Feasibility For All Zila Road - V3!03!10-2023
Feasibility For All Zila Road - V3!03!10-2023
October, 2023
Bangladesh had one of the world's fastest-growing economies during the preceding
decade. Infrastructure development in several areas, including transportation, is being
carried out throughout the country to attain economic prosperity and the title of a developed
country. Traffic congestion is, nevertheless, quite typical in Bangladeshi cities and has
become a routine occurrence. After the grand opening of Padma Bridge, the dream project
of this nation, communication between the south-west region and the capital city Dhaka
has grown significantly, and interactions have increased at their peak. Khulna, Bagerhat,
and Satkhira are the main administrative headquarters to face the direct impact of the
Padma Bridge on this region.
The proposed road, 17 zilla roads, is not adequate in width to call a highway and
accommodate the upcoming demand of this region to connect with the capital city Dhaka.
The AADT data indicates significant motorized traffic, particularly auto rickshaws, and
motorcycles, dominating the roadways in most areas. Heavy and medium trucks also
contribute to the traffic load, while non-motorized transport is comparatively lower. Notably,
zones like Z-7043, Z-7603, Z-7704, and several others exhibit remarkably intense traffic
loads, signalling imminent congestion issues and potential gridlocks. As this busy road is
very narrow, two vehicles running side by side face difficulty overtaking. Driving on the
existing road can cause the vehicle to overturn at any time by breaking the edge of the
bituminous road. Also, the road has dangerous bends, leading to fatal accidents. However,
it is a matter of sorrow that, since the construction of the National Highway today, no
important activities have been undertaken to develop the highway. The influence of the
mentioned highway in the expansion of trade and commerce is immense. However, the
road's narrowness cannot fulfil the expected role in meeting the increased demand as a
national highway. Improvement of these 17 zilla roads (120 Km) will cost approximately
24025.312 million BDT, including surfacing, land acquisition, engineering works, protective
work, tree uprooting, and plantation.
The feasibility has been carried out to assess the project's economic and financial viability.
After a rigorous assessment, it is found that the project is not financially viable as it is a
service-sector project. However, from the economic point of view, the project is extremely
viable as the economic NPV = Tk. 20,396.63 Lac, IRR = 29% and BCR = 1.20. As a result,
financial profit/benefit will not be available from the project, i.e., financial net present value
(NPV) becomes negative, the financial benefit distress ratio (BCR), and financial internal
rate of return (IRR) are zero. However, considering the Vehicle Operating Cost and Travel
Time Cost Savings, users' economic profit/benefit will be achieved. Based on this
economic analysis, the project is feasible.
In light of the factors above, it is imperative to widen the proposed 17 zilla roads of Khulna-
Bagerhat-Satkhira to a width of 18 to 34 feet in order to boost economic activity in the
south-west region, promote business, safe traffic, prevent accidents, and lessen human
suffering.
To
Executive Engineer
Roads and Highways Department,
Bagerhat, Satkhira, Khulna
Dear Sir,
The final report on "Improvement of Important District Highways to Appropriate Level of
Standard and Width (Khulna Circle)" is prepared and submitted for your reference.
Please accept our submission and oblige thereby.
Sincerely,
TABLE OF CONTENTS
SECTION 1: BASIC INFORMATION ----------------------------------------------------------------------------- 1
5.1 ENVIRONMENTAL, CLIMATE CHANGE, AND DISASTER RISK ANALYSIS -------------------------------- 125
5.1.1 EIA -------------------------------------------------------------------------------------------------------- 125
5.1.2 Scopes of EIA ------------------------------------------------------------------------------------------ 125
5.1.3 Methodology -------------------------------------------------------------------------------------------- 126
5.1.4 Limitations of the Study ------------------------------------------------------------------------------ 126
5.2 ASSESSMENT OF DISASTER RESILIENCE OF THE PROJECT -------------------------------------------- 127
5.2.1 Physio-Chemical Environment --------------------------------------------------------------------- 127
5.2.1.1 Geology and Seismicity ------------------------------------------------------------------------ 127
5.2.1.2 Geology -------------------------------------------------------------------------------------------- 127
5.2.1.3 Soil Characteristics ------------------------------------------------------------------------------ 128
5.2.1.4 Seismicity ------------------------------------------------------------------------------------------ 128
5.2.1.5 Climate --------------------------------------------------------------------------------------------- 130
5.2.1.6 Cyclone and Tidal Surge ----------------------------------------------------------------------- 130
5.2.1.7 Floods ---------------------------------------------------------------------------------------------- 131
5.2.1.8 Ground Water Quality -------------------------------------------------------------------------- 131
5.2.1.9 Surface Water Quality -------------------------------------------------------------------------- 132
5.2.1.9.1 Khulna ---------------------------------------------------------------------------------------- 132
5.2.1.9.2 Bagerhat ------------------------------------------------------------------------------------- 132
5.2.1.9.3 Satkhira --------------------------------------------------------------------------------------- 132
5.2.1.10 Ecological Environment----------------------------------------------------------------------- 133
5.2.1.10.1 Floral Diversity ---------------------------------------------------------------------------- 134
5.2.1.10.2 Tree ------------------------------------------------------------------------------------------ 134
5.2.1.10.3 Herb ----------------------------------------------------------------------------------------- 135
5.2.1.10.4 Reptiles ------------------------------------------------------------------------------------- 135
5.2.1.10.5 Mammals ----------------------------------------------------------------------------------- 135
5.2.2 Checklist of Environmental Components -------------------------------------------------------- 136
5.2.3 Environmental Impacts Evaluation ---------------------------------------------------------------- 137
5.2.3.1 Environmental Impact Evaluation Methodology ------------------------------------------ 137
9.1 SIGNIFICANT RISKS THAT MAY AFFECT THE PROJECT: ------------------------------------------------- 224
9.2 CATEGORIZED THE RISK EVENT ---------------------------------------------------------------------------- 224
9.3 POSSIBLE MITIGATION MEASURES NEEDED: ------------------------------------------------------------- 225
List of Tables
Table 1-1: Basic Information ........................................................................................... 1
Table 3-1: Ponds Need to be Filled for Road Extension (Z-7045).................................. 76
Table 3-2: Ponds Need to be Filled for Road Extension (Z-7716).................................. 77
Table 3-3: Ponds Need to be Filled for Road Extension (Z-7714).................................. 77
Table 3-4: Ponds Need to be Filled for Road Extension (Z-7045).................................. 78
Table 3-5: Ponds Need to be Filled for Road Extension (Z-7801).................................. 79
Table 3-6: Ponds Need to be Filled for Road Extension (Z-7704).................................. 80
Table 3-7: Ponds Need to be Filled for Road Extension (Z-7610).................................. 81
Table 3-8: Ponds Need to be Filled for Road Extension (Z-7552).................................. 81
Table 3-9: Ponds Need to be Filled for Road Extension (Z-7552).................................. 81
Table 3-10: Areas That are Not Expected to Have a Major Impact ................................ 83
Table 3-11: Stakeholders and Their Roles .................................................................... 86
Table 4-1: Lane Configuration ....................................................................................... 92
Table 4-2: Surfacing Type ............................................................................................. 92
Table 4-3: Pavement Condition Criteria......................................................................... 94
Table 4-4: Pavement Condition Survey ......................................................................... 94
Table 4-5: Shoulder Inventory Survey ........................................................................... 95
Table 4-6: Design Standard .......................................................................................... 96
Table 4-7: Geometric Design Criteria ............................................................................ 96
Table 4-8: Minimum Curve Radius (meters) .................................................................. 97
Table 4-9: Minimum Design Transition Length (m) ........................................................ 97
Table 4-10: Extra Carriageway Widths on Curves (m) ................................................... 97
Table 4-11: Minimum Vertical Curve "K values" ............................................................ 98
Table 4-12: Minimum Super-elevation requirements (%) ............................................... 98
Table 4-13: Vehicle Equivalency Factors .................................................................... 100
Table 4-14: AADT Calculation for Z-7040 (Obtain from RHD) ..................................... 104
Table 4-15: Traffic Survey for Z-7040 (Conducted by Consultant) ............................... 104
Table 4-16: AADT Calculation for Z-7045 (Obtain from RHD) ..................................... 105
Table 4-17: Traffic Survey for Z-7045 (Conducted by Consultant) ............................... 105
Table 4-18: AADT Calculation for Z-7615-1(Dacope-Barobaria-Magurkhali), Z-7615-2
(Magurkhali-Tala Road) (Obtain from RHD) ................................................................. 106
Table 4-19: Traffic Survey for Z-7615-1(Dacope-Barobaria-Magurkhali), Z-7615-2
(Magurkhali-Tala Road) (Conducted by Consultant) .................................................... 107
Table 4-20: AADT Calculation for Z-7043 (Obtain from RHD) ..................................... 107
Table 4-21: Traffic Survey for Z-7043 (Conducted by Consultant) ............................... 108
List of Figures
Figure 2-1: Methodology of Feasibility Study ------------------------------------------------------- 5
Figure 2-2: Organogram of Geo Smart Planning -------------------------------------------------- 9
Figure 2-3: Flexible Pavement’s Cross-Section and Longitudinal Profile for Z-7040 ------ 9
Figure 2-4: Plan of Rigid pavement 2+600 to 3+000,3+800 to 4+100, 5+000 to 5+500,
16+300 to 16 +500, 26+700 to 25+900, 28+700 to 29+200------------------------------------ 11
Figure 2-5: Flexible Pavement Design of Z-7615 ------------------------------------------------ 12
Figure 2-6: Plan of Flexible Pavement for Z-7603 ----------------------------------------------- 13
Figure 2-7: Rigid Pavement Design for Z-7603 -------------------------------------------------- 15
Figure 2-8: Flexible Pavement Design for Z-7043 ----------------------------------------------- 17
Figure 2-9: Rigid Pavement Design for Z-7043 -------------------------------------------------- 19
Figure 2-10: Flexible Pavement Design for Z-7045 --------------------------------------------- 20
Figure 2-11: Rigid Pavement Design for Z-7045 ------------------------------------------------- 21
Figure 2-12: Flexible Pavement Design for Z-7701 --------------------------------------------- 22
Figure 2-13: Flexible Pavement Design for Z-7704 --------------------------------------------- 24
Figure 2-14: Flexible Pavement Design for Z-7714 --------------------------------------------- 25
Figure 2-15: Rigid Pavement Design for Z-7714 ------------------------------------------------- 27
Figure 2-16: Flexible Pavement Design for Z-7716 --------------------------------------------- 28
Figure 2-17: Flexible Pavement Design for Z-7801 --------------------------------------------- 29
Figure 2-18: Rigid Pavement Design for Z-7801 ------------------------------------------------- 30
Figure 2-19: Flexible Pavement Design for Z-8409 --------------------------------------------- 31
Figure 2-20: Rigid Pavement Design for Z-8409 ------------------------------------------------- 32
Figure 2-21: Flexible Pavement Design for Z-7552 --------------------------------------------- 33
Figure 2-22: Rigid Pavement Design for Z-7552 ------------------------------------------------- 36
Figure 2-23: Flexible Pavement Design for Z-7613 --------------------------------------------- 37
Figure 2-24: Flexible Pavement Design for Z-7610 --------------------------------------------- 37
Figure 2-25: Rigid Pavement Design for Z-7613 ------------------------------------------------- 39
Figure 2-26: Rigid Pavement Design for Z-7618 ------------------------------------------------- 41
Figure 3-1: SWOT Analysis --------------------------------------------------------------------------- 88
Figure 4-1: Location of Khulna Circle Road ------------------------------------------------------- 89
Figure 4-2: SN Calculation Formula ---------------------------------------------------------------- 99
Figure 5-1: Proposed Project Site on Soil Track Map of Bangladesh ---------------------- 128
Figure 5-2: Proposed Project Site and Earthquake Zone of Bangladesh ----------------- 129
Figure 5-3: Locations of the Proposed Project Site on Bangladesh's Cyclone and Flood
Affected Risk Map --------------------------------------------------------------------------------------- 131
Figure 5-4: Word Scales for Various Scenarios ------------------------------------------------- 138
List of Pictures
Picture 3-1: Ferry Ghat Mor Intersection----------------------------------------------------------- 46
Picture 3-2: Barakpur Bazar Mor Intersection ---------------------------------------------------- 47
Picture 3-3: Gazir Hat Mor Intersection ------------------------------------------------------------ 48
Picture 3-4:Terokhada Mor Intersection ----------------------------------------------------------- 49
Picture 3-5: Katenga Bazar Mor Intersection ----------------------------------------------------- 50
Picture 3-6: Tetokhada Bus Stand Mor Intersection -------------------------------------------- 51
Picture 3-7: Chourangi Mor Intersection ---------------------------------------------------------- 52
Picture 3-8: Shahpur Bazar Mor Intersection ----------------------------------------------------- 53
Picture 3-9: Fultala Bus Stand Mor Intersection ------------------------------------------------- 54
Picture 3-10: Fokirhat Dagbangla Mor Intersection --------------------------------------------- 55
Picture 3-11: Madrasha Ghat Mor Intersection --------------------------------------------------- 56
Picture 3-12: Chowronggir Mor Intersection ------------------------------------------------------ 57
Picture 3-13: Fokirapul Mor Intersection ----------------------------------------------------------- 58
Picture 3-14: Bangla Bazar Mor Intersection ----------------------------------------------------- 59
Picture 3-15: Kuniya Bus Stand Mor Intersection------------------------------------------------ 60
Picture 3-16: Upazila Mor Intersection ------------------------------------------------------------- 61
Picture 3-17: Majhi Barir Mor Intersection --------------------------------------------------------- 62
Picture 3-18: Vasha Mor Intersection -------------------------------------------------------------- 63
Picture 3-19: Shialkathi Mor Intersection ---------------------------------------------------------- 64
Picture 3-20: Shyamnagor Char Rasta Mor Intersection -------------------------------------- 65
Picture 3-21: Hostel Mor ------------------------------------------------------------------------------- 66
Picture 3-22: Sankorkati Hatkhola Mor Intersection--------------------------------------------- 67
Picture 3-23: Gobindopur Bazar Mor Intersection ----------------------------------------------- 68
Picture 3-24: Kolaroa Mor Intersection ------------------------------------------------------------- 69
Picture 3-25: Kolagaci Mor Intersection ------------------------------------------------------------ 70
Picture 3-26: Saroskati Chourasta Mor Intersection -------------------------------------------- 71
Picture 3-27: Firoj Chairman Barir Mor Intersection --------------------------------------------- 72
Picture 3-28: Tala Mor Intersection ----------------------------------------------------------------- 73
Picture 3-29: Majhiara Bazar Intersection --------------------------------------------------------- 74
Picture 3-30: Paikgacha Road and Z-7613 Crossing Intersection --------------------------- 75
ABBREVIATIONS
Section 2: Introduction
The past decade has witnessed Bangladesh's economic growth soaring remarkably,
positioning the nation among the world's fastest-growing economies. As it fervently
pursues the coveted status of a developed nation, strategic investments have been
channelled into various sectors, particularly infrastructure development. Within this
landscape, transportation infrastructure has emerged as a linchpin for progress. The
inauguration of the Padma Bridge, a monumental project, has unfurled new dimensions of
connectivity between the bustling capital, Dhaka, and the vibrant south-west region.
This newfound connectivity has resonated profoundly within the administrative epicentres
of Khulna, Bagerhat, and Satkhira, which are steadfast guardians of this dynamic realm.
Khulna, the third-largest city in Bangladesh, occupies a dual role as both a district and
divisional headquarters. As a strategic nucleus, Khulna is indispensable by orchestrating
communication networks spanning myriad directions. In tandem, the strategic significance
of Bagerhat, often hailed as the "front door" to the south-west, is accentuated by the
presence of the Mongla sea-port. Consequently, Bagerhat's stature has surged,
underscoring the exigency for comprehensive enhancements in transportation
infrastructure that can seamlessly facilitate the movement of goods, resources, and human
capital. Echoing this narrative, Satkhira's prominence is articulated through its twin roles
as a significant shrimp producer and the site of the Vomra land port. These dual attributes
precipitate the pressing need for robust transportation links that bridge this vibrant region
with Dhaka's economic heart.
However, these transformative prospects are juxtaposed with various challenges intrinsic
to the prevailing road infrastructure, including the proposed 17 zilla roads in the Khulna-
Bagerhat-Satkhira region. Designed as connectivity conduits, these roads fail to meet the
The feasibility study on the Improvement and Widening of the Zila road mentioned in List
of Roads for Conducting Feasibility Study Table supports some major-specific fields,
including a traffic study, engineering survey including a topographic survey, geological and
geotechnical Investigations, social and environmental analysis with a preparation of a
socio-economic report, Resettlement Action Plan (RAP). The objective of this feasibility
study is:
The proposed extension road will significantly improve the current road network and
relieve the traffic burden and carrying capacity. The proposed route will connect the most
peripheral area with the core central CBD area with optimum traffic pressure within the
urban roadways. It will be essential in reducing traffic jams on urban roads and developing
a better network.
• The report is output mainly relies on the limited information and data provided by
RHD and other Government Offices.
• The economic viability of the project could have been enhanced considerably by
considering the following information:
• The corridor of the topographic survey measured 30.47m on average, 15.23m left,
and 15.23m right from the route centreline.
• A particular survey conducted for the Bridge, Chhara/Canal/Khal, and River Study
Area of selected road route alignment is presented in the following chapters.
Data Processing Software: Trimble Business Centre 2.4 used for post-processing
The following equipment was deployed for the Topo survey works:
Geo Smart Planning is an organization that has been involved successfully in projects,
consultancy, training, and all other sectors of development, engaging a group of young
professionals with diverse backgrounds. GSP always believes in the motive that
sustainable development comes not only from some specific sectors but also from the
multi-stages of the environment. This thinking is organized by a group of Urban and Rural/
Regional planners, Engineers, architects, Sociologists, economists, agriculturalists, and
Software developers who pioneer their sector. Geo Smart Planning thinks that only proper,
thoughtful planning and timely execution can run the development process smoothly.
However, it offers a full range of services from project conception to completion, including-
project preparatory technical assistance, project identification, techno-economic feasibility
study, field surveys/investigations, environmental and social impact assessment, planning,
detailed design, architectural design, documentation, project management, monitoring,
and evaluation, etc. It has expertise in project, review, baseline, end line, all kinds of
surveys using different tools and techniques (such as GIS-based survey, Census survey,
etc.), database design and management, image processing and analysis using remote
sensing, hazard, and risk mapping, training, reporting, etc.
Figure 2-3: Flexible Pavement’s Cross-Section and Longitudinal Profile for Z-7040
Figure 2-4: Plan of Rigid pavement 2+600 to 3+000,3+800 to 4+100, 5+000 to 5+500,
16+300 to 16 +500, 26+700 to 25+900, 28+700 to 29+200
In the Khulna-Bagerhat-Satkhira Region, the network of 17 zilla roads plays a vital role in
connecting communities, facilitating trade, and supporting local economies. Among these
roads, Z-7040, the Dighalia(Ralighate)-Arua-Gazirhate-Tarokhada Road, is a crucial link
between Dighalia and Tarokhada, fostering mobility and trade opportunities. Similarly,
Road Z-7045, the Tarokhada-Mollahate Road, connects Tarokhada and Mollahate,
potentially enhancing the efficiency of goods transportation. Another critical route, Z-7615,
the Dacope-Barobaria-Magurkhali-Tala Road, interlinks Dacope, Barobaria, Magurkhali,
and Tala, highlighting its significance for local movement and agricultural activities.
In evaluating the demand analysis for these roads, a recurring theme emerges: the existing
narrow road widths are becoming increasingly inadequate to accommodate the growing
traffic volumes and meet the demands of economic expansion. These roads, essential for
trade, transportation, and economic growth, suffer from traffic congestion, limiting their
potential impact. To address this issue and pave the way for efficient connectivity,
widening these roads becomes imperative. By expanding the road widths of these critical
corridors, the region can overcome its current limitations and unlock opportunities for
enhanced trade, commerce, and overall socio-economic progress.
The prevailing state of the 17 zila road networks within the expansive Khulna Circle
presents a formidable challenge in meeting the multifaceted demands stemming from a
burgeoning population, escalating economic activities, and heightened traffic flow. As
urbanization accelerates and communities expand, these roadways are strained by
congestion, operational inefficiencies, and less-than-optimal traffic management
strategies. These challenges engender time wastage and exacerbate environmental
concerns from heightened vehicular emissions. The 17 district highways, characterized by
their limited width and the absence of dedicated lanes catering to slow-moving vehicular
traffic (SMVT) and non-motorized traffic (NMT), fall short of accommodating the diverse
spectrum of road users. The occurrence of congested intersections and the absence of
segregated provisions for distinct vehicle types further compound the situation. Inadequate
road safety measures add to the complexity, putting lives at risk and leading to avoidable
delays. Moreover, vehicular breakdowns magnify the problem by causing road capacity to
contract to a single lane, exacerbating traffic bottlenecks and gridlock.
This project will involve improving and widening 17 important zila roads of Khulna Circle.
Improvements and widening will include multifaceted components such as the expansion
of the existing road, curve straightening and existing pavement strengthening, and road
safety improvement and signalization.
Beyond mere economic expansion, the project's relevance is resplendent. The upgraded
road infrastructure can engender social inclusivity by augmenting access to essential
services encompassing education, healthcare, and markets. This transformation opens up
new avenues for small-scale businesses, emerging entrepreneurs, and steadfast farmers,
leading to reduced transportation costs and expanded market opportunities. The impacts
extend further into the domain of environmental stewardship. The capacity to mitigate
traffic congestion and shorten travel times is paramount in reducing emissions and
enhancing air quality, aligning seamlessly with the districts' fervent commitment to
sustainability.
Khulna, Satkhira, and Bagerhat collectively form a dynamic economic and cultural hub
within Bangladesh, marked by diverse industries, bustling commerce, and thriving
agricultural activities. The existing road networks face mounting challenges as these
districts experience steady population growth, expanding urbanization, and heightened
trade. Congestion, operational inefficiencies, and inadequate road standards have
hindered the region's economic potential, compelling the need for transformative
improvements.
Moreover, after the inauguration of Padma Bridge, the accessibility from Dhaka to these
three districts increased. Improving regional-level accessibility in this region should be a
top national development goal since it provides prospects for long-term social and
economic development and mitigates the adverse effects of natural catastrophes on
regions in developing nations like Bangladesh. Academics have investigated the causes
and implications of traffic congestion in many industrialized cities using various models.
These 17 Zila roads are crowded, and traffic volume is growing daily. A massive highway
serves the population of the area connected by these highways. However, the roadways
are not broad enough to accommodate the purpose. As a result, the feasibility study is
critical in the current situation to ease urban traffic congestion.
The impact of the highway as a connecting road for meeting increased economic needs
and expanding trade and commerce is immense. However, the road's narrowness cannot
fulfil the expected role in meeting the increased demand as a national highway. If the
project is implemented, all the region's people, traders, beneficiaries, students, and others
will benefit, especially from the expansion of trade and commerce, which will keep the
country's economic wheel moving through import and export.
Availability of land is crucial; evidence should be provided that the land is owned (or can
be accessed) by the organization, which has the full title to use it, or has to be purchased
(or rented) through the acquisition/requisition process. Besides, it should address if any
utility shifting is required. Identify the issues of disaster risks (existing and future) in the
proposed location and the project site on the hazard map.
• Demolition is needed for old buildings and semi-pucca shops, pucca market tin-
shed shops, and hotels.
• Many trees from both sides of the road needed to be cut for the expansion.
• There is agriculture and barren land on the both side of the road.
• There are semi-pucca and tin shed commercial structure on the north side of the
road.
• There are pucca, semi-pucca and tin shed commercial structure on the north side
of the road.
13+820 Yes
13+840 Yes
13+855 Yes
14+075 Yes
14+270 Yes
14+590 Yes
14+600 Yes
14+790 Yes
14+860 Yes
14+985 Yes
15+170 Yes
17+415 Yes
18+260 Yes
18+430 Yes
18+910 Yes
5+225 Yes
5+490 Yes
5+695 Yes
6+570 Yes
6+830 Yes
6+910 Yes
rehabilitation may be required. Navigation may be slightly disrupted. Habitat and water
quality may be partially affected.
Small-scale mining
activities have little impact.
The required number of
materials will not cause
changes in topography,
Geography, Landforms,
topography, geology and
Geology, and Soils
soil. The mining risk is
negligible as mining will
only be carried out during
construction. The pond is
located next to the road.
an efficient and cost-effective transport network is considered one of the key determinants
in achieving the growth and poverty reduction goals set out in the Sustainable
Development Goals and Vision 2041.
3.4 Stakeholders
Construction projects have common characteristics: they will always have a project doer,
client, and beneficiary. Considering only Road construction, it has familiar and unique
stakeholders. There is a variation in primarily external stakeholders in developed and
developing countries.
• To learn about the present socio-economic & environmental conditions of the study
area and its improvement.
• To facilitate the stakeholders, identify the problems and prospects of the project
and conflict of interest among all groups.
• Provides the necessary funds for the project; Ensures that the funds
Donor/Financi are utilized for the purpose; checks if funds are used for this particular
er activity.
• Approves the request for additional budget from client/ERA
4.1 Location
The study area encompasses the strategic and vibrant Khulna-Bagerhat-Satkhira region
in southwestern Bangladesh, where economic dynamism and connectivity converge. This
pivotal region is a crucial nexus, bridging Dhaka's bustling capital city with the expansive
south-west. This region, which consists of important administrative districts and economic
hubs, has much growth potential as long as infrastructure and connections are improved.
The study area encompasses the Khulna, Bagerhat, and Satkhira Districts in the
southwestern region of Bangladesh, within the Khulna Division. These districts hold
historical, cultural, and economic significance, shaped by their geographic attributes and
thriving industries. Bagerhat District, strategically situated between 21°49' and 22°59'
north latitudes and 89°32' and 89°98' east longitudes, is known for its abundant shrimp
production and the vital Mongla sea-port. With an extensive road network totaling 440.776
kilometers, Bagerhat plays a crucial role in internal and national connectivity.
Satkhira District, positioned between 21°36' and 22°54' north latitudes and 88°54' and
89°20' east longitudes, thrives on its rich history, cultural heritage, and economic
contributions. It boasts vital rivers and a prominent land port that significantly influences
trade and commerce, particularly shrimp farming. The district's road network of 278.95
kilometers is pivotal in connecting the region's distinct areas and bridging the gap between
India and Bangladesh.
Bagerhat and Satkhira Districts represent a dynamic region driven by agriculture, fishing,
and trading activities. This area is poised for further growth with diverse geographical
features like rivers, sea-ports, and fertile lands. The road network within these districts is
an essential backbone for economic prosperity, internal connectivity, and facilitating trade,
underscoring the need for comprehensive analysis and development to ensure efficient
transportation, economic growth, and improved quality of life for the local communities.
Dacope stands out with its intricate network of waterways that serve as vital channels for
transportation, agriculture, and fishing. It is also home to the renowned Sundarbans, the
world's largest mangrove forest, harboring diverse wildlife, including the Bengal tiger and
saltwater crocodile. Barobaria boasts a rich and diverse cultural blend shaped by the
coexistence of various communities over time.
Tala, Fultola, and Shahapur are notable for their cultural festivals and traditional
handicrafts, highlighting the significance of artistry in these regions. Maximil, Dumuria, and
Goaldanda rely on agriculture for sustenance, mainly cultivating paddy, jute, and various
fruits. Shatkhira is the largest sub-district, encompassing the UNESCO-listed Sundarbans
mangrove forest while grappling with urbanization-induced challenges.
Asasuni, with its historic Asasuni Rajbari and Shyamnagar Fort, carries echoes of the past.
Paikgacha is blessed with natural beauty thanks to its proximity to the Sundarbans and
economic activities like shrimp farming and fish processing. The regions share the
common predicament of traffic congestion due to population growth, migration, and a lack
of road infrastructure. Consequently, air pollution is a pressing issue exacerbated by
outdated vehicle emissions and the use of traditional fuels.
Terokhada and Mollahat are defined by their communication networks, consisting of roads
and waterways while striving to address traffic-related challenges. Despite these issues,
the study area retains its cultural richness, thriving festivals, and traditional practices,
underscoring the resilience and uniqueness of each region within the larger tapestry of
southwestern Bangladesh. Efforts to mitigate environmental problems and improve
infrastructure are crucial for ensuring these diverse locales' sustainable and vibrant future.
This section describes the main components, technology adopted, design, standards, and
specifications. The basic idea of the survey area for the whole project is defined as follows:
• The corridor of the topographic survey measured 30.47m on average, 15.23m left
and 15.23m right from the route center line.
• A particular survey was conducted for Bridge, Canal/Khal, and River
Study Areas of selected road route alignment are presented in the following sub-sections.
Chainage Proposed
Road Length Existing Lane
District Lane
No From To (km) Configuration
Configuration
Khulna Z-7040 00+000 29+200 29.2 2L, 3.5m 2L, 7.5m
Khulna Z-7045 00+000 11+820 11.82 2L, 3.5m 2L, 7.5m
Khulna Z-7615 08+800 24+300 15.50 2L, 3.5m 2L, 7.5m
Khulna Z-7043 00+000 28+780 28.78 2L, 3.5m 2L, 7.5m
Khulna Z-7603 37+200 45+500 8.30 2L, 3.5m 2L, 7.5m
Bagerhat Z-8409 00+000 24+470 24.47 2L, 3.5m 2L, 7.5m
Bagerhat Z-7801 00+000 22+855 22.885 2L, 3.5m 2L, 7.5m
Bagerhat Z-7718 00+000 42+000 42.00 2L, 3.5m 2L, 7.5m
Bagerhat Z-7704 28+863 36+833 7.97 2L, 3.5m 2L, 7.5m
Bagerhat Z-7701 00+000 25+892 25.892 2L, 3.5m 2L, 7.5m
Bagerhat Z-7045 11+720 19+987 8.267 2L, 3.5m 2L, 7.5m
Bagerhat Z-7714 00+000 10+450 10.45 2L, 3.5m 2L, 7.5m
Bagerhat Z-7716 00+000 10+740 10.74 2L, 3.5m 2L, 7.5m
Satkhira Z-7618 00+000 31+945 31.945 2L, 3.5m 2L, 7.5m
Satkhira Z-7552 11+382 19+925 8.543 2L, 3.5m 2L, 7.5m
Satkhira Z-7610 7+020 40+000 32.980 2L, 3.5m 2L, 7.5m
Satkhira Z-7613 00+000 10+100 10.1 2L, 3.5m 2L, 7.5m
4.2.1.3 Shoulder
Shoulder width varies from 0.5 to 1m along the Project Road. The whole shoulder is
earthen.
Chainage Pavement
District Road No Remarks
From To Condition
Item Standard
Priority: Geometric Design Standards for RHD (2000)
Geometric Design
Reference: AASHTO Standard
Priority: Pavement Design Guide for RHD (2005)
Pavement Design
Reference: AASHTO Standard (1993)
impact on the surrounding environment when the existing radius of the curve does not
meet the standard. Rated values and adopted values are described below, respectively.
2) Minimum Transition Length: 45 m for 7%, 25m for 5% and 15m for 3% Super-
elevation. The minimum straight transition length is 15m.
Single Lane
Two Lane Roads
Radius (m) Roads
3.7 m wide 5.5 m, 6.2 m wide 7.3 m wide
15 1.8 2.4 2.1
16 to 20 1.5 2.1 1.8
21 to 35 1.2 1.8 1.5
36 to 65 0.9 1.5 1.2
66 to 120 0.6 1.2 0.9
121 to 200 Nil 0.9 0.6
201 to 350 Nil 0.6 Nil
351 to 600 Nil 0.6 Nil
601 to 1000 Nil Nil Nil
The vertical curve denoted by K, which RHD standards have specified, shall be taken as
9 as the minimum value.
Single Lane
Two lane single carriageway roads (5.50 m, 6.2
Design Speed Roads (3.70 m
m, 7.3 m carriageway)
(km/hr) carriageway)
ISD SSD ISD OSD
30 4 2 4 18
40 9 4 9 35
50 18 9 18 70
65 35 18 35 140
80 - 35 70 270
100 - 70 140 540
4.2.3.4 Crossfall
Crossfall is set in accordance with the RHD standards as 3% for Road and 2% for Bridge.
4.2.3.5 Super-elevation
Super-elevation is set in accordance with RHD standards as 7%, 5% and 3% for Radius
of Curve of 65m, 120m and 250m, respectively.
Sight Distance
Design 25 30 45 60 90 120 180 250 360
Speed Curve Radii (m)
(km/hr) 20 35 65 120 250 500 1000 2000 4000
Minimum Super-elevation requirements (%)
30 7 5 3 Nil Nil - - - -
40 - 7 5 3 Nil Nil - - -
50 - - 7 5 3 Nil Nil - -
65 - - - 7 5 3 Nil Nil -
80 - - - - 7 5 3 Nil Nil
100 - - - - - 7 5 3 Nil
The AASHTO Pavement Guide determines the pavement layer thickness to provide load-
carrying capacity corresponding to the design structural number (SN). The SN is
calculated using the following formula:
The design lane ESAL has been calculated using the following basic equation:
where,
DL = Lane Distribution Factor (0.75 for undivided road with two lane carriageway)
n = Design Period
The Project's Terms of Reference require that new pavements are to be designed for a
10-year life, with provision for overlays during or at the end of that period to extend the life
to 15-20 years. Therefore, in order to provide a foundation that can sustain 20 years of
structural life, the ESALs (Equivalent Standard Axle Loads) have been calculated for 20
years from the base year to determine the required thickness of the pavement layers. Axle
load equivalency factor for the Project is shown in Tables below along with the predicted
number of 18-kip equivalent single-axle load applications (W18) for the Project.
4.2.6.2 Drains
(a) The need for cross drainage, road surface drainage, and sub-surface drainage.
(b) Drain design should prevent silt deposition (too shallow a fall) and excessive scour
(too steep a fall).
(c) Open-lined drains should be in shallow dishes rather than steep-sided U or V-
sections.
(d) In built-up areas, channel drains deeper than 250 mm should be covered for
pedestrians' and vehicles' safety and convenience.
(e) The drain should terminate or run out satisfactorily without risk of causing erosion
or other problems.
(f) The drain should be capable of being cleaned and maintained easily.
4.2.6.3 Barriers
The New Jersey-type barrier is the preferred divider on RHD roads. In urban and semi-
urban areas in Bangladesh, both New Jersey Barrier type and island-type medians should
be appropriate depending on the availability of land. Fencing along dividers/medians to
restrict pedestrians crossing the roads rampantly is also necessary.
For rural Highways, the desirable width of dividers/medians on rural highways is 5.0 m,
but this could be reduced to 3.0 m where land is limited. The normal standard practice for
divided rural highways is to provide 3.0 m separators between opposing direction
roadways, when there is no serious land scarcity. In case of severe constraint situations,
New Jersey-type barriers with a height of a minimum of 1.55 m over the carriageway,
absolute minimum width of barrier at base being 1.0 m and an absolute minimum of 0.60
m width inner paved shoulders with retro-reflective road markings, barrier reflector etc. are
provided.
It includes a description of the output and the expected utilization rate. These elements
describe the service provision from the supply side in the context of the forecasted
demand.
Estimated the financial needs for project design, implementation, and operations;
componentwise cost estimates should be provided based on evidence.
Considering the volume of works, the capacity of implementing agency, budget flow
(MTBF ceiling), project priority, etc., a realistic project timeline and the implementation
schedule should be provided (for example, a Gantt chart with the work plan).
After the construction of a new road, traffic depends upon the following factors:
1. Normal Growth
2. Generated Growth
3. Diverted Growth
4. Seasonal Fluctuations
5. Irregular Movement
The combined effect of these processes cannot be separated. In this analysis, we can
attempt to present our observed changes before and after the development.
The methodology for traffic volume survey is generally uniform for all surveyors. The
surveyor must know what traffic is moving through the given intersection to conduct this
survey. Then he needs to prepare a tally sheet to count traffic. Then comes the central
part, time selection. After selecting a specific time, he must count at that given place. The
counting should be time-specific to achieve accurate data. Then comes the part of the
calculation. There are PCU values for every transport. The researchers calculate the total
PCU value to know the traffic volume condition of that given intersection or place.
The survey will provide traffic volume data. There will be data for traffic numbers and
directions.
These data can interpret the peak and off-peak flow schedule of traffic in that place. It
also identifies the most traffic-caring road. That will remark the origin and destination of
that traffic. These data can also interpret prominent transport on that road. The kind of
traffic moving from there mostly. These data will help us to know that place's present
condition and also help forecast future needs. This will be helpful for transportation
planners and engineers to determine the future road condition and the solution for current
problems, if any.
The comparative analysis of traffic conditions on road Z-7040, derived from both the Road
and Highway Department (RHD) data and a consultant's survey, reveals some noteworthy
trends. While the RHD data reports an Average Annual Daily Traffic (AADT) of 3081
vehicles, the consultant's survey indicates a slightly higher AADT of 3173 vehicles. In
terms of traffic categories, the consultant's survey reveals increases in heavy, medium,
and small trucks, as well as the presence of large buses not accounted for in the RHD
data. Additionally, the consultant's survey reports higher counts of auto rickshaws,
motorcycles, and cycle rickshaws. Although both datasets agree on the total non-
motorized traffic count, the consultant's survey suggests an evolving traffic landscape,
possibly influenced by factors like population growth and changing transportation
preferences.
Cycle Rickshaw 13
Cart 0
Motorized 2745
Non-Motorized 110
Total AADT 2855
The traffic conditions on road Z-7045, as reported by the Road and Highway Department
(RHD) data and a consultant's survey, offer valuable insights into the road's usage and
patterns. According to the RHD data in Table 4.16, the Average Annual Daily Traffic
(AADT) is calculated at 2759 vehicles. In this dataset, heavy, medium, and small trucks
are notable contributors to the traffic, with 4.0, 41.0, and 123.0 counts, respectively.
Additionally, the presence of large and medium buses, micro buses, and a modest number
of utility vehicles and cars are evident. Auto rickshaws, motorcycles, and bicycles also
make up a significant portion of the traffic. On the other hand, the consultant's survey data
in Table 4.17 indicates a slightly higher AADT of 2855 vehicles. Notably, the consultant's
survey reports higher counts for heavy, medium, and small trucks, large and medium
buses, micro buses, utility vehicles, and cars. Furthermore, the survey reveals an increase
in auto rickshaws, motorcycles, and cycle rickshaws. However, it's essential to note that
the non-motorized traffic count is lower in the survey data compared to the RHD data.
Overall, these datasets suggest that road Z-7045 experiences significant vehicular traffic,
with the consultant's survey data indicating a potentially growing trend in various vehicle
categories.
The traffic conditions on road Z-7043, as reported by the Road and Highway Department
(RHD) data in Table 4.20 and the consultant's survey data in Table 4.21, provide a
valuable perspective on the road's usage and traffic patterns. According to the RHD data,
the Average Annual Daily Traffic (AADT) is calculated at 9421 vehicles, with a significant
presence of auto rickshaws, motorcycles, and bicycles. Notably, the consultant's survey
data reports a slightly higher AADT of 9593 vehicles, indicating a potential increase in
traffic over time. Moreover, the survey data reveals higher counts in various vehicle
categories, including trucks, buses, utility vehicles, cars, auto rickshaws, motorcycles, and
bicycles. The consultant's survey also records a slightly higher count of non-motorized
traffic. Overall, these datasets underscore the importance of accurate and up-to-date traffic
data for informed road planning and development, suggesting a growing trend in traffic
volume for road Z-7043.
suggesting a high degree of consistency between the two data sources. Both datasets
indicate a substantial presence of heavy and medium trucks, buses, utility vehicles, cars,
auto rickshaws, motorcycles, and bicycles. The consultant's survey also captures a
consistent count of non-motorized traffic. These aligned results highlight the reliability and
agreement between the RHD data and the consultant's survey, reinforcing the robustness
of the traffic information for roads Z-7603-1 and Z-7603-2.
The traffic conditions on road Z-8409, as reported by the Road and Highway Department
(RHD) data in Table 4.24 and the consultant's survey data in Table 4.25, provide insight
into the road's traffic patterns. According to the RHD data, the Average Annual Daily Traffic
(AADT) is calculated at 2,893 vehicles, with a notable presence of small trucks, micro
buses, utility vehicles, cars, auto rickshaws, motorcycles, bicycles, and cycle rickshaws.
In contrast, the consultant's survey data reports a slightly higher AADT of 3,030 vehicles,
indicating a potential increase in traffic. Both datasets align closely in terms of vehicle
categories, with consistent counts for various vehicle types, including small trucks, micro
buses, utility vehicles, cars, auto rickshaws, and two-wheelers. The consultant's survey
data also captures a similar count of non-motorized traffic. Overall, these datasets provide
a consistent picture of the traffic conditions on road Z-8409, with the consultant's survey
data suggesting a marginal growth in traffic volume over the RHD data.
Bi-Cycle 987
Cycle Rickshaw 58
Cart 10
Motorized 4149
Non-Motorized 1055
Total AADT 5204
The traffic conditions on road Z-7801, as reported by the Road and Highway Department
(RHD) data in Table 4.26 and the consultant's survey data in Table 4.27, provide valuable
insights into the road's traffic patterns. According to the RHD data, the Average Annual
Daily Traffic (AADT) is calculated at 5,001 vehicles, with a mix of various vehicle
categories, including trucks, buses, utility vehicles, cars, auto rickshaws, motorcycles,
bicycles, cycle rickshaws, and carts. In contrast, the consultant's survey data reports a
slightly higher AADT of 5,204 vehicles, indicating a potential increase in traffic volume.
Both datasets exhibit a close alignment in terms of vehicle categories, with consistent
counts for heavy, medium, and small trucks, as well as buses, utility vehicles, and two-
wheelers. The consultant's survey data also captures a similar count of non-motorized
traffic. Overall, these datasets offer a consistent depiction of the traffic conditions on road
Z-7801, with the consultant's survey data hinting at a modest growth in traffic compared to
the RHD data.
The traffic conditions on road Z-7716, as reported by the Road and Highway Department
(RHD) data in Table 4.28 and the consultant's survey data in Table 4.29, reveal the road's
traffic patterns. According to the RHD data, the Average Annual Daily Traffic (AADT) is
calculated at 1,023 vehicles, with a predominant presence of auto rickshaws, motorcycles,
bicycles, and a small number of trucks and buses. In contrast, the consultant's survey data
reports a slightly higher AADT of 1,135 vehicles, indicating a potential increase in traffic.
Both datasets exhibit consistency in vehicle categories, with modest counts for trucks,
buses, auto rickshaws, motorcycles, bicycles, and cycle rickshaws. The consultant's
survey data also captures a similar count of non-motorized traffic. Overall, these datasets
offer a coherent portrayal of the traffic conditions on road Z-7716, with the consultant's
survey data suggesting a marginal growth in traffic compared to the RHD data.
The traffic conditions on road Z-7718, as reported by the Road and Highway Department
(RHD) data in Table 4.30 and the consultant's survey data in Table 4.31, offer a
comprehensive view of the road's traffic patterns. According to the RHD data, the Average
Annual Daily Traffic (AADT) is calculated at 3,120 vehicles, with a significant presence of
medium and small trucks, buses, utility vehicles, cars, auto rickshaws, motorcycles,
bicycles, cycle rickshaws, and carts. In contrast, the consultant's survey data reports a
slightly higher AADT of 3,262 vehicles, suggesting a potential increase in traffic. Both
datasets align closely in terms of vehicle categories, with consistent counts for heavy and
medium trucks, small trucks, buses, utility vehicles, cars, auto rickshaws, motorcycles,
bicycles, and cycle rickshaws. The consultant's survey data also captures a similar count
of non-motorized traffic. Overall, these datasets provide a harmonious depiction of the
traffic conditions on road Z-7718, with the consultant's survey data indicating a marginal
growth in traffic volume over the RHD data.
The traffic conditions on road Z-7701, as reported by the Road and Highway Department
(RHD) data in Table 4.32 and the consultant's survey data in Table 4.33, provide an
overview of the road's traffic patterns. According to the RHD data, the Average Annual
Daily Traffic (AADT) is calculated at 482 vehicles, with a presence of small trucks, cars,
auto rickshaws, motorcycles, bicycles, cycle rickshaws, and carts. In contrast, the
consultant's survey data reports a higher AADT of 596 vehicles, indicating a potential
increase in traffic. Both datasets align closely in terms of vehicle categories, with
consistent counts for trucks, cars, auto rickshaws, motorcycles, bicycles, and cycle
rickshaws. The consultant's survey data captures a similar count of non-motorized traffic.
Overall, these datasets present a coherent picture of the traffic conditions on road Z-7701,
with the consultant's survey data suggesting a modest growth in traffic compared to the
RHD data.
The traffic conditions on road Z-7704, divided into five segments as indicated in Table
4.34 (RHD data) and Table 4.35 (consultant's survey data), provide a comprehensive view
of the road's traffic dynamics. According to the RHD data, the Average Annual Daily Traffic
(AADT) for each segment ranges from 3,322 to 7,870 vehicles. These figures include a
mix of vehicle categories such as trucks, buses, utility vehicles, cars, auto rickshaws,
motorcycles, bicycles, cycle rickshaws, and carts. In contrast, the consultant's survey data
consistently reports higher AADT numbers for each segment, ranging from 3,431 to 8,886
vehicles, suggesting a potential increase in traffic. Both datasets closely align in terms of
vehicle categories, with consistent counts for various vehicle types across the segments.
The consultant's survey data also captures a similar count of non-motorized traffic. Overall,
these datasets offer a comprehensive and consistent depiction of the traffic conditions on
road Z-7704, with the consultant's survey data indicating slightly higher traffic volumes
across all segments compared to the RHD data.
In the absence of RHD traffic data for road Z-7014, the consultant's survey data provides
valuable insights into the road's traffic conditions. According to the consultant's survey, the
Average Annual Daily Traffic (AADT) on this road is reported as 1,100 vehicles. This
dataset encompasses a variety of vehicle categories, including heavy trucks, medium
trucks, small trucks, large buses, medium buses, micro buses, utility vehicles, cars, auto
rickshaws, motorcycles, bicycles, cycle rickshaws, and carts. It presents a comprehensive
view of the traffic composition, indicating a moderate traffic volume on the road. While a
direct comparison with RHD data is unavailable, the consultant's survey data serves as a
critical resource for understanding and planning for the traffic dynamics on road Z-7014.
The traffic conditions on road Z-7618, divided into two segments as presented in Table
4.38 (RHD data) and Table 4.39 (consultant's survey data), provide insights into the road's
traffic dynamics. According to the RHD data, the Average Annual Daily Traffic (AADT) for
both segments is calculated at 1,072 vehicles. These figures encompass a range of
vehicle categories, including trucks, buses, utility vehicles, cars, auto rickshaws,
motorcycles, bicycles, cycle rickshaws, and carts. In contrast, the consultant's survey data
consistently reports higher AADT numbers for both segments, totaling 1,199 vehicles. This
suggests a potential increase in traffic, with both datasets closely aligning in terms of
vehicle categories, with consistent counts for various vehicle types across the segments.
The consultant's survey data also captures a similar count of non-motorized traffic. Overall,
these datasets offer a comprehensive and consistent depiction of the traffic conditions on
road Z-7618, with the consultant's survey data indicating slightly higher traffic volumes
compared to the RHD data for both segments.
Heavy Truck 2 2
Medium Truck 103 103
Small Truck 152 152
Large Bus 0 0
Medium Bus 0 0
Micro Bus 17 17
Utility 3 3
Car 19 19
Auto Rickshaw 1221 1221
Motor Cycle 1208 1208
Bi-Cycle 1012 1012
Cycle Rickshaw 23 23
Cart 9 9
Motorized 2725 2725
Non-Motorized 1044 1044
Total AADT 3769 3769
According to the RHD data, the Average Annual Daily Traffic (AADT) for both segments is
calculated at 3,652 vehicles, with a mix of vehicle categories including trucks, buses, utility
vehicles, cars, auto rickshaws, motorcycles, bicycles, cycle rickshaws, and carts. In
contrast, the consultant's survey data consistently reports a slightly higher AADT for both
segments, totaling 3,769 vehicles, indicating a potential increase in traffic. Both datasets
align closely in terms of vehicle categories, with consistent counts for heavy and medium
trucks, small trucks, micro buses, utility vehicles, cars, auto rickshaws, motorcycles,
bicycles, and cycle rickshaws. The consultant's survey data also captures a similar count
of non-motorized traffic. Overall, these datasets provide a comprehensive and consistent
portrayal of the traffic conditions on road Z-7552, with the consultant's survey data
suggesting a modestly higher traffic volume compared to the RHD data for both segments.
Cart 0.0
Motorized 4400.0
Non-Motorized 418.0
Total AADT 4818.0
The traffic conditions on road Z-7610, as reported in Table 4.42 (RHD data) and Table
4.43 (consultant's survey data), offer valuable insights into the road's traffic dynamics.
According to the RHD data, the Average Annual Daily Traffic (AADT) on this road is
calculated at 4,818 vehicles, comprising various vehicle categories such as trucks, buses,
utility vehicles, cars, auto rickshaws, motorcycles, bicycles, cycle rickshaws, and carts. In
contrast, the consultant's survey data consistently reports a higher AADT of 4,938
vehicles, indicating a potential increase in traffic. Both datasets closely align in terms of
vehicle categories, with consistent counts for medium and small trucks, micro buses, utility
vehicles, cars, auto rickshaws, motorcycles, bicycles, and cycle rickshaws. The
consultant's survey data also captures a similar count of non-motorized traffic. Overall,
these datasets provide a comprehensive and coherent depiction of the traffic conditions
on road Z-7610, with the consultant's survey data suggesting slightly higher traffic volumes
compared to the RHD data.
The traffic conditions on road Z-7613, as depicted in Table 4.44 (RHD data) and Table
4.45 (consultant's survey data), offer a clear picture of the road's traffic dynamics.
According to the RHD data, the Average Annual Daily Traffic (AADT) on this road is
calculated at 4,194 vehicles, encompassing various vehicle categories including trucks,
buses, utility vehicles, cars, auto rickshaws, motorcycles, bicycles, cycle rickshaws, and
carts. In contrast, the consultant's survey data consistently reports a slightly higher AADT
of 4,345 vehicles, suggesting a potential increase in traffic. Both datasets closely align in
terms of vehicle categories, with consistent counts for medium and small trucks, micro
buses, utility vehicles, cars, auto rickshaws, motorcycles, bicycles, and cycle rickshaws.
The consultant's survey data also captures a similar count of non-motorized traffic. Overall,
these datasets offer a comprehensive and coherent depiction of the traffic conditions on
road Z-7613, with the consultant's survey data indicating a slightly higher traffic volume
compared to the RHD data.
5.1.1 EIA
Environmental Impact Assessment (EIA) is a formal process to examine the ecological
consequences of proposed projects and policies and suggest relevant management
actions. The objective of an EIA is to ensure that potential problems are foreseen and
addressed at an early stage in the project's planning and design. An EIA should-
• Review the sites of intersection for the Improvement of 17 Important Zila Roads,
different components/ interventions are to be implemented and identify potential
environmental impacts to be considered in the project's planning, design, and
implementation stage.
• Identify sources of impacts of the project activities during pre-construction,
construction, and operational stages on the various environmental parameters and
recognize those critical to the change resulting from the project's development or
construction phase.
• Recommend an Environmental Management Plan (EMP) to avoid or mitigate
adverse environmental impacts and enhance the positive contributions of the
project site in Improvement of 17 Important Zila Roads.
• Prepare an implementable Environmental Management Plan (EMP) integrating the
measures to the identified/anticipated impacts with suggested mitigation measures
and an appropriate monitoring and supervision mechanism to ensure EMP
implementation.
5.1.3 Methodology
The EIA study has been carried out as an essential obligation of TOR and DOE
requirements for such a project. This report is based on the primary data generated during
the study period, secondary data from various sources, and information from field visits
and the project proponent. An evaluation of the statement followed these to delineate the
significant environmental issues relating to the project of the proposed site in the
Improvement of 17 Important Zila Roads in Khulna Circle. During this process, the
following steps have been observed.
The task of preparing the EIA report consisted of the following sequential components:
Scoping and field visits to the project sites identified the environmental parameters/
components (relevant to the project actions) which are susceptible to being affected. The
field visit also included a participatory approach, which involved discussions with local
people to determine the perceptions and priorities of the stakeholders in the Project area.
Apart from the local people, information was also obtained from the local school teacher
and the local government. Information was also derived from secondary sources like
different reports, journals, Satellite Image Analysis, research papers, NGOs, government
officials, etc.
5.2.1.2 Geology
The geology of Bangladesh is generally dominated by poorly consolidated sediments
deposit over the past 10,000 to 15,000 years (Holocene age). It is mainly characterized by
a basin's rapid subsidence and filling in which a colossal thickness of deltaic sediments
was deposited gradually from the north to the south. The delta building continues in the
present Bay of Bengal, and a broad fluvial front of the Ganges-Brahmaputra-Meghna
(GBM) River system gradually follows it from behind. The area is located within the Bengal
Delta, which is a large deltaic plain formed by the confluence of the Ganges, Brahmaputra,
and Meghna rivers. These rivers have deposited large amounts of sediment, creating a
flat, low-lying terrain prone to flooding and other geological hazards. The sediment
deposits consist of sand, silt, clay, and gravel and are interbedded with clay and silt layers.
These sediments have been found to be rich in minerals, including coal and natural gas.
Project
Site
The soil type in Khulna, Satkhira, and Bagerhat, Bangladesh, is likely to be predominantly
alluvial. Alluvial soil is formed by depositing sediment from rivers and is commonly found
in the low-lying delta regions of Bangladesh. Alluvial soil in Bangladesh is usually
composed of clay, silt, and sand and is known for its high fertility and water-holding
capacity. The soil in Khulna, Satkhira, and Bagerhat is also very porous, meaning it can
hold much water. This is important for agriculture, as it allows the crops to get the water
they need during the dry season.
5.2.1.4 Seismicity
Bangladesh is divided into four seismic zones (Zone-I, II, III, & IV). The project area is
shown on the earthquake zone map, where the proposed roads of Khulna, Satkhira, and
Bagerhat fall into Zone I. The seismic coefficient of 0.12 shall be followed during the
infrastructure design, and the national building code of Bangladesh is to be followed during
design works.
5.2.1.5 Climate
Bangladesh is located in the central part of the Asiatic monsoon region, where the climate
is tropical. The relatively small size of the country and generally low-lying areas cause
moderate spatial variation of temperature, precipitation, relative humidity, wind speeds,
and other climatic variables. Three seasons are generally recognized as a hot, muggy
summer from March to June and a hot, humid, and rainy monsoon season from June to
November. More than 85% of the total annual rainfall occurs, and a moderately cold, dry
winter from December to February. The beginning of the rainy season varies from year to
year; heavy rains may commence between mid-April and early June and may end between
the end of September and mid-November.
Khulna is located in Bangladesh's delta region, which has a tropical wet and dry climate.
Khulna gets less rainfall than other parts of Bangladesh due to its location and the effects
of the Sundarbans south of the city. Its annual average rainfall is 1,878.4 mm (73.95 in)h
about 87 percent falling between May and October. Khulna also receives heavy rain from
cyclones in the Bay of Bengal. The city has an annual average temperature of 26.3 °C
(79.3 °F), with monthly averages ranging from 11.4 °C (52.5 °F) on January mornings to
34.6 °C (94.3 °F) during April afternoons.
Like Khulna, Bagerhat is also located in the delta region of Bangladesh, which has a
tropical wet and dry climate. Heavy rains and high humidity characterize the wet season
in Bagerhat. The average annual rainfall in Bagerhat is 1,695 mm (66.7 in). The wettest
month is July, with an average rainfall of 350 mm (13.8 in), and the driest month is
December, with an average rainfall of 16 mm (0.63 in). The average temperature in
Bagerhat is 28.9°C (84.02°F). The hottest month is May, with an average temperature of
33.3°C (91.94°F), and the coldest month is January, with an average temperature of
23.8°C (74.84°F).
Satkhira, located in the delta region of Bangladesh, experiences a tropical wet and dry
climate. Satkhira has a monthly mean temperature above 18 °C (64 °F) every month of
the year and typically a pronounced dry season, with the driest month having precipitation
less than 60mm (2.36 in). The annual average maximum temperature reaches 35.5 °C
(95.9 °F); the minimum temperature is 12.5 °C (54.5 °F). The annual rainfall is 1710 mm
(67 in).
the offshore islands of Bhola, Hatiya, Sandwip, Manipura, Kutubdia, Maheshkhali, Nijhum
Dwip, Urir Char and other newly formed islands. The Management Information &
Monitoring (MIM) prepared a cyclone risk map. The figure shows that the proposed project
site doesn’t fall under the Cyclone-affected area.
Figure 5-3: Locations of the Proposed Project Site on Bangladesh's Cyclone and Flood
Affected Risk Map
Source: (SPARRSO, Banglapedia, 2020)
5.2.1.7 Floods
Bangladesh is prone to flooding; coastal flooding and bursting Bangladesh's riverbanks
are common and severely affect the country's landscape. 75% of Bangladesh is less than
10m above sea level, and 80% is floodplain. Therefore, the above figure shows the project
site's position over Bangladesh's flood risk map. It can be observed that the proposed
project areas are subject to coastal tidal surge-prone areas. So, the site's height and flood
level should be considered during design. The map shows that the project area falls into
Monsoon Flood Area
tube wells is easy and cheap, enabling a large water volume to pump anywhere.
Consequently, there are many public and private wells in the study area.
5.2.1.9.2 Bagerhat
The main Rivers beside the proposed road are the Bhairab River, Balaswar River,
Kaliganga River, Madhumati River, and Dharatan Rivers. All the rivers are tidal. The river
water is saline with a high sediment load and high turbidity. The surface water quality is
not so good. The rivers are polluted with industrial waste, agricultural runoff, and sewage.
Kendua Bil also exists in the proposed project area. Typically, households use pond water
for various domestic and sometimes agricultural purposes. Ponds are also generally used
for fish culture.
5.2.1.9.3 Satkhira
The main Rivers beside the proposed road are the Kobadak River, Kopotakkho River,
Betna River, Kholpetua River, and Chuna River. All the rivers are tidal. The river water is
saline with a high sediment load and high turbidity. The surface water quality of these
rivers is generally poor. They are polluted with organic matter, nutrients, and heavy metals
from sewage, agricultural runoff, and industrial pollution. Typically, households use pond
water for various domestic and sometimes agricultural purposes. Ponds are also generally
used for fish culture.
From the surface water quality test, it was observed that river surface water contains fecal
coliform. River water is also saline. It may cause a human health hazard. So, laborers
should use PPE (like hand gloves and safety boots). Saltwater can be very damaging to
concrete. The adequate clear cover should also reinforce the concrete. Rich concrete with
a low water-cement ratio may also use, which makes the concrete impervious & will protect
the reinforcement from saltwater. The admixture may also use to protect concrete from
saltwater. Aggregates for making concrete should be thoroughly washed with fresh water
to reduce the chloride ion concentration.
This baseline ecological study considered the macroecological aspects of the proposed
reconstruction of the road project site and the adjacent areas. Macroecological factors
primarily consist of floral and faunal diversity; descriptions of these diversities are
presented below.
5.2.1.10.2 Tree
The proposed reconstruction of the for Improvement of Important District Highways,
Khulna Circle project site as well as the adjacent areas include trees like- Abroma augusta
(Ulatkambal), Acacia moniliformis (Akashmoni), Aegle marmelos (Bel), Albizia lebbeck
(Sirish), Albizia procera (Silkaroi), Albizia richrdiana (Gogon Sirish), Alstonia scholaris
(Chatim), Annona reticulata (Ata), Areca catechu (Supari), ArtocaRAPus heterophyllus
(Kathal), ArtocaRAPus lakoocha (Dewa), Averrhoa carambola (Kamranga), Azadirachta
indica (Nim). Bambusa sp.(Bans), Barringtonia acutangular (Hijal). Bombax ceiba
(Shimul), Borassus flabelifer (Tal), Carica papaya (Papay), Citrus grandis (Jambura),
Citrus limon (Lebu), Cocos nucifera (Narikel), Crataeva nurvala (Baroon), Dillenia indica
(Chalta), Diospyros blancoi (Bilatigab), Diospyros perigrina (Deshigab), Erythrina ovalifolia
(Talimandar), Ficus benghalensis (Bot), Ficus religiosa (Assawath), Lagerstromin
speciose (Jarul), Lennea coromandelica (Zika), Litchi chinensis (Lichu), Mangifera indica
(Aum). Moringa oleifera (Sajna), Musa sapientum (Kala), Neolamarckia cadamba
(Kadam), Ocimum americanum (Tulshi), Phoneix Sylvestris (Khejur), Phyllanthus
reticulatus (Amloki). Polyalthia longifolia (Debdaru), Pongamia pinnata (Karoch), Psidium
guajava (Peyara), Spondias dulcis (Amra), Syzygium cumini (Jum), Syzygium
samarangense (Jamrul), Streblus asper (Sheora), Swietenia mahagoni (Mahogoni),
Syzygium cumini (Kalojam), Tamarindus indica (Tetul), Tectona grandis (Segun),
5.2.1.10.3 Herb
The project site, as well as the adjacent areas, include herbs like Alternanthera
philoxiroides (Helencha), Arundo donax (Baranal), Ceratophyllum desmersum (Jhangi),
Eclipta alba (Kalokeshi), Eichhornia crassipes (Kochuripana), Enhydra fluctuans
(Helencha), Fimbristylis milliaceae (Joina), Hygroryza aristate (Putki), Hydrocharis dubia,
Ipomoea aquatica (Kalmi sak), Lemnapera Pusilla (Khudipana), Limnophila sessiliflora
(Bijatighas), Ludwigia abscendens (Keshordam), Ludwigia hyssopifolia (Keshordam),
Mersilea quadrifoliate (Susnisak), Monochoria hatata (Kechur), Myriophyllum tetrandrum,
Nachamendra alternifolia (Kaisa), Nymphaea nouchali (Shapla), Nymphaca stellate
(Nilshapla), Nymphoides indicum (Panchuli), Phragmites karka (Nol), Pistia stratiotes etc.
5.2.1.10.4 Reptiles
The proposed reconstruction road site include trees like the species include: Common
skunk (Mabuya carinata), garden lizard (Calotes versicolor), Bengal Monitor
(Varanusbengalensis), Water Monitor (Varanus salvator), Common vine Snake, Painted
Bronzeback tree snake, Common Bronzeback, Tree Snake Common Wolfe Snake, Indo
Chinese rat Snake, and Checkered Keelback.
5.2.1.10.5 Mammals
The proposed road site includes common species are House Mouse (Mus musculus),
Asian House Shrew (Suncus murinus), Common Mongoose (HeRAPestes edwarsii),
Jungle Cat (Felis chaus), Small Indian Civet (Viverrricula indica), Indian Palm Civet
(Paradoxurus hermaphroditus), Asiatic Jackal (Canis aureus), short-nosed bat
(Cynopterus sphinx), and Indian Flying Fox (Pteropus giganteus).
Surface
Sl. Land Ground Water Atmosphere Noise
Water
Bottom
2 Soil Profile Flow Regime Air Flow Duration
Interface
Loss of Flow Climatic
3 Water Quality Frequency
Agricultural Land Variation Changes
Floodplains or Water Ground Water Fugitive Dust
4
Swamps Quality Table & Recharge & Visibility
Drainage Aquifer
5 Land use Heat Radiation
Pattern Characteristics
Engg. & Mineral Water
6 Existing Use
Resources Balance
7 Buffer Zones Flooding
Waste
Existing
8 Generation &
Use
Disposal
Transportation Salinity
9
System Intrusion
Sl. Health and Safety Social and Economic Aesthetic and Cultural
1 Physical Safety Population Landscape
Psychological Well-
2 Employment Biota
being
Parasitic/Infectious
3 Housing Wilderness
Disease
4 Psychological Disease Education Water Quality
5 Disease Vectors Utilities Atmospheric Quality
Crop
6 Fugitive Dust & Visibility
Production/Damage
7 Scenic Beauty
8 Sense of Community
9 Community Structure
10 Manmade Objects
11 Historic Places/Structure
12 Religious Places/Structures
Waste Generation &
13
Disposal
14 Compositions
The identified environmental impacts have been evaluated based on their types, extent,
spatial and temporal dimensions, likelihoods, reversibility, and scale of magnitudes. In this
study, the “Delphi Approach” has been followed for evaluating environmental impacts
using expert judgment. Several round table discussion meetings were made with the team
members to finalize the evaluation. In this evaluation, a matrix method has been adopted
to indicate the magnitude of each impact based on a word scale defined by word scenario
instead of a numeric scale. The word scales for various scenarios are outlined below:
Consequence
Reversibility
Likelihood
Temporal
Spatial
Nature
Potential Impacts
Fr/Lk/O In/Mr/M/
D/Id S/L Lo/W R/Ir
/Sl/Rr Sg/Ct
Construction phase
Consequence
Reversibility
Likelihood
Temporal
Spatial
Nature
Potential Impacts
Fr/Lk/O In/Mr/M/
D/Id S/L Lo/W R/Ir
/Sl/Rr Sg/Ct
Waste generation
Air pollution
Noise generation
Noise generation D S Lo R Fr M
Water resources
Consequence
Reversibility
Likelihood
Temporal
Spatial
Nature
Potential Impacts
Fr/Lk/O In/Mr/M/
D/Id S/L Lo/W R/Ir
/Sl/Rr Sg/Ct
Fisheries
Ecosystem
Consequence
Reversibility
Likelihood
Temporal
Spatial
Nature
Potential Impacts
Fr/Lk/O In/Mr/M/
D/Id S/L Lo/W R/Ir
/Sl/Rr Sg/Ct
Socioeconomic condition
M
Possibility of employment
D S W R Lk (positive
opportunities
)
+Sg
Impact on communication: the
Id S Lo R Lk (positive
communication may be developed
)
Air pollution
Noise
Noise generation Id L Lo Ir Lk M
Waste generation
Consequence
Reversibility
Likelihood
Temporal
Spatial
Nature
Potential Impacts
Fr/Lk/O In/Mr/M/
D/Id S/L Lo/W R/Ir
/Sl/Rr Sg/Ct
Water resources
Fisheries
Consequence
Reversibility
Likelihood
Temporal
Spatial
Nature
Potential Impacts
Fr/Lk/O In/Mr/M/
D/Id S/L Lo/W R/Ir
/Sl/Rr Sg/Ct
disturbance in the migration
channel
Ecosystem
Socioeconomic condition
M
Employment opportunities Id L W Ir Lk (positive
)
Induced infrastructural Sg
development, rural and regional Id L W Ir Lk (positive
development )
The environmental impacts identified in this study were later evaluated by considering their
types, spatial dimensions and temporal extents, reversibility, frequency of occurrences,
and scale of magnitudes. Then, mitigation measures have been suggested to prevent
environmental pollution in compliance with ECA 1995. All identified impacts were further
evaluated in letter scale of magnitude with and without the mitigation measures adopted.
The table below represents the mitigation measure required for controlling the negative
impacts of project activities and contingency measures required for reducing the risk of
accidental hazards, and enhancement measures for positive impacts with regard to
sustainable implementation and operation of the project, ensuring environmental and
community safety. The consequence analysis with and without consideration of the
mitigation measures adopted would give an impression of the effectiveness of the
measures. The details of the mitigation measures for various anticipated environmental
impacts are outlined in the table below.
mitigation measures
measures adopted
Consequence with
Consequence with
Compensation/
Enhancement/
Institution (s)
no mitigation
Contingency
Responsible
Mitigation/
measure
adopted
Impact
of construction
waste
Impact on
benthic habitat
• Limiting dredging activities RHD /
due to soil M Mr
within defined area if possible Contractor
extraction from
the river
Loss of
ecosystem
• Limiting vegetation clearance
habitat due to RHD /
Mr and base stripping within In
site Contractor
project boundary
establishment
activities
• Restrict night lights at places
Disturbance to
where necessary
nocturnal
• Keep provision of outdoor
animal due to RHD /
Mr lights with shade directed In
lighting in Contractor
downwards
construction
• Cut-off time to switch off
site
unnecessary lights at night
Measures for enhancing Socioeconomic condition
• The labor recruitment policy
should be formulated in such a
way that the local laborers can
easily get chance of
Possibility of M employment in the power plant RHD,
Sg
employment (positiv project Contractor,
(positive)
opportunities e) • Govt./NGOs should provide NGOs
support skill development
program and income
generation activities to local
people
Impact on
communication: • For the increased movement
+Sg
the of people and heavy vehicles ++Sg
(positiv RHD
communication the road networks should be (positive)
e)
may be developed
developed
Measures for controlling negative impacts on socioeconomic
• Manage separate water and
sanitation facilities for the
construction workers in the
project area so that they
Imposing the
cannot make any disturbance
pressure and
to the existing facilities of the RHD /
disturbance to
Mr local people Contractor/ In
the existing
• Provision of appropriate DPHE
water-sanitation
water supply and sanitation
facilities
facilities at construction site as
well as labor sheds
• Provision of rain water
harvesting system at
• Arrangements of gloves,
helmets, sunglasses and other RHD /
tools, dresses & uniforms for Contractor
Occupational
Mr each worker so that the / Civil In
health hazard
workers can keep themselves Surgeon
safe from any kinds of office
accident
Post-construction/Operation phase
Air Pollution Control
Rise of local air
Mr In
temperature
Generation of • Regular inspection of road
fugitive fitness certificates of the
Mr In
particulate vehicles
RHD/BRT
matter • Safety and emergency plan
A / DoE
Emission of for accidental hazard
SO2, NOx • Remote monitoring and
Mr In
within ECR control of total process
1997 limit
Emission of
Mr In
CO, CO2
Noise control
• Project must be designed so
as to ensure Bangladesh’s
standard of emission
• Provision of buffer zone and
green belt
Noise • Maintain DoE standard of RHD/BRT
M In
generation Noise level A/DoE
• Introduce and enforce
vehicle speed limit
• Switch off / throttle down all
vehicle and engine of vessel
when not in use
Controlling waste generation and its impacts
• On site waste collection and
disposal system should be
Waste
provided
generation and RHD/Upaz
• Provision of different waste
discharge to Mr ila In
bin with color code for different
natural Parishad
waste (recyclable, reusable,
environment
biodegradable, hazardous,
etc) in road side, parking
Construction
Monitoring EMP
implementation
Daily monitoring
• Mitigation measures and
• Enhancement Project area documenting
measures and quarterly
• Contingency reporting
• Compensation
Waste generation
Project area and Labor
• Construction Quarterly
shed
• Domestic
RHD/
Daily monitoring Contractor
Implementation of onsite
and
waste management plan
Within project area documenting,
and noise management
and quarterly
plan
reporting
Post-construction/Operation
towards windward
direction
Waste generation
Project area and Labor
• Project Quarterly
shed
• Domestic
Implementation of Air
quality management Daily monitoring
plan, Noise management Within project area and quarterly
plan, Waste reporting
management plan
Groundwater table
Implementation of Land
Inside and outside the Quarterly in a
and agriculture
project year
management plan
Construction
Post-construction
Construction
Regular
Implementation of RHD/
monitoring and
Ecosystem management Within project area
quarterly DoE
plan
reporting
Post-construction
Mathavanga River
Kobadak River &
Water quality monitoring Arpangasia River
(BOD, COD, Heavy
metal, pH, salinity, Total Samples should be RHD/
hardness, Nitrate, collected from three Quarterly
points (left, middle and DoE
Suspended Solid, Total
solid, Temperature, Oil right bank) along the
cross section of the
and grease, etc)
river at suggested
locations during both
ebb and flood tide
➢ Consultation with local people: Consult with local people to understand the
community's perception of the project-related activities and to identify social issues
related to the project.
An organized checklist should follow inspection, observation, consultation, and reporting.
The monitoring checklist should be developed during the preparation of the Environmental
and Social Action Plan at the stage of the detail design of the project.
The compliance monitoring report and checklist should be indexed and annexed with the
monthly and annual monitoring reports. It may be required to submit the annual monitoring
report to the Department of Environment to renew the Environmental Clearance Certificate
each year.
(1 + r )
c1
NPV of a Project = t
- Initial investment
t =1
Cash Flow
Years Present Value Factor for (12%) Present Value (Lac)
(Lac)
-1,20,000
1 0.8928 107136.00
(initial)
2 85,770.06 0.7971 68367.31
3 34,483.06 0.7117 24541.59
NPV -15929.90
The net present value represents the net benefit over and above the compensation for
risk. Hence the decision rule associated with the net present value criterion is: Accept the
project if the net present value is positive and rejects the project if the net present worth is
negative. (If the net present value is zero, it is a matter of indifference.).
This is a service organization project, as all the roads and bridges under the project will be
constructed/reconstructed toll-free. Consequently, no financial benefit will be obtained
from the project, i.e., the net present value (NPV) is negative (Table 6-1).
(1 + r )
c1
Investment = t
t =1
Here, IRR (0%) < Discount Rate (12%), NPV will be < 0
This is a service organization project, as all the roads and bridges under the project will be
constructed/reconstructed toll-free. Consequently, no financial benefit will be obtained
from the project, i.e., the internal financial rate of return (IRR) is zero (0) (Table 6-2).
Where,
I = initial investment
This is a service organization project, as all the roads and bridges under the project will be
constructed/reconstructed toll-free. Consequently, no financial benefit will be obtained
from the project, i.e., the financial benefit-cost ratio (BCR) is zero (0) (Table 6-3).
However, economic benefits to the users will be achieved considering the savings in
transport operating and travel costs. In this case, economic analysis is more important
than financial analysis for service organizations. Based on the economic analysis of the
proposed project, the project is reasonably feasible. For NPV, IRR, BCR, and NBCR, the
project's total budget is 240253.12 (Lac) BDT, where the discount rate is assumed to be
12%, the initial investment is 1,00,000 (Lac) BDT, and the life cycle of the project for
investment is 3 years.
(1 + r )
c1
NPV of a Project = t
- Initial investment
t =1
Cash Flow
Years Present Value Factor for (12%) Present Value (Lac)
(Lac)
-1,00,000
1 0.8928 -89280
(initial)
2 89,770.06 0.7971 71555.71483
3 50,483.06 0.7117 35928.7938
NPV 20396.63
The net present value represents the net benefit over and above the compensation for
risk. Hence the decision rule associated with the net present value criterion is: Accept the
project if the net present value is positive and rejects the project if the net present value is
negative. (If the net present value is zero, it is a matter of indifference).
Here the value of NPV is positive, meaning the project is accepted (Table 6-4).
(1 + r )
c1
Investment = t
t =1
Cash Flow
Years Present Value Factor for (12%) Present Value (Lac)
(Lac)
1 -1,00,000 (initial) 0.8928 -89280
2 89,770.06 0.7971 71555.71483
3 50,483.06 0.7117 35928.7938
IRR 29%
Here, IRR (29%) > Discount Rate (12%), NPV will be > 0 (Table 6-5)
Where,
I = initial investment
Cash Flow
Years Present Value Factor for (12%) Present Value (Lac)
(Lac)
-1,00,000
1 0.8928 -89280
(initial)
2 89,770.06 0.7971 71555.71483
3 50,483.06 0.7117 35928.7938
BCR 1.20
The two benefit-cost ratio measures give the same signals because the difference is unity
(Table 6-6). The following decision rules are associated with them:
So, the BCR and NBCR values are accepted for this project.
Quantity
Quantity
Quantity
Quantity
BDT.)
BDT.)
BDT.)
BDT.)
Code
Rate
Rate
Rate
Unit
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Bagerhat
Bagerhat
Bagerhat
Satkhira
Satkhira
Satkhira
Khulna
Khulna
Khulna
Total
Total
A Revenue
Supply and
Services
325
Printing and
510 L.S 0 4 5 9
Binding
2
325
33.
510 Stationery L.S 25 3.5 5 0
5
4
321
Publication and
112 L.S 17 4 8 0 29
Tendering
5
311 Honorium (For
133 PIC, PSC, TEC & L.S 25 2 5 0 32
2 TOC)
322
110 Laboratory Testing L.S 21 8 10 0 39
5
325 Consultancy
710 (Survey, Design L.S 0 20 0 0 20
1 and Soil Testing)
325 Consultancy
710 (Design and L.S 0 0 0 0 0
1 Drawing)
325
Supervision
710 L.S 91 0 0 0 91
Consultant
1
325
Ceremonies/Festiv
730 L.S 50 0 10 0 60
als (Inauguration)
1
382
119 Other expenses L.S 0 0 0 0 0
9
323
110 Foreign training L.S 0 0 0 0 0
1
41. 313
Sub-Total (A): 229 43 0
5 .5
B Capital 0
Acquisition and
0
purchase of assets
411 Purchase of
Numb 10 10
210 inspection vehicle 1 100 1 100 2 200
er 0 0
1 (Jeep)
411 Purchase of
Numb
210 inspection vehicle 3 75 225 3 225
er
1 (pick-up)
411 Purchase of
Numb 1.
210 Inspection Vehicle 5 2 10 4 6 9 16
er 5
1 (Motorcycle)
411
Purchase of dump Numb 13
210 0 0 0 1 130 1 130
truck (10-ton) er 0
1
411
Purchase of Pay Numb 12 20
210 1 120 1 200 2 320
Loader er 0 0
1
411
Purchase of Pea Numb 20
210 1 200 1 200
Grader er 0
1
411
Purchase of dump Numb
210 0 0 0 0 0
trucks er
1
411 Engineering
230 Machinery (Total Set 4 15 60 4 60
4 Station)
411
Non-residential Numb
120 0 0 0 0 0
buildings er
1
411
Residential Numb
110 0 0 0 0 0
building er
1
Accumulation of
0 0
resources
414 35 164 270 34 452 138 481
46 89. 13.
110 Acquisition of land Hectre .6 87. 93. 3. 9.6 .35 10.
2.1 494 18
1 8 8 55 67 1 4 96
Construction and
0 0
completion
411
General and site 78. 117 53. 250
130 L.S. 0
facilities 76 .85 69 .3
2
411 Maintenance
116 304
130 during L.S. 188 0
.4 .4
2 construction
Earthworks (road
411 Lac 14 531 14. 790 30 451 43. 177
embankment 36 14.
130 Cubic .5 4.3 245 5.3 9. 8.0 355 37.
widening, new 6 59
2 Meter 2 2 85 7 57 1 85 7
construction)
411
11. Flexible
130
Pavement:
2
Upgrading the existing
3.05m and 3.70m wide
roads to 5.50m Main Lane
and 7.30m Bituminous
Surface with 1.80m
Reinforcement of 51
210 210
existing pavement Km 4.1 .4 4.1
.92 .92
- 3.00 m 4
Elevation of 14 21 317 662 979
31. 46.
existing pavement Km .9 2.4 1.8 7.4 9.3
45 38
- 3.05 m 3 2 2 9 1
Reconstruction of 2.9 300 2.9 300
Km
existing pavement 4 .66 4 .66
411 Construction of 68
8. 575 9.1 575
130 Rigid Pavement - meter 7.5 0.8 0
37 4.6 7 4.6
2 7.3 m 3
411 250 250
Rigid Pavement 425 425
130 meter 3.0 3.0
Construction 0 0
2 8 8
411 Rigid Pavement 55 207 207
3.7 3.7
130 Construction - 5.5 meter 5. 3.9 3.9
3 3
2 m 56 1 1
411
Footpath
130 meter 0 0
construction
2
411
Construction of
130 Km 0 0
road divider
2
411
A) New Jersey
130 Km 0 0
Barrier
2
b) Road median Km 0 0
411 Development of
Numb 146 146
130 approach to side 0
er .88 .88
2 roads
411 16
Intersection Numb 100 114
130 7 20 140 6 6. 13
construction er 0 0
2 67
411
Construction of U
130 Km 0 0
Loop/Underpass
2
411 Bus-bay
Numb 744 744
130 construction 30 30
er .86 .86
2 (...mix...mix...m)
411 30 691
a) Reconstruction 19 20. 391 230 695
130 meter 80 23 .2 294 1.4
of culvert 1 5 5.5 0 .92
5 6 2
b) Culvert 416 416
meter 208 20 208
widening 0 0
c) Culvert New 111
20. 112 100
construction (at meter 55 471 33 0 559 85.
43 3.5 62
new location) 5
411 273
a) PC Girder 200 335 738 113
130 meter 800 22 89.
Bridge 00 .9 9.8 5.9
31 8
b) RCC Girder
meter 0 0
Bridge
c) Construction of
Bridge Approach
meter 0 0
Road (Total ...T
Bridges) ...m
411 d) Electrification
Numb
230 (Lighting)-- On 0 0
er
3 Bridges
411
Construction of Numb
130 0 0
Bailey Bridge er
3
411
Construction of Numb
130 0 0
foot over bridge er
3
Drain construction
411
(given in iBAS
130 0 0
Code may be for
7
WDB)
411
Drain
130 0 0
construction
2
Total
Econom Quantit
Item no. & Description Unit Rate (in Lac
ic Code y
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255104 Stationery L.S 25.00
Publication and
3211125 L.S 17.00
Tendering
Honorium (For PIC,
3111332 L.S 25.00
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 21.00
3257101 Supervision Consultant L.S 91.00
Ceremonies/Festivals
3257301 L.S 50.00
(Inauguration)
Sub-Total (A): 229.00
B Capital
Acquisition and purchase of
assets
Purchase of inspection
4112101 Number 1.00 100.00 100.00
vehicle (Jeep)
Purchase of inspection
4112101 Number 3.00 75.00 225.00
vehicle (pick-up)
Purchase of Inspection
4112101 Number 5.00 2.00 10.00
Vehicle (Motorcycle)
4112101 Purchase of Pay Loader Number 1.00 120.00 120.00
4112101 Purchase of Pea Grader Number 1.00 200.00 200.00
Purchase of dump
4112101 Number
trucks
Engineering Machinery
4112304 Set 4.00 15.00 60.00
(Total Station)
Accumulation of
resources
16,487.
4141101 Acquisition of land Hectre 35.68 462.10
80
Construction and
completion
General and site
4111302 L.S. 78.76
facilities
Maintenance during
4111302 L.S. 188.00
construction
Earthworks (road
Lac Cubic 5,314.3
4111302 embankment widening, 14.52 366.00
Meter 2
new construction)
0.0313
b) Sign post Number 380.00 11.93
9
12,900. 0.0233
c) Concrete guide post Number 301.60
00 8
0.0880
d) Concrete km post Number 67.00 5.90
6
5,709.9 0.0111
e) Road marking Square meter 63.60
0 4
0.7730
f) Directional sign Number 50.00 38.65
0
g) Cantilever directional
Number 12.00 3.59 43.05
sign
h) Reflecting Road 14,200. 0.0091
Number 130.22
Stads 00 7
4111302 tree planting Km 37.00 4.70 173.84
4911111 Utility sifting Number 750.00 1.02 764.40
64,264.
Sub-total (Capital) (b):
46
64,493.
Total (A+B):
46
(c) Physical Contingency
Physical Contingency (1.00%) 644.93
(d) Price Contingency
Price Contingency (1.00%) 644.93
65783.3
Total = (A+B+C+D)
2
6.4.1 Z-7040
Table 6-10: Cost Breakdown for Z-7040
Total
Econom Quantit
Item no. & Description Unit Rate (in Lac
ic Code y
BDT.)
1 2 3 4 5 6 7
A Revenue
3255104 Stationery L.S 5.00
Publication and
3211125 L.S 3.00
Tendering
Honorium (For PIC,
3111332 L.S 5.00
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 4.00
3257101 Supervision Consultant L.S 18.00
Ceremonies/Festivals
3257301 L.S 10.00
(Inauguration)
Sub-Total (A): 45.00
B Capital
Acquisition and purchase of
assets
Purchase of inspection
4112101 Number 1.00 100.00 100.00
vehicle (Jeep)
Purchase of Inspection
4112101 Number 1.00 2.00 2.00
Vehicle (Motorcycle)
4112101 Purchase of Pay Loader Number 1.00 120.00 120.00
4112101 Purchase of Pea Grader Number 1.00 200.00 200.00
Engineering Machinery
4112304 Set 1.00 15.00 15.00
(Total Station)
Accumulation of
resources
7,440.0
4141101 Acquisition of land Hectre 12.00 620.00
0
Construction and
completion
General and site
4111302 L.S. 19.69
facilities
Maintenance during
4111302 L.S. 60.00
construction
Earthworks (road
Lac Cubic 1,281.0
4111302 embankment widening, 3.50 366.00
Meter 0
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and
7.30m Bituminous Surface with 1.80m
Reconstruction of
existing pavement - 5.50 Km 4.00 202.83 811.30
m
Reinforcement of
1,504.7
existing pavement - 3.70 Km 23.717 63.45
9
m
Main road widening
1,429.9
(3.70m to 5.50m = 1.8m Km 23.717 60.29
2
= 2x0.90m)
"Surfacing (5.50 m)
(Main lane with widening 2,035.2
Km 27.717 73.43
3.70 m + widening 1.8 7
m)
Upgradation of existing 7.30m Main Lane
to Bituminous Surface
Construction of Rigid 1,351.3
4111302 meter 1.90 711.21
Pavement - 7.3 m 0
4111302 Intersection construction Number 4.00 20.00 80.00
a) Reconstruction of
4111305 meter 29.00 20.50 594.50
culvert (...t, ...m)
c) Culvert New
construction (at new meter 8.00 20.00 160.00
location) 11, 33m
Drain construction (may
4111302
be given for RHD)
0.1429
a) Concrete U drain meter 450.00 64.34
8
4000.0 0.0601
b) Surface drain meter 240.63
0 6
Protective work (types
4111302
and ...m)
a) Concrete Slope 1250.0
Square meter 0.0190 23.69
Protection 0
c) RCC Retaining Wall meter 500.00 0.86 431.09
22800. 0.0675 1,539.6
d) Palisading meter
00 3 8
20. Signs, signals, km
4111302 posts, road markings,
etc
5651.0
a) Traffic sign Number 100.00 5.65
0
3140.0
b) Sign post Number 100.00 3.14
0
5000.0 2338.0
c) Concrete guide post Number 116.90
0 0
1711.9 1114.0
e) Road marking Square meter 19.07
5 0
0.7725
f) Directional sign Number 12.00 9.27
0
g) Cantilever directional
Number 2.00 3.59 7.18
sign
h) Reflecting Road 5000.0 0.0091
Number 45.85
Stads 0 7
4111302 tree planting Km 15.00 4.70 70.47
4911111 Utility sifting Number 250.00 1.05 262.50
20,044.
Sub-total (Capital) (b):
23
20,089.
Total (A+B):
23
(c) Physical Contingency
Physical Contingency (1.00%) 200.89
(d) Price Contingency
Price Contingency (1.00%) 200.89
20491.0
Total = (A+B+C+D)
1
6.4.2 Z-7043
Table 6-11: Cost Breakdown for Z-7043
Total
Econom Quantit
Item no. & Description Unit Rate (in Lac
ic Code y
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255104 Stationery L.S 5.00
Publication and
3211125 L.S 5.00
Tendering
Honorium (For PIC,
3111332 L.S 5.00
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 5.00
3257101 Supervision Consultant L.S 20.00
Ceremonies/Festivals
3257301 L.S 10.00
(Inauguration)
Sub-Total (A): 50.00
B Capital
Acquisition and purchase of
assets
Purchase of inspection
4112101 Number 1.00 75.00 75.00
vehicle (pick-up)
Purchase of Inspection
4112101 Number 1.00 2.00 2.00
Vehicle (Motorcycle)
Engineering Machinery
4112304 Set 1.00 15.00 15.00
(Total Station)
Accumulation of
resources
4,560.0
4141101 Acquisition of land Hectre 7.68 593.75
0
Construction and
completion
Maintenance during
4111302 L.S. 58.00
construction
Earthworks (road
Lac Cubic
4111302 embankment widening, 2.60 366.00 951.60
Meter
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and
7.30m Bituminous Surface with 1.80m
Reconstruction of
1,295.0
existing pavement - 5.50 Km 5.974 216.78
3
m
Reinforcement of
1,031.8
existing pavement - 3.70 Km 16.263 63.45
5
m
Reinforcement of
existing pavement - 5.50 Km 2.412 94.31 227.48
m
Main road widening
1,063.6
(3.70m to 5.50m = 1.8m Km 16.263 65.40
0
= 2x0.90m)
"Surfacing (5.50 m)
(Main lane with widening 1,822.6
Km 24.830 73.40
3.70 m + widening 1.8 4
m)
Upgradation of existing 7.30m Main Lane
to Bituminous Surface
Construction of Rigid 2,807.0
4111302 meter 3.95 710.64
Pavement - 7.3 m 1
a) Reconstruction of 1,886.0
4111305 meter 92.00 20.50
culvert (...t, ...m) 0
Drain construction (may
4111302
be given for RHD)
0.1324
c) Concrete U drain meter 100.00 13.24
0
8000.0 0.0601
d) Surface drain meter 481.26
0 6
b) Construction of tow- 1000.0 0.0572
meter 57.26
walls 0 6
0.8621
c) RCC Retaining Wall meter 500.00 431.09
8
8900.0 0.0950
d) Palisading meter 845.88
0 4
20. Signs, signals, km
4111302 posts, road markings,
etc.
0.0565
a) Traffic sign Number 100.00 5.65
0
0.0314
b) Sign post Number 100.00 3.14
0
2500.0 0.0233
c) Concrete guide post Number 58.45
0 8
0.0880
d) Concrete km post Number 30.00 2.64
0
1413.3 0.0111
e) Road marking Square meter 15.74
1 4
0.7730
f) Directional sign Number 10.00 7.73
0
g) Cantilever directional
Number 2.00 3.59 7.18
sign
2000.0 0.0091
h) Reflecting Road Stads Number 18.34
0 7
4111302 tree planting Km 7.00 4.70 32.89
4911111 Utility sifting Number 200.00 1.84 367.50
18,143.
Sub-total (Capital) (b):
20
18,193.
Total (A+B):
20
(c) Physical Contingency
Physical Contingency (1.00%) 181.93
(d) Price Contingency
Price Contingency (1.00%) 181.93
18557.0
Total = (A+B+C+D)
6
6.4.3 Z-7045
Table 6-12: Cost Breakdown for Z-7045
Economi Item no. & Description Unit Quantit Rate Total (in
c Code y Lac
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3211125 Publication and Tendering L.S 3.00
3111332 Honorium (For PIC, PSC, L.S 5.00
TEC & TOC)
3221105 Laboratory Testing L.S 4.00
3257101 Supervision Consultant L.S 18.00
3257301 Ceremonies/Festivals L.S 10.00
(Inauguration)
Sub-Total (A): 45.00
B Capital
Acquisition and purchase of assets
Purchase of inspection 1.00 75.00 75.00
4112101 Number
vehicle (pick-up)
Purchase of Inspection Number 1.00 2.00 2.00
4112101
Vehicle (Motorcycle)
4112304 Engineering Machinery 1.00 15.00 15.00
Set
(Total Station)
Accumulation of
resources
4141101 Acquisition of land Hectre 5.50 580.00 3,190.00
Construction and
completion
4111302 General and site facilities L.S. 19.69
Maintenance during 24.00
4111302 L.S.
construction
4111302 Earthworks (road Lac 1.60 366.00 585.60
embankment widening, new Cubic
construction) Meter
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
Reconstruction of existing Km 2.00 202.83 405.65
pavement - 5.50 m
Reinforcement of existing Km 8.276 63.45 525.09
pavement - 3.70 m
Main road widening (3.70m Km 8.276 63.45 525.09
to 5.50m = 1.8m = 2x0.90m)
"Surfacing (5.50 m) Km 10.276 73.43 754.57
(Main lane with widening
3.70 m + widening 1.8 m)
6.4.4 Z-7603
Table 6-13: Cost Breakdown for Z-7603
Total
Economi Item no. & Quantit
Unit Rate (in Lac
c Code Description y
BDT.)
1 2 3 4 5 6 7
A Revenue
3255104 Stationery L.S 5.00
Publication and
3211125 L.S 3.00
Tendering
Honorium (For PIC,
3111332 L.S 5.00
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 4.00
3257101 Supervision Consultant L.S 15.00
Ceremonies/Festivals
3257301 L.S 10.00
(Inauguration)
Sub-Total (A): 42.00
B Capital
Acquisition and purchase of
assets
Purchase of Inspection
4112101 Number 1.00 2.00 2.00
Vehicle (Motorcycle)
Construction and
completion
General and site
4111302 L.S. 19.69
facilities
Maintenance during
4111302 L.S. 16.00
construction
Earthworks (road
Lac Cubic
4111302 embankment widening, 0.85 366.00 311.10
Meter
new construction)
11. Flexible
4111302
Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
Reconstruction of
existing pavement - Km 1.988 216.10 429.61
5.50 m
Reinforcement of
existing pavement - Km 5.582 63.45 354.16
3.70 m
Reinforcement of
existing pavement - Km 0.300 94.33 28.30
5.50 m
Main road widening
(3.70m to 5.50m = Km 5.582 65.11 363.42
1.8m = 2x0.90m)
"Surfacing (5.50 m)
(Main lane with
Km 7.900 66.99 529.26
widening 3.70 m +
widening 1.8 m)
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Construction of Rigid
4111302 meter 0.400 711.38 284.55
Pavement - 7.3 m
a) Reconstruction of
4111305 meter 6.00 20.50 123.00
culvert (...3, ...6m)
Drain construction
4111302 (may be given for
RHD)
0.1324
a) Concrete U drain meter 100.00 13.24
0
0.0601
b) Surface drain meter 800.00 48.13
6
Protective work (types
4111302
and ...m)
a) Construction of tow- 0.1407
meter 500.00 70.37
walls 4
0.8760
b) RCC Retaining Wall meter 200.00 175.21
5
0.0852
c) Palisading meter 5930.00 505.39
3
20. Signs, signals, km
4111302 posts, road markings,
etc.
0.0564
a) Traffic sign Number 50.00 2.82
0
0.0314
b) Sign post Number 50.00 1.57
0
0.0233
c) Concrete guide post Number 400.00 9.35
8
0.0880
d) Concrete km post Number 10.00 0.88
0
0.0111
e) Road marking Square meter 871.55 9.71
4
0.7730
f) Directional sign Number 10.00 7.73
0
g) Cantilever
Number 2.00 3.58 7.16
directional sign
h) Reflecting Road 0.0092
Number 200.00 1.84
Stads 0
4111302 tree planting Km 2.00 4.70 9.40
4911111 Utility sifting Number 100.00 1.05 105.00
3,428.8
Sub-total (Capital) (b):
9
3,470.8
Total (A+B):
9
(c) Physical Contingency
Physical Contingency (1.00%) 34.71
6.4.5 Z-7613
Table 6-14: Cost Breakdown for Z-7040
Total
Econom Quantit
Item no. & Description Unit Rate (in Lac
ic Code y
BDT.)
1 2 3 4 5 6 7
A Revenue
3255104 Stationery L.S 5.00
Publication and
3211125 L.S 3.00
Tendering
Honorium (For PIC,
3111332 L.S 5.00
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 4.00
3257101 Supervision Consultant L.S 20.00
Ceremonies/Festivals
3257301 L.S 10.00
(Inauguration)
Sub-Total (A): 47.00
B Capital
Acquisition and purchase of
assets
Purchase of inspection
4112101 Number 1.00 75.00 75.00
vehicle (pick-up)
Purchase of Inspection
4112101 Number 1.00 2.00 2.00
Vehicle (Motorcycle)
Engineering Machinery
4112304 Set 1.00 15.00 15.00
(Total Station)
Accumulation of
resources
1,297.8
4141101 Acquisition of land Hectre 10.50 123.60
0
Construction and
completion
General and site
4111302 L.S. 19.69
facilities
Maintenance during
4111302 L.S. 30.00
construction
Earthworks (road
Lac Cubic 2,185.0
4111302 embankment widening, 5.97 366.00
Meter 2
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and
7.30m Bituminous Surface with 1.80m
Reconstruction of
existing pavement - 5.50 Km 0.97 237.35 230.23
m
Reinforcement of
existing pavement - 3.70 Km 9.580 63.45 607.83
m
Main road widening
(3.70m to 5.50m = 1.8m Km 9.580 64.85 621.24
= 2x0.90m)
Road New Construction
- 5.50m (Bridge Km 2.583 272.41 703.63
Approach)
"Surfacing (5.50 m)
(Main lane with widening
Km 13.180 73.42 967.65
3.70 m + widening 1.8
m)
Upgradation of existing 7.30m Main Lane
to Bituminous Surface
Construction of Rigid
4111302 meter 0.52 712.69 370.60
Pavement - 7.3 m
c) Culvert New
construction (at new meter 47.00 20.50 963.50
location) 10, 47m
Drain construction (may
4111302
be given for RHD)
0.1324
a) Concrete U drain meter 200.00 26.49
5
1200.0 0.0601
b) Surface drain meter 72.19
0 6
Protective work (types
4111302
and ...m)
a) Concrete Slope 10000. 0.0167
Square meter 167.80
Protection 00 8
b) Construction of tow- 2000.0 0.1484
meter 296.88
walls 0 4
3000.0 0.8621 2,586.5
c) RCC Retaining Wall meter
0 8 3
16000. 0.0675 1,080.4
d) Palisading meter
00 3 8
4111302 Ferry construction Number 3.00 215.21 645.64
20. Signs, signals, km
4111302 posts, road markings,
etc
0.0565
a) Traffic sign Number 80.00 4.52
0
0.0313
b) Sign post Number 80.00 2.51
8
3000.0 0.0233
c) Concrete guide post Number 70.14
0 8
0.0880
d) Concrete km post Number 15.00 1.32
0
0.0111
e) Road marking Square meter 834.26 9.29
4
0.7730
f) Directional sign Number 10.00 7.73
0
g) Cantilever directional
Number 4.00 3.59 14.35
sign
h) Reflecting Road 2000.0 0.0091
Number 18.34
Stads 0 7
J) Guard rail meter
Tree removal and
4111302 Number
uprooting
4111302 tree planting Km 7.00 4.70 32.89
4911111 Utility sifting Number 200.00 0.13 26.49
13,152.
Sub-total (Capital) (b):
78
13,199.
Total (A+B):
78
(c) Physical Contingency
Physical Contingency (1.00%) 132.00
(d) Price Contingency
Price Contingency (1.00%) 132.00
13463.7
Total = (A+B+C+D)
8
Total
Econom
Item no. & Description Unit Quantity Rate (in Lac
ic Code
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255102 Printing and Binding L.S 5.00
3255104 Stationery L.S 5.00
Publication and
3211125 L.S 8.00
Tendering
Honorium (For PIC,
3111332 L.S 5.00
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 10.00
Ceremonies/Festivals
3257301 L.S 10.00
(Inauguration)
Sub-Total (A): 43.00
B Capital
Acquisition and purchase of
assets
Purchase of inspection 100.0
4112101 Number 1 100.00
vehicle (Jeep) 0
Purchase of Inspection
4112101 Number 4.00 1.50 6.00
Vehicle (Motorcycle)
Purchase of dump truck 130.0
4112101 Number 1.00 130.00
(10-ton) 0
200.0
4112101 Purchase of Pay Loader Number 1.00 200.00
0
Accumulation of
resources
343.6 4,529.6
4141101 Acquisition of land Hectre 13.18
7 1
Construction and
completion
General and site
4111302 L.S. 53.69
facilities
Maintenance during
4111302 L.S. 116.40
construction
Earthworks (road
Lac Cubic 309.5 4,518.0
4111302 embankment widening, 14.59
Meter 7 1
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and
7.30m Bituminous Surface with 1.80m
Reinforcement of
existing pavement - 3.00 Km 4.10 51.44 210.92
m
Reconstruction of
106.5 2,466.9
existing pavement - 5.50 Km 23.16
1 2
m
Main road widening
(3.00m to 5.5m = 2.45m Km 4.10 82.67 338.96
= 2*1.225m)
Reinforcement of
3,018.1
existing pavement - 3.70 Km 51.56 58.54
3
m
Reinforcement of
147.6 1,289.7
existing pavement - 5.50 Km 8.73
7 9
m
Main road widening
2,718.9
(3.70m to 5.50m = 1.8m Km 52.23 52.05
2
= 2x0.90m)
Road New Construction
124.9
- 5.50m (Bridge Km 2.20 274.77
0
Approach)
Hard solder construction 1,273.5
Km 37.52 33.95
(2x 0.90 m = 1.80 m) 6
"Surfacing (5.50 m)
(Main lane with widening 8,248.4
Km 98.45 83.79
3.70 m + widening 1.8 2
m)
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Reconstruction of
265.9 2,111.3
existing pavement - 7.30 Km 7.94
1 3
m
201.0 1,595.9
Surfacing (7.30 m) Km 7.94
0 4
Construction of Rigid
4111302 meter 0.80 0.00 -
Pavement - 7.3 m
Rigid Pavement 555.5 2,073.9
4111302 meter 3.73
Construction - 5.5 m 6 1
166.6 1,000.0
4111302 Intersection construction Number 6.00
7 0
a) Reconstruction of
4111305 meter 23.00 30.26 695.92
culvert (...t, ...m)
b) Culvert widening (...t, 4,160.0
meter 208.00 20.00
...m) 0
c) Culvert New
construction (at new meter 33.00 0.00 -
location) 11, 33m
4111303 a) PC Girder Bridge 7,389.8
meter 335.90 22.00
1 (50.00m) 0
Drain construction
4111302 (may be given for
RHD)
a) Concrete U drain meter 9,610.00 0.09 853.31
6.5.1 Z-7701
Table 6-16: Cost Breakdown for Z-7701
Total
Economi Item no. & Quantit
Unit Rate (in Lac
c Code Description y
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255102 Printing and Binding L.S 5.00
3255104 Stationery L.S 5.00
Publication and
3211125 L.S 8.00
Tendering
Honorium (For PIC,
3111332 L.S 5.00
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 10.00
Ceremonies/Festivals
3257301 L.S 10.00
(Inauguration)
Sub-Total (A): 43.00
B Capital
Acquisition and purchase of
assets
Purchase of Inspection
4112101 Number 1.00 2.00 2.00
Vehicle (Motorcycle)
Construction and
completion
General and site
4111302 L.S. 8.15
facilities
Maintenance during
4111302 L.S. 20.00
construction
Earthworks (road
embankment Lac Cubic
4111302 1.26 366.00 461.89
widening, new Meter
construction)
11. Flexible
4111302
Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
Reconstruction of
existing pavement - Km 1.180 259.68 306.42
5.50 m
Reinforcement of
existing pavement - Km 9.986 67.15 670.54
3.70 m
Main road widening
(3.70m to 5.50m = Km 10.214 61.90 632.25
1.8m = 2x0.90m)
"Surfacing (5.50 m)
(Main lane with
Km 11.352 76.59 869.42
widening 3.70 m +
widening 1.8 m)
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Rigid Pavement
4111302 meter 0.228 454.52 103.63
Construction - 5.5 m
Intersection
4111302 Number 1.00 200.00 200.00
construction
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number 2.00 43.50 86.99
...m
a) Reconstruction of 1,600.0
4111305 meter 80.00 20.00
culvert (...t, ...m) 0
4111303 a) PC Girder Bridge (6, 2,332.0
meter 106.00 22.00
1 300.616m) 0
0.1065
a) Concrete U drain meter 500.00 53.27
4
Protective work (types
4111302
and ...m)
a) Concrete Slope 0.0167
Square meter 4800.00 80.54
Protection 8
16660.0 0.1025 1,707.8
b) Palisading meter
0 1 2
Signs, signals, km
4111302 posts, road markings,
etc.
0.0565
a) Traffic sign Number 60.00 3.39
0
0.0313
b) Sign post Number 60.00 1.88
3
0.0233
c) Concrete guide post Number 1500.00 35.07
8
0.0883
d) Concrete km post Number 12.00 1.06
3
0.0111
e) Road marking Square meter 2957.52 32.95
4
f) Directional sign Number 4.00 16.50 66.00
g) Cantilever
Number 8.00 2.82 22.52
directional sign
h) Reflecting Road 0.0091
Number 2300.00 21.09
Stads 7
J) Guard rail meter 800.00 0.060 48.00
Tree removal and
4111302 Number 1500.00 0.0030 4.50
uprooting
4111302 tree planting Km 11.41 1.186 13.53
4911111 Utility sifting Number 30.00
9,414.9
Sub-total (Capital) (b):
1
9,457.9
Total (A+B):
1
6.5.2 Z-7801
Table 6-17: Cost Breakdown for Z-7801
Total
Econom Quantit
Item no. & Description Unit Rate (in Lac
ic Code y
BDT.)
1 2 3 4 5 6 7
A Revenue
Sub-Total (A): 0.00
B Capital
Accumulation of
resources
1,571.2
4141101 Acquisition of land Hectre 3.00 523.76
7
Construction and
completion
General and site
4111302 L.S. 8.15
facilities
Maintenance during
4111302 L.S. 30.00
construction
Earthworks (road
Lac Cubic
4111302 embankment widening, 2.111 366.00 772.63
Meter
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and
7.30m Bituminous Surface with 1.80m
Reconstruction of
existing pavement - 5.50 Km 0.360 236.78 85.24
m
Reinforcement of
1,372.5
existing pavement - 3.70 Km 21.632 63.45
0
m
Main road widening
1,336.1
(3.70m to 5.50m = 1.8m Km 22.082 60.51
4
= 2x0.90m)
"Surfacing (5.50 m)
(Main lane with widening 3,381.8
Km 22.050 153.37
3.70 m + widening 1.8 9
m)
Upgradation of existing 7.30m Main Lane
to Bituminous Surface
Rigid Pavement
4111302 meter 0.450 573.87 258.24
Construction - 5.5 m
4111302 Intersection construction Number 1.00 200.00 200.00
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number 2.00 43.50 86.99
...m
a) Reconstruction of
4111305 meter 16.00 20.00 320.00
culvert (...t, ...m)
4111303 a) PC Girder Bridge (6,
meter 42.00 22.00 924.00
1 300.616m)
Protective work (types
4111302
and ...m)
a) Concrete Slope 4800.0 0.0167
Square meter 80.54
Protection 0 8
6000.0 1.3135 7,881.0
b) RCC Retaining Wall meter
0 0 0
27960. 0.1025 2,866.1
c) Palisading meter
00 1 8
20. Signs, signals, km
4111302 posts, road markings,
etc
0.0565
a) Traffic sign Number 150.00 8.48
3
0.0314
b) Sign post Number 150.00 4.71
0
2000.0 0.0233
c) Concrete guide post Number 46.76
0 8
0.0882
d) Concrete km post Number 23.00 2.03
6
5558.9 0.0111
e) Road marking Square meter 61.93
0 4
f) Directional sign Number 8.00 16.50 131.99
g) Cantilever directional
Number 14.00 2.82 39.41
sign
h) Reflecting Road 3000.0 0.0091
Number 27.51
Stads 0 7
J) Guard rail meter 920.00 0.060 55.20
Tree removal and 3000.0
4111302 Number 0.0030 9.00
uprooting 0
4111302 tree planting Km 22.35 1.209 27.01
4911111 Utility sifting Number 60.00
21,648.
Sub-total (Capital) (b):
80
21,648.
Total (A+B):
80
(c) Physical Contingency
Physical Contingency (1.00%) 216.49
(d) Price Contingency
Price Contingency (1.00%) 216.49
22081.7
Total = (A+B+C+D)
8
6.5.3 Z-7714
Table 6-18: Cost Breakdown for Z-7714
Total (in
Econom Quantit
Item no. & Description Unit Rate Lac
ic Code y
BDT.)
1 2 3 4 5 6 7
A Revenue
Sub-Total (A): 0.00
B Capital
Acquisition and purchase of
assets
Purchase of inspection
4112101 Number 1.00 100.00 100.00
vehicle (Jeep)
Purchase of Inspection
4112101 Number 1.00 2.00 2.00
Vehicle (Motorcycle)
4112101 Purchase of Pay Loader Number 1.00 130.00 130.00
4112101 Purchase of Pea Grader Number 1.00 200.00 200.00
Accumulation of
resources
4141101 Acquisition of land Hectre 7.190 411.45 2,958.34
Construction and
completion
General and site
4111302 L.S. 8.15
facilities
Maintenance during
4111302 L.S. 10.00
construction
Earthworks (road
Lac Cubic
4111302 embankment widening, 1.783 366.00 652.58
Meter
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and
7.30m Bituminous Surface with 1.80m
Reinforcement of
existing pavement - 3.70 Km 2.448 113.68 278.30
m
Reinforcement of
existing pavement - 5.50 Km 6.270 167.19 1,048.28
m
Main road widening
(3.70m to 5.50m = 1.8m Km 2.448 57.24 140.13
= 2x0.90m)
Road New Construction
- 5.50m (Bridge Km 0.900 305.30 274.77
Approach)
"Surfacing (5.50 m)
(Main lane with widening
Km 9.845 76.26 750.81
3.70 m + widening 1.8
m)
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Rigid Pavement
4111302 meter 0.605 698.91 422.84
Construction - 5.5 m
4111302 Intersection construction Number 1.00 200.00 200.00
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number 2.00 43.50 86.99
...m
a) Reconstruction of
4111305 meter 89.00 20.00 1,780.00
culvert (...t, ...m)
4111303 a) PC Girder Bridge (6,
meter 137.90 22.00 3,033.80
1 300.616m)
2610.0 0.1065
c) Concrete U drain meter 278.04
0 3
Protective work (types
4111302
and ...m)
a) Concrete Slope 14400. 0.0189
Square meter 272.88
Protection 00 5
1600.0 1.3137
b) RCC Retaining Wall meter 2,102.00
0 5
5300.0 0.1025
c) Palisading meter 543.30
0 1
20. Signs, signals, km
4111302 posts, road markings,
etc
0.0565
a) Traffic sign Number 40.00 2.26
0
0.0315
b) Sign post Number 40.00 1.26
0
2000.0 0.0233
c) Concrete guide post Number 46.76
0 8
0.0881
d) Concrete km post Number 11.00 0.97
8
2727.3 0.0111
e) Road marking Square meter 30.38
5 4
f) Directional sign Number 4.00 16.50 66.00
g) Cantilever directional
Number 8.00 2.82 22.52
sign
h) Reflecting Road 2500.0 0.0091
Number 22.93
Stads 0 7
1800.0
J) Guard rail meter 0.060 108.00
0
Tree removal and 1000.0
4111302 Number 0.0030 3.00
uprooting 0
4111302 tree planting Km 9.606 1.147 11.02
4911111 Utility sifting Number 30.00
15,618.3
Sub-total (Capital) (b):
1
15,618.3
Total (A+B):
1
(c) Physical Contingency
Physical Contingency (1.00%) 156.18
(d) Price Contingency
6.5.4 Z-7716
Table 6-19: Cost Breakdown for Z-7040
Total
Economi Item no. & Quantit
Unit Rate (in Lac
c Code Description y
BDT.)
1 2 3 4 5 6 7
A Revenue
Sub-Total (A): 0.00
B Capital
Acquisition and purchase of
assets
Construction and
completion
General and site
4111302 L.S. 8.15
facilities
Maintenance during
4111302 L.S. 15.00
construction
Earthworks (road
Lac Cubic
4111302 embankment widening, 1.500 366.00 549.00
Meter
new construction)
11. Flexible
4111302
Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
Reinforcement of
existing pavement - Km 8.115 67.15 544.90
3.70 m
Reinforcement of
existing pavement - Km 2.464 98.02 241.51
5.50 m
"Surfacing (5.50 m)
(Main lane with
Km 10.579 73.43 776.82
widening 3.70 m +
widening 1.8 m)
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Intersection
4111302 Number 1.00 200.00 200.00
construction
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number 2.00 43.50 86.99
...m
Protective work (types
4111302
and ...m)
a) Concrete Slope 0.0189
Square meter 3600.00 68.22
Protection 5
0.1025
b) Palisading meter 2710.00 277.80
1
20. Signs, signals, km
4111302 posts, road markings,
etc
0.0565
a) Traffic sign Number 35.00 1.98
7
0.0314
b) Sign post Number 35.00 1.10
3
0.0233
c) Concrete guide post Number 400.00 9.35
8
0.0881
d) Concrete km post Number 11.00 0.97
8
0.0111
e) Road marking Square meter 2732.60 30.44
4
f) Directional sign Number 4.00 16.50 66.00
g) Cantilever
Number 8.00 2.82 22.52
directional sign
h) Reflecting Road 0.0091
Number 3000.00 27.51
Stads 7
J) Guard rail meter 400.00 0.060 24.00
Tree removal and
4111302 Number 1000.00 0.0030 3.00
uprooting
4111302 tree planting Km 10.579 1.042 11.02
4911111 Utility sifting Number 30.00
3,460.7
Sub-total (Capital) (b):
9
3,460.7
Total (A+B):
9
(c) Physical Contingency
Physical Contingency (1.00%) 34.61
(d) Price Contingency
Price Contingency (1.00%) 34.61
3530.0
Total = (A+B+C+D)
1
6.5.5 Z-7704
Table 6-20: Cost Breakdown for Z-7040
Total
Economi Item no. &
Unit Quantity Rate (in Lac
c Code Description
BDT.)
1 2 3 4 5 6 7
A Revenue
Sub-Total (A): 0.00
B Capital
Acquisition and purchase of
assets
Construction and
completion
General and site
4111302 L.S. 7.03
facilities
Maintenance during
4111302 L.S. 10.00
construction
Earthworks (road
embankment Lac Cubic
4111302 1.329 366.00 486.41
widening, new Meter
construction)
11. Flexible
4111302
Pavement:
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Reconstruction of
2,111.3
existing pavement - Km 7.94 265.91
3
7.30 m
1,595.9
Surfacing (7.30 m) Km 7.940 201.00
4
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number 2.00 43.50 86.99
...m
Drain construction
4111302 (may be given for
RHD)
180000.0 0.00498
a) CC block Number 898.01
0 9
20. Signs, signals, km
4111302 posts, road markings,
etc
a) Traffic sign Number 60.00 0.05650 3.39
b) Sign post Number 60.00 0.03133 1.88
c) Concrete guide
Number 1200.00 0.02338 28.06
post
d) Concrete km post Number 8.00 0.08750 0.70
e) Road marking Square meter 2244.51 0.01114 25.00
f) Directional sign Number 3.00 16.50 49.50
g) Cantilever
Number 6.00 2.82 16.89
directional sign
h) Reflecting Road
Number 2000.00 0.00917 18.34
Stads
J) Guard rail meter 4000.00 0.060 240.00
Tree removal and
4111302 Number 300.00 0.0030 0.90
uprooting
4111302 tree planting Km 7.970 1.339 10.67
4911111 Utility sifting Number 20.00
5,611.0
Sub-total (Capital) (b):
4
5,611.0
Total (A+B):
4
(c) Physical Contingency
6.5.6 Z-7045
Table 6-21: Cost Breakdown for Z-7045
Total
Economi Item no. & Quantit
Unit Rate (in Lac
c Code Description y
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
Sub-Total (A): 0.00
B Capital
Acquisition and purchase of
assets
Purchase of Inspection
4112101 Number 1.00 2.00 2.00
Vehicle (Motorcycle)
Construction and
completion
General and site
4111302 L.S. 7.03
facilities
Maintenance during
4111302 L.S. 10.00
construction
Earthworks (road
embankment Lac Cubic
4111302 0.85929 366.00 314.50
widening, new Meter
construction)
11. Flexible
4111302
Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
Reinforcement of
existing pavement - Km 4.10 51.44 210.92
3.00 m
Reconstruction of
existing pavement - Km 0.220 257.95 56.75
5.50 m
Main road widening
(3.05m to 5.5m = Km 4.10 82.67 338.96
2.45m = 2*1.225m)
Reinforcement of
existing pavement - Km 2.394 63.45 151.89
3.70 m
6.5.7 Z-8409
Table 6-22: Cost Breakdown for Z-8409
Total
Economi Item no. & Quantit
Unit Rate (in Lac
c Code Description y
BDT.)
1 2 3 4 5 6 7
A Revenue
Sub-Total (A): 0.00
B Capital
Acquisition and purchase of
assets
Construction and
completion
General and site
4111302 L.S. 7.03
facilities
Maintenance during
4111302 L.S. 21.40
construction
Earthworks (road
embankment Lac Cubic 1,281.0
4111302 3.50000 366.00
widening, new Meter 0
construction)
11. Flexible
4111302
Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
Reconstruction of
2,018.5
existing pavement - Km 21.402 94.31
1
5.50 m
Hard solder
1,273.5
construction (2x 0.90 Km 21.402 59.51
6
m = 1.80 m)
"Surfacing (5.50 m)
(Main lane with 1,989.1
Km 21.402 92.94
widening 3.70 m + 8
widening 1.8 m)
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Rigid Pavement
4111302 meter 0.950 632.97 601.32
Construction - 5.5 m
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number 4.00 43.50 173.98
...m
a) Reconstruction of
4111305 meter 20.00 20.00 400.00
culvert (...t, ...m)
Drain construction
4111302 (may be given for
RHD)
a) Concrete U drain meter 1900.00 0.10653 202.41
Protective work (types
4111302
and ...m)
a) Concrete Slope 0.01895
Square meter 1700.00 32.22
Protection 3
1.61200
c) RCC Retaining Wall meter 500.00 806.00
0
20. Signs, signals, km
4111302 posts, road markings,
etc
a) Traffic sign Number 150.00 0.05651 8.48
b) Sign post Number 150.00 0.03140 4.71
c) Concrete guide post Number 1150.00 0.02338 26.89
d) Concrete km post Number 24.00 0.08811 2.11
e) Road marking Square meter 7371.07 0.01114 82.11
f) Directional sign Number 2.00 16.50 33.00
g) Cantilever
Number 10.00 2.82 28.15
directional sign
h) Reflecting Road
Number 2300.00 0.00917 21.09
Stads
J) Guard rail meter 800.00 0.0600 48.00
Tree removal and
4111302 Number 1500.00 0.00300 4.50
uprooting
4111302 tree planting Km 22.742 1.190 27.06
4911111 Utility sifting Number 112.00
9,871.0
Sub-total (Capital) (b):
3
9,871.0
Total (A+B):
3
(c) Physical Contingency
Physical Contingency (1.00%) 98.71
(d) Price Contingency
Price Contingency (1.00%) 98.71
10068.4
Total = (A+B+C+D)
5
6.5.8 Z-7718
Table 6-23: Cost Breakdown for Z-7718
Total (in
Economi Item no. & Quantit
Unit Rate Lac
c Code Description y
BDT.)
1 2 3 4 5 6 7
A Revenue
Sub-Total (A): 0.00
B Capital
Acquisition and purchase of
assets
Construction and
completion
General and site
4111302 L.S. 8.240
facilities
Maintenance during
4111302 Km 24.160 0.828 20.000
construction
Earthworks (road
embankment Lac Cubic
4111302 5.936 599.00 3555.473
widening, new Meter
construction)
11. Flexible
4111302
Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
228.26
New Construction Km 1.770 404.021
0
Reconstruction of 221.33
Km 21.210 4694.537
Roads 6
"Surfacing (5.50 m)
(Main lane with
Km 24.160 91.613 3555.473
widening 3.70 m +
widening 1.8 m)
Upgradation of existing 7.30m Main
Lane to Bituminous Surface
Reconstruction of
existing pavement - Km
7.30 m
Surfacing (7.30 m) Km
Construction of Rigid
4111302 meter
Pavement - 7.3 m
Rigid Pavement 739.23
4111302 meter 0.800 591.386
Construction - 5.5 m 3
4111302 Footpath construction meter
Construction of road
4111302 Km
divider
4111302 A) New Jersey Barrier Km
b) Road median Km
Development of
4111302 approach to side Number
roads
Intersection
4111302 Number
construction
Construction of U
4111302 meter 1600.00 0.193 308.279
Loop/Underpass-... t
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number
...m
a) Reconstruction of
4111305 meter
culvert (...t, ...m)
b) Culvert widening
meter
(...t, ...m)
c) Culvert New
construction (at new meter 43.00 30.978 1332.042
location) 11, 33m
4111303 a) PC Girder Bridge
meter
1 (6, 300.616m)
b) RCC Girder Bridge
meter
(...t,...m)
c) Construction of
Bridge Approach
meter
Road (Total ...T
Bridges) ...m
d) Electrification
(Lighting)-- On
4112303 Number
Bridges, No. of
Bridges - 1 T
Construction of Bailey
4111303 Number
Bridge
Construction of foot
4111303 Number
over bridge
Drain construction
4111307 (given in iBAS Code
may be for WDB)
Drain construction
4111302 (may be given for
RHD)
a) RCC saucer drain meter
b) Cross drain meter
c) Concrete U drain meter
d) Surface drain meter
Protective work (types
4111302
and ...m)
a) Concrete Slope 3840.00
Square meter 0.022 84.288
Protection 0
b) Construction of
meter
tow-walls
c) RCC Retaining Wall meter
15000.0
d) Palisading meter 0.140 2105.785
0
e) River Bank
Protection Work meter
(Deposit Work)
f) CC block Number
g) Geo textile filter
fabrics
234.12 468.2402
4111302 Ferry construction Number 2.00
0 4
20. Signs, signals, km
4111302 posts, road markings,
etc
a) Traffic sign Number 200.000 0.061 12.116
b) Sign post Number 200.000 0.035 7.038
c) Concrete guide 2000.00
Number 0.023 46.260
post 0
d) Concrete km post Number 25.00 0.084 2.098
5846.40
e) Road marking Square meter 0.012 69.455
0
f) Directional sign Number
g) Cantilever
Number
directional sign
h) Reflecting Road
Number
Stads
i) Guard rail meter
j) Guide post branding Square meter 502.650 0.111 55.919
k) Shyavron Number 120.000 0.147 17.681
Tree removal and 18000.0
4111302 Number 0.003 54.000
uprooting 0
4111302 tree planting Km 22.980 0.408 9.367
4911111 Utility sifting Number 24.160 0.181 4.381
Sub-total (Capital) (b): 16063.98
Total (A+B): 16063.98
(c) Physical Contingency 160.64
Physical Contingency (1.00%)
(d) Price Contingency
Price Contingency (1.00%) 160.64
Total = (A+B+C+D) 16385.26
Satkhira RHD
Total (in
Economi
Item no. & Description Unit Quantity Rate Lac
c Code
BDT.)
1 2 3 4 5 6 7.00
A Revenue
Supply and Services
3255102 Printing and Binding L.S 4.00
3255104 Stationery L.S 3.50
3211125 Publication and Tendering L.S 4.00
Honorium (For PIC, PSC,
3111332 L.S 2.00
TEC & TOC)
3221105 Laboratory Testing L.S 8.00
Consultancy (Survey, Design
3257101 L.S 20.00
and Soil Testing)
Sub-Total (A): 41.50
B Capital
Acquisition and purchase of assets
Accumulation of resources
27,093.5
4141101 Acquisition of land Hectre 89.494
5
Construction and
completion
4111302 General and site facilities L.S. 117.85
Earthworks (road Lac
4111302 embankment widening, new Cubic 14.24585 7,905.37
construction) Meter
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and
3.70m wide roads to 5.50m Main Lane
and 7.30m Bituminous Surface with
1.80m
Elevation of existing
Km 31.45 6,627.49
pavement
Reconstruction of existing
Km 2.94 300.66
pavement
Main road widening (3.70m
Km 2.94 208.48
to 5.50m = 1.8m = 2x0.90m)
Road New Construction Km 26.725 2,886.33
"Surfacing (5.50 m) Km 57.6 4,407.33
97,645.8
Total = (A+B+C+D)
4
6.6.1 Z-7613
Table 6-25: Cost Breakdown for Z-7613
Total
Economi Quantit Rat
Item no. & Description Unit (in Lac
c Code y e
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255102 Printing and Binding L.S 1.00
3255104 Stationery L.S 1.00
3211125 Publication and Tendering L.S 1.00
Honorium (For PIC, PSC,
3111332 L.S 0.50
TEC & TOC)
3221105 Laboratory Testing L.S 2.00
Ceremonies/Festivals
3257301 L.S 5.00
(Inauguration)
Sub-Total (A): 10.50
B Capital
Acquisition and purchase of assets
Accumulation of
resources
4141101 Acquisition of land Hectre 12.41 4737.5
Construction and
completion
4111302 General and site facilities L.S. 21.62
Earthworks (road
Lac Cubic
4111302 embankment widening, 1.42982 523.31
Meter
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and 7.30m
Bituminous Surface with 1.80m
Elevation of existing 1870.46
Km 10.10
pavement 0
"Surfacing (5.50 m)
(Main lane with widening Km 9.525 734.67
3.70 m + widening 1.8 m)
Upgradation of existing 7.30m Main Lane
to Bituminous Surface
Rigid Pavement
4111302 meter 500 229.17
Construction
Development of approach
4111302 Number 0.125 28.31
to side roads
Bus-bay construction
4111302 Number 8.00 70.15
(...mix...mix...m) ...t = ...m
a) Reconstruction of
4111305 meter 40.00 1500.00
culvert (...20, ..2m)
1000.00
a) RCC saucer drain meter 130.77
0
Protective work (types
4111302
and ...m)
2500.00
a) Palisading meter 211.85
0
20. Signs, signals, km
4111302
posts, road markings, etc
b) Sign post and Road
Number 110.85
marking
Tree removal and
4111302 Number 20.00
uprooting
4111302 tree planting Km 10.00
4911111 Utility sifting Number 100.00
10298.6
Sub-total (Capital) (b):
6
10309.1
Total (A+B):
6
(c) Physical Contingency
Physical Contingency (1.00%) 103.9
(d) Price Contingency
Price Contingency (1.00%) 103.9
10515.3
Total = (A+B+C+D)
4
6.6.2 Z-7610
Table 6-26: Cost Breakdown for Z-7610
Total
Econom Quanti Rat
Item no. & Description Unit (in Lac
ic Code ty e
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255102 Printing and Binding L.S 1.00
3255104 Stationery L.S 0.50
3211125 Publication and Tendering L.S 1.00
Honorium (For PIC, PSC,
3111332 L.S 0.50
TEC & TOC)
3221105 Laboratory Testing L.S 2.00
Ceremonies/Festivals
3257101 L.S 5.00
(Inauguration)
Sub-Total (A): 10.00
B Capital
Acquisition and purchase of assets
Accumulation of resources
311.11
4141101 Acquisition of land Hectre 35.430
2
Construction and
completion
4111302 General and site facilities L.S. 35.52
Earthworks (road
Lac Cubic 4844.1
4111302 embankment widening, new 8.41
Meter 6
construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and 7.30m
Bituminous Surface with 1.80m
Reinforcement of existing
Km 2.940 300.66
pavement -
Main road widening (3.70m to
Km 2.940 208.48
5.50m = 1.8m = 2x0.90m)
2886.3
Road New Construction Km 26.725
3
"Surfacing (5.50 m)
2015.1
(Main lane with widening 3.70 Km 26.725
8
m + widening 1.8 m)
Upgradation of existing 7.30m Main Lane to
Bituminous Surface
Development of approach
4111302 Number 17 21.1
to side roads
Bus-bay construction
4111302 Number 8.00 60.89
(...mix...mix...m) ...t = ...m
Culvert New construction (at 7062.0
meter 321.00
new location) 53, 321m 0
Drain construction (may be
4111302
given for RHD)
a) RCC box/ covered drain meter 550.00 74.38
Protective work (types and
4111302
...m)
a) Concrete Slope Protection Square 22900.
228.08
and Geo textile meter 00
1170.0
c) RCC Retaining Wall meter 697.32
00
27494. 3501.0
d) Palisading meter
00 9
20. Signs, signals, km posts,
4111302
road markings, etc
a) Traffic sign and Road
Number 132.84
marking
4111302 Tree removal and uprooting Number 5.00
4111302 tree planting Km 75.17
4911111 Utility sifting Number 145.71
22605.
Sub-total (Capital) (b):
02
22615.
Total (A+B):
02
(c) Physical Contingency
Physical Contingency (1.00%) 226.15
(d) Price Contingency
Price Contingency (1.00%) 226.15
23067.
Total = (A+B+C+D)
32
6.6.3 Z-7552
Table 6-27: Cost Breakdown for Z-7552
Total
Economi Quantit Rat
Item no. & Description Unit (in Lac
c Code y e
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255102 Printing and Binding L.S 1.00
3255104 Stationery L.S 1.00
3211125 Publication and Tendering L.S 1.00
Honorium (For PIC, PSC,
3111332 L.S 0.50
TEC & TOC)
3221105 Laboratory Testing L.S 2.00
Ceremonies/Festivals
3257301 L.S 5.00
(Inauguration)
Sub-Total (A): 10,50
B Capital
Acquisition and purchase of assets
Accumulation of
resources
4141101 Acquisition of land Hectre 7.01 8321.72
Construction and
completion
4111302 General and site facilities L.S. 10.73
Earthworks (road
Lac Cubic
4111302 embankment widening, 0.9721 559.96
Meter
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and 7.30m
Bituminous Surface with 1.80m
Elevation of existing
Km 6.750 1435.31
pavement – 5.50 m
"Surfacing (5.50 m)
(Main lane with widening Km 6.750 526.64
3.70 m + widening 1.8 m)
6.6.4 Z-7618
Table 6-28: Cost Breakdown for Z-7618
Total (in
Econom Quantit Rat
Item no. & Description Unit Lac
ic Code y e
BDT.)
1 2 3 4 5 6 7
A Revenue
Supply and Services
3255102 Printing and Binding L.S 1.00
3255104 Stationery L.S 1.00
Publication and
3211125 L.S 1.00
Tendering
Honorium (For PIC,
3111332 L.S 0.50
PSC, TEC & TOC)
3221105 Laboratory Testing L.S 2.00
Ceremonies/Festivals
3257301 L.S 5.00
(Inauguration)
Sub-Total (A): 10,50
B Capital
Acquisition and purchase of
assets
Accumulation of
resources
4141101 Acquisition of land Hectre 34.644 13723.22
Construction and
completion
4111302 General and site facilities L.S. 49.98
Earthworks (road
Lac Cubic
4111302 embankment widening, 3.43393 1977.94
Meter
new construction)
4111302 11. Flexible Pavement:
Upgrading the existing 3.05m and 3.70m
wide roads to 5.50m Main Lane and
7.30m Bituminous Surface with 1.80m
Elevation of existing
Km 14.6000 3321.72
pavement – 5.50 m
"Surfacing (5.50 m)
1130.222
(Main lane with widening Km 14.600
5
3.70 m + widening 1.8 m)
Upgradation of existing 7.30m Main Lane
to Bituminous Surface
Rigid Pavement
4111302 meter 2030.00 1212.11
Construction
Development of
4111302 Number 2.8 65.65
approach to side roads
Bus-bay construction
4111302 (...mix...mix...m) ...t = Number 6.00 553.64
...m
c) Culvert New
construction (at new meter 150.00 3000.00
location)
4111303 a) PC Girder Bridge (6,
meter 800.00 20000.00
1 300.616m)
Drain construction (may
4111302
be given for RHD)
a) RCC Box/Covered
meter 600.00 81.14
drain
7.1 Introduction
The Roads and Highways Department (RHD) was founded in 1962 under the former road
Division of MORTB. The department is responsible for the construction and maintenance
of the major road network of Bangladesh. It is officially defined as follows: "The Roads and
Highways Department has a sustainable capacity to plan, manage and deliver its full range
of responsibilities regarding the main road and bridge network and to be accountable for
these duties". The Assets of RHD have been conservatively estimated at BDT 460 billion,
of which the most significant proportion by far is the value of the 21,590 km of road and
the 16,985 bridges. These assets are probably the greatest of any organization in
Bangladesh, and maintaining their value is vital to the country’s economy.
RHD is accountable for completing road, rebuilding, and maintenance projects on time
and in an environmentally friendly manner, the project will require a variety of managers
and expert laborers in this regard. The Department of Roadways and Highways (RHD) is
currently developing and maintaining several significant bridges, culverts, and national,
regional, and district roads.
In the field level, the Roads and Highways Department (RHD) are ten distinct zones, each
tasked with specific geographical areas and responsibilities. Among these zones, the
Khulna Zone is a significant entity, overseeing the infrastructure and road networks within
its jurisdiction. Notably, the Khulna Zone administers the Khulna Circle, a substantial
administrative unit encompassing the districts of Khulna, Bagerhat, and Satkhira. Khulna
Circle Roads and Highways Department, as the Circle Office of the Department of Roads
and Highways, is responsible for the development and maintenance of significant bridges
and culverts, as well as national, regional, and district roads that are located in Khulna,
Bagerhat and Satkhira district administrative unit.
Furthermore, the Khulna Circle RHD has rollers, trucks, and office vehicles to maintain the
roads under them. The contractor will be chosen in such a way that they will supply the
necessary equipment to complete the work efficiently. In this context, the Khulna Circle
RHD can execute the work given the available resources and equipment.
Hire, use, or benefit from child labor: Child labor (as defined by ILO Conventions 138
and 182) means that no workers under the age of 14 may be hired as general laborers,
and workers under the age of 17 are to be hired for hazardous jobs such work on
scaffolding, no structures elevated above the ground, etc.
Bonded labor: All forms of bonded and forced labor, as ILO Conventions 29 and 105, will
not be permitted. Forced labor, including prison or debt bondage labor, lending of money
(debt slavery), or withholding remuneration or identity papers by employers or outside
recruiters, will not be permitted on any work sites.
Equal treatment and equal opportunity: RHD expects contractors to hire workers based
on skill and ability to work. There must be equal treatment and opportunity (ILO
Conventions 100 and 111, and ILO Code of Practice for HIV/AIDS 85) for all seeking
Minimum wage: RHD expects the contractor to pay all laborers and employees according
to minimum wage standards defined in the Bangladesh Labor Act.
To that end, the contractor will be required to provide each person hired with a written
contract stating the above and confirming that these conditions are being upheld and
including the names and contact information of people to contact within the contractor's
organization, RHD, and with the Engineer, that any person wishing to file a complaint or a
concern can reach without fear of retribution. RHD will instruct the Engineer to undertake
a monthly random check of these documents, report this to RHD, and take immediate, on-
the-spot action if non-compliance is identified.
Mitigation
Conflicts may occur between residents who feel that they have received unfair wages.
External workers from outside the project area will be deployed during construction. Then
conflict may also arise between residents and external workers because of changes to
local customs if external workers cannot understand local businesses.
Mitigation
Several consultations have been conducted with residents about local conflicts of interest.
Local people should be employed for the construction works to the maximum extent
possible. Any workers from other countries should be taught to respect local customs to
facilitate good relationships with locals.
The lodgings of the project workers should be equipped with sufficient living facilities to
keep workers at the project as much as possible.
There are so many unwanted happenings that may occur during construction periods.
Proper contingency planning is required to overcome any undesirable situation. Otherwise,
that will hamper the progress of work. As preparedness works, adequate contingency
planning is essential for smooth progress.
Mitigation
• All the emergency telephone numbers of all the departments like Police stations,
fire service & civil defense, truck & bus stands, hospitals, clinics, etc. have to be
saved.
• Emergency on-call physician,
• Standby transport facilities to deal with any accidental case,
• Arrangement of Safe havens (within the road construction area), preferably
nearby schools, may be used as an emergency shelter during any disaster like
Cyclone.
• Storage of the material should not create an obstacle to the movement of
vehicles and pedestrians.
Mitigation
The Contractor must have an effective Worker Health and Safety Plan supported by
trained first aid personnel and emergency response facilities. Construction contracts will
include standard Worker Health and Safety measures, and contractors must implement
these fully. Contractors are required to implement precautions to protect the health and
safety of workers. At EIA, the "Work Safety in Common Operation and Construction" will
be provided to be enforced by the Contractor.
Mitigation:
• Large stockpiles will have to provide near the construction area with properly
fenced to minimize the spreading of dust from air blowing. The large volume of
construction materials should be in a large stockpile.
• A separate batch plant should be maintained for concrete mixing as the nearest
place to the construction area if required.
• A small stockpile in the construction area will be used for essential items.
• Separate boundary (temporary) will have to be maintained for the stockpile with
and outside of construction pollution from fuel and lubricants.
Impacts: Proper placing of fuel and lubricants is essential to prevent damage to the
surrounding environment, and measures are to be taken before starting the work.
Mitigation:
• Raised platform (brick soling with neat cement finishing) shall be constructed
before starting working.
• The place should be well protected and prepared before starting work. The place
should be in a safe site of the construction area.
Impacts: Many people will work on the project, and 70-75% will reside in construction
camps. The absence of a proper labor camp will create problems during construction.
Mitigation:
The first task is an analysis of the applicable legal framework, including identifying and
analyzing pertinent laws and regulations that may affect the project. The legal and
regulatory aspects that need to be reviewed are listed below.
- The enabling PPP legislation, especially looking for particular requirements imposed
on projects, such as minimum capital value and maximum contractual duration;
- The public procurement law may be partially applicable, especially in search of general
contractual and procurement guidelines;
- Legislation referring to foreign investment, property, and labor issues;
- Legislation related to land use planning and environmental laws;
- Sector-specific legislation, for example, corrections legislation, may regulate whether
the private sector can operate a prison PPP;
- Legal aspects of dispute resolution and intellectual property, among others;
- Legislation relating to the granting of ownership/control of public assets or
responsibility for the delivery of public services to third parties; and
- Legal treatment of revenue sources associated with the concession.
The second task is the assessment of the legal readiness of the procuring authority.
Although this particular issue may have already been checked, it is important to review at
this stage whether the promoting authority and other institutions involved have the legal
authority to launch the project or proceed with the approval as needed. In some countries,
the legal empowerment issues also apply to the formal responsibility for the appraisal
exercises. Some countries require official feasibility exercises to be conducted. In this
case, there can be requirements about which governmental bodies should be included
and how. Therefore, the legal due diligence must conclude which authorities should be
involved and to what extent in each case.
The third task is an in-depth legal analysis of the main project issues. Large infrastructure
projects often have particularities with significant legal implications. It is thus very important
during the appraisal to assess the adherence of several aspects of the project to the
general legal framework. Particular attention should be given to the legal feasibility of:
Land and property - Type of rights that can be assigned to the private
assets issues sector.
- The country-specific issues surrounding land
availability (which can take the form of right of
way or clearance for transportation projects and/or site
ownership for facilities).
- Rules regarding ownership of assets.
- limited Resources
- cost of project
- cutting down roadside trees will hamper the ecology and environment
- political will and stakeholder support
- uncertainties involved (travel time delay or accident may occur during the construction
phase)
Risk management is one of the nine knowledge areas the Project Management Institute
propagated. Furthermore, in the construction project management context, risk
management is a comprehensive and systematic way of identifying, analyzing, and
responding to risks to achieve the project objectives. The benefits of the risk management
process include identifying and analyzing risks, improving construction project
management processes, and effectively using resources. In the construction project
management, risk management is a comprehensive and systematic way of identifying,
analyzing, and responding to risks to achieve project objectives. To manage the risk
effectively and efficiently, the contractor must understand risk responsibilities, event
conditions, preference, and management capabilities.
When decision-makers have many alternatives, they have more power to control the
outcome. But the data must be good. Avoiding prejudices, such as paying more attention
to information that is easy to access, is also essential.
• Make a Plan
• Organize the Analytic Framework
• Identify and Define Alternatives
• Assess the Alternatives
• Compare the Alternatives
• Report the Results
• A Project brief has been provided to the participant with the objective and purpose of
the project.
• Different stakeholders, including local public representatives, attended the discussion
meeting.
• Participants expressed their positive attitude toward the project and enquired when the
project implementation would start. They informed them that after the feasibility, the
government would imitate the necessary measures for implementing the project.
• The consultations were also conducted with local intellectuals (like Mayor, School
teachers, Mosque imams, Local elites, Journalists, Sarak Paribahan Malik Samity
etc.). They were afraid for the safety and security of local people during construction.
They are thinking about the accidental problem during construction. But consulting with
the social and environmental study team ensured proper safety measures would be
taken during the project's construction.
• Stakeholders also expressed concern regarding the timing of the compensation,
fearing that the money would not arrive at the proper time and would take time, but we
assure them that we are working hard to offer the compensation where it is needed as
quickly as feasible.
• The participants desire that due to the acquisition of their land, they should
compensate adequately so affected people can economically rehabilitate themselves.
Land costs should be considered, and business-like tree plantation and fish cultivation
costs should be regarded as compensation activities.
• According to the participant's opinion, the land value will vary due to location and
request us to collect that mouza-wise; we ensure that we are doing that.
• Valuation of the property should be carefully calculated reasonably; we ensure that the
valuation of the property has been included in our questionnaires.
• Request them for cooperation during a household survey, and they ensure that.
11.2 Recommendation
➢ Re-construction of the road for Z-7043 should be provided at the given chainage:
Chainage KM
From To
02+500 03+500 1.00
03+600 04+300 0.70
04+500 06+975 2.475
07+285 09+100 1.815
➢ Pavement Strengthening of the road for Z-7043 should be provided at the given
chainage:
Chainage
KM
From To
00+375 02+390 2.015
09+825 10+075 0.250
10+200 14+275 4.075
14+500 16+925 2.425
20+300 22+000 1.700
22+150 23+175 1.025
23+350 27+200 3.850
27+400 28+475 1.075
➢ Pavement Raising of the road for Z-7043 should be provided at the given
chainage:
Chainage
KM
From To
02+500 03+500 1.00
03+600 04+300 0.70
04+500 06+975 2.475
07+285 09+100 1.815
➢ Pavement Widening of the road for Z-7043 should be provided at the given
chainage:
Chainage
KM
From To
00+375 02+390 2.015
➢ Rigid Pavement of the road for Z-7043 should be provided at the given chainage:
Chainage
KM
From To
00+000 00+375 0.375
02+390 02+500 0.110
03+500 03+600 0.100
04+300 04+500 0.200
06+975 07+285 0.310
09+100 09+825 0.725
10+075 10+200 0.125
14+275 14+500 0.225
16+925 17+500 0.575
18+100 18+300 0.200
20+125 20+300 0.175
22+000 22+150 0.150
23+175 23+350 0.175
27+200 27+400 0.200
28+475 28+780 0.305
Location
Road Length (meters)
From Ch: To Ch:
11+732 15+082 3.350
Z-7552
15+642 19+082 3.440
Z-7618 13+500 31+280 17.780
11.3 Conclusion
The following conclusions are being made after the comprehensive study with a detailed
investigation. RHD, Bagerhat has taken a plan for the construction of Improvement and
Widening of Kochua to Depara Road Bagerhat to meet up the increasing demand of traffic
and hence safe and comfortable traffic movement.
The EIA has been carried out to assess all the predicted environmental impacts. The
assessment includes impacts on physical settings, impacts on air quality, impacts on water
resources, impacts on land and agricultural resources, impacts on fisheries, impacts on
ecosystem resources, and impacts on socio-economic environment.
Negative impacts during the pre-construction and construction phases include air and
noise pollution, disruption to water resources, disturbance to fisheries habitat, removal of
existing mangroves along the rivers and disturbance to society due to an increase of noise
level. On the contrary, construction works will create employment opportunities and better
livelihoods for local people.
The project's potential benefits will compensate for the negative impact if the prescribed
EMP is implemented. The proposed project will create enormous potential for the region's
economic and social development. It will offer many job opportunities during its lifetime,
starting from its construction, where the local people will get priority. The project's negative
impact on Physical, Water resources, Agriculture, Land and Soil, Fisheries, Ecology and
Socio-economic environment was found minor and can be mitigated/compensated by
adopting different environmental and pollution abatement measures. Therefore, it can be
concluded that the proposed project is socially viable and environmentally feasible.
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-17
Section-18
Section-19
Section-20
Section-21
Section-22
Section-23
Section-24
Section-25
Section-26
Section-27
Section-28
Section-29
Section-30
Section-31
Section-32
Section-33
Section-34
Section-35
Section-36
Section-37
Section-38
Section-39
Section-40
Section-41
Section-42
Section-43
Section-44
Section-45
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-1
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-1
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-1
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-17
Section-18
Section-19
Section-20
Section-21
Section-1
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-17
Section-18
Section-19
Section-20
Section-21
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-17
Section-18
Section-19
Section-20
Section-21
Section-22
Section-23
Section-24
Section-25
Section-26
Section-27
Section-28
Section-29
Section-30
Section-31
Section-32
Section-33
Section-34
Section-35
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-17
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-17
Section-18
Section-19
Section-20
Section-21
Section-22
Section-23
Section-24
Section-25
Section-26
Section-27
Section-28
Section-29
Section-30
Section-31
Section-32
Section-2
Section-3
Section-4
Section-5
Section-6
Section-7
Section-8
Section-9
Section-10
Section-11
Section-12
Section-13
Section-14
Section-15
Section-16
Section-17
Section-18
Section-19
Section-20
Section-21
References
Burt, R. D., Thiede, H., Barash, E. T., & Sabin, K. (2006). Recent condom use by arrested
injection drug users in King County, Washington, USA. International Journal of Drug
Policy, 17(3), 222-229.
Cohen, L. (1995). Time-frequency analysis (Vol. 778). New Jersey: Prentice hall.
DeCorla-Souza, P., & Cohen, H. (1999). Estimating induced travel for evaluation of metropolitan
highway expansion. Transportation, 26(3), 249-262.
Cervero, R., & Duncan, M. (2006). 'Which reduces vehicle to travel more: jobs-housing balance
or retail-housing mixing?. Journal of the American planning association, 72(4), 475-490.
Duranton, G., & Turner, M. A. (2011). The fundamental law of road congestion: Evidence from
US cities. American Economic Review, 101(6), 2616-52.
Graham, D. J., McCoy, E. J., & Stephens, D. A. (2014). Quantifying causal effects of road
network capacity expansions on traffic volume and density via a mixed model propensity
score estimator. Journal of the American Statistical Association, 109(508), 1440-1449.
Goodwin, H. (1996). In pursuit of ecotourism. Biodiversity & Conservation, 5(3), 277-291.
Handy, S., & Boarnet, M. G. (2014). Impact of highway capacity and induced travel on passenger
vehicle use and greenhouse gas emissions. California Environmental Protection Agency,
Air Resources Board, Retrieved August 28, 2015.
Hansen, M., & Huang, Y. (1997). Road supply and traffic in California urban areas.
Transportation Research Part A: Policy and Practice, 31(3), 205-218.
Holder, R. W., & Stover, V. G. (1972). An evaluation of induced traffic on new highway
facilities.
Hymel, S., & Katz, J. (2019). Designing classrooms for diversity: Fostering social inclusion.
Educational Psychologist, 54(4), 331-339.
Hymel, K. M., Small, K. A., & Van Dender, K. (2010). Induced demand and rebound effects in
road transport. Transportation Research Part B: Methodological, 44(10), 1220-1241.
Klaver, W. J., Henk, H., & Speckamp, W. N. (1989). Synthesis and absolute configuration of the
Aristotelia alkaloid peduncularine. Journal of the American Chemical Society, 111(7),
2588-2595.
Kockelman, P. (2010). Enemies, parasites, and noise: How to take up residence in a system
without becoming a term in it. Journal of Linguistic Anthropology, 20(2), 406-421.
Lee, D. B., Klein, L., & Camus, G. (1998). Induced traffic and induced demand in benefit-cost
analysis-draft.
Low, N., & Odgers, J. (2012). Rethinking the cost of traffic congestion, lessons from Melbourne's
city link toll roads. Urban policy and research, 30(2), 189-205.
Mokhtarian, P. L. (2002). Telecommunications and travel: The case for complementarity. Journal
of industrial ecology, 6(2), 43-57.
Loutan, C., Klauer, P., Chowdhury, S., Hall, S., Morjaria, M., Chadliev, V., ... & Gevorgian, V.
(2017). Demonstration of essential reliability services by a 300-MW solar photovoltaic
power plant (No. NREL/TP-5D00-67799). National Renewable Energy Lab. (NREL),
Golden, CO (United States).
Loudon, W. R., Parameswaran, J., & Gardner, B. (1997). Incorporating feedback in travel
forecasting. Transportation Research Record, 1607(1), 185-195.
MacDonald, A. H., Schiffer, R. P., & Samarth, H. N. (2005). Ferromagnetic semiconductors:
moving beyond (ga, mn) as. Nature Materials, 4(3), 195-202.
Næss, P., Nicolaisen, M. S., & Strand, A. (2012). Traffic forecasts ignoring induced demand: a
shaky fundament for cost-benefit analyses. European Journal of Transport and
Infrastructure Research, 12(3), 291-309.
Noland, R. B. (2001). Relationships between highway capacity and induced vehicle travel.
Transportation Research Part A: Policy and Practice, 35(1), 47-72.
Odgers, C. L., Moffitt, T. E., Tach, L. M., Sampson, R. J., Taylor, A., Matthews, C. L., & Caspi,
A. (2009). The protective effects of neighborhood collective efficacy on British children