SF 10 23
SF 10 23
IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all.
The effectiveness of the IMCA Safety Flash system depends on members sharing information and so avoiding repeat incidents.
Please consider adding [email protected] to your internal distribution list for safety alerts or manually submitting
information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.
The worker was refilling the sand pot with an abrasive material to continue sandblasting operations. After
confirming the air supply valve from the temporary air dryer to the sand pot was shut-in, the worker attempted to
disconnect the air supply valve (Figure 1 – Right Circle) from the air dryer. As he tried to access this coupling, he
loosened the T-connection. The T-connection blew off and broke the braided steel whip check or safety cable which
hit the worker causing injury.
IMCA store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.
IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or
recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory
or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.
© 2022 Page 1 of 6
• The bull hose configuration on the air inlet valve from the platform air compressor was installed in a horizontal
position. This added weight caused the T-connection to be off-centre at the time of operation, adding stress on
the associated couplings and baling wire. The added weight, combined with the worker’s force when
manipulating the air supply valve to the sand pot, resulAted in air escaping the inlet valve from the platform
compressor, likely causing the connection to come loose.
BSEE recommendations
• Ensure all risks and associated mitigations of this kind of task are fully understood;
• Install stainless steel tie wires in addition to whip checks on bull hoses to reduce the risk of disconnection;
• Install 90-degree fittings (see illustration) to eliminate the horizontal orientation of the supply hose, reducing
the stress at each connection;
• Where practical, depressurize equipment prior to adjusting valves;
• Inspect all equipment and parts pre-job to ensure they are in adequate condition.
Members may wish to refer to:
• Failure of a high pressure gas charging hose
• Air hose connection failure
Robust and stringent controls, restricting personnel from entering the drop zone, reduced the potential for harm.
These included hard barriers at deck level directly underneath the work area, and additional temporary barriers to
create a wider exclusion zone to take into consideration the dropped object cone of exposure. No personnel were
in the line of fire at the time of the incident.
Dropped bracket (Right) Intact manhole door raised, showing bracket in upright position.
The dropped object bracket was in similar position due to previous
unreported incident.
Learning
• Although the first incident was recorded within the pipelay team handover notes, there was a failure to formally
report it within the company incident reporting system - all damage incidents should be reported to ensure the
correct level of investigation, and so that corrective and preventative actions are identified and implemented;
• The equipment design and layout failed to identify the clash points created when manhole gates were left in
the open position.
Members may wish to refer to:
• Crane contact with pipelay tower resulting in dropped object
• Equipment on quay damaged when vessel started listing
Life Saving
Crew were involved in the second end transfer of a 4" (10cm) production
Rule(s)
flexible up to the top module of the pipelay system. As the second end was Energy
Line of Fire
being transferred, the tensioners were in the following position: upper Isolation
tensioner – open, lower tensioner - closed. To allow the weight to
be transferred onto the A&R wire the lower tensioners were
opened. This then resulted in the production flexible rotating due
to the residual torsion that had been built up within the line. A
16.5te chain used for the transfer of the second end was still
attached to the pull-in head, as the flexible pipe began to rotate,
this chain also spun. Two crew members who were observing the
operation were stood nearby and were almost struck by the
spinning chain.
During transit through heavy seas, a fridge tore loose from the messroom wall and fell on its side. The incident
occurred when the vessel was transiting out to the field and was experiencing 3-4m seas. During one large roll, a
tall fridge in the messroom came away from the bulkhead after its primary securing brackets were pulled out of the
bulkhead due to the motion of the vessel. The fridge swung on the last remaining fixing before falling on its side.
The fridge was secured to the deck with cargo straps and later returned to the upright position, inspected by the
ships electrician and secured to the bulkhead with alternative suitable fixings.