power quality recorders will also record voltage dips and interruptions. Such information is used
during the RMS and EMT model validation (see sections E.5 and E.6).

A simulation guideline is provided as a separate document - P13906 Recommended Practice for Grid Code
Compliance Studies for Renewable Energy Power Plants and Hybrid Power Plants (MPE, 2021)

E.2 Testing of Grid Code Compliance (During Commissioning)


Some of the testing for Grid Code compliance requirements forms part of the commissioning process.
However, these two different processes should not be confused.

The Grid Code compliance aspects are discussed in sections E.3 to E.7.

An overview of commissioning of the generator installation is dealt with in section 2.7.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


65

E.3 Dry Run


This is an internal process to test all the Grid Code requirements that will be conducted during the
compliance process with RETEC. A test procedure is compiled and submitted to RETEC by the Generator
for approval. Once approved, the test procedure is then performed internally to evaluate compliance
before the formal test commences.

More details can be found in the Grid Code Secretariat document titled Renewable Power Plant Grid Code
Compliance Test Guideline - Version 3.0 (GCS, undated).

E.4 Compliance testing


Compliance testing is done similar to the Dry Run, but in the presence of RETEC delegates. A formal report
is submitted to RETEC after testing. Subsequently, NERSA will approve the report and Grid Code
compliance of the installation.

More details and reporting formats can be found in the Grid Code Secretariat document titled Renewable
Power Plant Grid Code Compliance Test Guideline - Version 3.0 (GCS, undated). Key tests are summarised
below for information. Also refer to Appendix 2 of the SAGC Network Code (NERSA, 2022) and Appendix
3 of the SAGC Information Exchange Code (NERSA, 2022).

The following tests are conducted:

• Absolute active power constraint


• Delta production active power constraint
• Active power gradient constraint
• Power curtailment during frequency variations
o Frequency Controller Response Performance: Under-frequency
o Frequency Controller Response Performance: Over-frequency
• Reactive power control function category B and C
o Reactive power control at Pmax
o Reactive power control at fixed Power of 20% Pmax
• Power factor control
• Voltage control function
o Test 1: Set the Droop to 4%: (Qmax)/4% Un
o Test 2: Set the Droop to 8%: (Qmax)/8% Un
• Testing of SCADA Grid Code Compliance

In addition to the above, the following compliance checks are done over a longer time period:

1. Low Voltage Ride Through and High Voltage Ride Through Capabilities

The LVRT and HVRT cannot be tested due to the impact on the network and neighbouring
customers. The results of the simulation studies are accepted until proven incorrect.

The response of the installation is monitored during normal operations, when faults do occur on
the network. Based on the response of the plant during such conditions, a non-compliance may
be flagged (if it is the case).

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


66

2. Power Quality

Grid Code Compliance for power quality is proven by using on-site measurements only after
commissioning. These are done according to Appendix 13 of the RPP Grid Code.

The report for power quality compliance is sent to the Distributor for approval, before RETEC and
NERSA will consider the compliance.

E.5 RMS models


The required dynamic models must operate under Root Mean Square (RMS) or phasor-domain simulation
and Electromagnetic Transient (EMT) simulation to replicate the performance of the RPP facility or
individual units for analysis of the following network aspects:

(a) RPP impact on network voltage stability


(b) RPP impact on QOS at PoC
(c) RPP switching transients impact on network performance
(d) RPP impact on breakers TRV (Transient Recovery Voltage)
(e) RPP impact on network insulation co-ordination requirements
(f) RPP impact on network protection co-ordination
(g) RPP FRT (Fault Ride Through) capability for different types of faults and positions
(h) RPP response to various system phenomena such as:
(i) switching on the network
(ii) power swings
(iii) small signal instabilities

These models are tested against the commissioning test results and recordings of real events. Section 14
of the RPP code provides details on how the models are to be validated.

E.6 EMT models


EMT models must include all parameters required for EMT simulations such as positive, negative and zero
sequence impedances for all elements, magnetising curves, losses and tap changer data for transformers
as well as positions of surge arresters and their V/I characteristics. EMT models must also include all
protection and control functions of the plant.

These models are tested against the commissioning test results and recordings of real events. Section 14
of the RPPGC and Section 13 of the BESFCC provides details on how the models are to be validated.

E.7 Power Quality


Note the Distributor’s responsibility to allocate the power quality emission limits to all generators larger
than 5 MW.

Compliance to the Grid Code requirements for units smaller than 5 MW is achieved via NRS 097-2-1 and
IEC 61000-3-3 or IEC 61000-3-5 certification of the generator. This means that individual units are tested
according to these standards. For inverters larger than 1 MW, this can be achieved by testing to similar
standards, such as IEEE 1547 or IEEE 519 and the above IEC documents.

Units larger than 5 MW require a suitable measurement data set and analysis in terms of the apportioned
values. This requires at least one week of measured data.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


67

Note that the Distributor must sign off on the power quality assessment before Grid Code compliance will
be issued.

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


68

Appendix F - NERSA Requirements for Generators and Distributors

In terms of ERA Schedule 2 (15 December 2022 updated 17 January 2023)32 the following registration and
licensing requirements apply:

• Exempt from NERSA registration and licensing:


o EG of any size which are primarily for self-consumption (not for wheeling/export)
o EG for wheeling/export up to 100kW
• Require NERSA registration but exempt from licensing:
o EG for wheeling/export over 100kW

Additional notes:

• EG of any size are exempt from NERSA licensing.


• The above applies whether the EG has storage or not.
• All EG, irrespective of size, need to comply with the Codes and Distributor requirements, and the
Distributor needs to keep a record of these systems.
• Although the regulations are not clear on licensing and registration of stand-alone BESF, it is
understood that such BESF should be treated as a generator and should comply with registration
requirements based on their maximum output in kW and self-consumption characteristics, as
indicated above.

For generators required to register, NERSA has the following documents available on their website (at
the time of publication):

• APPLICATION FOR REGISTRATION OF AN ELECTRICITY GENERATION FACILITY IN TERMS OF


SHEDULE 2 OF THE ELECTRICITY REGULATION ACT, 2006 (ACT NO. 4 OF 2006) (NERSA, 2022) (Note
this applies for all generators larger than 100 kW).
• REGISTRATION PROCEDURE IN TERMS OF SCHEDULE 2 OF THE ELECTRICITY REGULATION ACT,
2006 (ACT NO. 4 OF 2006) (NERSA, 2022)

F.1 Requirements for generators


The requirements for generators that NERSA may check compliance with are listed in section 12 of the
registration procedure (these are all included and covered in processes described in this document):

12. STANDARD CONDITIONS FOR REGISTERED FACILITIES

12.1 The registered facilities shall comply with the following technical
standards and/or specifications issued in terms of the Act:

(a) NRS 097 Parts 1 and 2: Grid Interconnection of Embedded Generation

(b) South African Grid Codes

32
Electricity Regulation Act: Amendment: Licensing Exemption and Registration Notice. Govt Gazette No 47877, 17
January 2023)

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


69

(c) South African Grid Code Requirements for Renewable Power Plants

(d) SANS 10142 Parts 1 to 4: The Wiring of Premises

(e) NRS 047: Electricity Supply: Quality of Service

(f) NRS 048: Electricity Supply: Quality of Supply

(g) NRS 057/SANS 474: Code of Practice for Electricity Metering.

F.2 Requirements of the Distributor (Network Service Provider)


The requirements for the Distributor are listed in sections 10 and 11 of the NERSA registration procedure.

10.1 The NSP shall not unreasonably deny grid connection to an eligible generator in accordance
with section 21(3) of the Act, which states:

“A transmission or distribution licensee must, to the extent provided for in the licence, provide non-
discriminatory access to the transmission and distribution power systems to third parties.”

10.2 Any dispute between an eligible generator and the NSP may be referred to NERSA in writing
for resolution.

10.3 The NSP shall take all necessary steps to ensure the safety of their operating personnel with
regard to generation. As a minimum, notices must be placed on the circuits where this generation
is available so that they are visible to the operators. The locations must be marked on all operating
diagrams.

10.4 The NSP must ensure that the generation facilities install appropriate protection and
metering at the connection point.

10.5 The NSP must maintain a database of all generation facilities within its area. The database
shall incorporate, as a minimum, the following information:

a) The technology of the generation

b) The capacity installed

c) Its location (both on the network and GPS)

d) Whether there is energy storage associated with it

e) The customer’s name and account number.

10.6 The NSPs must report the following information to NERSA on an annual basis (within three
(3) months after their financial year-end), or as and when necessary:

(a) The number of installations for each technology

(b) The total capacity for each technology installed

(c) The total energy each technology has generated onto their system in each ‘Time-of-Use tariff’
metered time period

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW


70

(d) Complaints that they have received from customers on the same circuit, as the generation
facility, about quality of supply

(e) All safety-related incidents involving this generation

(f) The tariffs applicable to these installations (if energy is sold to the municipality).

11.1 The HoD: ELC shall submit an annual report (calendar year) to the Electricity Subcommittee
on the registered generation facilities in the Republic of South Africa for noting. This report shall,
as a minimum, contain the:

a) total registered capacity of registered generation facilities;

b) complaints relating to registered generation facilities; and

c) incidents/accidents that occurred as a result of these generation facilities.

11.2 The report shall be shared with the public by publishing it on the NERSA website. If necessary,
the report shall also be shared with other Government entities

End

Guide for Municipalities on Processing Embedded Generator Applications Larger than 1 MW

You might also like