Pfmea Format
Pfmea Format
KEY DATE
CORE TEAM
0
FMEA NO REV.NO
PREPARED BY
ACTION RESULTS
RESPONSIBILITY
ACTION
& TARGET COMP. SEV OCCR DETECT RPN
TAKEN
DT
0
Process FMEA Score Card
Very High Loss of primary function 100% production scrapped and/or manufacturing stopped 8
8
High: Frequent 20 per thousand pieces (2% Per 1000) Greater than or equal to 0.78
Failures
10 per thousand pieces (1% Per 1000) Greater than or equal to 0.86 7
6
5 per thousand pieces (0.5% Per 1000) Greater than or equal to 0.94
Moderate:
Occasional Failures 2 per thousand pieces (0.2% Per 1000) Greater than or equal to1.0 5
4
1 per thousand pieces (0.1% Per 1000) Greater than or equal to1.1
Low: Relatively Few 0.5 per thousand pieces (0.05% Per 1000) Greater than or equal to1.2 3
Failures
2
0.1 per thousand pieces (0.01% Per 1000) Greater than or equal to1.3
Remote: Failures is
Unlikely < 0.1 per thousand pieces Greater than or equal to1.67 1
Very Remote Controls will probably not detect Control is achieved with indirect or random checks only
9
Remote Controls have poor chance of detection Control is achieved with visual inspection only 8
Very Low Controls have poor chance of detection Control is achieved with double visual inspection only
7
Low Control may detect Control is achieved with charting methods, such as SPC 6
Very High Controls almost certain to detect Error detection in operation. Cannot pass defect on 2
Very High Controls certain to detect Defect cannot be made because of error proofing
1