Coil Type Boiler O&m Manual
Coil Type Boiler O&m Manual
To,
MERCURY SHIPS REPAIRS PVT. LTD.
T-10/3rd Floor, Rayhilsort Residency
Dr Pickle Road Karwar – 581301, Karnataka
Dear Sir,
Thanking you therefore in the meantime and assuring you of our best
services at all time.
Faithfully Yours,
For
PAR TECHNO-HEAT PVT. LTD.
(HIREN BELADIYA)
2|Page
INDEX
1. BASIC DATA..............................................................................................................................................4
2. DESIGN DATA...........................................................................................................................................5
3. BOUGHT OUT SPECIFICATIONS............................................................................................................6
3.1 BLOWER SPECIFICATION.....................................................................................................................6
3.2 BFW PUMP SPECIFICATION.................................................................................................................7
3.3 DIESEL PUMP SPECIFICATION............................................................................................................7
4. PREPARATION FOR COMMISSIONING OF COIL TYPE BOILER........................................................8
4.1 GENERAL INTRODUCTION............................................................................................................9
4.2 CHECK LIST BEFORE STARTING CTB UNIT................................................................................9
4.3 STARTING PROCESS (IN MANUAL MODE)...............................................................................10
4.4 STARTING PROCESS (IN AUTO MODE).....................................................................................11
4.5 PRE-COMMISSIONING PROCEDURE & CHECKS.......................................................................12
4.6 BRINGING CTB ON RANGE &WATER RAISING........................................................................12
4.7 RAISING TEMPERATURE.............................................................................................................13
4.8 SHUT DOWN PROCEDURE..........................................................................................................14
4.9 REASON FOR FLAME FAILURE...................................................................................................14
5. GENERAL OPERATING INSTRUCTION PERTINENT POINTS OF COMBUSTION ECONOMY AND
THERMAL EFFICIENCY..................................................................................................................................15
5.1 FURNACE MANAGEMENT............................................................................................................16
5.2 COMBUSTION................................................................................................................................16
5.3 FUEL BURNING EQUIPMENT AND COMBUSTION...................................................................16
6. MAINTANACE OF CTB...........................................................................................................................17
6.1 FOR DAILY MAINTENANCE CHECK............................................................................................18
6.2 FOR WEEKLY/MONTHLY MAINTENANCE WORK...................................................................18
6.3 FOR ANNUAL MAINTENANCE.....................................................................................................18
6.4 FOR ROUTINE MAINTENANCE...................................................................................................19
6.5 FOR PERIODICAL MAINTENANCE..............................................................................................19
7. PROCEDURE FOR LAYING UP CTB......................................................................................................21
7.1 DRY METHOD................................................................................................................................22
7.2 WET METHOD...............................................................................................................................22
3|Page
1. BASIC DATA
NAME OF PARTY : MERCURY SHIPS REPAIRS PVT LTD.
Faithfully Yours,
For
PAR TECHNO-HEAT PVT.LTD.
(HIREN BELADIYA)
4|Page
2. DESIGN DATA
1. CODE AND TYPE OF OILER : IBR 1950 & ITS LATEST AMMENDMENT
5. FUEL : DIESEL
5|Page
3. BOUGHT OUT SPECIFICATIONS
3.1 BLOWER SPECIFICATION
No
Detail FD FAN
.
4 OPERATING TEMPRATURE(°C) 30
6 MOTOR HP 3 HP
DRIVESIDE ANTICLOCKWISE
8 ORIENTATION
BOTTOM HORIZONTAL
6|Page
3.2 BFW PUMP SPECIFICATION
SN DETAIL PUMP
2 QTY 2 Nos.
3 CAPACITY 17 LPM
5 MOTOR HP 7.5 HP
SN DETAIL PUMP
2 QTY 1 Nos.
3 CAPACITY 300LPH
5 MOTOR HP 1 HP
7|Page
4. PREPARATION FOR
COMMISSIONING OF COIL TYPE
BOILER
8|Page
1. PREPARATION FOR COMMISSIONING STARTING OF
CTB
9|Page
Main outlet steam line to be connects with process.
A) Start feed water pump and make continuous flow at CTB outlet.
F) After receiving of flame (check by instrument & visual from burner glass).
Start secondary burner nozzle and open second level air damper.
G) Maintain pressure of steam by operating MSSV for Avoiding high pressure &
low feed water pressure tripping.
Note: If flame is not observed after starting pilot burner, do not try
continuously without making sufficient air purging to avoid back firing.
10 | P a g e
4.4 STARTING PROCESS (IN AUTO MODE)
11 | P a g e
4.5 PRE-COMMISSIONING PROCEDURE & CHECKS
A) Remove all foreign materials from the CTB such as scaffolding, unused bolts
and nuts, loose gaskets, planks rods etc... And close cover plates tightly.
C) Check for dummies in the lines or at the valves, remove them if they are placed
for hydraulic test.
D) Pass the stop valve and drain /blow down valves etc... Make sure they open
and close without strains.
E) See the dampers are in working order and check their positions are correctly
marked.
F) Check the fan bearing and grease them. See the bearing sleeves are tight and
locked. Make sure the directions of rotation of the fans are correct.
G) See the alignment of the V-belt and their tension .The belt should not be too
tight.
H) Inspect the fuel burning equipment. See that the Air Nozzles are fitted
properly and air passages are clear...
I) Close the FD fan inlet damper and start the fan. Open the damper and see the
electric load. Check the leakages on the ducting. Keep that fan shut.
J) CTB Feed Water pump - Remove the belt from pump with motor start the
motor and confirm the direction of rotation .Put belt to pump with motor.
Prime the pump. Rotate the pump by hand and satisfy the pump is free.
K) Open the air vent valve on the CTB. Start BFW pump and take feed water in the
coil. Do not use very hot water.
L) Open the drain valves and be sure that no air locks. Close the drain valves.
12 | P a g e
A) Raise Pressure gradually. Start FD fan and adjust the draft control the dampers
to get the required draft. Watch the fire conditions. Fire should be uniform
throughout the grate. When header pressure gauge indicates about 2.5
Kg/Cm2. close their vent. “Always maintain half gauge glass of water tank".
C) Keep the main feed water pump always ON, even when the system is not
in firing mode.
D) After satisfying that all the dirt’s are cleared from the CTB, raise the
temperature to working temperature.
Firing:
B) Though out the starting up period, the fire should be so regulated that temp of
the Coil tube metal should not exceed 400-degree C.
13 | P a g e
4.8 SHUT DOWN PROCEDURE
A) Stop Fuel Supply
B) Run Continuous Air Blower and Feed Water Pump Until Outlet Water Temp.
reach 50 to 60 0C
C) Then after close MSSV and Switch off all Blowers and Pumps.
- Set distance
B) During Operation
14 | P a g e
5. GENERAL OPERATING
INSTRUCTION PERTINENT
POINTS OF COMBUSTION
ECONOMY AND THERMAL
EFFICIENCY
15 | P a g e
5.1 FURNACE MANAGEMENT
Take care of the combustion. See the ignition of the fuel and sufficient air is
received in the right zone for combustion. “Watch the Chimney". "No black smoke
comes over from the chimney".
5.2 COMBUSTION
The efficiency of the CTB depends on the complete combustion of the fuel without
much excess air. The CO2 and O2 must be monitored and recorded. The CO 2 must be
12.5 to 14 percentages and O2 should not be more than 7 to 6 percent for this firing.
16 | P a g e
6. MAINTANACE OF CTB
17 | P a g e
6.1 FOR DAILY MAINTENANCE CHECK
A) Gauge Glasses of Water and fuel tank
B) Drain Valves.
D) Hydraulic Test of the CTB at 1.5 times of working Pressure after assembly of
the valves & mountings.
E) Greasing and over hauling of all the motor bearings, blowers, pumps etc.
18 | P a g e
6.4 FOR ROUTINE MAINTENANCE
A) Tighten the gland bolts of the valves after water raised in the coil.
B) Lubricate all the bearings, feed the bearing temp. Check for any abnormal
sound. Check the holding down bolts.
C) See the valve spindles are free from dust and operated freely. Check the valves
are not closed too tight. If they are too tight ease it back by one round.
Thermic fluid heater should be over hauled once in a year and the certificate to
be renewed.
Stop the CTB and allow to cool isolate the CTB from the range. Put dummy
between the stop valve and Water line. Remove the mountings. Open the header
caps. Arrange for tube cleaning. Use flexible shaft and cutter for cleaning inside
the tubes.
Make scaffolding inside the combustion chamber and clean the tubes externally.
Use flexible shaft and cutter for cleaning inside the tubes.
Use rough emery papers clean the chamber wherever approach is there. The
faraway tube surface can be cleaned by chains.
Over haul all the mountings. Lap the valve seats. Test all the valves hydraulically
once and half times of working pressure.
After the cleaning is completed request the CIB Inspector for dry inspection.
When the dry inspection is done prepare the CTB for hydraulic test.
19 | P a g e
Put blind on the mountings except air vent valve, feed check valve and blow down
valve. Fit back the feed line valve, feed check valve, air vent valve and blow down
valve. Keep air vent valve open. Take cold water through the coil. When water
rushes out from coil air vent, close the valve. Fill up the coil. Close air valve when
water comes out with force. Raise the pressure by hand pump to 1.5 times of the
working pressure. Check for leakages .Pressure should remain constant for ten
minutes. If the test is successful release the pressure slowly.
Empty out the coil. Open the end cover plate. After drying out the inside of the
combustion chamber, apply "Appexior" of ferrotol paint. Fit back the end plate.
Remove all the foreign materials from the combustion chamber.
20 | P a g e
7. PROCEDURE FOR LAYING UP
CTB
21 | P a g e
There are two methods of protection the water side of idle water heaters, the
choice of method is governed by the length of time the water is to be out of service
and how quickly the CTB may be required for service.
22 | P a g e
CTB is idle. Luck warm water promotes corrosion. For this reasons feed valves and all
water connections should be tight at all times.
If it is necessary for such an idle CTB to be returned to service, the CTB should be
heavily blow down during warming up, and before it is placed on the line, to re-
establish correct working level in tank and to reduce CTB water alkalinity to prevent
carry over.
In addition to protecting the integral or water side, of these heating surface in the
above recommended manner. It is desirable that the external, or gas side, tubes be
cleaned of soot and foreign deposit and heat the gas passages be thoroughly cleaned
and air dried. Trays of quick lime should be placed in the combustion chamber and in
the various case passages to absorb moistures. The dampers should be closed to
prevent air circulation. The quick lime should be examined and renewed at regular
intervals as it deteriorates through absorption of moisture.
23 | P a g e