Guide EG 1MW and Larger Working Version January 2023 4
Guide EG 1MW and Larger Working Version January 2023 4
January 2023
Sustainable Energy Africa NPC, Solar Training Centre, Power System Dynamics, Digsilent Buyisa
2
Acknowledgements
The development of the document was supported and guided by the AMEU Grid Code Subcommittee:
Disclaimer: This Guide is intended to help Distributors in processing generator applications. Guide users are
responsible for ensuring all relevant legislation, regulations and other compliances have been adhered to. Neither
the authors or contributors, nor any organisation associated with the development of this Guide are liable for any
loss or damages that may occur as a result of using this Guide.
Section 1
GENERAL and REGULATORY
•INFORMATION PURPOSES: look at for
Background information
context or for information on the regulatory
Overview of the process environment governing EG >1MW
Regulatory context - Electricity sector
Regulatory context - Municipal
Authorisations required
Section 3
•INFORMATION PURPOSES: look at for
FINANCIAL and BILLING general information on these topics
Background information on tariffs, billing,
metering etc
Table of Contents
Definitions............................................................................................................................................... 6
General Definitions .............................................................................................................................. 6
Definitions of Parties Involved ............................................................................................................. 7
Acronyms ................................................................................................................................................ 9
1 Introduction .................................................................................................................................. 11
1.1 Purpose of this document ...................................................................................................... 11
1.2 Regulatory overview .............................................................................................................. 12
1.3 Size categories ....................................................................................................................... 15
1.4 Overview of the process: From application to compliance sign-off ......................................... 16
1.5 Municipal own procurement processes .................................................................................. 17
1.6 Other considerations .............................................................................................................. 18
1.7 Life cycle costing considerations ............................................................................................. 21
1.8 Assumptions regarding Distributor capabilities....................................................................... 21
2 Municipal Processes ...................................................................................................................... 22
2.1 Step 1: Application ................................................................................................................. 22
2.2 Step 2: Evaluate Application ................................................................................................... 24
2.3 Step 3: Budget Quote (Grid Strengthening Studies) ................................................................ 33
2.4 Step 4 – Contracting/ Legal compliance and authorisations .................................................... 35
2.5 Step 5: Design ........................................................................................................................ 40
2.6 Step 6: Construction ............................................................................................................... 42
2.7 Step7: Commissioning ............................................................................................................ 44
2.8 Step 8: Grid Code Compliance ................................................................................................ 47
2.9 Step 9: Authorisation Close-Out ............................................................................................. 50
3 Financial and billing considerations ................................................................................................ 51
3.1 Tariffs..................................................................................................................................... 51
3.2 Metering and billing ............................................................................................................... 51
3.3 Budgets and quotes ............................................................................................................... 51
4 References..................................................................................................................................... 52
Appendix A Indicative Cost of Equipment .......................................................................................... 53
Appendix B Connection Configurations and Agreement Options ....................................................... 55
Definitions
General Definitions
After Diversity Maximum Statistical value that is used to design networks taking into account
Demand that there is diversity in the demand from customers in the network.
Embedded Generation A legal entity that operates one or more unit(s) that is connected to
the Distribution System.
Alternatively, a legal entity that desires to connect one or more unit(s)
to the Distribution System.
Distribution Code Legal set of documents compiled to establish the reciprocal
obligations of industry participants around the
use of the DS and operation thereof.
EMT Simulations EMT simulations are used to evaluate stability of the network and
results are provided as waveforms.
Grid Code Legal set of documents compiled to establish the reciprocal
obligations of industry participants around the
use of the TS and operation of the interconnected power system (IPS).
May also include reference to the Distribution Code.
Grid Code Compliance Process or status of complying with all relevant requirements from
the South African Grid Code.
Grid Impact Study Simulation study to evaluate the impact of a generator on the
network – may be limited to impact at the Point of Connection, or on
broader network beyond the PoC.
Hosting Capacity Capacity of the grid (Transmission level) or network (Distribution
level) to accommodate generators, i.e. how much generation can be
connected without the need to upgrade any grid components.
Network Study General term for simulation studies to evaluate the impact of a
generator on the Distributor network (sometimes used
interchangeably with ‘Grid Impact Study’.
Network Hosting Study Simulation study to determine the generation hosting capacity of the
network.
Operational Notification Written permission granted by the Distributor for the Customer to
commence with commissioning, or commercial operation.
RMS Simulations RMS simulations are phasor-type simulations, where only the
magnitude and phase of the network variables are evaluated. These
are dynamic simulations to evaluate the stability of the network, but
at a slower time scale than EMT simulations.
Point of connection The electrical node(s) on the Network Service Provider’s network
where the embedded generator‘s electrical equipment is physically
connected to the Network Service Provider‘s electrical equipment.
(Eskom definition in document 240-61268576).
The electrical node on a distribution system where a customer’s
assets are physically connected to the Distributor’s assets (SAGC).
Point of supply Physical point on the electrical network where electricity is supplied
to a customer.
Small Scale Embedded Embedded generator in category A (up to 1 MW).
Generation
Network Service A legal entity that is licensed to provide network Manage, maintain, operate and expand
Provider services through the ownership and maintenance network.
of an electricity network. Approve connection requests
Informs Eskom.
Eskom State Owned Enterprise and main supplier of Main supplier and owner of national grid
electricity in South Africa. It is (at the time of
publication) a vertically integrated utility
comprising of generation, the system operator,
transmission and distribution.
System The legal entity licensed to be responsible for Control and operate the TS
Operator short-term reliability of the integrated power Dispatch generation
system (IPS), and is in charge of controlling and Balance supply and demand
operating the transmission system (TS) and
dispatching generation (or balancing the supply
and demand) in real time. The SO requires
information on embedded generators connected
to the network for appropriate forecasting and
scheduling of power production. Aspects such as
frequency control are the responsibility of the SO.
Distribution The Distribution Network Operator (DNO) Control and operate the distribution
Network manages the operational aspects of their network. network
Operator This mostly involves voltage regulation and
thermal management of equipment.
Transmission A legal entity that is licensed to own and maintain
Network Service a network on the TS.
Provider
Other municipal Interaction as required by wheeling
Distributors agreements
Traders A legal entity licensed or registered to engage in Comply to licensing conditions
the buying and selling of electricity as a commercial
activity.
Retailer A legal entity licensed to engage in the retail buying Comply to licensing conditions
and selling of electricity as a commercial activity,
whether for the account of the person involved
therein, or on behalf of someone else.
Acronyms
AC Alternating Current
ADMD After Diversity Maximum Demand
AGUP Allowable Grid Unavailability Period
AMEU Association of Municipal Electricity Utilities
B-BBEE Broad-based Black Economic Empowerment
BESF Battery Energy Storage Facility (alternative to BESS)
BESFCC Battery Energy Storage Facility Connection Code
BESS Battery Energy Storage System (alternative to BESF)
CUOSA Connection and Use of System Agreement
DC Direct Current
DMRE Department of Mineral Resources and Energy
DOE Department of Energy
DNO Distribution Network Operator
DS Distribution System
DSO Distribution System Operator
ECSA Engineering Council of South Africa
EG Embedded Generator
EIA Environmental Impact Assessment
ERA Electricity Regulation Act (Act No. 4 of 2006) as amended
EMT Electromagnetic Transient
ERA Electricity Regulation Act
FAT Factory Acceptance Testing
GCAC Grid Code Advisory Committee
GCS Grid Code Secretariat
ha hectare
IDP Integrated Development Plan
IPP Independent Power Producer
IPS Interconnected Power System
IRP Integrated Resource Plan
kV kilovolt
kW kilowatt
LV Low Voltage
MFMA Municipal Finance Management Act
MW Megawatt
MV MegaVolt
MVA MegaVolt-Amperes
MVar MegaVolt-Amperes reactive power
NMD Notified Maximum Demand
NERSA National Energy Regulator of South Africa
NSP Network Service Provider
REIPPPP Renewable Energy Independent Power Producer Procurement Program
REDZ Renewable Energy Development Zone
1 Introduction
Municipalities are experiencing a sharp rise in applications to connect generators to distribution systems.
The size of generation applications has until recently been largely within the Small Scale Embedded
Generator (SSEG) < 1 MW range. However, recent amendments to the Electricity Regulation Act Schedule
2 (reduced licensing requirements) has resulted in many more larger generator connection applications.
In terms of the clause 4(1) of the Distribution Code, Distribution Network Code (NERSA, 2022), Distributors
are obliged to consider connection applications from such generators, whether they have processes and
policies in place for this or not 1. While many of these Distributors have processes to enable Small Scale
Embedded Generators (SSEG) – i.e. below 1 MW - to connect, this is often not the case for larger
generators, and the regulatory and technical environment is substantially different for such generators.
This guide provides support to municipal Distributors in this regard. The focus is on the electrical aspects
of (renewable) generators2 connecting to municipal networks. However, non-electrical compliances and
considerations are also noted, and further references provided.
1. Distributor
a. The process to be followed to enable generator applications
b. Proposed steps to follow to assess the application
c. Assessing the network capacity
d. Role in the evaluation of Grid Code compliance
e. Overview of regulatory processes
2. Generator/Customer
a. Understand the process that the Distributor will follow
b. Checklist of the Distributor requirements
c. Grid/network and Grid Code compliance studies overview
d. Overview of regulatory processes
Note that the document remains a guide. As such, Distributors may modify, add, or remove steps and
requirements as is necessary according to their operational requirements. The intent is to cover all
1
Legal Framework Applicable to Embedded Generation in South African Municipalities. Pinsent Masons for
Sustainable Energy Africa, September 2022. Available at www.sseg.org.za
2 At the time of publication, non-renewable generators have to follow the SAGC – Transmission Code. Some aspects
for licensing etc. may differ from this document. It is, however, unlikely that large non-renewable generators will
require connection to the municipal network. It is anticipated that a new code under development will address all
generator aspects in one document.
processes to be followed, but some aspects may not be covered in detail since they may already be in
place or covered elsewhere, e.g. regulatory approvals for Rights-of-Way, etc.
It remains the responsibility of prospective Generators/Customers to make sure all regulatory, technical,
procedural and other aspects are suitably adhered to in terms of national and municipal frameworks and
requirements.
Note that the current RPP Grid Code does not make a distinction between Generators who sell energy, and
embedded generators largely for self-consumption. Where unclear, Grid Code requirements are to be
applied at the Generator point of connection, not at the Customer point of connection.
If the licensed Distributor is unable to provide access to the network at the point of connection applied
for, it must provide reasons and advise the customer of alternative options available, which includes
increasing the capacity of an existing connection.
Each Distributor is required in terms of paragraph 4(2) of the Distribution Code to make available to the
customers the 'Customer Connection Information Guide' which shall cover as a minimum:-
• the process to follow when applying for supply at the specific Distributor;
• information requirements of the Distributor from the customer to effect an appropriate
connection; and
• the process and related timeframes which follow the application.
Municipal Distributors have the duty to develop electricity services policies relating to, inter alia, the
connection of generation systems to the distribution system and to pass and implement by-laws with
respect to the electricity distribution functions.
If there is no policy document or by-law issued by a municipal Distributor governing the application
process for generation systems, the application for connection should be dealt with in accordance with
the Distribution Network Code, the RPP Code, the BESF Code and the ERA, as amended.
3
This section is largely informed by Legal Framework applicable to Embedded Generation In South African
Municipalities. September 2022. Pinsent Masons, for the Municipal Embedded Generation Support Programme,
available at www.sseg.org.za.
The absence of a policy document regulating the application process for connection of an EG facility 1
MW or larger is insufficient grounds for the municipal Distributor to refuse to consider the connection to
the municipality's distribution system. An application for connection can be submitted in accordance with
the provisions of the Distribution Code.
Paragraph 4.4 of the Distribution Code states that the Generator/Customer must enter into a Connection
Agreement with the licensed Distributor before any actual connection to the distribution system can take
place. This will require that Generators/Customers comply with all municipal requirements, including
application and assessment processes. This also implies that, amongst other activities, appropriate
studies are done to ascertain whether Customers, including Generators, can be connected
EG of any size are exempt from NERSA licensing. The above applies whether the EG has storage or not.
All EG, irrespective of size, need to comply with the Codes and Distributor requirements, and the
Distributor needs to keep a record of these systems.
Although registration is a simpler and quicker process than licensing, there are still requirements to be
complied with and the process can take time5.
More details on NERSA’s registration process and requirements for Generators/Customers and
Distributors are provided in Appendix F.
Note: Although the regulations are not clear on licensing and registration of BESF, it is understood that
stand-alone BESF should be treated as a generator and should comply with registration requirements
based on their output in kW and self-consumption characteristics, as indicated above.
4
First released on 15 December 2022 with a re-release on 17 January 2023 with a minor correction. Available here:
Electricity Regulation Act: Amendment: Licensing Exemption and Registration Notice. Govt Gazette No 47877, 17
January 2023)
5
Note that the recent Energy Action Plan Update, January 2023 released by the South African Government states
that NERSA registration timeframes have now been reduced from 4 months to 19 days.
For municipal own-procurement (municipal owned or via an IPP), legal analyses indicate that a Section 34
Ministerial Determination is not required for generators > 1MW7 (as long as individual generators are
below any licensing threshold that is set in Schedule 2 of the ERA), but note that DMRE still considers it
necessary (in terms of Regulation 5 of the New Generation Regulations). Such application to the Minister
should be in accordance with Regulation 5 of the New Generation Regulations, including feasibility
studies, proof of compliance with the MFMA and other municipal regulations, and proof of alignment with
the municipal IDP.
Installation safety remains the responsibility of the Distributor, delegated to the owner or tenant via
responsibility for the Certificate of Compliance. To this effect, compliance to the relevant documents from
the SANS 10142-series are required, including SANS 10142-2 for larger installations.
6
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022)
7
For example Constitutional and Legislative Competence and Authority of Municipalities to Procure or Buy New
Generation Capacity - Part B: Overview Legal Framework. Western Cape provincial Government MER Programme –
Energy Projects Report, November 2021, and Legal Framework Applicable to Embedded Generation in South African
Municipalities. Pinsent Masons for Sustainable Energy Africa, September 2022.
These size categories are important since some Grid Code requirements differ between the categories.
The size referred to in Table 1 refers to the rated AC capacity of the generator installation, and not the
anticipated net export capacity.
Note that while some regulatory documents classify generators according to their apparent power rating
(in kVA or MVA), others classify them only based on their active power output (in kW or MW). In many
instances the two can be used interchangeably, however, it is recommended for consistency that
municipalities communicate with prospective Generators/Customers based on the active power (MW)
output of the generator, with the understanding that reactive power (MVar) range shall meet the
applicable requirements of the Grid Code and apparent power (MVA) shall remain within the rating of all
associated equipment and applicable Grid Code category requirements.
8
Category B is subdivided at 5 MW in the BESFCC only (at the time of publication), but certain requirements, e.g.
power quality, follows the same categorisation in the RPPGC.
•SUBMIT APPLICATION
•Distributor provides information pack
•Customer fills in application form
STEP 1: •Customer pays application fee
•EVALUATE APPLICATION
•Distributor (or developer) undertakes Grid Impact Studies
•Distributor identifies any grid strengthening requirements
STEP 2 •Distributor provides Cost Estimate Letter
•BUDGET QUOTE
•Customer pays Budget Quote fee
•Distributor (or developer) undertakes detailed grid strengthening studies (if needed)
STEP 3 •Distributor costs strengthening etc
•Distributor provides Budget Quote (typically 85% accurate)
•CONTRACTING/LEGAL
•Parties negotatiate relevant agreements, such as the Connection Agreement, Use of System
STEP 4 Agreement, Self-Build Agreement.
•All permitting/authorisation secured
•DESIGN
•Distributor design undertaken (as needed)
STEP 5 •Customer completes design of plant, regulatory approvals
•CONSTRUCTION
•Distributor constructs infrastructure (as applicable, indicated by Grid Impact and Strengthening studies)
•Customer constructs plant
STEP 6 •Distributor monitors & approves connection works
•COMMISSIONING
•Generator Plant Commissioning
STEP 7
•GRID CODE
•Grid Code Compliance verification
STEP 8
•AUTHORISATION CLOSE-OUT
•Distributor checks all documentation, agreements, specifications etc in place
STEP 9 •Formal close-out
Figure 1: High-Level overview of process (showing progression and relevant party for different steps)
Any PPA with a duration longer than 3 years needs to comply with MFMA Section 33 processes, including
requirements around public notices and consulting relevant national and provincial government
departments (specific Distributor supply chain policies may also include other conditions in this regard).
Expenditure by municipalities must not only be according to sound procedures but must be included in
council approved budgets, considering both capital costs and operational costs.
Specific Distributor Supply Chain Management Policies may also have relevant provisions regarding such
procurement.
Procurement should be in terms of the Preferential Procurement Policy Framework Act, 2000, and
associated Regulations, including B-BBEE and local content provisions. Exemptions may be applied for
from Department of Trade, Industry and Competition, although in the past these have seldom been
granted. Local content requirements are being revised with a view to facilitating generation
development10.
9
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022).
10
Address by President Cyril Ramaphosa on actions to address the electricity crisis, 25 July 2022.
A PPP is defined as a contract between a public‐sector institution and a private party, where the
private party performs a function that is usually provided by the public sector and/or uses state
property by agreement. Most of the project risk (technical, financial and operational) is transferred
to the private party. The public sector pays for a full set of services, including new infrastructure,
maintenance and facilities management, through monthly or annual payments. In a traditional
(non PPP) government project, the public sector pays for the capital and operating costs, and
carries the risks of cost overruns and late delivery. (Source: National Treasury PPP Manual and
Practice Notes).
1.6.1 Self-consumption
Self-consumption generation refers to the condition where the generator is sized mainly to support the
existing load and export to the network is secondary – if it takes place at all. Customers with such
characteristics are also called prosumers. The generator may typically be sized for the customer’s
expected base load (during peak generation). It would typically be installed to reduce the electricity bill.
In the South African context, this may also include the use of storage to allow stand-by operation during
interruptions (such as load-shedding).
Customers should note that self-consumption will potentially have less impact on the network and enable
a simpler assessment process than for generators exporting all of their power. The network impact is
reduced since the maximum instantaneous rejection is limited to relatively small values in line with the
load size, i.e. if the network is adequate for the load it should be able to accommodate the generator.
Note that a grid impact study will still be required – even where customers do not export onto the network
(e.g. to assess generator rejection impact etc).
Four-quadrant metering should be installed. For Distributors that do not have any four-quadrant meters
available, an export block device may be applicable as an interim measure. Export may be allowed at a
later stage only when a four-quadrant meter can be installed. It is recommended that the Distributor
monitors the meter for possible reverse feed, even in the presence of reverse block devices.
Note on export/reverse blocking: Note that while EG with reverse blocking can have reduced impact on
the grid, the Grid Code still applies and grid impact studies are still needed.
Therefore, dispatchable, and partially dispatchable embedded generation should be encouraged as this
could potentially support the network and alleviate the impact of loadshedding. This could include
generators having some form of storage.
Apart from reactive power control and frequency response control, both the risk mitigation and recent
government procurement programmes require that the generators provide additional ancillary services,
namely instantaneous reserve and regulating reserve.
These requirements are in the RPP Grid Code but have not been enforced operationally before. The
appropriateness of EG installed for self-consumption to comply with these requirements is under debate,
and future regulatory revisions may modify such requirements. Any Customer wishing to install such a
generator should enquire with the SO and/or NERSA about these requirements as part of their process.
In the interim, should ancillary services be required beyond standard generator capability requirements
listed in the Grid Code, these will be contracted specifically by the SO.
All battery storage facilities of category B2 and up must have the capability to provide ancillary services
by default.
11
Ancillary services may also refer to the grid stability support provided by e.g. large industrial loads, etc. This is
however, not applicable in the current context.
This is a significant endeavor and typically will require substantial allocation of staff capacity, often need external
expert support, and require staff training to manage such processes.
Aspects such as decommissioning, waste management and site restoration, including financial provisions
for these tasks, would typically be included in the environmental management plan. It is the Distributor’s
prerogative to request these details.
12
Where a Distributor does not have a process in place for SSEG, contact the SSEG support team for assistance:
[email protected].
2 Municipal Processes
This section contains the steps to be followed by a Distributor from the time a Customer intending to
install a generator (hereinafter referred to as the ‘Customer’) applies for a connection point, up to the
time of Commercial Operation. High-level descriptions of the Customer processes that may occur in
parallel to the Distributor processes are also provided. No proposed timelines are provided at this stage
and may be added in a future revision of this document.
The processes assumes that no hosting capacity study has been done, i.e. the Distributor does not know
how much generation can be accommodated at various levels in the network. This means that each
application is reviewed on its own, taking other installed and approved generator installations into
account. A hosting capacity study should ideally be done along with the periodic network development
planning exercises, as it will allow for more rapid generator application assessment.
This steps in this section may form the basis for a customised internal municipal guideline.
Distributor:
• Provides information pack to customer, including the application form
• Invoices the customer for the application fee (as applicable)
Customer:
• Completes the application form for generator
• Submits the completed application form
• Pays the application fee
Initial interactions with the Customer should be handled by the Customer Care department (or equivalent
section), who will communicate internally with the Network Planning Department. Future interactions
may be between the Network Planning Department and the Customer directly. The process starts when
a Customer applies for a generator connection point. This application is required in all cases:
2. New generator application – the Customer only has a load supply point (Point of Supply)
3. Amended generator application – the existing generator capacity is increased (or decreased)
Grid stability and network interference is likely to change at the point of connection, hence grid impact
studies are required.
The Distributor should ensure that the Customer understands the process via the provision of an
information pack.
Once the application fee has been paid, the application will be processed, generally by the Distributor’s
Network Planning Department. The customer will receive a Cost Estimate Letter after the evaluation of
the application (Step 2).
NOTE: Other departments / sections will also need to be advised, e.g. quality of supply, protection, legal,
metering and billing. It is important that the relevant people be informed of the generator application as
soon as possible to prevent delays later in the project. It is useful to include these sections and timeline
for the process in an internal municipal guideline.
13
As an example, Eskom’s 2022/23 fees on application to produce a Cost Estimate Letter are shown here:
Figure 2: Distributor evaluation process and components (‘D’ refers to Appendix D, numbers to section numbers in the document)
1. Check for impact on the network in the area to see if the generator can be connected without grid
strengthening, or if such strengthening is necessary
2. Deliver basic information on grid strengthening to enable an indicative Cost Estimate Letter so
Customers can assess financial feasibility of the project.
Note that existing generators are considered during this phase of the evaluation, but other applications
that are not at Budget Quote fee payment stage (Step 3) are typically not considered.
Small-scale embedded generators (i.e. <1MW) may be evaluated by following a simplified connection
criteria assessment as per the NRS097-2-315 instead of doing grid impact studies. The NRS097-2-3 covers
generator impact at the PoC but also considers the cumulative grid impact (i.e. hosting capacity) of all
other embedded generators on that section of the network, including on the relevant MV feeder.
One of the outputs of a hosting capacity study would be to determine internal, network-specific, simplified
connection criteria for generators larger than 1 MW.
If the proposed connection point and/or surrounding network does not have sufficient capacity for the
generator to connect, the customer should be advised that (a) the process will take longer and (b) the
cost to connect may be significantly higher as network upgrades are needed. An indication of such costs
will be given in the Cost Estimate Letter.
14
Note on terminology: Grid Impact Studies can also be termed Network Studies, or Network Impact Studies – there
appears to be no standard way of using these terms – either locally or internationally. In this document ‘Grid Impact
Studies’ will be used since this is the term familiar to many Distributors.
15
The NRS 097-2-3 criteria may be adapted for local Distributor conditions. Note that the use of the NRS097-2-3 in
evaluating generator connections should be documented in a municipal policy document, which should also clarify
any adaptations to the NRS097-2-3 criteria.
The customer should also be given options to reduce their impact on the network (e.g. by installing a
smaller system) to potentially avoid the need for upgrades.
Fair share of hosting capacity: Municipalities may elect to allocate network capacity for generation
connections on a “first-come, first-served” basis, or to apportion quantities of network capacity to
customers such that the total available capacity can be fairly shared amongst many or all customers,
should they wish to connect a generator at a later stage. Assessments should also consider how much
of other customers’ fair share of the network generator hosting capacity is used, since this affects the
potential cost of connection for future customers. Currently there are no guidelines in place for
sharing of hosting capacity or network upgrade costs, and no legal requirements exist in this regard.
An overview of the network study evaluation process is provided in Figure 2. This figure also indicates
Data requirements, Simulation Permutations and Acceptable Grid Impact, as well as relevant departments
that need to be consulted during the evaluation process, i.e. Protection, Power Quality, Network Control
and Maintenance.
1. Grid Impact Studies done in-house: provided the Distributor has sufficient staff with appropriate
training and experience using a suitable software package. Associated costs are covered by the
application fee.
2. Outsource to specialist company: the Distributor may outsource the Grid Impact Study to a
specialist company. Associated costs are covered by the application fee.
NOTE: This may imply a more costly application fee, since external consultants may be more
expensive than internal staff. This should be a pass-through cost to the Customer.
3. The Customer’s engineering team does the Grid Impact Study:
a. The Distributor will provide the customer with the Grid Impact Study Specification
Guideline16 which sets out the work to be undertaken.
b. The Distributor’s planning department will provide the necessary network information for
the studies to be done. Network information may need to cover additional parts of the
network up to the Eskom point of delivery to evaluate changes in the agreement with
Eskom as well.
c. The Distributor will evaluate the study to determine if the generator can connect without
adverse impact on the grid.
It is noted that there may be conflict of interest when Customers have their own specialists
to conduct the Grid Impact or Strengthening Studies. For this reason, sign-off by an
independent ECSA registered professional17 is required for these studies – paid for by the
16
Available at https://www.sseg.org.za/grid-impact-study-specification-guide/
17
Ideally, the independent professionally registered person should be procured by the Distributor to reduce conflict
of interest. However, the code of conduct for professionally registered persons mitigates the risk.
Customer - along with any internal reviews that the Distributor conducts (e.g. technical and
financial evaluation committee reviews).
Note: In the case that the Customer does the Grid Impact Study, it is possible that the Grid Strengthening
Study (Step 3) is included to make it a combined study. The proposed solution will still have to be evaluated
by the Distributor and be accepted at the relevant technical and commercial committees.
2.2.3 Protection
Protection aspects include monitoring fault levels as well as to ensure protection coordination. The
Distributor need to evaluate the requirements for updated protection settings or even protection
upgrades during the Grid Impact Study. This should be included in the scope of work of the party
undertaking the study.
Fault Levels
As part of the Grid Impact Studies, fault levels are calculated under all conditions to ensure they remain
within existing equipment specifications. These results provide an input into the protection settings and
selection of protection equipment. Fault current withstand and breaker rupturing values should be
considered to ensure that the system may be operated safely.
Protection Coordination
Protection coordination studies need to be done separately to ensure correct operation of protection for
the various network conditions as well as prevent nuisance tripping where possible.
Auto-reclosers
If there are reclosers upstream of the generator, the speed of closing should be coordinated with the anti-
islanding requirement of the generator. The standard anti-islanding requirement is that generators
disconnect from an islanded network within 2 s. Therefore, reclosing times should be longer than 2 s.
Background Levels
The Distribution System Operator (DSO) should supply background power quality information (i.e.
historical information), including reliability of the network. This may be at the closest node in the network
where a PQ recorder is available. If no suitable power quality data is available, the Customer is referred
to the NRS 048-2 compatibility levels. Note that all generators must be designed to withstand the
NRS 048-2 compatibility levels, including appropriate response when these levels are exceeded, e.g.
disconnect from the system to protect themselves.
The background levels should be provided to the Customer along with the Cost Estimate Letter.
Monitoring
It is required that generators larger than 5 MW all have PQ recorders installed at the PoC 18. This may also
be at the customer’s cost, and should be included in the Budget Quote (see Step 3). In line with Grid Code
and legal requirements, these instruments must be compliant to IEC 61000-4-30.
Such installation should be undertaken with or before generator installation.
Note that it is the Customer’s responsibility to monitor power quality at the PoC (monitoring may be
periodic or ongoing/permanent – the latter is suggested for EG>5MW) and they should be informed of this
responsibility. This requirement should also be included in the relevant Distributor policy documents.
Apportioning
The RPP Grid Code requires that apportioning for power quality parameters be done for all generators
larger than 5 MW following the IEC 61000-3-6/7/13 (or as simplified in NRS 048-4) documents.
Apportioning shall be done for voltage harmonics, voltage flicker and voltage unbalance. Other
parameters may be added to a Connection Agreement based on particular local network performance,
such as inter-harmonics, rapid voltage changes etc.
The quality of supply parameters and emission limits needs to be included in the Connection and Use of
System agreement with the Customer. Apportioned power quality emissions levels should be provided
along with the Cost Estimate Letter.
Note: Where the Distributor’s PoD with Eskom may be affected, e.g. reverse power flow to Eskom, it may
be required to update the Connection and Use of System agreement between the Distributor and Eskom.
In this case, the power quality emission limits from the Distributor may change. This needs to be taken into
account when calculating the emission limits for the generator.
2.2.5 Maintenance
The impact of network extensions and/or strengthening on maintenance requirements should be
assessed. The following impacts should be considered:
18
The Distributor may also require this of smaller generators should they consider this necessary (in which case it
should be specified in their policy and by-law). As per clause 9(3) of the RPPGC, the RPP shall monitor and report the
power quality. In view of the simplified power quality requirements for units smaller than 5 MW, it is recommended
to require the permanent PQ recorder only for larger units.
New equipment may also have special maintenance requirements, e.g. if new breakers are SF6 insulated.
This should be discussed and agreed with the maintenance/operational department, as well as
operational philosophies.
For a network point that may not have high enough reliability, the potential improvement of network
interruption and dip performance should be considered, which may be addressed via improved
maintenance philosophies.
Where a generator should preferably not be subjected to loadshedding, the connection point may need
to change to ensure that loads may be disconnected while the generator remains connected (if there is
sufficient export capacity). This can be dealt with on a case-by-case basis.
Grid availability
It is good practice to agree on the expected availability of the grid connection point. This is often referred
to as the allowed grid unavailability period (AGUP) per year. Penalties for less availability may be
appropriate in some circumstances e.g. in the Power Purchase Agreement (PPA).
Since loadshedding is outside the control of the Distributor, it should be excluded from AGUP.
Ramp rate(s)
Although the voltage changes are evaluated during the Grid Impact Study, it is better to prevent such
voltage changes. Therefore, appropriate ramp rates should be set where the generator can control this,
e.g. for wind generation tripping off during overspeed conditions, or PV during partially cloudy days.
Battery charging
The potential impact of generators with battery storage, especially after a long interruption, needs to be
evaluated. In general the charging rate should be limited to the ADMD value.
Note that a smaller value than the ADMD may be appropriate in congested networks.
1. The daily voltage variations - This may require updating tap-changer settings, or control voltage
levels upstream in the network.
2. Change in power flow - This is evaluated during the Grid Impact Study and some network
contingencies may require specific operating procedures, e.g. requesting a reduction in power
output or changing the reactive power control of the generator.
3. Loadshedding impacts - Generators will reduce the load that is switched out per block during
loadshedding. It may also be desirable to exclude generators from loadshedding schedules to
rather assist the Grid.
The letter should clarify power quality emissions level apportionment, and should clearly state that the
cost estimate is non-binding. Should the Customer accept the Cost Estimate Letter and choose to proceed
and where strengthening is required, a Grid Strengthening Study will need to be undertaken (see Step 3).
Reserving capacity: The Cost Estimate Letter does not guarantee that the generator will be able to
connect at the proposed point of connection. For example, should another generator apply to connect
to the same network, the available capacity is allocated to the generator who accepts the Budget
Quotation first, i.e. pays the Budget Quote fee.
This will depend on the pricing philosophy, i.e. where the Distributor can fund most of the network
upgrades with a long-term cost-recovery plan, they may not wait for Budget Quote acceptance before
allocating network capacity.
Outputs:
19
A table with costs is provided in Error! Reference source not found. to assist with the calculation of indicative strengthening c
osts (Appendix A costs need to be adjusted for inflation etc).
Distributor:
• Issues Budget Quote fee invoice to Customer
• Undertakes (or outsources) detailed Grid Strengthening Study (as relevant)
• Issues Budget Quote to Customer
Customer:
• Pays Budget Quote fee
• Accepts Budget Quote in writing
When the Customer accepts the Cost Estimate Letter, the municipal Distributor invoices for the Budget
Quote fee20 to cover the work involved in undertaking any detailed studies necessary to enable the Budget
Quote to be issued. This quote should have a high certainty level21 to allow the customer to secure
funding.
The Budget Quote fee should reflect the work needed in preparation of the Budget Quote: if no grid
strengthening study is required (as determined in Step 2) the fee should be reduced as the Distributor has
20
Note that the Cost Estimate Letter is a non-binding estimate of the cost implications for the Customer/Generator,
including initial estimate of grid strengthening cost if applicable. The Budget Quote fee covers the work involved in
establishing costs with adequate certainty – including grid strengthening study costs if relevant – such strengthening
costs are then presented in the Budget Quote.
21
Eskom typically issues this quote with an 85% confidence level.
minimal work to do in preparing the Budget Quote. If grid strengthening study is required, the fee should
be adequate to cover this.
• network capacity allocation can be reserved for the Customer (with a time validity limit, aligned
with NERSA registration timeframes if applicable)
• any grid strengthening studies can commence
Grid strengthening studies should build on the indicative strengthening findings from the Step 2 study,
reviewing different options to select the best one, and establishing adequately detailed equipment
characteristics to enable accurate costing.
As explained in NRS 069:2018 section 6.4.3 Table 1, assets paid for by the customer and transferred to
the municipal Distributor cannot be included in the asset base on which the Distributor makes a
financial return. Over time this will erode the municipal asset base and can have an impact on recovery
of refurbishment or maintenance costs.
Although NRS 069 specifically states that it is not applicable to generators, it is recommended that the
legal principle of not making revenue on assets that the customer paid for should be applied regarding
generators too.
Ideally the asset is paid for by the Distributor, and the cost of grid expansion is recovered over time
through tariff charges, or if the Customer pays, they are compensated over time (based on connection
charges).
The NRS 069 speaks of cost apportionment of grid expansions that could benefit future Customers and
also highlights refunds to initial Customers (including reference to the distribution code).
If any department (protection, power quality, maintenance) has not yet given their inputs, it needs to be
covered in this Step. Ensure that inputs given, or concerns raised previously by these
departments/sections are adequately addressed during this stage.
Distributor:
• Issues relevant generic agreements to Customer
• Issues Letter of Consent to Connect for customer’s NERSA registration/licensing application
(if required)
• Checks environmental and necessary land-use authorisations obtained by customer
Customer:
• Signs relevant agreements
• Applies to NERSA for registration/licensing (if required)
• Obtains necessary environmental and land-use authorisations
The various agreements and authorisations that need to be considered and complied with amongst the
involved parties are discussed below.
Note that point 4 infers that the processing of the Customer application and finalising the
Connection Agreement have interdependencies. Final approvals cannot be given until all required
agreements have been signed off, irrespective of physical installation and/or commissioning
progress.
In addition, the following aspects should also be included in the generator Connection Agreement:
A customer that purchases the electricity from a generator via wheeling also needs an updated
Connection (and Use of System) agreement, since the relationship between the Distributor and this
customer changes significantly.
An example for a separate UoS could be when a third-party installs a generator onto a privately owned
network, e.g. large factory or residential estate.
A trading agreement indicates a reseller (“middleman”) in the distribution of the electricity. Where
applicable, a separate agreement needs to be entered into over and above the PPA. Currently, the
electricity regulation act prohibits that a trader sells electricity at a higher tariff than the Distributor in
whose area they are located.
In such cases where reverse feed will occur into the Eskom grid, a similar process will need to be followed
for an amended connection point with Eskom. Note that these costs need to be taken into account in the
Budget Quote, i.e. costs may be passed-through to the Customer.
22
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022).
not, whether it is in an urban area or not, and whether it falls within a Renewable Energy Development
Zone23. As a general guide, the following apply24:
• No environmental assessment required: generators under 10MW, on land <1ha, and involves
distribution/transmission infrastructure below 33kV outside an urban area, or below 275kV in
an urban area
• Basic environmental assessment required: generators between 10 and 20MW, or that cover
>1ha, or involve infrastructure over 33kV outside an urban area or over 275kV in an urban area
• Comprehensive environmental impact assessment required: generators over 20MW, or that
involve infrastructure over 275kV
Based on the above, rooftop solar PV projects are unlikely to require an environmental assessment. Multi-
MW ground-mounted solar generators are likely to take enough land area to trigger an environmental
assessment (~1.6 MW per ha of land). Greenfield sites/ vacant land usually requires a comprehensive
assessment.
There is a national focus on reducing the environmental regulatory requirements for solar projects in
areas of low and medium environmental sensitivity25. Normally, a Basic Environmental Assessment
process can take around 8 months for final approval by a Competent Authority (including a public
participation process) and a Comprehensive Environmental Assessment 16 months. However the January
2023 Energy Action Plan update states that “Embedded Generation projects have been gazetted as
Strategic Integrated Projects, reducing timeframes for environmental authorisations to 57 days” 26.
The Competent Authority is normally the province (although in certain circumstances it may be the
Minister).
• Water use license (assessment included in the EIA) – associated with significant use of water,
storage of water, discharge into water resources and altering of watercourses, amongst other
criteria. Should this authorisation be necessary, specialist studies will need to be undertaken,
and approval will take at least 90 days. It should be noted that solar and wind projects generally
do not require large amounts of water.
• Biodiversity permit (this need is identified during the EIA) – associated with threatened or
protected species. The permit should be applied for before construction, and can take 20-30
working days.
• National Heritage Resources Permit (this is part of the EIA) – associated with impact on a
national heritage resource. Where applicable, authorisation is required before developing the
project, and approval is part of the environmental authorisation.
23
Due to an in-depth Strategic Environmental Assessments conducted in determining the Renewable Energy
Development Zones (REDZ), the decision-making timeframes are significantly reduced for such zones.
24
See EIA GUIDELINE FOR RENEWABLE ENERGY PROJECTS, Dept of Environmental Affairs, 2013, and associated
Activity Listings GNR 544, GNR545 and GNR546 for a more complete set of criteria.
25
Address by President Cyril Ramaphosa on actions to address the electricity crisis, Union Buildings, Tshwane, 25
July 2022
26
Energy Action Plan Update, January 2023 (page 9). South African Government.
• Approval in terms of the Astronomy Geographic Act – where the site may affect areas declared
uniquely suited to optical or radio astronomy.
• Civil aviation approval – where the plant may impact a runway or airport, a Glint and Glare
Assessment may be needed.
• Mineral and Petroleum Resources Development Regulations - where the use of land may impact
on petroleum resource development. Approval is not required outside of mining areas.
Approval is required prior to using the land, and timeframes are uncertain but the process may
take 6 months.
• Electronic communications approvals – in terms of the Electronic Communications Act 36 of
2005, these may be applicable where ‘electronic communications network facilities’ pass over
private property or interfere with buildings to be erected.
• Atmospheric emissions, waste management, and community hazard management
authorisations may be needed in the case of generators with harmful atmospheric emissions,
utilise waste as a feedstock (biogas or biomass generators), or store hazardous material such as
fuel, respectively27.
As a part of the process of obtaining necessary approvals, required specialist studies may also include
traffic impact, decommissioning and disposal, groundwater, tourism, noise, visual, agricultural potential,
and socio-economic assessments.
Where projects include batteries, a battery energy storage system assessment must be conducted, and
it must be flagged in the environmental assessment.
A change in zoning may be necessary to establish a generator on a piece of land, such as to a suitable
‘Utility’ zoning. Any such changes need to be consistent with the municipal or provincial Spatial
Development Framework. Typically a rooftop solar PV system (e.g. on a mall) will not require a zoning
change as the principle site activity has not changed. A solar generator developed on vacant land will
typically require rezoning. Depending on the original zoning, an environmental impact assessment may
be triggered.
Subdivision of agricultural land is subject to more stringent approvals in terms of the Subdivision of
Agricultural Land Act 70 of 1970. This normally take 3 to 6 months.
Note that the Energy Action Plan update of January 2023 states that land use authorisations for energy
projects have been priorioritised, and timeframes reduced to 30 days 28.
Depending on the site location, servitudes may also need to be registered by the Customer.
Note that land use is often regarded as one of the more problematic aspects, unless the Customer already
owns the land. Long-term lease and use of land permissions may also be registered at the Deeds office.
27
Goldblatt M. Mapping of authorisation processes for renewable energy projects, 2015. PDG
28
Energy Action Plan Update, January 2023 (page 9). South African Government.
Building plan approvals are necessary for site development, which may take between 30 and 60 days.
The built structure needs to be signed off by a suitably qualified person, e.g. ECSA registered civil engineer.
The requirements should be set or confirmed in terms of the National Building Regulations and Standards
Act.
Wind load can play a significant role, even for PV systems, and should not be disregarded.
Municipal land29
Leasing or otherwise using municipal land is regulated by the MFMA and associated Regulations, and
relevant municipal by-laws where established. Depending on the value and length of a land lease,
different conditions for approval apply, ranging from simple Council approval to more complex processes
involving public participation.
Distributor:
• Select and specify equipment to be procured and installed
• Provide necessary guidance to customer to design and install interconnection equipment
• Proceed with procurement
Where grid strengthening or upgrades are necessary for the generator to connect, detailed design can
commence once the Budget Quote is accepted. The Grid Strengthening Study provides key parameters
to inform detailed design. The design department process is no different to any other network upgrade
process.
29
Further information is available in National Treasury MFMA Circular No. 118, Municipal Finance Management Act
No. 56 of 2003: Legal Framework for Procurement of New Generation Energy Capacity by Municipalities and
Municipal Entities (June 2022).
During the design stage, all equipment requirements are converted to specifications, e.g. insulation
coordination, protection selection and coordination, transformer specifications etc.
Should a dedicated transformer be selected for a customer, this transformer may be specified for
harmonics and small DC current injection. This may allow for a higher embedded generator penetration
capacity for the same transformer capital costs.
Protection coordination may include that the relays and breakers cannot be unidirectional and should
operate for a fault in any direction.
Design also includes revised Single Line Diagrams, layouts (if necessary), external services, and civil works,
particularly if network reinforcement is needed.
2.5.2 Step 5B: Generator Planning and Design (Including Grid Code Compliance Studies)
Customer:
• Undertake the necessary studies for PoC impact (Grid Impact)
• Undertake impact assessments for generator collector network and infrastructure
• Undertake interconnection equipment design if required (see Step 5A)
• Undertake Grid Code Compliance Simulations
• Design generator and related infrastructure
• Specify equipment
Part of the generator planning and design is to ensure that all associated equipment that is selected is
appropriately sized. This process is similar to the Grid Impact Study, except here the focus is on the new
generator collector network and infrastructure. Note that transformers should be specified appropriately
for the increased harmonic loading on the transformers.
This design work is entirely the responsibility of the Customer, and the Distributor is not required or
advised to review, approve or accept designs for equipment beyond the Customer PoC.
Simulations
The following simulation studies should be done by the Customer to check that designs align with Grid
Code compliance:
Based on the design and simulation work, equipment should be specified so procurement can proceed.
2.6 Step 6: Construction
Once designs are complete and appropriate approvals have been given, the construction can commence.
• Factory Acceptance Testing (FAT) is the testing that’s conducted by the manufacturer in the factory
prior to shipping to site.
• Site Acceptance Testing (SAT) is the testing that’s conducted in the field either by the vendor or by
the on-site commissioning team. These are the standalone tests of the equipment to confirm no
damage during shipping or installation.
• Site Integration Testing (SIT) is the testing conducted on-site to confirm equipment functions as a
subsystem or system.
• Type Testing is the testing that is done on one piece of equipment, for example in an accredited test
laboratory, and accepted as representative of other equipment that are manufactured in the same
way and to the same specifications.
Internal quality checks, e.g. Clerk of Works inspections, remain the responsibility of the Distributor.
Part of the construction phase includes installing the necessary municipal metering, and potentially
upgrading or updating protection equipment in the case of grid strengthening.
Once the municipal network construction is complete, the Customer should be notified in writing.
The municipal Distributor should allow access to their substation for cabling termination to the outgoing
feeder to the Customer PoC.
Distributor:
• Provide Customer with written permission to enable commissioning to proceed
• Attend aspects of generator commissioning (e.g. anti-islanding)
• Check commissioning documentation submitted (commissioning report, anti-islanding
certification)
• Provide Customer written permission for Commercial Operation
Customer:
• Pre-commissioning checklist (internal)
• Pre-commissioning tests (internal)
• Commissioning tests (internal)
• Commissioning checks with Distributor present (e.g. anti-islanding)
• Provide documentation to Distributor (commissioning report, anti-islanding certification)
Commissioning is the process of bringing the newly installed generator and associated equipment into
service and confirming that all operational requirements are met.
2.7.1 Pre-commissioning
Pre-commissioning is done by the Customer to verify that each piece of equipment meets the technical
requirements of the project. Pre-commissioning activities test equipment as standalone items. Tests
during pre-commissioning don’t necessarily operate the equipment as a system yet. Each piece of
equipment is individually confirmed to be ready for further commissioning tests.
The set and sequence of tests depends on the installation, i.e. the type and number of equipment items
installed. A pre-commissioning procedure and checklist should be compiled to ensure that everybody
knows what will happen, as well as what to do should tests go wrong. The safety aspects during pre-
commissioning are extremely important, especially since some protection aspects have not yet been fully
tested and commissioned.
During pre-commissioning, the entire installation is checked to ensure that everything is installed correctly
and is able to operate individually as expected. The following list contains examples of typical electrical
tests:
• Grounding and bonding checks- confirm the integrity of the earthing system that sufficient bonding
between metallic parts is done; by measuring the resistance of bonds.
• Cold loop checks- confirm that all cable and conductors are terminated to the correct terminal blocks.
• Megger checks- apply a voltage across the cable conductor and insulation to confirm that the cable
has not been damaged or punctured to degrade the dielectric properties of the cable.
• Test DC voltage and polarity- confirm that the DC voltage is of the correct magnitude and polarity at
the inverter input, or battery connection points.
• Hot loop checks- confirm calibration settings and ranges of control loops. This confirms that ranges
and setpoints are correct for each control point.
• AC phase checks- verify the installation of each electrical phase in the correct order using a phase
rotation meter.
• Transformer checks-
o Take oil samples before and after energization. The samples are compared to see if any
differences could indicate an internal problem within the transformer.
o Winding resistance measurements are taken as well to measure insulation resistance.
o Transformer ratios are measured once tap changes are set to confirm that the primary and
secondary windings are correct.
o Open circuit tests- conducted to measure the no-load current losses.
o Short-circuit tests performed with reduced voltage to the primary winding to measure full-load
current losses.
• During protection relay testing, primary and secondary injections are performed on CTs and VTs to
verify relay settings are correct.
• Interlock verification (where installed)- interlocks are verified by operating equipment with no bus
voltage applied. Different operating configurations are selected to verify that interlocks are
functioning correctly before applying any bus power to the system.
• Battery discharge tests– confirm how many hours of rated voltage and current can be supplied during
charge and discharge cycles.
The Distributor may require submission of all test reports and certificates prior to commissioning.
Written permission (Operational Notification for Commissioning) should be provided by the Distributor
before synchronisation of the generator with the distribution system is attempted, and the Customer
should ensure that such permission has been obtained.
The set and sequence of tests depends on the installation. A commissioning procedure and checklist
should be compiled, as well as to provide clarity on what to do if things do go wrong.
It is also at this point that certain safety aspects may be tested in the presence of Distributor staff, such
as the anti-islanding function. Note that the SANS 10142 Certificate of Compliance (electrical installation)
should check this as well.
2.7.4 Documentation
IEC 62446 provides the full set of documentation required for a PV installation. The main items are listed
below. In the absence of similar documentation for other technologies, the below is the recommended
minimum list of documentation to be provided by the Installer to the Customer:
• System data
o Basic system information
o System designer information
o System installer information
• Wiring diagrams
o General
o Array – general specifications (PV-only)
o PV string information (PV-only)
o Array electrical details (PV-only)
o AC system
o Earthing and overvoltage protection
• String layout (PV-only)
• Datasheets
• Mechanical design information
• Emergency systems
• Operation and maintenance information
• Test results and commissioning data
The Distributor will require relevant test results and commissioning data, and proof that anti-islanding
operates correctly.
Customer:
• Pre-Construction:
o Compile model of the generator for Grid Code Compliance simulations
o Confirm Grid Code Compliance via simulations
• Post-Construction:
o Submit test procedure to Distributor/RETEC
o Conduct compliance testing dry run
o Conduct compliance tests with Distributor/RETEC
o Submit compliance reports to Distributor/RETEC
• Post-Commercial Operation Date (when commissioning is complete):
o Undertake RMS and EMT modelling
o Submit RMS and EMT modelling reports to Distributor/RETEC
o Undertake power quality compliance assessment
o Submit power quality compliance reports to Distributor/RETEC
Distributor:
• Allocate power quality emissions limits to generators (if >5 MW)
• Confirm that Grid Code compliance is achieved (with RETEC)
• Sign off on power quality assessment
The Grid Code is a set of documents that govern the access to the transmission system (TS) or the
distribution system (DS) and operation of the interconnected power system (IPS). All parties need to
comply to the provisions of the relevant Grid Code(s); this section deals with the requirements for the
renewable embedded power plants.
Compliance to the Grid Code refers to the entire facility and not individual units or turbines. Amendments
to ERA Schedule 2 do not relax any Grid Code requirements.
Note: The RPP Grid Code was written with large generators in mind – typically over 20 MVA. The
appropriateness of requiring grid support and SCADA functionality, for example, for generators of under 5
or 10 MW as is currently required in the Code is under consideration. Should a 2 MW self-consumption PV
installation on a mall be required to support the network in a similar manner to a 100 MW plant? Why
include SCADA capabilities when the municipal Distributor is unlikely to ever have such functionality in
place? Nevertheless, the Grid Code in its current form is legally binding, which is reflected in this document.
Exemptions may be applied for in terms of the relevant governance codes. Note that permanent
exemption requests are seldom approved.
Responsibility for Grid Code compliance lies with the Customer. The Renewable Energy Technical
Evaluation Committee (RETEC) undertakes compliance assessments and submit results to NERSA who
then certify compliance. The role of the Distributor in the compliance verification process is limited.
In terms of the RPP Grid Code Appendix 9, the compliance assessment tests need to be repeated every 6
years. The results are submitted by the Customer to RETEC and the relevant Distributor for approval in
each cycle.
It is recommended that the Distributor has an internal process to continuously monitor compliance in
terms of impact on the network, e.g. protection coordination, power quality etc.
Note that NERSA has accountability to approve the Grid Code compliance status, based on RETEC advice.
RETEC remains responsible for reviewing all Grid Code compliance aspects. The Distributor’s inputs are
often requested, e.g. for power quality.
Note that the Customer is responsible and accountable for Grid Code compliance. All steps are to be done
by the Customer to the satisfaction of RETEC. The Distributor may assist in reviewing the results when
requested by RETEC.
GCC simulation
A simulation model of the generator is compiled and a range of simulations performed, including around
frequency tolerance and support, reactive power capabilities, voltage ride-through and harmonic
resonance screening.
Some commissioning tests also form part of Grid Code compliance (see Step7: Commissioning).
Dry run
This is an internal customer process where all compliance requirements tests are pre-checked in
preparation for formal RETEC evaluation.
Compliance testing
Testing is undertaken in the presence of RETEC delegates, including active power constraint, power
curtailment during frequency variations, reactive power control, power factor control and voltage control
function.
In addition, voltage ride-through and power quality tests are undertaken over a longer time period.
Voltage ride-through requirements are deemed compliant based on the simulation results. However,
should any non-compliance be detected by the Distributor or the Customer, this shall be addressed and
corrected. The timeline for corrections should be agreed between both parties, including NERSA (via
RETEC/GCAC).
For units up to 5 MW, Grid Code compliance can be confirmed by way of type test certificates, i.e. NRS
097-2-1 for harmonic emissions and SANS/IEC61000-3-3/5 for voltage flicker emissions.
For units of 5 MW and larger, the power quality compliance must be measured within 6 months. The
Customer must show, by analysis of the power quality measurements, that the plant complies with the
emission limits. Appendix 13 of the RPPGC provides more guidance on the power quality compliance
aspects.
These models need to be compiled and run to replicate a range of relevant generator performance
characteristics.
Power quality
It is the Distributor’s responsibility to allocate power quality emissions limits to generators larger than
1MW. For smaller generators (less than 1 MVA) NRS097-2-1 may be used. At least one weeks’ worth of
measured power quality data is needed for compliance verification. The current practice is that the
Distributor needs to sign-off on the power quality assessment before Grid Code compliance will be verified
by RETEC.
AUTHORISATIONS SUMMARY:
The Distributor checks that all the necessary authorisations, agreements and compliances are in
place before close-out.
Customer:
• Provides all related information (as per previous sections)
Distributor:
• Checks documentation received
• Formal close-out and informs customer
In this step the Distributor checks all aspects relating to the compliance of the Customer. It includes
confirming the following:
• Network assets have been constructed to their standards, and that they have the necessary
certificates and specifications in their possession.
• Necessary agreements are in place (connection, wheeling etc).
• NERSA registration or licensing completed if relevant.
• Commissioning report complete.
• Grid Code compliance report submitted to RETEC.
• Letter provided by the Grid Code Secretariat that they are satisfied that all Grid Code
requirements have been met.
• Environmental, land use and other authorisations are in place and validated by the necessary
authorities.
• Written permission for Commercial Operation has been issued.
3.1 Tariffs
Managing the integration of several large generators is not a historical competency of most Distributors
and they typically will require additional capacity to manage these operations. Protection and quality of
supply require dedicated staff and sections that cooperate closely with the planning section. Costs for
additional staff members will need to be included in budgets and recovered through cost-reflective tariffs.
Most Distributors do not have NERSA-approved Use of System tariffs for generators and wheeling
customers. Distributors need to determine Use of System tariffs and submit them for approved by NERSA
in order to connect generators to the network.
For prosumers (i.e. customers with generators for the primary purpose of self-consumption), cost-
reflective basic charges are critical to ensure cost recovery despite reduced consumption. Export credits
are also an important element of a prosumer tariff to compensate customers for feeding electricity into
the network. Many Distributors are already implementing export credits in line with the principle of
avoided costs (i.e. export credit compensation should align with the value of what the Distributor would
have paid for that unit of energy from the wholesale market). The principle of export cost compensation
in line with avoided cost is suitable for larger than 1 MW generators.
The methodology used to calculate connection charges must be approved by NERSA, in line with NRS 069.
If the Transmission System requires modifications to connect the generator, any changes in such charges
to the Distributor should be passed through to that Customer.
30
Infrastructure development capital cost recovery policies of Cape Town and George can be referred to for
examples of such approaches.
4 References
Eskom. (2018). Standard for the Interconnection of Embedded Generation. Eskom.
GCS. (undated). Renewable Power Plant Grid Code Compliance Test Guideline - Version 3.0. RSA Grid Code
Secretariat.
MPE. (2021). Recommended Practice for Grid Code Compliance Studies for Renewable Energy Power Plants
and Hybrid Power Plants (P13906). MPE.
NERSA. (2022). RSA Distribution Code, Distribution Network Code. Pretoria: NERSA.
NERSA. (2022). The South African Grid Code: The Information Exchange Code.
NERSA. (2022). The South African Grid Code: The Network Code.
NRS. (2014). NRS 097 Grid Interconnection of Embedded Generation, Part 2: Small Scale Embedded
Generation, Section 3: Simplified utility connection criteria for low-voltage connected generators.
Johannesburg: NRS.
NRS. (2020). NRS 097 Grid Interconnection of Embedded Generation, Part 2: Small Scale Embedded
Generation, Section 1: Utility Interface (Amendment 2.1 ed.). Johannesburg: NRS.
33 kV busbar (Main sub) (incl. all building works & Lot R 9 070 000
common services)
11kV busbars - main sub (incl. all building works & Lot R 6 460 000
common services)
11kV busbars - switching sub (incl. all building works & Lot R 3 349 000
common services)
• Connection Agreement
(Distributor-Customer/Generator)
• PPA (generator-municipality)
• Connection Agreement
(Distributor-Generator)
• PPA (Generator-customer)
• Wheeling agreement (Generator-
Distributor-customer)
• Connection Agreement
(Distributor-Generator)
• PPA (Generator-trader)
• Wheeling agreement (Generator-
Distributor-trader)
• Trading agreement (trader-
Distributor)
Customer/Generator in municipal
network wheels across Eskom network
to a trader on a different Distributor’s
network:
Distributor Processes
This section covers the Distributor process.
Wheeling
Trading
PPP (Public Private Partnership)
(other)
OTHER AUTHORISATIONS
Astronomy Geographic Advantage Act 21 of 2007, (AGA
Act) permit
Civil Aviation Act 13 of 2009 approval for a wind facility
Mineral Petroleum Resources Development Act 28 of
2002 (MPRDA)- Section 53 approval
Electronic Communications Act 36 of 2005 (ECA)
DMRE ERA Section 34 Ministerial Determination
(other)
See also the Grid Code Secretariat document titled Renewable Power Plant Grid Code Compliance Test
Guideline - Version 3.0 (GCS, undated).
Islanding
Ancillary Services
Instantaneous Reserve
Regulating Reserve
Ramp Rates
Testing
Power Assessment:
Absolute Active Power Constraint
Active Power Gradient Constraint
Active Power Curtailment during Frequency Deviations
Reactive Power (Q) Full Capability of the Plant
(𝑃𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 above 50%)
Reactive power Full Capability of the Plant at 20%
Pmax)
Power Plant Control Modes
Reactive Power (Q) Control at 𝑃𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒
Power Factor Control
Voltage Control
SCADA Testing
Power Quality
Meets emission limits
Filter required and installed
RMS model (usually Digsilent PowerFactory)
EMT model (usually PSCAD)
RETEC
RETEC approval
• The surrounding network data, at least up to one voltage level above the proposed point of
connection:
o All cable and conductor parameters, including impedance per length, length of cable or
conductor, topology with dimensions, thermal limits.
o Relevant transformer parameters, including percentage impedance, winding and core losses,
tap changer settings (transformer test sheets).
o Other generation in the relevant network (generic information per generation type).
o A list of network contingencies that the Distributor deems realistic (as planned).
The network operational conditions (voltage levels, loading of equipment etc) need to be within
acceptable levels for all these cases.
31
Available at https://www.sseg.org.za/grid-impact-study-specification-guide/
1. Select an appropriate node on the network where the installation can connect.
In practice this will be a node closest to the planned installation that can successfully transfer the
energy generated.
2. Select an appropriate voltage level for the point of connection:
a. SSEG (up to 1 MW) generally connect at LV
b. Generators >1MW and < 20 MW generally connect at MV
c. Generators larger than 20 MW generally at HV
3. Evaluate network capacity:
a. Voltage levels in surrounding network and one voltage level up
b. Thermal capacity of lines and transformers in surrounding network and one voltage level
up
c. Voltage changes at all nodes in the surrounding network and one voltage level up
4. Evaluate fault levels for all study cases
a. The recommended short-circuit calculation method is according to IEC60909.
5. Adjust generation power factor for maximum leading and lagging and review point 3.
6. Evaluate appropriate network contingencies and review points 3 and 4.
7. Consider alternative point of connection and / or different voltage level.
8. Consider the reliability of the point of connection, i.e. the frequency and duration of interruptions
of this network point. Improved reliability may be required by the Customer/Generator and may
be funded via a special reliability charge as part of the tariff. (Also see AGUP in section 2.2.4).
9. Consider possible change in demand at Eskom Point(s) of Delivery (inform Eskom if relevant,
including consideration of Connection Agreement amendments).
The following studies, which form part of the design of the generator plant phase, are also included during
this phase of simulation studies.
• Short-circuit studies
• Rapid Voltage Fluctuations
• Protection coordination
Apart from the 3 times resonance screening, the latest version of the Grid Code does not require power
quality simulation to prove Grid Code Compliance, and such compliance is proven by using on-site
measurements of all steady-state power quality parameters:
Note that power quality recorders will also record voltage dips and interruptions. Such information is used
during the RMS and EMT model validation (see sections E.5 and E.6).
A simulation guideline is provided as a separate document - P13906 Recommended Practice for Grid Code
Compliance Studies for Renewable Energy Power Plants and Hybrid Power Plants (MPE, 2021)
The Grid Code compliance aspects are discussed in sections E.3 to E.7.
More details can be found in the Grid Code Secretariat document titled Renewable Power Plant Grid Code
Compliance Test Guideline - Version 3.0 (GCS, undated).
More details and reporting formats can be found in the Grid Code Secretariat document titled Renewable
Power Plant Grid Code Compliance Test Guideline - Version 3.0 (GCS, undated). Key tests are summarised
below for information. Also refer to Appendix 2 of the SAGC Network Code (NERSA, 2022) and Appendix
3 of the SAGC Information Exchange Code (NERSA, 2022).
In addition to the above, the following compliance checks are done over a longer time period:
1. Low Voltage Ride Through and High Voltage Ride Through Capabilities
The LVRT and HVRT cannot be tested due to the impact on the network and neighbouring
customers. The results of the simulation studies are accepted until proven incorrect.
The response of the installation is monitored during normal operations, when faults do occur on
the network. Based on the response of the plant during such conditions, a non-compliance may
be flagged (if it is the case).
2. Power Quality
Grid Code Compliance for power quality is proven by using on-site measurements only after
commissioning. These are done according to Appendix 13 of the RPP Grid Code.
The report for power quality compliance is sent to the Distributor for approval, before RETEC and
NERSA will consider the compliance.
These models are tested against the commissioning test results and recordings of real events. Section 14
of the RPP code provides details on how the models are to be validated.
These models are tested against the commissioning test results and recordings of real events. Section 14
of the RPPGC and Section 13 of the BESFCC provides details on how the models are to be validated.
Compliance to the Grid Code requirements for units smaller than 5 MW is achieved via NRS 097-2-1 and
IEC 61000-3-3 or IEC 61000-3-5 certification of the generator. This means that individual units are tested
according to these standards. For inverters larger than 1 MW, this can be achieved by testing to similar
standards, such as IEEE 1547 or IEEE 519 and the above IEC documents.
Units larger than 5 MW require a suitable measurement data set and analysis in terms of the apportioned
values. This requires at least one week of measured data.
Note that the Distributor must sign off on the power quality assessment before Grid Code compliance will
be issued.
In terms of ERA Schedule 2 (15 December 2022 updated 17 January 2023)32 the following registration and
licensing requirements apply:
Additional notes:
For generators required to register, NERSA has the following documents available on their website (at
the time of publication):
12.1 The registered facilities shall comply with the following technical
standards and/or specifications issued in terms of the Act:
32
Electricity Regulation Act: Amendment: Licensing Exemption and Registration Notice. Govt Gazette No 47877, 17
January 2023)
(c) South African Grid Code Requirements for Renewable Power Plants
10.1 The NSP shall not unreasonably deny grid connection to an eligible generator in accordance
with section 21(3) of the Act, which states:
“A transmission or distribution licensee must, to the extent provided for in the licence, provide non-
discriminatory access to the transmission and distribution power systems to third parties.”
10.2 Any dispute between an eligible generator and the NSP may be referred to NERSA in writing
for resolution.
10.3 The NSP shall take all necessary steps to ensure the safety of their operating personnel with
regard to generation. As a minimum, notices must be placed on the circuits where this generation
is available so that they are visible to the operators. The locations must be marked on all operating
diagrams.
10.4 The NSP must ensure that the generation facilities install appropriate protection and
metering at the connection point.
10.5 The NSP must maintain a database of all generation facilities within its area. The database
shall incorporate, as a minimum, the following information:
10.6 The NSPs must report the following information to NERSA on an annual basis (within three
(3) months after their financial year-end), or as and when necessary:
(c) The total energy each technology has generated onto their system in each ‘Time-of-Use tariff’
metered time period
(d) Complaints that they have received from customers on the same circuit, as the generation
facility, about quality of supply
(f) The tariffs applicable to these installations (if energy is sold to the municipality).
11.1 The HoD: ELC shall submit an annual report (calendar year) to the Electricity Subcommittee
on the registered generation facilities in the Republic of South Africa for noting. This report shall,
as a minimum, contain the:
11.2 The report shall be shared with the public by publishing it on the NERSA website. If necessary,
the report shall also be shared with other Government entities
End