IRP Transmission and Distribution Projects
IRP Transmission and Distribution Projects
This appendix describes the transmission and distribution projects that have been
completed since our 2014 IRP, projects that are underway, and projects that we plan to
start after 2020.
A Vermont Public Service Board Order in Docket No. 8069 required us to examine
rebuilding and relocating the Barre South End substation as well as converting all area
substations to 12.47 kV to improve reliability in the Barre area. We are designing the
Barre South End substation with a 15/28-MVA transformer and three circuits to
provide complete feeder backup to nearby substations, which will significantly improve
reliability for local residents and businesses. This necessitated rebuilding the Barre North
End substation as well as rebuilding the Websterville substation.
The new Barre North End substation enables full feeder backup to the new Barre South
End substation and partial feeder backup to the Berlin substation.
The VELCO Connecticut River Valley Study, which focuses on the need to upgrade the
VELCO Coolidge to Ascutney 115-kV transmission line, shows that these two
subtransmission lines are overloaded following certain contingencies on the VELCO
transmission system. These post-contingency overloads expose the Connecticut River
Valley to low voltages and possible voltage collapse.
three miles were adequate for current conditions and do not require reconductoring.
Project completion: October 2016.
The conversion relieved the overloaded Essex circuit, increased capacity to serve existing
and new load, corrected low voltages, increased operational flexibility, and greatly
enhanced feeder backup between the Gorge, Essex, and Ethan Allen substations. In
addition, the conversion enables us to defer the construction of a new 115-kV-to-
12.47-kV substation in the Susie Wilson Road area of Essex.
To address these aged facilities and improve reliability, we rebuilt the Graniteville
substation with new components that included a 7.5/10.5-MVA, 34.5-kV-to-12.47-kV
transformer, an oil containment system, and associated bus work and foundations
together with new distribution feeder circuit breakers, voltage regulators, security system,
and a control cabinet. This larger transformer enables quarry-area motors to start
without voltage flicker, and allows for future backup of the Websterville substation. We
also converted the 2.4-kV distribution line between the two substations to 12.47-kV to
supply Wetmore Morse loads from the rebuilt Graniteville substation. Wetmore Morse
substation was retired and the Wetmore load is now fed off the 61G1 (Websterville)
circuit. The new Graniteville 12kV circuits was able to pick up majority of the existing
61G1 circuit heading to Williamstown.
That line contained structures installed between 1938 and 1951 together with #2 ACSR,
and suffered from aging poles, crossarms, and insulators, all making the line vulnerable
during storms. Terms of the acquisition required CVPS to reconstruct the line by
2016—an obligation that we inherited.
As such, we rebuilt the subtransmission line by installing new poles, crossarms, and
insulators. While we reused the existing conductor, we redesigned the line to accept a
larger capacity 477 ACSR conductor in the future.
These upgrades not only improve reliability and enhance safety, but also enable growth
on the distribution system.
Replacing the substation and converting the area’s feeders enables the two area
substations to back up each other, lowers distribution line losses, accommodates new
loads, and enhances the accommodation of distributed generation installations.
standard 13.8-kV transmission supply from the National Grid Wilder substation hydro
generation bus, and limited feeder backup all contributed to this inadequacy.
We replaced and installed a new outdoor relaying cabinet including new SCADA and
communication equipment; a 25KVA station service transformer including steel pedestal
and concrete foundation; AC & DC distribution panels; a 48VDC battery bank with
charger; new insulators for all bus work, disconnects, and air breaks; and lightning
arresters for B-40 line termination, and upgraded the substation ground grid. All new
equipment is within the existing switching station fence. This equipment modernization
enables us to properly operate the substation, and improves its safety and reliability.
To add the new feeder, we rebuilt one-half mile of the existing 3309 transmission line
between the Gorge substation and the downtown Winooski redevelopment area,
upgrading the 3309 transmission conductor and installing the underbuilt 16Y3 feeder.
We also upgraded the Gorge substation with a circuit breaker, reactor, and voltage
regulators to accommodate the new feeder.
As a result of adding this new feeder, we improved reliability, created a full-time feeder
backup, enhanced the thermal performance of the 3309 transmission conductor,
replaced aged equipment, reduced line losses, enhanced area voltage performance
following certain contingencies, and deferred the need for another substation in the area.
Woodford Road Substation Upgrade and Pickett Hill Substation New Construction
Our Woodford Road substation used to include a 46-kV switching infrastructure and
one 12.5-MVA, 46-kV-to-12.47-kV transformer supplying two 12.47-kV distribution
feeders. Much of this equipment, however, was near the end of its useful life (so old in
most cases that replacement parts were no longer available). We upgraded some of this
equipment; and we retired some and replaced it with new equipment at our new Pickett
Hill substation. We built the Picket Hill substation near a new VELCO Bennington
substation to more easily connect to their transmission system.
As such, we plan to convert and rebuild the substation on a new larger site. We plan to
install a new 15/28-MVA, 34.5-kV-to-12.47-kV transformer; oil containment; three
12.47-kV distribution circuits; three 34.5-kV breakers (two for transmission and one for
transformer bank); and associated circuit breakers, voltage regulators, bus work,
foundations, fence, ground grid, security system, control cabinet, and switchgear.
The new substation would still be centrally located in Chittenden County, and allow for
the reconfiguration of existing circuit loads among the Gorge, Ethan Allen, Dorset
Street, Essex, and Tafts Corners substations. The upgrade would thus enhance feeder
backup in this area, extend the useful lives of the adjacent substations, address aging
infrastructure, and improve safety and reliability.
We have petitioned the Vermont Public Utilities Commission for a certificate of public
good (CPG), and expect to begin construction in 2019.
Once finished, this substation will be able to provide full feeder backup to the Barre
North End substation and partial feeder backup to the Graniteville and Websterville
substation.
VEC first identified this project in their most recent Integrated Resource Plan as a way
to manage assets and address safety issues. The Public Utilities Commission approved
the project in its order in Case No. 17-2675-PET dated September 26, 2017.
When completed, the new tap line will automatically sectionalize our B8 line. If a fault
occurs on one section of that line, this upgraded configuration will still allow energy to
flow to VEC’s substations while shutting off the faulted line. For line faults east of our
Cambridge substation, VEC’s Johnson substation would lose power; for line faults west
of our Cambridge substation, VEC’s Pleasant Valley substation and our Jeffersonville
substation would lose power. In both cases, however, VEC’s Cambridge and
This project reconductors the Bethel to East Barnard (Line 107) to 477 ACSR
conductor. This line is 6.3 miles long, however, we plan to reconductor only a small
portion of it (0.22 miles of 3/0 ACSR) because most of it is already thermally adequate
(4/0 ACSR). Accordingly, we plan to replace this 0.22 miles of 3/0 ACSR located at the
Bethel end of the line with 477 ACSR. This line is part of a 46-kV transmission loop in
the Middlebury, Windsor, and Chelsea areas.
We have obtained a CPG to rebuild this line with new structures and a larger 477 ACSR
conductor. This addresses the overloading and lower line losses, and remediates the
structural issues. We began construction in September, 2018.
We submitted this Rutland Reliability Plan to the Public Utility Commission in 2015.
Without reconductoring, the existing Florence to West Rutland line could not carry peak
demand. In addition, the Rutland area system substantially benefits from integrating
VMPD by effectively adding another 115/46-kV transformer to support the area’s
46-kV network (via Florence to West Rutland). This extra source improves area voltage
and reduces loading on the area’s other transformers, which could otherwise exceed their
ratings post-contingency. Substation upgrades are required at Marble Street and Lalor
Avenue to support this project. These upgrades will improve the connectivity and
reliability of the former VMPD system that serves our customers in Florence, Danby,
and Proctor. The project includes several components.
Upgrading the West Rutland Transmission Substation consists of adding two 46-kV
Vacuum Circuit Breakers transmission breakers (B-4 and B-5) to replace the two existing
1969-vintage OCBs (B-7 and B-56). These vintage breakers have proven troublesome,
experiencing many failures. We are also replacing the bus and line instrument transformers
(as they have reached their limit for useful life) and adding a new security system.
We will
Rebuilding the West Rutland to Marble Street (Line 39) Subtransmission Line.
rebuild approximately 0.56 miles of 46-kV transmission line from Marble Street
Substation to West Rutland Substation with 477 ACSR.
We will rebuild
Rebuilding the Marble Street to Proctor (Line 37) Subtransmission Line.
approximately 7.22 miles of 46-kV transmission line from the Florence Substation to the
Marble Street Substation with 477 ACSR.
Rebuilding the Evergreen Tap to West Rutland (L43) Subtransmission Line. We will rebuild
approximately 0.94 miles of 46-kV transmission line from Evergreen Tap to West
Rutland Substation (Line 43) with 477 MCM ACSR conductor. The larger conductor on
Line 43 allows this radial feed to become part of the looped transmission system in the
Rutland Area.
In the 248 process under Docket 8605, the need to upgrade this line was identified in the
VELCO Connecticut River Valley Project filing. The VELCO pre-filed testimony stated
“Related to these improvements, GMP will replace conductors for three 46 kV line
sections: the East Middlebury to Smead Road line (Project 143180 completed in 2016),
the Bethel to East Barnard line (Project 148615 FY2019), and the Windsor to Taftsville
line (Project 148614 FY2020).”
ISO-New England and VELCO studies determined that upgrading an existing 115 kV
line, supplemented with other component transmission and subtransmission upgrades,
would be the most cost-effective solution to mitigate the identified concerns. As such,
we plan to reconductor the Taftsville to Windsor (Line 105) to 795 ACSR conductor.
This line is part of a 46-kV transmission loop in the Middlebury, Windsor, and Chelsea
areas.
The rebuilt substation would be equipped with new transmission circuit breakers, two
capacitor banks, a new 15/28-MVA transformer, and three 12.47-kV feeders. The new
substation will permit full feeder backup to the Graniteville substation and partial feeder
backup to the Barre South End substation.
In October 2018, we filed for a certificate of public good with the Public Utilities
Commission. We intend to begin construction in spring 2019.
We plan to initially supply the Danby substation from the 46-kV Marble Street to Danby
Quarry subtransmission line, relieving capacity issues by providing a portion of the load
presently supplied by the Wallingford substation. The 12.47-kV distribution installed at
the Danby substation will supply the Danby Imperial Quarry, thus improving voltage
regulation at the quarry.
Next, we plan to build a new 46-kV tie line from the Dorset substation, forming a three-
way network that adds capacity to both the Danby and Wallingford substations (and
thus the surrounding area) while providing backup for the latter. The three-way network
also enhances area reliability by reconfiguring two relatively long and weak radial 46-kV
subtransmission lines, the Marble Street to Danby Quarry line and the Blissville to
Dorset line.
After this 46-kV tie line is built, we will be able to reconductor the Marble Street to
Danby line to 477 ACSR without interrupting service to Danby substation customers,
including the quarry. In addition, should it become necessary, we could build a new
46 kV tie line from the Bromley substation to either the Danby substation or the Dorset
substation to further increase network reliability in the area.
We plan to convert the Fair Haven and Hydeville substations from 46/4.16 kV to
46/12.47 kV with all new components including, at minimum. a top nameplate
10.5-MVA, 46-kV-to-12.47-kV transformer, oil containment system, and associated bus
work and foundations. Also included would be distribution feeder circuit breakers,
voltage regulators, security system, and a control cabinet. The larger transformer will
allow for feeder backup capability between these substations, for the Castleton
substation, and for potential future ties to the Carvers Falls and Poultney area
substations. Converting these substations to 12.47 kV will also reduce losses.
Our plan for the substation comprises a 28-MVA, 69-kV-to-12.47-kV transformer with
oil containment, a high-side circuit breaker, three distribution circuits with circuit
breakers and voltage regulation for each feeder, motor-operated load break switches, and
SCADA. The transmission supply will be from the 69-kV Searsburg-to-Dover
subtransmission line.
We initially intended to site the substation close to the load to reduce system losses, but
the adjacent land owner would not grant us access, thus the project is on hold until we
can find a suitable parcel of land.
After acquiring property for siting, the current plan is to install the NTA solution in
2023.
All told, the upgrade addresses aging infrastructure, improves system operation, corrects
deficiencies, and improves safety and reliability.
The 750 MCM copper underground cables, summer rated at 619 amps, do not fully
utilize the capacity of the 14-MVA transformer; the 350 MCM copper underground
cable getaways, summer rated at 384 amps, constrain the North Brattleboro substation’s
ability to backup area substation feeders.
To relieve these constraints, we plan to replace the current cables with 1,000 MCM
copper cables, and upgrade the existing 328-amp voltage regulators to 437-amp
regulators, which will allow for greater flexibility with circuit ties during planned outages
and contingencies. Overall, the upgrades will improve reliability and increase the
substation’s transfer capacity.
We plan to replace the three 12.5-kV vacuum circuit breakers. with new 12.5-kV ABB
RMAG circuit breakers, raise the existing steel to accommodate the new 12.5-kV circuit
breakers, and install steel adapters to mount the new 12.5-kV breakers on existing
foundations. In addition, we plan to install new conduit and control cables, add cameras
to the security system, install a new RTU, add line voltage transmitters to each
distribution circuit, and replace the existing electromechanical protection with new
microprocessor-based protective relays housed in a new outdoor relay cabinet.
Richmond Substation
The primary reason for completing this project is to improve reliability. The upgrades to
the substation would be comprised of adding two breakers, replacing an existing recloser
with a breaker associated relaying and control house. This will improve reliability to
customers served out of Richmond and Bolton.