Epc Schedule
Epc Schedule
132
SCHEDULE – A
(See Clauses 2.1 and 8.1)
SITE OF THE PROJECT
1 The Site
1.1 Site of the [Intermediate-Lane] Project Highway shall include the land, buildings,
structures and road works as described in Annex-I of this Schedule-A.
1.2 The dates of handing over the Right of Way to the Contractor are specified in
Annex-II of this Schedule-A.
1.3 An inventory of the Site including the land, buildings, structures, road works,
trees and any other immovable property on, or attached to, the Site shall be
prepared jointly by the Authority Representative and the Contractor, and such
inventory shall form part of the memorandum referred to in Clause 8.2.1 this
Agreement.
1.4 The alignment plans of the Project Highway are specified in Annex-III. In the case
of sections where no modification in the existing alignment of the Project
Highway is contemplated, the alignment plan has not been provided. Alignment
plans have only been given for sections where the existing alignment is proposed
to be modified.
1.5 The status of the environment clearances obtained or awaited is given in Annex-
IV.
222
Annex I
(Schedule-A)
Site
1. Site
1.1 The project road starts from Chalsa at Chainage 105 km and passing through Chalsa, Sulkapara,
Grassmore, Banarhat, Binnaguri and ends at Telipara Ch. 145.644 km (Existing Chainage). The Project
Road is a connection between Chalsa and Telipara. The project road lies in Jalpaiguri district of West
Bengal. The District is in plain to rolling terrain.
2. Land
The Site of the Project Highway comprises the land described below:
CHAINAGE Average Existing ROW
From To (m)
108000 108500 FOREST (Land Not Required for 2-lane Paved Shoulder)
108500 109000 FOREST (Land Not Required for 2-lane Paved Shoulder)
109000 109500 FOREST (Land Not Required for 2-lane Paved Shoulder)
109500 110000 FOREST (Land Not Required for 2-lane Paved Shoulder)
110000 110500 FOREST (Land Not Required for 2-lane Paved Shoulder)
110500 111000 FOREST (Land Not Required for 2-lane Paved Shoulder)
111000 111500 FOREST (Land Not Required for 2-lane Paved Shoulder)
111500 112000 FOREST (Land Not Required for 2-lane Paved Shoulder)
112000 112500 FOREST (Land Not Required for 2-lane Paved Shoulder)
112500 113000 FOREST (Land Not Required for 2-lane Paved Shoulder)
333
CHAINAGE Average Existing ROW
From To (m)
113000 113500 FOREST (Land Not Required for 2-lane Paved Shoulder)
113500 114000 FOREST (Land Not Required for 2-lane Paved Shoulder)
114000 114500 FOREST (Land Not Required for 2-lane Paved Shoulder)
114500 115000 FOREST (Land Not Required for 2-lane Paved Shoulder)
115000 115500 FOREST (Land Not Required for 2-lane Paved Shoulder)
115500 116000 FOREST (Land Not Required for 2-lane Paved Shoulder)
116000 116500 56.91
116500 117000 66.47
117000 117500 89.71
117500 118000 85.26
118000 118500 91.09
118500 119000 112.28
119000 119500 63.33
119500 120000 89.88
120000 120500 56.00
120500 121000 45.90
121000 121500 35.55
121500 122000 30.00
122000 122500 30.00
122500 123000 29.14
123000 123500 60.40
123500 124000 60.27
124000 124500 FOREST (Land Not Required for 2-lane Paved Shoulder)
124500 125000 FOREST (Land Not Required for 2-lane Paved Shoulder)
125000 125500 FOREST (Land Not Required for 2-lane Paved Shoulder)
125500 126000 FOREST (Land Not Required for 2-lane Paved Shoulder)
126000 126500 FOREST (Land Not Required for 2-lane Paved Shoulder)
126500 127000 FOREST (Land Not Required for 2-lane Paved Shoulder)
127000 127500 FOREST (Land Not Required for 2-lane Paved Shoulder)
127500 128000 31.08
128000 128500 30.77
128500 129000 35.11
129000 129500 84.69
444
CHAINAGE Average Existing ROW
From To (m)
3. Carriageway
The present carriageway of the Project Highway varies from 6.4m to 6.7m [intermediate lane].
The type of the existing pavement isflexible as per Following details -
Chainage Carriageway
555
124+000 125+500 Flexible Pavement 6.5
4. Major Bridges
The Site includes the following Major Bridges:
Existing Type of Structure
Total
S. No. Chainage Sub- Super- Span Arrangement(m)
Foundation Width(m)
(km) Structure Structure
PSC-T
1 107.725 Well Wall 3 X 42.89 10.6
Girder
PSC-T 1 X 42.9+
2 114.721 Well Wall 10.7
Girder 5 X 43.5+1 X 42.9
Balanced 1 X39.15 +
3 119.275 Well Wall 10.9
Cantilever 1 X12.15 + 1 X39.15
Continuous
RCC box
1 X39.28 + 1 X12.8 + 1
4 123.71 Well Wall with 10.9
X39.28
balanced
Cantilever
PSC-T 1 X20.78 +
5 126.623 Well Wall 10.6
Girder 7 X43.6 + 1 X20.78
The Site includes the following ROB (road over railway line)/RUB (road under railway line):
Type of Structure No. of Spans
S. Chainage Width
Super with Span
No. (km) Foundation (m)
Structure Length (m)
Nil
6. Grade Separators
7. Minor Bridges
5 CELL_5 X
9 117.400 RCC Box RCC Box RCC Box 10.5 12.5
3_BOX
10 117.55 Well Wall T Beam 1 X 13.2 7.6 8.7
11 120.975 Well Wall Slab 2 X 6.85 7.5 10.95
1 X 6.37 +
12 124.525 Well Wall Slab 7.5 8.3
3 X 10.05
13 125.57 Well Wall Slab 2 X 6.9 10 11
14 125.702 Open RCC RCC 1 X 6.85 11.1 12
15 140.275 Open RCC RCC 1 X 7.0 11 12.45
Nil
The details of bypasses are as follows: Formatted: List Paragraph1, Space Before: 0
Name of Bypass Chainage Length Carriageway pt, After: 0 pt, Line spacing: single, Outline
S. No. numbered + Level: 1 + Numbering Style: 1, 2,
(Town) From (km) To (km) (km) Width (m) Type
3, … + Start at: 1 + Alignment: Left + Aligned
Nil at: 0" + Indent at: 0.5", No widow/orphan
control, Don't adjust space between Latin and
Asian text, Don't adjust space between Asian
1.16. Other Structures text and numbers
Formatted: Font: Calibri, 11 pt, Not Bold
2. Following are the details of existing causeways: Formatted: Indent: Left: 0.56", Space
Before: 0 pt, After: 6 pt, No bullets or
Existing Chainage Structure Openings / Spans X
S. No Width (m) Formatted: Font: (Default) Calibri, 11 pt, Font
(km) Type Length color: Auto, English (United States)
NIL Formatted: Font: (Default) Calibri, 11 pt,
English (United States)
Formatted: Font: (Default) Calibri, 11 pt,
English (United States)
Formatted: Font: (Default) Calibri, 11 pt,
English (United States)
Formatted: Font: (Default) Calibri, 11 pt,
English (United States)
999
Annex-II
(Schedule-A)
Annex-III
(Schedule-A)
Alignment Plans
The existing alignment of the Project Highway shall be modified in the following sections
as per the alignment plan indicated below:
Environmental Clearances
Not Required
Appendix A- I
Existing Chainage Design Chainage Formatted: Font: (Default) Calibri, 11 pt, Bold
Sl. No.
(Km) (Km)
1 105.0000 105.000
2 106.0000 106.000
3 107.0000 107.000
4 108.0000 108.000
5 109.0000 109.000
6 110.0000 109.995
7 111.0000 110.996
8 112.0000 111.997
9 113.0000 112.998
10 114.0000 113.997
11 115.0000 114.997
12 116.0000 115.998
13 117.0000 116.997
14 118.0000 117.998
15 119.0000 118.997
16 120.0000 119.998
17 121.0000 120.996
18 122.0000 121.997
19 123.0000 122.997
20 124.0000 123.998
21 125.0000 124.997
22 126.0000 125.998
23 127.0000 126.996
24 128.0000 127.993
25 129.0000 128.996
26 130.0000 129.995
27 131.0000 130.998
28 132.0000 131.995
29 133.0000 132.996
30 134.0000 133.995
31 135.0000 134.995
121
212
Existing Chainage Design Chainage
Sl. No.
(Km) (Km)
32 136.0000 135.996
33 137.0000 136.997
34 138.0000 137.996
35 139.0000 138.996
36 140.0000 139.995
37 141.0000 140.996
38 142.0000 141.997
39 143.0000 142.996
40 144.0000 143.996
41 144.644 144.632
131
313
SCHEDULE – B
(See Clauses 2.1)
141
414
Annex I
(Schedule-B)
a. The Project Highway starts at Design Chainage Km 105+000 (at Chalsa) & ends at Km
145+632(atTelipara) in the state of West Bengal. Total Existing Length of Project road is 40.644
Km and Design Length of project is 40.632 Km. The project highway Two Lane with Paved
Shoulders shall be constructed as per Schedule D.
The Project Highway shall follow the existing alignment unless otherwise specified by the
Authority and shown in the alignment plans specified in Annex-III of Schedule-A. Geometric
deficiencies, if any, in the existing horizontal and vertical profiles shall be corrected as per the
prescribed standards for Plain/Rolling terrain to the extent land is available.
b. Width of Carriageway
Geometric design and general features of the Project Highway shall be in accordance with
Section 2 of the Manual.
The design speed shall be100 km/h(ruling) and 80 km/h(minimum) design speed for
Plain /Rolling terrain in accordance with section 2 of IRC: SP: 73-2015 1. As
Formatted: Font: 11 pt, Highlight per khasra-n
Formatted: Left, Numbered + Level: 1 + Bemet
2.2.3 Improvement of the existing road geometry Numbering Style: 1, 2, 3, … + Start at: 1 +
Alignment: Left + Aligned at:2. 0.25"
As +per presenta
Indent
In the following sections, where improvement of the existing road geometrics to the at: 0.5", Don't hyphenate Bemetarabyepa
prescribed standards is not possible, the existing road geometrics shall be improved Formatted: Font: 11 pt, Highlight
# To confirm this appro
to the extent possible within the given right of way and proper road signs and safety Formatted: List Paragraph1, Indent: Hanging:
0.81", Space After: 5 pt, Outline numbered +
measures shall be provided for safe regulation of fast moving, slow moving and Level: 2 + Numbering Style: 1, 2, 3, … + Start
at: 1 + Alignment: Left + Aligned at: 0.5" +
pedestrian traffic: Indent at: 0.75", No widow/orphan control,
Don't adjust space between Latin and Asian
text, Don't adjust space between Asian text
and numbers
S. Design Chainage (Km) Length Formatted: Left, Numbered + Level: 1 +
Remarks Numbering Style: 1, 2, 3, … + Start at: 1 +
No (m)
From To Alignment: Left + Aligned at: 0.25" + Indent
NIL at: 0.5", Don't hyphenate
Formatted: Font: 11 pt, Font color: Custom
Color(RGB(211,223,238)), Highlight
2.4In the following sections, where improvement of the existing road geometrics to the Formatted: Font: 11 pt, Highlight
prescribed standards is not possible within existing ROW, the existing road geometrics shall Formatted: Justified, Indent: Left: 0.5"
be improved to the extent possible within the given right of way and proper road signs and Formatted: Justified
safety measures shall be provided: Formatted: Indent: Left: -0.44", Hanging:
0.56"
2.3
Formatted: Space Before: 18 pt, Line
spacing: Multiple 1.15 li
Realignment Sections:-
Existing Chainage Design Chainage
(Km) (Km) Length
Sl. No Remarks
(Km)
From From From To
Nil
Sl. Corr. DesignChainage (Km) Length (Km) Name of Remark Formatted: Font: (Default) Times New
Roman, 10 pt, Font color: Auto
161
616
No From To Bypassvillage sSide Formatted: Font color: Auto
b) In open area, width of paved shoulders shall be 1.5m on both side and width of earthen
shoulder shall be 2 m on either side
C) In open area(With both side trapezoidal drain), width of paved shoulders shall be 2.5m on
both side and width of earthen shoulder shall be 1 m on either side.
171
717
d) Design and specification of paved shoulder and granular material shall confirm to
the requirements specified in paragraph 5.9.9 and 5.9.10 of the Manual.
2.7.1 Lateral and vertical clearances at underpasses and provision of guardrails/crash barriers shall be
as per paragraph 2.11 of the Manual.
2.7.2 Lateral clearance: The width of the opening at the underpasses shall be as follows:
2.8.1 Lateral and vertical clearances at overpasses and provision of guardrails/crash barriers Formatted: Font: Not Bold
Formatted: Font: Not Bold
shall be as per paragraph 2.11 of IRC: SP: 73-2015.
i.2.8.2 Lateral clearance: The width of the opening at the vehicle overpasses shall be as Formatted: Font: Not Bold
Formatted: Space After: 4 pt, Don't add
follows: space between paragraphs of the same style,
Line spacing: 1.5 lines, Outline numbered +
Sl. Design Chainage Level: 3 + Numbering Style: 1, 2, 3, … + Start
Span/opening (m) Remarks at: 1 + Alignment: Left + Aligned at: 0" +
No. (Km) Indent at: 0.5", Don't hyphenate
NIL Formatted: Font: Not Bold
Formatted: Font: Bold
Formatted: Normal, Indent: Left: 0.33",
Space Before: 12 pt
2.9 Service roads
Service roads shall be constructed at the locations and for the lengths indicated below:[Refer to
paragraph 2.13 of the Manual and provide details]
Indicative typical cross sections along with different types of cross-sections required to be Formatted: Justified, Indent: Left: 0.3",
Space After: 0 pt, Line spacing: 1.5 lines
developed in different segments of the project highway are indicated in Appendix B-I.
Cross Section schedule for the project highway is as follows:
Existing Chainage(km) Design Chainage(km) Length
Sl No TCS Type
From To From To (m)
1 105.000 105.520 105.000 105.520 0.52 TCS -2
2 105.520 106.540 105.520 106.540 1.02 TCS-1
3 106.540 106.860 106.540 106.860 0.32 TCS -2
4 106.860 116.313 106.860 116.310 9.45 TCS-1
5 116.313 116.558 116.310 116.555 0.245 TCS -2
6 116.558 117.594 116.555 117.590 1.035 TCS-1
7 117.594 117.912 117.590 117.910 0.32 TCS-3
8 117.912 119.655 117.910 119.650 1.74 TCS-1
9 119.655 120.147 119.650 120.140 0.49 TCS -2
10 120.147 124.573 120.140 124.570 4.43 TCS-1
11 124.573 125.518 124.570 125.510 0.94 TCS-3
12 125.518 134.029 125.510 134.020 8.51 TCS-1
13 134.029 134.905 134.020 134.90 0.88 TCS -2
14 134.905 141.000 134.900 140.990 6.09 TCS-1
15 141.000 142.867 140.990 142.860 1.87 TCS -2
16 142.867 145.644 142.860 145.632 2.772 TCS-1
191
919
S.No. TCS Type TCS Configuration Length(Km)
1 TCS-1 Overlay of flexible pavement for Two lane 35.047
carriageway with paved shoulder in Rural area
Overlay of flexible pavement with BC and DBM for
2 TCS-2 Two lane carriageway with paved shoulder in built up 4.325
are(both side cover drain)
Overlay of flexible pavement with BC and DBM for
3 TCS-3 Two lane carriageway with paved shoulder in Rural 1.26
area with both side trapezoidal drain
Total 40.632
Formatted: Space After: 0 pt
[Typical Cross Sections are appended separately]
Note 1: The cross section schedule given in above table is indicative and stretches may increase or
decrease depending upon profile designed by contractor however, this shall not be treated as
change of scope.
3 AT-GRADE INTERSECTIONS
All intersections and grade separators shall be as per Section 3 of the Manual. Existing
intersections which are deficient shall be improved to the prescribed standards.
Properly designed intersections shall be provided at the locations and of the types and features
given in the tables below:
a) Major Intersections
b) Minor Intersections
Subject to minimum of the following Crust as per the design is as follows. Formatted: Left, Indent: Left: 0.5", Line
spacing: 1.5 lines, Widow/Orphan control,
Don't hyphenate
For Flexible Pavement
DBM Total
BC
GSB WMM Grading-II Thickness
Grading-II
(mm) (mm) (in two Layer) (mm)
(mm)
(mm)
Widening
200 250 85 40 590
Portion
Overlay
- - 50 40 90
Portion
i. Design Traffic
Notwithstanding anything to the contrary contained in this Agreement or the Manual, the
Contractor shall be design of Flexible pavement considering 15 years design life.&design
traffic of 24 MSA
However, In any case the proposed crust composition shall not be less than that given
in the table below:
Not with standing anything to the contrary contained in this Agreement or the Manual,
the Contractor shall design the pavement for design traffic as given below.
DBM Total
GSB WM BC
Grading-II Thickness
(mm Grading-II
(in two Layer) (mm)
(mm) (mm)
(mm)
Widening
200 250 85 40 590
Portion
Overlay
- - 50 40 90
Portion
Refer to paragraph 5.9.7 of the Manual and specify the sections, if any, to be reconstructed.
6 ROADSIDE DRAINAGE
Drainage system including surface and subsurface drains for the Project Highway shall be provided
as per section 6 ofof IRC: SP: 73-2015.RCC covered drain shall be provided in both side of
Built-Up areas at following locations.
222
222
Existing Chainage(km) Design Chainage(km) Total
Length(km) Side
From To From To Length(km)
PCCTrapezoidal Drain:
NOTE: The locations of Drains at roadway shall be as per cross section type given at Schedule D. In
all built up areas RCC covered drains with Footpath shall be provided. Suitable crossing shall
be provided at approaches to properties etc. invert levels of drains shall be decided on the basis
of ground slopes of adjoining properties and open grounds
NOTE: In cutting portions PCCTrapezoidal Drain of suitable size shall be constructed in consultation
with Authority Engineer.
NOTE: Above length of the lined drains are indicative and least specified. The actual length of
the lined drains shall be determined by the Contractor keeping in view the drainage
location and in accordance with the Manual requirements with approval from the
Authority's Engineer. Any increase in the length of drain as specified in above
location shall not constitute a Change of Scope.
7 DESIGN OF STRUCTURES
7.1 General
i.7.1.1 Allbridges, culverts and structures shall be designed and constructed in accordance Formatted: Justified, Space Before: 0 pt,
After: 0 pt, Don't add space between
with section 7 of the Manual (IRC: SP: 73-2015) and shall conform to the cross-sectional paragraphs of the same style, Line spacing:
1.5 lines, Outline numbered + Level: 3 +
features and other details specified therein. All designs shall be in conforming with is Numbering Style: 1, 2, 3, … + Start at: 1 +
Alignment: Left + Aligned at: 0" + Indent at:
IRC and International Codes. The deviation shown in Schedule – D shall be taken in to 0.5", Don't hyphenate
considerations.
ii.7.1.2 The width of carriageway of new major & minor bridges shall be as mentioned below:
2 Minor Bridge
Span arrangement of Major and Minor Bridge shall be designed by contractor on the
basis of detailed surveys & investigations subject to minimum specified in GAD as per
para 7.3.2 of this schedule. Founding levels shall be decided after detailed Geo-
Technical investigation, Waterway, road top level, soffit etc. shall be decided on the
basis of land survey conforming to various codal provision applicable
7.1.17.1.3 Thefollowing structures shall be provided with footpaths:
S. No.
7.1.27.1.4 The following structures shall be designed to carry utility services specified
in table below:
Culvert
Location Type Of Proposed Span
Sl.
Design Culvert(Proposed) Arrangement
Chainage(km)
3.0m X 4.0m
1 105.505 RCC BOX
(Single Cell)
RCC BOX 3.0m X 4.0m
2 108.747
(Single Cell)
RCC BOX 4.0m X 4.0m
3 109.367
(Single Cell)
RCC BOX 4.0m X 3.0m
4 110.467
(Single Cell)
RCC BOX 3.0m X 4.0m
5 112.171
(Single Cell)
RCC BOX 2.0m X 3.0m
6 117.031
(Single Cell)
RCC BOX 2.0mX2.0m
7 117.235
(Single Cell)
RCC BOX 3.0m X 4.0m
8 118.956
(Single Cell)
RCC BOX 3.0m X 3.0m
9 119.990
(Single Cell)
RCC BOX 2.0m X 3.0m
10 128.122
(Single Cell)
RCC BOX 3.0m X 3.0m
11 134.700
(Single Cell)
• RCC BOX- ReignforcedCcement Cconcrete box type
• Note:- It is clarified that as per site requirement New Culverts if required for drainage
arrangement shall be identified & constructed if any during development shall be
constructed as per standard set forth in Schedule ‘D’& as per instruction of Authority
Engineer
Nil
7.2.37.2.4 Additional new culverts (given in table below) shall be constructed for width
equal to the roadway width of the Project Highway & as per typical cross-section given
in IRC: SP: 73-2015:
Proposed Span
Sl. Design Chainage(km) Proposed Type
Arrangement
2.0m X 3.0m
1 119.543 RCC Box Culvert
(Single Cell)
2.0mX2.0m
2 129.621 RCC Box Culvert
(Single Cell)
2.0mX2.0m
3 130.950 RCC Box Culvert
(Single Cell)
252
525
Proposed Span
Sl. Design Chainage(km) Proposed Type
Arrangement
2.0mX2.0m
4 131.995 RCC Box Culvert
(Single Cell)
2.0m X 3.0m
5 133.944 RCC Box Culvert
(Single Cell)
2.0m X 3.0m
6 135.300 RCC Box Culvert
(Single Cell)
2.0m X 3.0m
7 136.950 RCC Box Culvert
(Single Cell)
2.0mX2.0m
8 137.730 RCC Box Culvert
(Single Cell)
2.0m X 3.0m
9 138.950 RCC Box Culvert
(Single Cell)
2.0mX2.0m
10 139.850 RCC Box Culvert
(Single Cell)
2.0mX2.0m
11 142.933 RCC Box Culvert
(Single Cell)
2.0mX2.0m
12 143.970 RCC Box Culvert
(Single Cell)
2.0mX2.0m
13 144.625 RCC Box Culvert
(Single Cell)
NOTE: Where the Existing Bridge reconstructed as New Bridge at same place, dismantling of
Existing Major/Minor bridge shall be carried out with all lead and lifts. Temporary diversion
works shall be constructed as per Fig. 9.26 of manual IRC: SP: 73-2015 and as per para 112 of
standards and specifications of Indian Roads Congress (MORTH) Fifth Revision-2013 with
adequate cross drainage structure and traffic safety and control devices. The diversions shall be
maintained in satisfactory condition till such time they are required and as directed by the
Authority Engineer. If the diversion is not possible within ROW the bridges shall be constructed
by half / half portion to continuing the traffic flow.
Nil
272
727
S. Design Proposed Proposed span Formatted: Font: (Default) Times New
Proposed Roman, Bold
No Chainage structural arrangement Remarks
Width(m)
. (Km) configuratio (m) Formatted: Font: (Default) Times New
nsuperstruct Roman, Bold
NIL
Formatted: Font: (Default) Times New
Roman, Bold
7.3.3 Repairs of the existing minor bridges shall be undertaken as follows:
Formatted: Font: (Default) Times New
Roman, Bold
Existing
Formatted: Font: (Default) Times New
Existing Design River/ Carriagewa Total Roman, Bold
Sl. Type of Span Arrangement
Chainage Chainage Nallah y Width Width Formatted: Font: Not Bold, Font color: Auto
Structures (No. x Length) (m)
(m) (m)
SLAB
1 109.103 109.102 STREAM 1 X 6.8 11.30 12.35
BRIDGE
SLAB
2 111.630 111.628 STREAM 1 X 6.75 10.80 11.68
BRIDGE
1 X 6.8M+
KALIKHOL A-P_SLAB
3 112.818 112.814 1 X 13.25M+1 X 7.50 8.55
A P-P_T-BEAM
6.8M
SLAB
4 113.548 113.544 STREAM 1 X 6.7 10.60 11.45
BRIDGE
AMBAKHO SLAB
5 114.118 114.116 2 X 9.9 10.10 10.95
LA BRIDGE
SLAB
6 115.930 115.901 STREAM 1 X 6.94 11.60 12.80
BRIDGE
1 X 13.3 + 1 X 13.3
7 116.750 116.744 SUKHANI RCC T-BEAM 7.50 8.32
+ 1 X 13.3
MOYNA
8 117.400 117.397 BOX BRIDGE 5 CELL_5 X 3_BOX 10.50 12.50
KHOLA-I
KALI SLAB 1 X 6.37 +
9 124.525 124.517 7.50 8.30
KHOLA BRIDGE 3 X 10.05
4 363.628 Gainsari Jn Railway 2x18+1x30 12.90m Formatted: Line spacing: 1.5 lines
The grade separated structures shall be provided at the locations and of the type and Formatted: Font: Bold
Formatted: Line spacing: Multiple 1.15 li
length specified in paragraphs 2.10 of this Annex-I.
Formatted: Line spacing: Multiple 1.15 li
g.7.6 List of Major Bridges and Structures Formatted: Indent: Left: 0", Hanging:
0.33", Space Before: 10 pt, After: 0 pt, Don't
The following is the list of the Major Bridges whichare proposed to be retained with add space between paragraphs of the same
style, Line spacing: 1.5 lines, Outline
repair. numbered + Level: 2 + Numbering Style: 1, 2,
3, … + Start at: 1 + Alignment: Left + Aligned
Existing at: 0" + Indent at: 0.33", Don't hyphenate
Existing
Design River/ Carriagewa Total Formatted: Space Before: 0 pt, After: 0 pt,
Sl Chainag Type of Span Arrangement Line spacing: 1.5 lines
Chainage Nallah y Width Width
e Structures (No. x Length) (m)
(m) (m) Formatted: Space Before: 0 pt, After: 0 pt,
Don't add space between paragraphs of the
MURTI PSC T same style, Line spacing: 1.5 lines, Outline
1 107.725 107.721 3 X 42.89 7.40 10.60 numbered + Level: 2 + Numbering Style: 1, 2,
RIVER GIRDER
3, … + Start at: 1 + Alignment: Left + Aligned
PSC-T 1 X 42.9+ at: 0" + Indent at: 0.33", Don't hyphenate
2 114.721 114.719 JALDHAKA 7.40 10.70
GIRDER 5 X 43.5+1 X 42.9
BALANCED 1 X39.15 +
3 119.275 119.270 GATHIA CANTILEVE 1 X12.15 + 1 7.37 10.90
R X39.15
CONTINUOU
S RCC
BOXWITH 1 X39.28 + 1 X12.8
4 123.710 123.696 KUJI DIANA 7.40 10.90
BALANCED + 1 X39.28
CANTILEVE
R
PSC-T 1 X20.78 +
5 126.623 126.616 DIANA 7.40 10.60
GIREDR 7 X43.6 + 1 X20.78
303
030
h.7.7 Repairs and strengthening of bridges and structures
Formatted: Space Before: 0 pt, After: 0 pt,
Line spacing: 1.5 lines
The existing major and minor bridges to be repaired/strengthened, and the nature and
extent of repairs /strengthening required are given below:
A. Minor
B.A. Bridges
Existing Design
Sl. Nature and extent of repairs /strengthening to be carried out
Chainage Chainage
Jacketing of Abutment walls (RCC M30) with HYSD Reinforcement
Dismantling of existing Wing Wall
Construction of new Wing Wall (PCC M20)
Patching of damaged concrete surface of Deck Slab
Replacement of Expansion Joint
1 109.103 109.102
Dismantling of damaged Railing
Construction of Crash barrier
Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Jacketing of Abutment walls (RCC M30) with HYSD Reinforcement
Dismantling of existing Wing Wall
Construction of new Wing Wall (PCC M20)
Patching of damaged concrete surface of Deck Slab
Replacement of Expansion Joint
2 111.630 111.628
Dismantling of damaged Railing
Construction of Crash barrier
Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Jacketing of Abutment walls (RCC M30) with HYSD Reinforcement
Patching of damaged concrete surface of Deck Slab
Replacement of Expansion Joint
3 112.818 112.814
Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Jacketing of Abutment walls (RCC M30) with HYSD Reinforcement
Dismantling of existing Wing Wall
Construction of new Wing Wall (PCC M20)
Patching of damaged concrete surface of Deck Slab
4 113.548 113.544
Replacement of Expansion Joint
Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Dismantling of existing Wing Wall
Construction of new Wing Wall (PCC M20)
Patching of damaged concrete surface of Deck Slab
5 114.118 114.116 Replacement of Expansion Joint
Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Dismantling of existing Wing Wall
Construction of new Wing Wall (PCC M20)
6 115.930 115.901 Patching of damaged concrete surface of Deck Slab
Replacement of Expansion Joint
Dismantling of damaged Railing
313
131
Existing Design
Sl. Nature and extent of repairs /strengthening to be carried out
Chainage Chainage
Construction of Crash barrier
Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Construction of new Wing Wall (PCC M20)
Patching of damaged concrete surface of Deck Slab
Replacement of Expansion Joint
7 116.750 116.744
Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Jacketing of Abutment walls (RCC M30) with HYSD Reinforcement
8 117.400 117.397
Protection Work
Patching of damaged concrete surface of Deck Slab
Replacement of Expansion Joint
9 124.525 124.517 Replacement of drainage spout
Replacement of existing bituminous concrete wearing coat
Protection Work
Formatted: Space After: 4 pt, Don't add
B. Major Bridge space between paragraphs of the same style,
Line spacing: single, Numbered + Level: 1 +
Existing Design Numbering Style: A, B, C, … + Start at: 1 +
Sl. Nature and extent of repairs /strengthening to be carried out Alignment: Left + Aligned at: 0.75" + Indent
Chainage Chainage
at: 1", Don't hyphenate
Replacement of Expansion Joint
Replacement of drainage spout
1 107.725 107.721 Dismantling of existing bituminous concrete wearing coat
Laying of wearing Course
Strengthening of pedestal by 10mm thick steel plate jacketing
Replacement of Expansion Joint
Replacement of drainage spout
Dismantling of existing bituminous concrete wearing coat
2 114.721 114.719
Laying of wearing Course
Laying of shortcrete cement on footpath
Strengthening of pedestal by 10mm thick steel plate jacketing
Replacement of Expansion Joint
Replacement of drainage spout
Dismantling of existing bituminous concrete wearing coat
3 119.275 119.270 Laying of wearing Course
Applying cement based polymer mortar (@ 20% of surface area)
Epoxy bonding
Strengthening of pedestal by 10mm thick steel plate jacketing
Replacement of Expansion Joint
Replacement of drainage spout
Dismantling of existing bituminous concrete wearing coat
4 123.710 123.696 Laying of wearing Course
Laying of shortcrete cement on footpath
Applying cement based polymer mortar (@ 20% of surface area)
Strengthening of pedestal by 10mm thick steel plate jacketing
Replacement of drainage spout
Dismantling of existing bituminous concrete wearing coat
5 126.623 126.616
Laying of wearing Course
Strengthening of pedestal by 10mm thick steel plate jacketing
C. ROB / RUB
323
232
Design Nature and extent of repairs /strengthening to be
S. No. Formatted: Space Before: 0 pt, After: 0 pt
Chainage (Km) carried out
NIL Formatted Table
Formatted: Space Before: 0 pt
Formatted: Space Before: 0 pt, After: 0 pt
Formatted: Space Before: 0 pt, After: 0 pt,
Don't add space between paragraphs of the
same style, Line spacing: single, Numbered +
Level: 1 + Numbering Style: A, B, C, … + Start
1D. Overpasses/Underpasses and other structures at: 1 + Alignment: Left + Aligned at: 0.75" +
Indent at: 1", Don't hyphenate
Design
S. Formatted: Space Before: 0 pt, After: 0 pt
Chainage Nature and extent of repairs /strengthening to be carried out
No.
(Km) Formatted Table
NIL
NIL Formatted: Font color: Auto
Length
Chainage (m)
Sl No. Type
(km)
U/S D/S
Guide Bund
1 107.721 129.270 25.854
2 114.719 303.844 60.769 Guide Bund
3 119.27 90.717 18.143 Guide Bund
4 123.696 89.788 17.958 Guide Bund
5 126.616 350.000 70.000 Guide Bund
333
333
k.9.1 Road side furniture shall be provided in accordance with the provisions of Section 9 of Formatted: Indent: Left: 0.25", Hanging:
the IRC: SP: 73-201507. 0.33", Line spacing: single, Outline numbered
+ Level: 2 + Numbering Style: 1, 2, 3, … +
Start at: 1 + Alignment: Left + Aligned at:
a) Pedestrian guard rails: At built up area. 0.33" + Indent at: 0.58", Don't hyphenate
b) Delineators: For curve location, approaches of all structure, junction and bus bay location.
c) Cats Eye: both side all along the project road
9.19.2Overhead traffic signs: location and size
Full width
1. Overhead Traffic signs: 2 8 3 locations Formatted: Indent: Left: 0.5", Space Before:
6 pt, After: 4 pt, No bullets or numbering,
Overhead Traffic Signs (locations & Size) shall conform to the Manual of Specifications Don't hyphenate
(IRC: 67). The locations of overhead signs shall be finalized in consultation with
Authority Engineer
Note: All Traffic Signs for Road Users would be provided as per Manual. However the
Contractor shall provide minimum numbers of Cautionary, Mandatory, Warning and
Informatory Traffic Sign Boards as mentioned below:
13 Junction
i. Stop Sign 10 900mm Octagon
ii. Give Way Sign 10 900 mm triangle:
iii. speed limt 10 600 circular:
343
434
S. No Location Numbers Size
Direction and Place
iv. Flag Type Direction Sign 30 Identification signs upto 0.9
sqm size board
10 COMPULSORY AFFORESTATION
[Refer to paragraph 12.1 of the Manual and specify the number of trees which are required
to be planted by the Contractor as compensatory a forestation.]
About 5 times of no of trees are required to be planted which are failed due to
construction.
Major Bridge 5 1000 for approach of Major Bridge ,@ 50m length at each side
Minor Bridge 15 3000 for approach of Major Bridge ,@ 50m length at each side
Not Applicable
363
636
SCHEDULE – C
(See Clauses 2.1)
PROJECT FACILITIES
The Contractor shall construct the Project Facilities in accordance with the provisions
of this Agreement. Such Project Facilities shall include:
a) Toll plaza
b) Roadside furniture;
c) Pedestrian facilities;
d) Tree plantation;
e) Truck lay-byes;
f) Bus-bays and bus shelters;
g) Rest areas; and
h) Road Boundary Stones (RBS);
i) Street Lighting;
j) Traffic Aid Posts; Formatted: Indent: Left: 0.31", Space
Before: 0 pt, After: 12 pt, Line spacing: 1.5
k) Medical Aid Posts; lines, Numbered + Level: 1 + Numbering Style:
a, b, c, … + Start at: 1 + Alignment: Left +
l) Highway Patrol Units; Aligned at: 0.5" + Indent at: 0.75", Don't
keep with next, Don't hyphenate
m) Emergency Medical Services; Formatted: Font: Bold
p) Advance Traffic Management System (ATMS); Formatted: Font: (Default) Times New
Roman, Bold, Not Italic
q) Operation and Maintenance Centre. Formatted: Font: (Default) Times New
Roman, Bold, Not Italic
Formatted: Font color: Auto
4
Formatted: Font: (Default) Times New
Others to be specified Roman, 12 pt, Not Italic, Font color: Auto
c) Landscaping & Tree Plantation shall be provided in accordance with the manual Formatted: Indent: Left: 0.25", Space
Before: 12 pt, Don't add space between
paragraphs of the same style, Line spacing:
and Specifications and Standards as referred in Schedule DRoadside 1.5 lines, Numbered + Level: 1 + Numbering
Style: a, b, c, … + Start at: 1 + Alignment:
furniture; Left + Aligned at: 0.5" + Indent at: 0.75",
Formatted: Font: (Default) Arial, English
The roadside furniture shall include the provision of: (United States)
Traffic signs include roadside signs, overhead signs and kerb-mounted signs along the
entire Project Highway as per the manual of specifications.
b) Pavement Markings:
Pavement markings shall cover road marking as per the manual of specifications.
c) LED Traffic Blinkers:
LED Traffic Blinkers for the entire project highway at the locations as suggested in
Manual.
d) Crash barrier
Delineators for the entire Project Highway at the locations as suggested in Manual. Formatted: Normal, Indent: Left: 0.5"
414
141
Formatted: Indent: Left: 0.5", First line: 0",
Tab stops: Not at 1"
424
242
*The ffinal locations of Bus Bays shall be finalized by Authority
Engineer
h)g) Rest areas;
Formatted: Font: (Default) Times New
Design Chainage Roman, 10 pt, Not Italic
(Km.) Formatted Table
S. No. Design Chainage (Km) Location Formatted: Font: (Default) Times New
Roman, 10 pt, Not Bold, Not Italic, Font color:
NIL Auto
Formatted: Font color: Auto
Formatted: Indent: Left: 0", First line: 0",
Tab stops: Not at 1"
434
343
SCHEDULE – D
(See Clauses 2.1)
444
444
Annex - I
(Schedule-D)
Specifications and Standards for Construction Formatted: Font: 14 pt, Bold
2.2. Covered drains has been provided at the edge of ROW and chequered tilesPavered
blocksflooring haves been provided in the available space between the edge of
carriageway and drain-cum-footpath (TCS-IVI& TCS-IVB) in the built-up area.
S.No. Clause Modified provisions Formatted: Normal, Level 2, Line spacing:
1.5 lines, Don't hyphenate
As per Schedule B and
1. 7.8 (River training work) drawing. Excluding the
any amendment of IRC-89
454
545
SCHEDULE - E
(See Clauses 2.1 and 14.2)
MAINTENANCE REQUIREMENTS
1 Maintenance Requirements
1.1 The Contractor shall, at all times maintain the Project Highway in
accordance with the provisions of this Agreement, Applicable Laws and
Applicable Permits.
1.2 The Contractor shall repair or rectify any Defect or deficiency set forth in
Paragraph 2 of this Schedule-E within the time limit specified therein and
any failure in this behalf shall constitute non-fulfillment of the Maintenance
obligations by the Contractor. Upon occurrence of any breach hereunder, the
Authority shall be entitled to effect reduction in monthly lump sum payment
as set forth in Clause 14.6 of this Agreement, without prejudice to the rights
of the Authority under this Agreement, including Termination thereof.
1.3 All Materials, works and construction operations shall conform to the
MORTH Specifications for Road and Bridge Works, and the relevant IRC
publications. Where the specifications for a work are not given, Good
Industry Practice shall be adopted.
5 Emergency repairs/restoration
160
160
Annex - I
(Schedule-E)
The Contractor shall repair and rectify the Defects and deficiencies specified in this
Annex-I of Schedule-E within the time limit set forth in the table below.
161
161
Nature of Defect or deficiency Time limit for
repair/rectification
(ii) Edge drop at shoulders exceeding 7 (seven) days
40 mm
(iii) Variation by more than 15% in the 30 (thirty) days
prescribed side (embankment)
slopes
(iv) Rain cuts/gullies in slope 7 (seven) days
(v) Damage to or silting of culverts 7 (seven) days
and side drains
(vi) Desilting of drains in urban/semi- 24 hours
urban areas
(vii) Railing, parapets, crash barriers 7 (seven) days (Restore
immediately if causing
safety hazard)
(c) Road side furniture including
road sign and pavement
marking
(i) Damage to shape or position, poor 48 hours
visibility or loss of retro-
reflectivity
(ii) Painting of km stone, railing, As and when
parapets, crash barriers required/Once every year
(iii) Damaged/missing road signs 7 (seven) days
requiring replacement
(iv) Damage to road mark ups 7 (seven) days
(d) Road lighting
(i) Any major failure of the system 24 hours
(ii) Faults and minor failures 8 hours
(e) Trees and plantation
(i) Obstruction in a minimum head- 24 hours
room of 5 m above carriageway or
obstruction in visibility of road
signs
(ii) Removal of fallen trees from 4 hours
carriageway
(iii) Deterioration in health of trees and Timely watering and
bushes treatment
162
Nature of Defect or deficiency Time limit for
repair/rectification
(iv) Trees and bushes requiring 30 (thirty) days
replacement
(v) Removal of vegetation affecting 15 (fifteen) days
sight line and road structures
(f) Rest area
(i) Cleaning of toilets Every 4 hours
(ii) Defects in electrical, water and 24 hours
sanitary installations
(g) [Toll Plaza]
(h) Other Project Facilities and
Approach roads
(i) Damage in approach roads, 15 (fifteen) days
pedestrian facilities, truck lay-
byes, bus-bays, bus-shelters, cattle
crossings, [Traffic Aid Posts,
Medical Aid Posts] and service
roads
(ii) Damaged vehicles or debris on the 4 (four) hours
road
163
Nature of Defect or deficiency Time limit for
repair/rectification
(d) Bearings (metallic) of bridges
(i) Deformation, damages, tilting or 15 (fifteen) days
shifting of bearings Greasing of metallic
bearings once in a year
(e) Joints
(i) Malfunctioning of joints 15 (fifteen) days
(f) Other items
(i) Deforming of pads in elastomeric 7 (seven) days
bearings
(ii) Gathering of dirt in bearings and 3 (three) days
joints; or clogging of spouts, weep
holes and vent-holes
(iii) Damage or deterioration in kerbs, 3 (three) days
parapets, handrails and crash (immediately within 24
barriers hours if posing danger to
safety)
(iv) Rain-cuts or erosion of banks of 7 (seven) days
the side slopes of approaches
(v) Damage to wearing coat 15 (fifteen) days
(vi) Damage or deterioration in 30 (thirty) days
approach slabs, pitching, apron,
toes, floor or guide bunds
(vii) Growth of vegetation affecting the 15 (fifteen) days
structure or obstructing the
waterway
(g) Hill Roads
(i) Damage to retaining wall/breast 7 (seven) days
wall
(ii) Landslides requiring clearance 12 (twelve) hours
(iii) Snow requiring clearance 24 (twenty four) hours
[Note: Where necessary, the Authority may modify the time limit for
repair/rectification, or add to the nature of Defect or deficiency before
issuing the bidding document, with the approval of the competent authority.]
164
164
SCHEDULE - F
(See Clause 3.1.7(a))
APPLICABLE PERMITS
1 Applicable Permits
1.1 The Contractor shall obtain, as required under the Applicable Laws, the
following Applicable Permits:
165
165
SCHEDULE – G
[DG(RD)&SS,
WHEREAS:
1. The Bank hereby unconditionally and irrevocably guarantees the due and
faithful performance of the Contractor‟s obligations during the {Construction
Period/ Defects Liability Period and Maintenance Period} under and in
accordance with the Agreement, and agrees and undertakes to pay to the
Authority, upon its mere first written demand, and without any demur,
reservation, recourse, contest or protest, and without any reference to the
Contractor, such sum or sums up to an aggregate sum of the Guarantee
Amount as the Authority shall claim, without the Authority being required to
prove or to show grounds or reasons for its demand and/or for the sum
specified therein.
166
166
2. A letter from the Authority, under the hand of an officer not below the rank
of [General Manager in the National Highways Authority of India], that the
Contractor has committed default in the due and faithful performance of all
or any of its obligations under and in accordance with the Agreement shall be
conclusive, final and binding on the Bank. The Bank further agrees that the
Authority shall be the sole judge as to whether the Contractor is in default in
due and faithful performance of its obligations during and under the
Agreement and its decision that the Contractor is in default shall be final and
binding on the Bank, notwithstanding any differences between the Authority
and the Contractor, or any dispute between them pending before any court,
tribunal, arbitrators or any other authority or body, or by the discharge of the
Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act
as if the Bank were the principal debtor and any change in the constitution of
the Contractor and/or the Bank, whether by their absorption with any other
body or corporation or otherwise, shall not in any way or manner affect the
liability or obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the
liability of the Bank under this Guarantee, to vary at any time, the terms and
conditions of the Agreement or to extend the time or period for the
compliance with, fulfillment and/ or performance of all or any of the
obligations of the Contractor contained in the Agreement or to postpone for
any time, and from time to time, any of the rights and powers exercisable by
the Authority against the Contractor, and either to enforce or forbear from
enforcing any of the terms and conditions contained in the Agreement and/or
the securities available to the Authority, and the Bank shall not be released
from its liability and obligation under these presents by any exercise by the
Authority of the liberty with reference to the matters aforesaid or by reason
of time being given to the Contractor or any other forbearance, indulgence,
act or omission on the part of the Authority or of any other matter or thing
whatsoever which under any law relating to sureties and guarantors would
but for this provision have the effect of releasing the Bank from its liability
and obligation under this Guarantee and the Bank hereby waives all of its
rights under any such law.
9. The Bank undertakes not to revoke this Guarantee during its currency, except
with the previous express consent of the Authority in writing, and declares
and warrants that it has the power to issue this Guarantee and the
undersigned has full powers to do so on behalf of the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent
by post addressed to the Bank at its above referred branch, which shall be
deemed to have been duly authorised to receive such notice and to effect
payment thereof forthwith, and if sent by post it shall be deemed to have
been given at the time when it ought to have been delivered in due course of
post and in proving such notice, when given by post, it shall be sufficient to
prove that the envelope containing the notice was posted and a certificate
signed by an officer of the Authority that the envelope was so posted shall be
conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain
in force and effect for up to the date specified in paragraph 8 above or until it
is released earlier by the Authority pursuant to the provisions of the
Agreement.
(Signature)
(Name)
(Designation)
(Code Number)
(Address)
$
Insert date being 2 (two) years from the date of issuance of this Guarantee (in accordance with
Clause 7.2 of the Agreement).
168
168
NOTES:
(i) The bank guarantee should contain the name, designation and code number
of the officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the
Bank as well as of issuing branch should be mentioned on the covering letter
of issuing branch.
169
169
Annex – II
(Schedule - G)
(See Clause 7.5.3)
[DG(RD)&SS,
WHEREAS:
(A) [name and address of contractor] (hereinafter called the “Contractor") has
executed an agreement (hereinafter called the “Agreement”) with the [name
and address of the authority], (hereinafter called the “Authority”) for the
construction of the ***** section of [National Highway No. **] on
Engineering, Procurement and Construction (the “EPC”) basis, subject to
and in accordance with the provisions of the Agreement.
(B) In accordance with Clause 7.5.3 of the Agreement, the Contractor may
withdraw the retention money (hereinafter called the “Retention Money”)
after furnishing to the Authority a bank guarantee for an amount equal to the
proposed withdrawal.
2. A letter from the Authority, under the hand of an officer not below the rank
of [General Manager in the National Highways Authority of India], that the
Contractor has committed default in the due and faithful performance of all
or any of its obligations for under and in accordance with the Agreement
shall be conclusive, final and binding on the Bank. The Bank further agrees
that the Authority shall be the sole judge as to whether the Contractor is in
default in due and faithful performance of its obligations during and under
170
170
the Agreement and its decision that the Contractor is in default shall be final,
and binding on the Bank, notwithstanding any differences between the
Authority and the Contractor, or any dispute between them pending before
any court, tribunal, arbitrators or any other authority or body, or by the
discharge of the Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act
as if the Bank were the principal debtor and any change in the constitution of
the Contractor and/or the Bank, whether by their absorption with any other
body or corporation or otherwise, shall not in any way or manner affect the
liability or obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the
liability of the Bank under this Guarantee, to vary at any time, the terms and
conditions of the Retention Money and any of the rights and powers
exercisable by the Authority against the Contractor, and either to enforce or
forbear from enforcing any of the terms and conditions contained in the
Agreement and/or the securities available to the Authority, and the Bank
shall not be released from its liability and obligation under these presents by
any exercise by the Authority of the liberty with reference to the matters
aforesaid or by reason of time being given to the Contractor or any other
forbearance, indulgence, act or omission on the part of the Authority or of
any other matter or thing whatsoever which under any law relating to sureties
and guarantors would but for this provision have the effect of releasing the
Bank from its liability and obligation under this Guarantee and the Bank
hereby waives all of its rights under any such law.
8. The Guarantee shall cease to be in force and effect 90 (ninety) days after the
date of the Completion Certificate specified in Clause 12.4 of the Agreement.
9. The Bank undertakes not to revoke this Guarantee during its currency, except
with the previous express consent of the Authority in writing, and declares
and warrants that it has the power to issue this Guarantee and the
undersigned has full powers to do so on behalf of the Bank.
171
171
10. Any notice by way of request, demand or otherwise hereunder may be sent
by post addressed to the Bank at its above referred branch, which shall be
deemed to have been duly authorised to receive such notice and to effect
payment thereof forthwith, and if sent by post it shall be deemed to have
been given at the time when it ought to have been delivered in due course of
post and in proving such notice, when given by post, it shall be sufficient to
prove that the envelope containing the notice was posted and a certificate
signed by an officer of the Authority that the envelope was so posted shall be
conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain
in force and effect up to the date specified in paragraph 8 above or until it is
released earlier by the Authority pursuant to the provisions of the
Agreement.
(Signature)
(Name)
(Designation)
(Code Number)
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number
of the officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the
Bank as well as of issuing branch should be mentioned on the covering letter
of issuing branch.
172
172
Annex – III
(Schedule - G)
(See Clause 19.2)
[DG(RD)&SS,
WHEREAS:
(A) [name and address of contractor] (hereinafter called the “Contractor") has
executed an agreement (hereinafter called the “Agreement”) with the [name
and address of the authority], (hereinafter called the “Authority”) for the
construction of the ***** section of [National Highway No. **] on
Engineering, Procurement and Construction (the “EPC”) basis, subject to
and in accordance with the provisions of the Agreement
(B) In accordance with Clause 19.2 of the Agreement, the Authority shall make
to the Contractor an interest bearing (@ Bank Rate) advance payment (herein
after called “Advance Payment”) equal to 10% (ten per cent) of the
Contract Price; and that the Advance Payment shall be made in two
installments subject to the Contractor furnishing an irrevocable and
unconditional guarantee by a scheduled bank for an amount equivalent to
110% (one hundred and ten percent) of such installment to remain effective
till the complete and full repayment of the installment of the Advance
Payment as security for compliance with its obligations in accordance with
the Agreement. The amount of {first/second} installment of the Advance
Payment is Rs. ------ cr. (Rupees ------ crore) and the amount of this
Guarantee is Rs. ------- cr. (Rupees ------ crore) (the “Guarantee
Amount”)$.
1. The Bank hereby unconditionally and irrevocably guarantees the due and
faithful repayment on time of the aforesaid instalment of the Advance
Payment under and in accordance with the Agreement, and agrees and
undertakes to pay to the Authority, upon its mere first written demand, and
$
The Guarantee Amount should be equivalent to 110% of the value of the applicable instalment.
173
173
without any demur, reservation, recourse, contest or protest, and without any
reference to the Contractor, such sum or sums up to an aggregate sum of the
Guarantee Amount as the Authority shall claim, without the Authority being
required to prove or to show grounds or reasons for its demand and/or for the
sum specified therein.
2. A letter from the Authority, under the hand of an officer not below the rank
of [General Manager in the National Highways Authority of India], that the
Contractor has committed default in the due and faithful performance of all
or any of its obligations for the repayment of the instalment of the Advance
Payment under and in accordance with the Agreement shall be conclusive,
final and binding on the Bank. The Bank further agrees that the Authority
shall be the sole judge as to whether the Contractor is in default in due and
faithful performance of its obligations during and under the Agreement and
its decision that the Contractor is in default shall be final and binding on the
Bank, notwithstanding any differences between the Authority and the
Contractor, or any dispute between them pending before any court, tribunal,
arbitrators or any other authority or body, or by the discharge of the
Contractor for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act
as if the Bank were the principal debtor and any change in the constitution of
the Contractor and/or the Bank, whether by their absorption with any other
body or corporation or otherwise, shall not in any way or manner affect the
liability or obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the
liability of the Bank under this Guarantee, to vary at any time, the terms and
conditions of the Advance Payment or to extend the time or period of its
repayment or to postpone for any time, and from time to time, any of the
rights and powers exercisable by the Authority against the Contractor, and
either to enforce or forbear from enforcing any of the terms and conditions
contained in the Agreement and/or the securities available to the Authority,
and the Bank shall not be released from its liability and obligation under
these presents by any exercise by the Authority of the liberty with reference
to the matters aforesaid or by reason of time being given to the Contractor or
any other forbearance, indulgence, act or omission on the part of the
Authority or of any other matter or thing whatsoever which under any law
relating to sureties and guarantors would but for this provision have the
effect of releasing the Bank from its liability and obligation under this
Guarantee and the Bank hereby waives all of its rights under any such law.
9. The Bank undertakes not to revoke this Guarantee during its currency, except
with the previous express consent of the Authority in writing, and declares
and warrants that it has the power to issue this Guarantee and the
undersigned has full powers to do so on behalf of the Bank.
10. Any notice by way of request, demand or otherwise hereunder may be sent
by post addressed to the Bank at its above referred branch, which shall be
deemed to have been duly authorised to receive such notice and to effect
payment thereof forthwith, and if sent by post it shall be deemed to have
been given at the time when it ought to have been delivered in due course of
post and in proving such notice, when given by post, it shall be sufficient to
prove that the envelope containing the notice was posted and a certificate
signed by an officer of the Authority that the envelope was so posted shall be
conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain
in force and effect up to the date specified in paragraph 8 above or until it is
released earlier by the Authority pursuant to the provisions of the
Agreement.
(Signature)
(Name)
(Designation)
$
Insert a date being 90 (ninety) days after the end of one year from the date of payment of the
Advance payment to the Contractor (in accordance with Clause 19.2 of the Agreement).
175
175
(Code Number)
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number
of the officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the
Bank as well as of issuing branch should be mentioned on the covering letter
of issuing branch.
176
176
SCHEDULE-H
(See Clauses 10.1.4 and 19.3)
190
190
PERCENTAGE
WEIGHTAGE IN
WEIGHTAGE
PERCENTAGE TO
ITEM STAGE OF PAYMENT vis a vis
THE CONTRACT
OVERALL
PRICE
PROJECT
(3)Super-
structure(including crash
1.08
barrier etc. complete in
all respect)
(4) Protection work 6.30
B- Widening and
repair of
(a) ROB Nil
(b) RUB Nil
*The above list is illustrative and may require modification as per the scope of the
work
1.3.1 Road works including approaches to minor bridges, Major Bridges and
Structures (excluding service road).
Procedure for estimating the value of road work done shall be as follows:
Table 1.3.1
Percentage
Stage of Payment Payment Procedure
-Weightage
191
191
Percentage
Stage of Payment Payment Procedure
-Weightage
(5) Widening and repair of minor 3.18 Cost of each minor bridge shall
bridges be determined on pro rata basis
with respect to the total linear
length of the minor bridges.
Payment shall be made on the
completion of a minor bridge.
192
192
Percentage
Stage of Payment Payment Procedure
-Weightage
Total no.
Stage for Payment : (i) 1 to 5-
on completion of all, (ii) 6 or
more – on completion of five.
(4) Pedestrian Overpasses Nil Same as for (3) above
(5) Grade Separated structure Nil
(a) Underpasses Nil Same as for (3 ) above
(b) overpasses Nil Same as for (3 ) above
@ For Example, if total length of the bituminous work to be done is 100km, the cost per km of
bituminous work shall be determined as follows:
Cost per km = P x weightage for road work x weightage for bituminous work x (1/L)
Where P= Contract Price
L = Total length in km
Similarly, the rates per km for stages (1), (2) and (4) above shall be worked out.
Table 1.3.2
Percentage
Stage of Payment Payment Procedure
-Weight age
193
193
Percentage
Stage of Payment Payment Procedure
-Weight age
1.3.3 Structure
Procedure for estimating the value of Structure work shall be as stated in the
194
194
table 1.3.3:
Table 1.3.3
Percentage-
Stage of Payment Payment Procedure
Weight age
Procedure for estimating the value of other works done shall be as stated in
the table 1.3.4:
Table 1.3.4
Percentage
Stage of Payment -Weight Payment Procedure
age
(iii) Road side drain 7.01 Unit of measurement is linear length in km.
Payment shall be made on pro rata basis
(iv ) Road sign, on completion of a stage in a length of not
marking, km stone 6.21 less than 10% ( ten percent) of the total
& safety devices etc. length.
2.2 payment for Maintenance shall be made in quarterly installments in accordance with the
provisions of Clause 19.7.
196
196
SCHEDULE - I
(See Clause 10.2.4)
DRAWINGS
1 Drawings
2 Additional Drawings
If the Authority‟s Engineer determines that for discharging its duties and
functions under this Agreement, it requires any drawings other than those
listed in Annex-I, it may by notice require the Contractor to prepare and
furnish such drawings forthwith. Upon receiving a requisition to this effect,
the Contractor shall promptly prepare and furnish such drawings to the
Authority‟s Engineer, as if such drawings formed part of Annex-I of this
Schedule-I.
197
197
Annex - I
(Schedule - I)
List of Drawings
[Note: The Authority shall describe in this Annex-I, all the Drawings that the
Contractor is required to furnish under Clause 10.2.]
198
198
SCHEDULE - J
(See Clause 10.3.2)
2 Project Milestone-I
2.1 Project Milestone-I shall occur on the date falling on the 180th (one hundred
and eightieth) day from the Appointed Date (the “Project Milestone-I”).
2.2 Prior to the occurrence of Project Milestone-I, the Contractor shall have
commenced construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an
amount not less than 10% (ten per cent) of the Contract Price.
3 Project Milestone-II
3.1 Project Milestone-II shall occur on the date falling on the 365th (three
hundred and sixty fifth) day from the Appointed Date (the “Project
Milestone-II”).
3.2 Prior to the occurrence of Project Milestone-II, the Contractor shall have
continued with construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an
amount not less than 30% (thirty per cent) of the Contract Price.
4 Project Milestone-III
4.1 Project Milestone-III shall occur on the date falling on the [550th (five
hundred and fiftieth)] day from the Appointed Date (the “Project Milestone-
III”).
4.2 Prior to the occurrence of Project Milestone-III, the Contractor shall have
continued with construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an
amount not less than 60% (sixty per cent) of the Contract Price.
5.1 The Scheduled Completion Date shall occur on the [650th (six hundred and
199
199
fiftieth)] day from the Appointed Date.
5.2 On or before the Scheduled Completion Date, the Contractor shall have
completed construction in accordance with this Agreement.
6 Extension of time
200
200
SCHEDULE - K
Tests on Completion
1.1 The Contractor shall, no later than 30 (thirty) days prior to the likely
completion of construction, notify the Authority‟s Engineer and the
Authority of its intent to subject the Project Highway to Tests, and no later
than 10 (ten) days prior to the actual date of Tests, furnish to the Authority‟s
Engineer and the Authority detailed inventory and particulars of all works
and equipment forming part of Works.
1.2 The Contractor shall notify the Authority‟s Engineer of its readiness to
subject the Project Highway to Tests at any time after 10 (ten) days from the
date of such notice, and upon receipt of such notice, the Authority‟s Engineer
shall, in consultation with the Contractor, determine the date and time for
each Test and notify the same to the Authority who may designate its
representative to witness the Tests. The Authority‟s Engineer shall thereupon
conduct the Tests itself or cause any of the Tests to be conducted in
accordance with Article 12 and this Schedule-K.
2 Tests
2.1 Visual and physical test: The Authority‟s Engineer shall conduct a visual and
physical check of construction to determine that all works and equipment
forming part thereof conform to the provisions of this Agreement. The
physical tests shall include [***].
2.2 Riding quality test: Riding quality of each lane of the carriageway shall be
checked with the help of a calibrated bump integrator and the maximum
permissible roughness for purposes of this Test shall be [2,000 (two
thousand)] mm for each kilometre.
2.3 Tests for bridges: All major and minor bridges shall be subjected to the
rebound hammer and ultrasonic pulse velocity tests, to be conducted in
accordance with the procedure described in Special Report No. 17: 1996 of
the IRC Highway Research Board on Nondestructive Testing Techniques, at
two spots in every span, to be chosen at random by the Authority‟s Engineer.
Bridges with a span of 15 (fifteen) metres or more shall also be subjected to
load testing.
2.4 Other tests: The Authority‟s Engineer may require the Contractor to carry out
or cause to be carried additional tests, in accordance with Good Industry
Practice, for determining the compliance of the Project Highway with
Specifications and Standards.
201
201
2.5 Environmental audit: The Authority‟s Engineer shall carry out a check to
determine conformity of the Project Highway with the environmental
requirements set forth in Applicable Laws and Applicable Permits.
2.6 Safety Audit: The Authority‟s Engineer shall carry out, or cause to be carried
out, a safety audit to determine conformity of the Project Highway with the
safety requirements and Good Industry Practice.
All Tests set forth in this Schedule-K shall be conducted by the Authority‟s
Engineer or such other agency or person as it may specify in consultation
with the Authority.
4 Completion Certificate
202
202
SCHEDULE - L
(See Clause 12.2 and 12.4)
PROVISIONAL CERTIFICATE
2 Works that are incomplete on account of Time Extension have been specified
in the Punch List appended hereto, and the Contractor has agreed and accepted
that it shall complete all such works in the time and manner set forth in the
Agreement. In addition, certain minor works are incomplete and these are not
likely to cause material inconvenience to the Users of the Project Highway or
affect their safety. The Contractor has agreed and accepted that as a condition
of this Provisional Certificate, it shall complete such minor works within 30
(thirty) days hereof. These minor works have also been specified in the
aforesaid Punch List.
(Signature) (Signature)
203
203
COMPLETION CERTIFICATE
1 I, ……………………. (Name of the Authority‟s Engineer), acting as the
Authority‟s Engineer, under and in accordance with the Agreement dated
………… (the “Agreement”), for [construction of the ****section (km ** to
km **) of National Highway No. ***] (the “Project Highway”) on
Engineering, Procurement and Construction (EPC) basis through
…………………. (Name of Contractor), hereby certify that the Tests in
accordance with Article 12 of the Agreement have been successfully
undertaken to determine compliance of the Project Highway with the
provisions of the Agreement, and I am satisfied that the Project Highway can
be safely and reliably placed in service of the Users thereof.
(Signature)
(Name)
(Designation)
(Address)
204
204
SCHEDULE - M
(See Clauses 14.6, 15.2 and 19.7)
1.1 Monthly lump sum payments for maintenance shall be reduced in the case of
non-compliance with the Maintenance Requirements set forth in Schedule-E.
1.3 The Authority‟s Engineer shall calculate the amount of payment reduction on
the basis of weightage in percentage assigned to non-conforming items as
given in Paragraph 2.
205
205
S. No. Item/Defect/Deficiency Percentage
(ii) Any Defects in superstructures, 10%
bearings and sub-structures
(iii) Painting, repairs/replacement 5%
kerbs, railings, parapets,
guideposts/crash barriers
(d) Roadside Drains
(i) Cleaning and repair of drains 5%
(e) Road Furniture
(i) Cleaning, painting, replacement of 5%
road signs, delineators, road
markings, 200 m/km/5th km stones
(f) Miscellaneous Items
(i) Removal of dead animals, broken 10%
down/accidented vehicles, fallen
trees, road blockades or
malfunctioning of mobile crane
(ii) Any other Defects in accordance 5%
with paragraph 1.
(g) Defects in Other Project 5%
Facilities
2.2 The amount to be deducted from monthly lump-sum payment for non
compliance of particular item shall be calculated as under:
R=P/IOO x M x L1/L
L1 = Non-complying length
For any Defect in a part of one kilometer, the non-conforming length shall be
taken as one kilometer.
206
206
SCHEDULE - N
(See Clause 18.1.1)
1.1 The provisions of the Model Request for Proposal for Selection of Technical
Consultants, issued by the Ministry of Finance in May 2009, or any
substitute thereof shall apply for selection of an experienced firm to
discharge the functions and duties of an Authority‟s Engineer.
2 Terms of Reference
The Terms of Reference for the Authority‟s Engineer (the “TOR”) shall
substantially conform with Annex 1 to this Schedule N.
200
200
Annex – I
(Schedule - N)
1 Scope
1.1 These Terms of Reference (the “TOR”) for the Authority‟s Engineer are
being specified pursuant to the EPC Agreement dated ........... (the
“Agreement), which has been entered into between the [name and address of
the Authority] (the “Authority”) and .......... (the “Contractor”) for [Two-
Laning] of the **** section (km ** to km **) of National Highway No. ** in
the State of *** on Engineering, Procurement, Construction (EPC) basis, and
a copy of which is annexed hereto and marked as Annex-A to form part of
this TOR.
1.2 The TOR shall apply to construction and maintenance of the Project
Highway.
2.1 The words and expressions beginning with or in capital letters and not
defined herein but defined in the Agreement shall have, unless repugnant to
the context, the meaning respectively assigned to them in the Agreement.
2.2 References to Articles, Clauses and Schedules in this TOR shall, except
where the context otherwise requires, be deemed to be references to the
Articles, Clauses and Schedules of the Agreement, and references to
Paragraphs shall be deemed to be references to Paragraphs of this TOR.
2.3 The rules of interpretation stated in Clauses 1.2, 1.3 and 1.4 of the
Agreement shall apply, mutatis mutandis, to this TOR.
3. General
3.1 The Authority‟s Engineer shall discharge its duties in a fair, impartial and
efficient manner, consistent with the highest standards of professional
integrity and Good Industry Practice.
3.2 The Authority‟s Engineer shall perform the duties and exercise the authority
in accordance with the provisions of this Agreement, but subject to obtaining
prior written approval of the Authority before determining:
201
201
(b) any additional cost to be paid by the Authority to the Contractor;
(d) any other matter which is not specified in (a), (b) or (c) above and which
creates an obligation or liability on either Party for a sum exceeding Rs.
5,000,000 (Rs. fifty lakh).
3.3 The Authority‟s Engineer shall submit regular periodic reports, at least once
every month, to the Authority in respect of its duties and functions under this
Agreement. Such reports shall be submitted by the Authority‟s Engineer
within 10 (ten) days of the beginning of every month.
3.4 The Authority‟s Engineer shall inform the Contractor of any delegation of its
duties and responsibilities to its suitably qualified and experienced personnel;
provided, however, that it shall not delegate the authority to refer any matter
for the Authority‟s prior approval in accordance with the provisions of
Clause 18.2.
3.5 The Authority‟s Engineer shall aid and advise the Authority on any proposal
for Change of Scope under Article 13.
3.6 In the event of any disagreement between the Parties regarding the meaning,
scope and nature of Good Industry Practice, as set forth in any provision of
the Agreement, the Authority‟s Engineer shall specify such meaning, scope
and nature by issuing a reasoned written statement relying on good industry
practice and authentic literature.
4 Construction Period
4.1 During the Construction Period, the Authority‟s Engineer shall review the
Drawings furnished by the Contractor along with supporting data, including
the geo-technical and hydrological investigations, characteristics of materials
from borrow areas and quarry sites, topographical surveys, and the
recommendations of the Safety Consultant in accordance with the provisions
of Clause 10.1.6. The Authority‟s Engineer shall complete such review and
send its observations to the Authority and the Contractor within 15 (fifteen)
days of receipt of such Drawings; provided, however that in case of a Major
Bridge or Structure, the aforesaid period of 15 (fifteen) days may be
extended upto 30 (thirty) days. In particular, such comments shall specify the
conformity or otherwise of such Drawings with the Scope of the Project and
Specifications and Standards.
4.2 The Authority‟s Engineer shall review any revised Drawings sent to it by the
Contractor and furnish its comments within 10 (ten) days of receiving such
Drawings.
202
202
4.3 The Authority‟s Engineer shall review the Quality Assurance Plan submitted
by the Contractor and shall convey its comments to the Contractor within a
period of 21 (twenty-one) days stating the modifications, if any, required
thereto.
4.4 The Authority‟s Engineer shall complete the review of the methodology
proposed to be adopted by the Contractor for executing the Works, and
convey its comments to the Contractor within a period of 10 (ten) days from
the date of receipt of the proposed methodology from the Contractor.
4.5 The Authority‟s Engineer shall grant written approval to the Contractor,
where necessary, for interruption and diversion of the flow of traffic in the
existing lane(s) of the Project Highway for purposes of maintenance during
the Construction Period in accordance with the provisions of Clause 10.4.
4.6 The Authority‟s Engineer shall review the monthly progress report furnished
by the Contractor and send its comments thereon to the Authority and the
Contractor within 7 (seven) days of receipt of such report.
4.7 The Authority‟s Engineer shall inspect the Construction Works and the
Project Highway and shall submit a monthly Inspection Report bringing out
the results of inspections and the remedial action taken by the Contractor in
respect of Defects or deficiencies. In particular, the Authority‟s Engineer
shall include in its Inspection Report, the compliance of the
recommendations made by the Safety Consultant.
4.9 For determining that the Works conform to Specifications and Standards, the
Authority‟s Engineer shall require the Contractor to carry out, or cause to be
carried out, tests at such time and frequency and in such manner as specified
in the Agreement and in accordance with Good Industry Practice for quality
assurance. For purposes of this Paragraph 4.9, the tests specified in the IRC
Special Publication-11 (Handbook of Quality Control for Construction of
Roads and Runways) and the Specifications for Road and Bridge Works
issued by MORTH (the “Quality Control Manuals”) or any
modification/substitution thereof shall be deemed to be tests conforming to
Good Industry Practice for quality assurance.
4.10 The Authority‟s Engineer shall test check at least 20 (twenty) percent of the
quantity or number of tests prescribed for each category or type of test for
quality control by the Contractor.
4.11 The timing of tests referred to in Paragraph 4.9, and the criteria for
203
203
acceptance/ rejection of their results shall be determined by the Authority‟s
Engineer in accordance with the Quality Control Manuals. The tests shall be
undertaken on a random sample basis and shall be in addition to, and
independent of, the tests that may be carried out by the Contractor for its own
quality assurance in accordance with Good Industry Practice.
4.12 In the event that results of any tests conducted under Clause 11.10 establish
any Defects or deficiencies in the Works, the Authority‟s Engineer shall
require the Contractor to carry out remedial measures.
4.13 The Authority‟s Engineer may instruct the Contractor to execute any work
which is urgently required for the safety of the Project Highway, whether
because of an accident, unforeseeable event or otherwise; provided that in
case of any work required on account of a Force Majeure Event, the
provisions of Clause 21.6 shall apply.
4.14 In the event that the Contractor fails to achieve any of the Project Milestones,
the Authority‟s Engineer shall undertake a review of the progress of
construction and identify potential delays, if any. If the Authority‟s Engineer
shall determine that completion of the Project Highway is not feasible within
the time specified in the Agreement, it shall require the Contractor to indicate
within 15 (fifteen) days the steps proposed to be taken to expedite progress,
and the period within which the Project Completion Date shall be achieved.
Upon receipt of a report from the Contractor, the Authority‟s Engineer shall
review the same and send its comments to the Authority and the Contractor
forthwith.
4.15 The Authority‟s Engineer shall obtain from the Contractor a copy of all the
Contractor‟s quality control records and documents before the Completion
Certificate is issued pursuant to Clause 12.4.
4.17 In the event that the Contractor carries out any remedial measures to secure
the safety of suspended works and Users, and requires the Authority‟s
Engineer to inspect such works, the Authority‟s Engineer shall inspect the
suspended works within 3 (three) days of receiving such notice, and make a
report to the Authority forthwith, recommending whether or not such
suspension may be revoked by the Authority.
4.18 The Authority‟s Engineer shall carry out, or cause to be carried out, all the
204
204
Tests specified in Schedule-K and issue a Completion Certificate or
Provisional Certificate, as the case may be. For carrying out its functions
under this Paragraph 4.18 and all matters incidental thereto, the Authority‟s
Engineer shall act under and in accordance with the provisions of Article 12
and Schedule-K.
5. Maintenance Period
5.1 The Authority‟s Engineer shall aid and advise the Contractor in the
preparation of its monthly Maintenance Programme and for this purpose
carry out a joint monthly inspection with the Contractor.
5.2 The Authority‟s Engineer shall undertake regular inspections, at least once
every month, to evaluate compliance with the Maintenance Requirements
and submit a Maintenance Inspection Report to the Authority and the
Contractor.
5.3 The Authority‟s Engineer shall specify the tests, if any, that the Contractor
shall carry out, or cause to be carried out, for the purpose of determining that
the Project Highway is in conformity with the Maintenance Requirements. It
shall monitor and review the results of such tests and the remedial measures,
if any, taken by the Contractor in this behalf.
5.5 The Authority‟s Engineer shall examine the request of the Contractor for
closure of any lane(s) of the Project Highway for undertaking
maintenance/repair thereof, and shall grant permission with such
modifications, as it may deem necessary, within 5 (five) days of receiving a
request from the Contractor. Upon expiry of the permitted period of closure,
the Authority‟s Engineer shall monitor the reopening of such lane(s), and in
case of delay, determine the Damages payable by the Contractor to the
Authority under Clause 14.5.
6.1 The Authority‟s Engineer shall determine the costs, and/or their
reasonableness, that are required to be determined by it under the Agreement.
6.2 The Authority‟s Engineer shall determine the period of Time Extension that
is required to be determined by it under the Agreement.
205
205
6.3 The Authority‟s Engineer shall consult each Party in every case of
determination in accordance with the provisions of Clause 18.5.
7. Payments
7.1 The Authority‟s Engineer shall withhold payments for the affected works for
which the Contractor fails to revise and resubmit the Drawings to the
Authority‟s Engineer in accordance with the provisions of Clause 10.2.4 (d).
(a) within 10 (ten) days of receipt of the Stage Payment Statement from the
Contractor pursuant to Clause 19.4, determine the amount due to the
Contractor and recommend the release of 90 (ninety) percent of the amount
so determined as part payment, pending issue of the Interim Payment
Certificate; and
(b) within 15 (fifteen) days of the receipt of the Stage Payment Statement
referred to in Clause 19.4, deliver to the Authority and the Contractor an
Interim Payment Certificate certifying the amount due and payable to the
Contractor, after adjustments in accordance with the provisions of Clause
19.10.
7.3 The Authority‟s Engineer shall, within 15 (fifteen) days of receipt of the
Monthly Maintenance Statement from the Contractor pursuant to Clause
19.6, verify the Contractor‟s monthly statement and certify the amount to be
paid to the Contractor in accordance with the provisions of the Agreement.
7.4 The Authority‟s Engineer shall certify final payment within 30 (thirty) days
of the receipt of the final payment statement of Maintenance in accordance
with the provisions of Clause 19.16.
The Authority‟s Engineer shall perform all other duties and functions as
specified in the Agreement.
9 Miscellaneous
9.2 The Authority‟s Engineer shall retain at least one copy each of all Drawings
206
206
and Documents received by it, including „as-built‟ Drawings, and keep them
in its safe custody.
9.3 Within 90 (ninety) days of the Project Completion Date, the Authority‟s
Engineer shall obtain a complete set of as-built Drawings, in 2 (two) hard
copies and in micro film form or in such other medium as may be acceptable
to the Authority, reflecting the Project Highway as actually designed,
engineered and constructed, including an as-built survey illustrating the
layout of the Project Highway and setback lines, if any, of the buildings and
structures forming part of Project Facilities; and shall hand them over to the
Authority against receipt thereof.
9.4 The Authority‟s Engineer, if called upon by the Authority or the Contractor
or both, shall mediate and assist the Parties in arriving at an amicable
settlement of any Dispute between the Parties.
9.5 The Authority‟s Engineer shall inform the Authority and the Contractor of
any event of Contractor‟s Default within one week of its occurrence.
207
207
SCHEDULE - O
(a) the estimated amount for the Works executed in accordance with
Clause 19.3.1 subsequent to the last claim;
(b) amounts reflecting adjustments in price for the aforesaid claim;
(c) the estimated amount of each Change of Scope Order executed
subsequent to the last claim;
(d) amounts reflecting adjustment in price, if any, for (c) above in
accordance with the provisions of Clause 13.2.3 (a);
(e) total of (a), (b), (c) and (d) above;
(f) Deductions:
(i) Any amount to be deducted in accordance with the provisions
of the Agreement except taxes;
(ii) Any amount towards deduction of taxes; and
(iii) Total of (i) and (ii) above.
(g) Net claim: (e) – (f) (iii);
(h) The amounts received by the Contractor upto the last claim:
(i) For the Works executed (excluding Change of Scope orders);
(ii) For Change of Scope Orders, and
(iii) Taxes deducted
208
208
3. Contractor’s claim for Damages
Note: The Contractor shall submit its claims in a form acceptable to the Authority.
209
209
SCHEDULE - P
(See Clause 20.1)
INSURANCE
1.1 The Contractor shall effect and maintain at its own cost, from the Appointed
Date till the date of issue of the Completion Certificate, the following
insurances for any loss or damage occurring on account of Non Political
Event of Force Majeure, malicious act, accidental damage, explosion, fire
and terrorism:
(a) insurance of Works, Plant and Materials and an additional sum of [15
(fifteen)] per cent of such replacement cost to cover any additional
costs of and incidental to the rectification of loss or damage including
professional fees and the cost of demolishing and removing any part
of the Works and of removing debris of whatsoever nature; and
(b) insurance for the Contractor's equipment and Documents brought
onto the Site by the Contractor, for a sum sufficient to provide for
their replacement at the Site.
1.2 The insurance under paragraph 1.1 (a) and (b) above shall cover the
Authority and the Contractor against all loss or damage from any cause
arising under paragraph 1.1 other than risks which are not insurable at
commercial terms.
The Contractor shall effect and maintain insurance cover for the Works from
the date of issue of the Completion Certificate until the end of the Defects
Liability Period for any loss or damage for which the Contractor is liable and
which arises from a cause occurring prior to the issue of the Completion
Certificate. The Contractor shall also maintain other insurances for
maximum sums as may be required under the Applicable Laws and in
accordance with Good Industry Practice.
3.1 The Contractor shall insure against its liability for any loss, damage, death or
bodily injury, or damage to any property (except things insured under
Paragraphs 1 and 2 of this Schedule or to any person (except persons insured
under Clause 20.9), which may arise out of the Contractor's performance of
this Agreement. This insurance shall be for a limit per occurrence of not less
than the amount stated below with no limit on the number of occurrences.
The insurance cover shall be not less than: Rs. [*****]
210
210
3.2 The insurance shall be extended to cover liability for all loss and damage to
the Authority's property arising out of the Contractor‟s performance of this
Agreement excluding:
(a) the Authority's right to have the construction works executed on,
over, under, in or through any land, and to occupy this land for the
Works; and
211
211
End of the Document
212
25-Dec-15 1:31:00 PM
25-Dec-15 1:32:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
26-Dec-15 5:33:00 PM
ultiple 1.15 li, Tab stops: 0.5", Left
26-Dec-15 5:34:00 PM
96", Relative to: Page, Vertical: 0.16",
17-Nov-15 12:55:00 PM
ertical: 0.08", Relative to: Paragraph,
25-Dec-15 1:31:00 PM
o: Paragraph, Horizontal: 0.13", Wrap
25-Dec-15 1:31:00 PM
ertical: 0.08", Relative to: Paragraph,
25-Dec-15 1:31:00 PM
o: Paragraph, Horizontal: 0.13", Wrap
25-Dec-15 1:31:00 PM
ertical: 0.08", Relative to: Paragraph,
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
mbering, Position: Horizontal: Left,
", Wrap Around
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
17-Nov-15 12:55:00 PM
25-Dec-15 1:31:00 PM
25-Dec-15 1:33:00 PM
25-Dec-15 1:33:00 PM