Inventory 1
Inventory 1
Management
Inventory Management at
Amazon.com
Cycle time
95% 5%
Input Wait for Wait to Move Wait in queue Setup Run Output
inspection be moved time for operator time time
Figure 12.1
Managing Inventory
10 20 30 40 50 60 70 80 90 100
CYCLE
ITEM COUNTING NUMBER OF ITEMS
CLASS QUANTITY POLICY COUNTED PER DAY
A 500 Each month 500/20 = 25/day
B 1,750 Each quarter 1,750/60 = 29/day
on hand
(maximum
Q
inventory
level) 2
Minimum
inventory 0
Time
Minimizing Costs
Objective is to minimize total costs
Table 12.4(c)
Total cost of
holding and
setup (order)
Minimum
total cost
Annual cost
Holding cost
Order quantity
= (Holding cost per unit per year)
2
æQö
= ç ÷H
è2ø
Minimizing Costs D
Annual setup cost = S
Q
Q
Q = Number of pieces per order Annual holding cost = H
2
Q* = Optimal number of pieces per order (EOQ)
D = Annual demand in units for the inventory item
S = Setup or ordering cost for each order
H = Holding or carrying cost per unit per year
2DS
Q* =
H
2(1,000)(10)
Q =
*
= 40,000 = 200 units
0.50
An EOQ Example 4
Determine expected number of orders
D = 1,000 units Q* = 200 units
S = $10 per order
H = $.50 per unit per year
Expected Demand D
number of = N = =
orders Order quantity Q*
1,000
N= = 5 orders per year
200
An EOQ Example
Determine optimal time between orders
D = 1,000 units Q* = 200 units
S = $10 per order N = 5 orders/year
H = $.50 per unit per year
250
T= = 50 days between orders
5
An EOQ Example 5
Determine the total annual cost
D = 1,000 units Q* = 200 units
S = $10 per order N = 5 orders/year
H = $.50 per unit per year T = 50 days
D Q
TC = S + H
Q 2
1,000 200
= ($10) + ($.50)
200 2
= (5)($10) + (100)($.50)
= $50 + $50 = $100
The EOQ Model
When including actual cost of material P
D Q
TC = S + H + PD
Q 2
Robust Model
▶ The EOQ model is robust
▶ It works even if all parameters and
assumptions are not met
▶ The total cost curve is relatively flat in
the area of the EOQ
An EOQ Example 6
Determine optimal number of needles to order
D = 1,000 units 1,500 units Q*1,000 = 200 units
S = $10 per order T = 50 days
H = $.50 per unit per year Q*1,500 = 244.9 units
N= 5 orders/year
Ordering old Q* Ordering new Q*
D Q
TC = S+ H
Q 2 1,500 244.9
= ($10) + ($.50)
1,500 200 244.9 2
= ($10) + ($.50)
200 2 = 6.125($10) +122.45($.50)
= $75 + $50 = $125 = $61.25 + $61.22 = $122.47
An EOQ Example
Determine optimal number of needles to order
D = 1,000 units 1,500 units Q*1,000
Only=2% 200less
units
than
S = $10 per order the
T =total cost of
50 days
H = $.50 per unit per year $125
Q*1,500 whenunits
= 244.9 the
N= 5 orders/year order quantity was
200
Ordering old Q* Ordering new Q*
D Q
TC = S+ H
Q 2 1,500 244.9
= ($10) + ($.50)
1,500 200 244.9 2
= ($10) + ($.50)
200 2 = 6.125($10) +122.45($.50)
= $75 + $50 = $125 = $61.25 + $61.22 = $122.47
Reorder Points
▶ EOQ answers the “how much” question
▶ The reorder point (ROP) tells “when” to order
▶ Lead time (L) is the time between placing and
receiving an order
ROP = d x L
D
d=
Number of working days in a year
Reorder Point Curve
Figure 12.5
Q*
Stock is replenished as order arrives
Inventory level (units)
Slope = units/day = d
ROP
(units)
Time (days)
Lead time = L
Reorder Point Example 7
Demand = 8,000 iPhones per year
250 working day year
Lead time for orders is 3 working days, may take 4
D
d=
Number of working days in a year
= 8,000/250 = 32 units
ROP = d x L
= 32 units per day x 3 days = 96 units
= 32 units per day x 4 days = 128 units
Production Order Quantity Model
1. Used when inventory builds up over a
period of time after an order is placed
2. Used when units are produced and
sold simultaneously Figure 12.6
t Time
Production Order Quantity Model
Q = Number of units per order p = Daily production rate
H = Holding cost per unit per year d = Daily demand/usage rate
t = Length of the production run in days
= pt – dt
Production Order Quantity Model
Q = Number of units per order p = Daily production rate
H = Holding cost per unit per year d = Daily demand/usage rate
t = Length of the production run in days
= pt – dt
However, Q = total produced = pt ; thus t = Q/p
Maximum Q Q d
inventory level =p p –d p =Q 1– p
2DS
Q *p =
( )
H éë1- d p ùû
2(1,000)(10)
Q *p =
0.50éë1- (4 8)ùû
20,000
= = 80,000
0.50(1 2)
= 282.8 hubcaps, or 283 hubcaps
Production Order Quantity Model
Note:
D 1,000
d=4= =
Number of days the plant is in operation 250
2DS
Q =
*
p æ Annual demand rate ö
H ç1- ÷
è Annual production rate ø
Quantity Discount Models
▶ Reduced prices are often available when larger
quantities are purchased
▶ Trade-off is between reduced product cost and
increased holding cost
D Q
TC = S + IP + PD
Q 2
2DS
Q* =
IP
2(5,200)($200)
Q$96* = = 278 drones/order
(.28)($96)
Infeasible – calculate Q*
for next-higher price
2(5,200)($200)
Q$98* = = 275 drones/order
(.28)($98)
Feasible
Quantity Discount Example
TABLE 12.3 Total Cost Computations for Chris Beehner Electronics
ANNUAL ANNUAL ANNUAL
ORDER UNIT ORDERING HOLDING PRODUCT TOTAL ANNUAL
QUANTITY PRICE COST COST COST COST
275 $98 $3,782 $3,773 $509,600 $517,155
1,500 $96 $693 $20,160 $499,200 $520,053
TC for Discount 1
530,000 –
Not Feasible TC for Discount 2
520,053 –
517,155 –
Feasible
510,000 –
Not Feasible
Possible Order
500,000 – Quantities
120 1,500
Order Quantity
Quantity Discount Variations
▶ All-units discount is the most popular form
▶ Incremental quantity discounts apply only to
those units purchased beyond the price
break quantity
▶ Fixed fees may encourage larger purchases
▶ Aggregation over items or time
▶ Truckload discounts, buy-one-get-one-free
offers, one-time-only sales