Subsea Engineering Sample Dissertation
Subsea Engineering Sample Dissertation
By
51657382
August 2017
EG59F9 – Individual Project in Subsea Engineering
ABSTRACT
One of the issues of the riser in the deep water field is high external pressure. It affects
the structural integrity of the riser, causing the collapse and buckling. Moreover, in the
deep water installation process, the riser will experience high tension and high bending
moment. To overcome these issues, a flexible riser is used. However, a flexible riser is
relatively expensive which is not preferable for some projects. Therefore, in this report,
the installability of a steel catenary riser (SCR) is analysed as an alternative to the flexible
riser. The material for SCR will be high-strength and ultra-high-strength material such as
X-80, X-90, X-100, or X-120 to obtain better structural integrity. The SCR diameter will
also be varied: 8 inch, 10 inch, 12 inch, 14 inch, and 16 inch.
The installation analysis will be performed in two fields in the Gulf of Mexico that
represents the metocean condition in the area. The first field is Stones which has a 2,914
meters water depth, and the second is Jack St. Malo, has a 2,134 meters water depth. The
installation method used is the J-lay method, the most common method for deep-water
installation, and the installation vessel used in this project is the Pathfinder vessel.
The Orcaflex 10.0 installation software will be applied in the analysis. The post-
processing analysis will be focused on the most critical section, which is the sagbend. The
feasibility will be confirmed regarding the load controlled combination (LCC) based on
the DNV-OS-F101 Submarine Pipeline Systems. Finally, the top tension of the SCR will
be assessed to confirm the feasibility of the Pathfinder vessel in this operation.
The result of the analysis is that SCR installation using the J-lay method and Pathfinder
vessel is applicable in both fields. However, there are some constraints in this operation,
such as the SCR maximum diameter, SCR minimum grade, and vessel heading.
Keywords: SCR, Installation; J-lay, Orcaflex, Gulf of Mexico, Stones, Jack St. Malo
I
EG59F9 – Individual Project in Subsea Engineering
ACKNOWLEGEMENTS
First of all, I am grateful to Allah SWT for his blessing for all this time.
This completion of this also not have been possible without the participation and
assistance of many people whose names may not all be enumerated. First, I am really
fortunate that, I have a very helpful supervisor, Dr. Antonis Karadimos from the
University of Aberdeen. Thank you for giving me the guidance and advice. Second, I
would also like to thanks to LPDP as my scholarship sponsor for providing me the
financial support for completing the MSc. Subsea Engineering.
Finally, I would like to thanks for my parents, Muhammad Ekotomo and Rini Ekotomo,
for all their prayers and motivation.
Nia
II
EG59F9 – Individual Project in Subsea Engineering
TABLE OF CONTENTS
ABSTRACT ...................................................................................................................... I
ACKNOWLEGEMENTS ................................................................................................ II
TABLE OF CONTENTS ............................................................................................... III
LIST OF TABLES ......................................................................................................... VI
LIST OF FIGURES ....................................................................................................... VII
LIST OF SYMBOLS AND NOTATIONS .................................................................... IX
ABBREVIATIONS ....................................................................................................... XII
CHAPTER ONE ............................................................................................................... 1
INTRODUCTION ................................................................................................ 1
1.1 Background .................................................................................................... 1
1.2 Aim and Objectives ........................................................................................ 2
1.3 Scope of the Work .......................................................................................... 3
1.4 Outline of the Report ...................................................................................... 3
CHAPTER TWO .............................................................................................................. 5
LITERATURE REVIEW ..................................................................................... 5
2.1 Material Development .................................................................................... 5
2.1.1 Development of High-Strength Steel ...................................................... 5
2.1.2 High-Strength Steel Standardisation ....................................................... 6
2.2 Steel Catenary Riser (SCR) ............................................................................ 8
2.2.1 Definition of SCR ................................................................................... 8
2.2.2 Basic Catenary Analysis ......................................................................... 9
2.2.3 Global Analysis ..................................................................................... 10
2.2.3.1 Top Tension ...........................................................................................11
2.2.3.2 Bending Moment ...................................................................................11
2.2.3.3 Strain ......................................................................................................11
2.2.3.4 Equivalent Stress ....................................................................................11
2.2.4 The Usage of Steel Catenary Risers in Deep-Water Environments ..... 12
2.2.4.1 SCR Installation Method in a Deep-Water Environment ......................12
2.2.4.2 SCR Sizing due to The Collapse and Buckling .....................................14
2.3 Airy and JONSWAP Waves ........................................................................ 15
2.4 Gulf of Mexico Fields .................................................................................. 16
2.4.1 Stones Field........................................................................................... 16
III
EG59F9 – Individual Project in Subsea Engineering
IV
EG59F9 – Individual Project in Subsea Engineering
V
EG59F9 – Individual Project in Subsea Engineering
LIST OF TABLES
VI
EG59F9 – Individual Project in Subsea Engineering
LIST OF FIGURES
VIII
EG59F9 – Individual Project in Subsea Engineering
Latin Characters
IX
EG59F9 – Individual Project in Subsea Engineering
V Vanadium
Riser apparent weight
Internal fluid weight
External fluid weight
Riser weight in the air
x Riser horizontal length
A particular length of a riser in vertical position
Greek Characters
XI
EG59F9 – Individual Project in Subsea Engineering
ABBREVIATIONS
XII
EG59F9 – Individual Project in Subsea Engineering
CHAPTER ONE
INTRODUCTION
1.1 Background
The riser is one of the main facilities in the oil and gas industry, especially in subsea
technology. To transport the production fluid, it connects the facilities located on the
seabed to the host facility on the sea surface. Nowadays, deep-water field development
has recently focused on the use of flexible risers because of its versatility. However,
flexibles tend to have high cost compared to the SCR, which is not convenient for the low
oil price climate of the past several of years.
The project will focus on SCR installation in the ultra-deep water case in the Gulf of
Mexico. Two fields that will be assessed in this report. First is Stones, the deepest field
in the Gulf of Mexico. It has a 2,914 m water depth, and it is located 322 km from south
of New Orleans [1]. Currently, Stones is using steel lazy wave risers (SLWR), which are
tied back to the FPSO. This project is still developing, with the next phase covering six
wells and a future artificial lift system [1]. The second field is Jack St. Malo, located 450
km southwest of New Orleans [2]. It has a 2,134 m water depth and is the largest field in
the Gulf of Mexico [2]. As a host facility, a floating semi-submersible with the top side
is used by Jack St. Malo. To connect host facility to the other facility on the seabed, an
SCR with buoyancy was installed [2]. Both projects experience high waves, high current
and high external pressure. Therefore, these projects need risers with a specific
requirement and installation method. For deep water, the SCR wall thickness should be
increased. However, with increasing the wall thickness, the tension and the bending
moment also will also increase. Therefore, these considerations need to be analysed.
The analysis will focus on the SCR installation using the J-lay method and Pathfinder as
the installation vessel in an empty condition. It is also incorporated with the wall thickness
calculation and the material grade selection for the SCR. The wall thickness calculation
is developed according to the DNV-OS-F101 and will include the local buckling and
1
EG59F9 – Individual Project in Subsea Engineering
vertical stability analysis. Moreover, the material grade selection will be based on the
LCC check, also according to DNV-OS-F101.
Orcaflex 10.0 will be used as the finite element installation software. The analysis
includes the static and dynamic condition with realistic and extreme load cases. In the
static analysis, the model will reach equilibrium in a static condition. It includes the
weight of the system and the initial vessel position. The result of the static analysis is the
initial condition for the dynamic condition. The dynamic analysis will include the effect
of the waves on the SCR during the installation process. There are two types of waves in
this analysis; the first is the Airy wave as the regular waves and the second is the
JONSWAP wave as irregular waves. Regular waves have the same wave height and
period, whereas irregular waves are shaped as a spectrum with different waves and
periods. The purpose of the dynamic analysis is to determine the actual behaviour of the
SCR while it is being installed.
Finally, the recommendations include the required material grade for each field. They
also provide the maximum diameter that is feasible to be installed in the Gulf of Mexico
and a vessel heading position recommendation while the SCR is being installed.
1. To analyse the feasibility of installing SCRs with 8 inch, 10 inch, 12 inch, 14 inch,
and 16 inch nominal diameters using X-80, X-90, X-100 and X-120 as the material
grade in a deep-water field;
2. To analyse the feasibility of the J-lay installation method in the Gulf of Mexico;
3. To analyse the Pathfinder vessel’s feasibility in the SCR deep-water installation
operations due to its motion and tensioner capacity;
4. To analyse the fabrication requirement of the SCR in deep-water applications;
5. To determine the vessel heading direction to avoid excessive stress during the
installation process.
2
EG59F9 – Individual Project in Subsea Engineering
1. The environmental conditions are taken from real projects in the Gulf of Mexico:
Stones and Jack St. Malo;
2. The SCR wall thickness is reviewed based on the buckling, vertical stability, and
allowable diameter-thickness ratio in the DNV-OS-F101;
3. The simulation is done in Orcaflex 10.0 as the installation software to provide the
static and dynamic analysis;
4. The wave type for the dynamic analysis includes Airy as the regular waves and
JONSWAP as the irregular waves;
5. The SCR is installed only in an empty condition;
6. The analysis focuses on the critical section of the SCR, and several identifications
are done to review the SCR regarding the stress, strain, and LCC check.
3
EG59F9 – Individual Project in Subsea Engineering
4
EG59F9 – Individual Project in Subsea Engineering
CHAPTER TWO
LITERATURE REVIEW
5
EG59F9 – Individual Project in Subsea Engineering
Table 2.2 shows that not only the yield and tensile strength increase along with the
material grade but also the yield ratio. A higher yield ratio will decrease the deformability
and the elongation of the pipe [4]. This issue can be a problem when these materials are
brought into a real project, especially when the field has a harsh environment such as an
earthquake prone area. Hence, it is important to reassess and improve the mechanical
properties of the material for some cases to ensure the safety of the pipe.
The X-80 material grade has been used in various projects since the eighties [5]. The first
project was the Megal II project in 1984, which produced a 44 inch diameter, 13.6 mm
6
EG59F9 – Individual Project in Subsea Engineering
thickness pipe geometry with 603 MPa and 737 MPa yield and tensile strength,
respectively [3]. Afterward, with some improvements, such as the use of manganese-
niobium-titanium steel without adding copper and nickel, a 56 inch diameter, 15.6 mm
thickness steel pipe was produced for the CSSR project. In 1992, a thicker X-80 grade
was produced for the Ruhrgas Pipeline Project in Germany with a 250 km length. It had
a 48 inch diameter with 18.3 mm thickness. Moreover, One of the latest projects was BG
Transco in the United Kingdom and it was in 2000 [3]. From these projects, it can be
concluded that the X-80 material grade is not categorised as new technology in the oil
and gas industry since it has been used for more than 30 years.
The utilisation of the higher-grade steel can reduce material usage by around 7%-8% and
costs by around 3%-5% [6]. Hence, the China National Petroleum Corporation has
conducted research on the X-90 material grade and successfully built the trial production
of X-90 pipes with 1,219 mm diameter that can be used for the eastern route of the Russia-
China Gas Pipeline [7].
The X-100 pipe fabrication has already met the requirements of the properties of UOE
pipe; therefore, this type started to be commonly used in 2002 [4]. One of the fields that
used the X-100 material grade is located in Northern Canada and was laid in winter 2004
[4].
In contrast to the lower grades, X-120 is still under research [5]. The main difference
between X-120 and X-100 is the composition of the bainite. In X-100, the lower bainite
is used while the higher bainite is used for X-120 to increase the material strength [4].
Occasionally, the manufacturer also adds some boron to increase the strength of the base
metal. It is important to remember that the increased strength will reduce the material’s
ability to elongate and deform; hence, to improve the material condition, the cooling
condition also needs to be improved during the accelerated cooling process [4].
7
EG59F9 – Individual Project in Subsea Engineering
One of the key steps in designing an SCR is conducting a global performance analysis to
understand the effect of the waves, wind, current, and vessel motions. This analysis is
done by simulating the SCR using the time or frequency domain, and the results are
compared with the standards. It is important to ensure that the result is below the
maximum allowable value from the standard. There are a few of standards that need to
be fulfilled. First is the DNV-OS-F101, which gives the allowable limits for collapse,
buckling, and combination load. Second is DNV-RP-F109 for the on-bottom stability of
8
EG59F9 – Individual Project in Subsea Engineering
the SCR when it is lying on the seabed, and finally the API RP 1111 for hoop and burst
strength [8].
Basically, SCR analysis depends on environmental conditions, such as the current, waves,
and vessel motions, but there are some critical parts that must be focussed on. The first
critical part of the analysis is the hang-off section. At the hang-off section, the tension is
relatively high and causes the highest von-Misses stress [8]. If the tension is high, a vessel
with high tensioner capacity is needed. This consequence causes high operational cost;
therefore, in some projects, a buoyancy module is employed to reduce the tension at the
hang-off section.
The second critical part is the sagbend section near the touchdown [8]. In this section, the
compression and bending moment are relatively high, thus it is prone to buckling and
collapse as the failure mode. The condition is worse when the riser is empty and the
environment has high waves, high current, or hurricanes. To conquer the issue, a larger
vessel displacement is needed, and the SCR must be located close to the vessel’s centre
of gravity. The other solution that can be used is a higher material grade. Using a higher
material grade will not reduce the compression or the bending moment, but it will increase
the maximum allowable stress of the SCR. In addition, using thicker riser will not
necessarily reduce the tension and bending moment. Otherwise, it will increase the load
caused by the submerged weight, even though the stress will be reduced because of the
larger cross section.
catenary length (s), hang-off angle (θ) and vertical distance (y). The apparent weight is
the total catenary weight in the water which are followed by the equations 1, 2, 3, and 4 :
= + + , (1)
= .( − ). . , (2)
= . . . , (3)
= . . . . (4)
The total catenary length is measured from the top point to the touchdown point, whereas
the hang-off angle is the angle between the catenary’s slope and the horizontal line. Thus,
the basic catenary equation forms the shape of the catenary, which is affected by the
weight, as shown in equation 5,
. (5)
= cosh −1 .
From the above equation, the horizontal length of the catenary can be known; therefore,
the total length and the top tension can be obtained by using equations 6 and 7;
. (6)
= . sinh ,
. (7)
= . cosh .
In addition, the top tension can be described using the relationship between touchdown
tension and the hang-off angle, as shown in equation 8,
= . (8)
10
EG59F9 – Individual Project in Subsea Engineering
2.2.3.3 Strain
The sagbend section has the greatest bending shape among the other sections. This section
will have a higher strain value, which can lead to fracture failure. In the DNV-OS-F101,
it is mentioned that the strain limit is 0.4% due to the initial fracture [12].
(9)
= . − + − + − .
√
11
EG59F9 – Individual Project in Subsea Engineering
The Von Misses equation is the combination of the axial stresses as the tension, hoop
stress, which happen at the bending section, and radial stress. The equations are shown in
equations 10, 11, and 12, respectively.
( . . ) (10)
=− ,
(11)
=( − ). − ,
2
(12)
= + ( − ).
2
Finally, the maximum allowable limit is obtained by multiplying the equivalent stress by
the design case factor.
The analysis must incorporate the riser sizing, material selection, installation method and
fatigue. In addition, the analysis has to follow codes as a recommended practice, including
API 2RD, DNV-OS-F101, and DNV-RP-F109. These standards have approximately 80%
of the yield strength for the design criteria and 100% for the abnormal condition that
needs to be satisfied in the analysis.
Figure 2.5 - S-Lay (Left) and J-Lay Installation Method (Right) [14]
12
EG59F9 – Individual Project in Subsea Engineering
The installation method that is usually used in deep-water applications is the laying
method. There are two types of laying methods, S-lay and J-lay, as shown in Figure 2.5.
The S-lay method is commonly used in mid-water depth areas such as the North Sea
which has around 300 m water depth [15]. It can install from 6 inch riser diameter up to
60 inch while the reeling method can have only up to 18 inch diameter with limited length
due to the carousel capacity [15]. For deeper-water riser installation, a steeper lay angle
of around 90 degrees is required to change the hang-off angle [16]. To achieve a steeper
lay angle, a higher tensioner capacity is needed. A high tensioner also keeps the curvature
of the riser from bending excessively [16]. The overbend section will experience a higher
strain; thus, it is important to have a displacement control check to ensure the riser
integrity. Moreover, the riser curvature is the main factor in deep-water installation;
hence, the stinger needs to be longer and follow the curvature needed. Otherwise, the riser
will bend excessively at the end of the stinger.
In deeper water, the elasticity of the catenary will have a significant effect caused by
waves and vessel movement [16]. Compared to the S-lay method, the J-lay method is
more suitable for deeper-water riser installation because of the elimination of the
overbend section. The J-lay method is also commonly used in the Gulf of Mexico area
[15].
Instead of having an extreme overbend section, the J-lay method uses a vertical tower that
has a one or a maximum of two welding stations; thus, the riser will have a 90-degree
departure angle. Limited welding stations are one of the reasons that this method has a
low lay rate in installation operations.
The operation begins with positioning the riser on the erector arm. After that, the erector
arm will bring the riser stalked up and move it to the tower using the elevator. The
following procedure is to weld the riser at the welding station to the previous riser;
subsequently, the elevator will operate the lay process to install the riser. The length of
the riser is limited to the stalk capacity [15]. The longer the riser is, the bigger the stalk
must be. On the other hand, a bigger stalk will affect the barge or vessel stability.
From structural integrity point of view, this method is better than the S-lay method
because it will have a bending moment only at the sagbend and there is no overbend
section. Hence, the tension at the riser will be reduced. In addition, the stinger will not be
13
EG59F9 – Individual Project in Subsea Engineering
needed, since the riser will enter the sea-water vertically. The vertical shape is also
beneficial for the touchdown of the riser since it will reach the seabed more precisely.
For the J-lay method, the most critical part is the touchdown point; it usually has the
highest bending moment and axial stress, and thus at that point it is necessary to do the
LCC check. The LCC check is a buckling analysis caused by the combination load, such
as external pressure, axial load, and bending moment. The hang-off sections also have
high tension, which determines the tensioner capacity. The tension of the hang-off section
depends on the riser size and the water depth. A bigger the riser or a deeper sea will
increase the tension on the hang-off section. Thus, it is important to review the best hang-
off angle for the riser during the operation. In addition, for the angle itself, it can be
arranged by setting up the tower inclination at the vessel.
Several big companies have already done some analysis of SCR installation operations in
deep water. First, McDermott analysed the Mars project in the Gulf of Mexico, which has
a water depth of almost 1000 m [13]. They used a Derrick Barge to do the riser
installation, and the analysis result showed that the J-lay method is feasible for this case
with fast cycle times because of the short water window and the vessel motion. To get
shorter cycle times, a multi-station vessel might be one of the solutions, for example the
Scarabeo vessel, owned by Saipem.
To prevent these failure modes, it is important to have sufficient wall thickness. Several
engineering standards mention the wall thickness requirement due to the riser buckling
and collapse. One of the standards is DNV-RP-F101. It gives the empirical method and
formula to calculate the critical pressure that later will be used in calculating the minimum
14
EG59F9 – Individual Project in Subsea Engineering
wall thickness required. These formulas also incorporate the effect of material properties,
bending, tension and the environmental load [17].
In the irregular wave, to get the fully developed sea, the wind must blow to achieve a
certain distance, called the fetch. The method that covers the fully developed sea is the
Pierson-Moskowitz Spectrum, which takes data from the deep water in the North Atlantic
sea [18]. It has unlimited fetch, and there is no swell. In fact, not all sea conditions are a
fully developed sea, such as, the condition when the wave is limited by the distance from
the shore or a production facility.
15
EG59F9 – Individual Project in Subsea Engineering
is built from the nonlinear wave interaction and from an empirical equation; an extra peak
enhancement factor is multiplied by the Pierson-Moskowitz spectrum, equation as shown
in Figure 2.6 [18] [19].
This report will discuss two fields in the Gulf of Mexico that are taken as the case of SCR
installation, Stones and Jack St. Malo. Both projects are categorized as ultra-deep water
projects. They have a 2,914 m and 2,134 m water depth respectively [21] [2].
Furthermore, Figure 2.7 shows the location of the Stones and Jack St. Malo fields, these
projects are located in the same block, called the Walker Ridge area.
Figure 2.8 - Steel Catenary Riser and Steel Lazy Waves Riser Comparison [25]
The Stones field uses a floating production storage and offloading (FPSO) vessel as the
host facility. This host facility is equipped with turret moored with a disconnectable buoy
that can be released and moved. The purpose of the disconnectable buoy is to avoid
hurricane events in particular areas [21]. For the risers, the Stones project uses 8 inch wet
insulated steel lazy wave risers (SLWR) that connect to the eight production manifolds
[21]. The difference between SCR and SLWR is that SLWR has buoyancy between the
sagbend section and the touchdown point, as shown in Figure 2.8 - Steel Catenary Riser
and Steel Lazy Waves Riser Comparison. The buoyancy can reduce the effect of the
FPSO motion and increase the fatigue life of the riser. From the economic point of view,
SLWR is more costly compare to the SCR, and it increases the complexity of the
installation.
The metocean condition is accounted as the extreme cases, therefore it is important set
the installation schedule correctly in time. According to the metocean data, high waves
happen in August, September, and October, which have 47.5 meter waves as the highest.
In contrast, the lowest waves happen around April, May, and June with 1.44 meters as
the lowest height [26]. Thus, it is recommended to do the installation during these months.
The highest current is from north-east and east directions at the depth around 47 m from
the sea surface. It is around 1.7 knots or 0.874 m/s [26].
This project is one of the most challenging projects in the Gulf of Mexico. First, it has the
deepest depth among the projects in this area. Second, it has an extreme metocean
condition. To face these challenges, significant riser design and installation are needed.
17
EG59F9 – Individual Project in Subsea Engineering
Malo project. These projects are accounted as deep-water project with around a 2,134 m
water depth.
Chevron has the biggest ownership share of Jack and St. Malo. In the Jack project,
Chevron owns 50%, while Maersk and Statoil own 25% each. Similarly, in the St. Malo
project, Chevron owns 51%, and the rest of the project is owned by Petrobras (25%),
Statoil (21.5%), ExxonMobil (1.25%), and ENI (1.25%) [27].
The first field discovered was St. Malo. It was found in October 2003, followed by Jack
in July 2004. In October 2010, the FEED of both projects was approved and fabrication
started. In March 2014, the production facility’s hull was moored and the topside
installed. Finally, in December 2014, Jack St. Malo had its first oil production [2]. [27]
There are two phases in Jack St. Malo. The first phase is four production wells at Jack,
and five at St. Malo which in 2016 produced 75,000 barrels of oil. The second phase’s
FEED was finished in October 2015. This phase has four additional wells, two in the Jack
field and two in the St. Malo field. The first oil for the second phase is expected in 2017
[2].
Instead of using FPSO, Jack St. Malo uses a floating semi-submersible with a 33,000 ton
topside as the host facility. It is tied back to the facility on the seabed [27]. As the
production line, SCR is used in the project. To minimize the effect of the wave and
current, the SCR is equipped with a buoyancy module. The SCR was fabricated at the
Technip Spoolbase in Theodore, Alabama [2]. For a deep-water project, the usage of SCR
needs to be analysed properly, because the external pressure will have a significant effect
on the structure itself. In the installing operation, specific equipment such as a big, stable
vessel is often needed. For this project, they used a brand new Saipem’s vessel which at
that time was the biggest installation vessel [2].
Compared with the Stones project, Jack St.Malo has a lower wave height throught-out
the year. The yearly wave height is around 3.44 meters, and the current speed is slightly
higher, around 1.38 m/s as the highest [28].
18
EG59F9 – Individual Project in Subsea Engineering
CHAPTER THREE
= . . . (13)
19
EG59F9 – Individual Project in Subsea Engineering
the wave height variation every month. Especially for the installation, the project schedule
needs to take into account the suitable month because of the wave and current conditions.
Finally, the environmental load will affect the total dynamic load in the system.
= . . + . + . . + . . . (14)
= . . + . , (15)
= . . + . , (16)
= . . + . . (17)
20
EG59F9 – Individual Project in Subsea Engineering
− (18)
= .
Ovality values vary depending on the fabrication process. The normal range is from 0-
0.6%, but based on the DNV-OS-F101, it is not allowed to taking account or advantage
in the calculation with the ovality less than 0.5% [29] [12]. In this report, the value is
taken from the SCR reeling and J-lay installation in Roncador field as the conservative
value, which is around 0.9% due to the residual stress [29]. In addition, if the ovality ratio
exceeds 3%, it is considered as an unstable factor and needs additional analysis.
21
EG59F9 – Individual Project in Subsea Engineering
SMYS SMTS
API Grade
MPa ksi MPa ksi
X-80 555 70300 625 90600
X-90 625 80500 695 100800
X-100 690 90600 760 110200
X-120 830 100100 915 312700
In the calculation the value used are and values, which follow the equations below,
= − , . , (19)
= − , . . (20)
, and , are temperature derating values for yield and ultimate stress which is
determined by the operation temperature if the operation temperature for C-Mn steel and
13Cr is above 50 degrees Celcius. In this operation, the highest temperature is 11.15
degrees Celsius, so these factors equal zero. Furthermore, since the installation is
considered a normal case, equals 0.96.
Every fabrication method will have a different effect on the material strength. If the
manufacturer does not mention the factor, the value from a standard will be used. Some
fabrication methods and factors are mentioned in the DNV-OS-F101, such as seamless,
UOE, and ERW. Seamless welded is typically used only for smaller tubular structure up
to 16 inch [31]. This structure is formed as a round billet by continuous casting. After
that, the billets go through the Mannesmann process. The other processes are categorised
as the seam welded method. First, the UOE method is done by pressing the steel plate
into U-shape, then to the O-shape, and then welded. Finally, to minimise the ovality, the
structure expanded circumferentially [32] . This method is used typically in bigger riser,
which is 16-64 inches. The ERW method is the most efficient because there are fewer
steps in the process [31]. ERW starts by forming the steel plate into a closed circular
shape and then seam welding the connection using the heat induction process. This
method can be used for the riser with a diameter range from 2.375 to 24 inches [31]. In
this report, the fabrication factors used are 1 as the seamless method and 0.93 as the ERW
method.
22
EG59F9 – Individual Project in Subsea Engineering
( ) (21)
− ≤
.
From equation 21, equals zero since the riser is lying on the seabed empty. The
collapse pressure can be found from equation 22,
(22)
( )− ( ) . ( ) − ( ) = ( ). ( ). ( ). . ,
where :
. . (23)
( )= ,
2. (24)
( )= . . ,
= − , (25)
=− ( ), (26)
(27)
=− ( ) + ( ). ( ). . ,
= ( ). ( ) , (28)
1 1 (29)
= − + ,
3 3
1 2 1 (30)
= − + ,
2 27 3
23
EG59F9 – Individual Project in Subsea Engineering
= cos , (31)
√
60 (32)
= −2√− . cos + .
3 180
− ≤ , (33)
.
where,
. (34)
= 35. . . ,
However, besides using thicker wall thickness, the propagation buckling can be avoided
by using the buckling arrestor.
. ≤ 1.00, (36)
= . . . . (37)
In the equation, is the safety factor, which per the recommended practice equals 1.1 if
there is no specific information from the project.
24
EG59F9 – Individual Project in Subsea Engineering
is the most critical part of the J-lay method because of the high bending moment, so the
LCC check will be done in this specific area.
LCC incorporates the bending moment and axial stress during the dynamic analysis. The
external pressure is also accounted for. These values are compared to the material strength
depending on the material grade used as the riser material. The LCC check creation needs
to fulfil equation 38 for safe operation,
| | . . −
. . + + . . ≤ 1.
. ( ) . ( ) ( ) (38)
where,
( )= . . ( − ). , (39)
( )= . .( − ) . , (40)
= (1 − ) + . , (41)
1− <
= ,
1−3 1− ≥ (42)
(43)
= .
25
EG59F9 – Individual Project in Subsea Engineering
26
EG59F9 – Individual Project in Subsea Engineering
CHAPTER FOUR
The analysis in this report used Orcaflex version 10.0 to simulate the behaviour of the
riser in the installation process, including the static and dynamic analysis. Orcaflex is
software for marine systems that has been used in many offshore engineering business.
The static analysis result shows the equilibrium condition of the system, which is the
starting point for the dynamic analysis. Furthermore, from the dynamic analysis, the
values for top tension, bending moment, and strain during the installation can be
determined. These values later will be the input for the limitation criteria equation to
determine the feasibility of the riser installation.
4.1 Input
To model the riser installation system, several inputs need to be added to the software.
The inputs include the SCR properties, environmental or metocean data for the Stones
and Jack St. Malo projects, and the vessel motion data.
27
EG59F9 – Individual Project in Subsea Engineering
4.1.2.3 Waves
Because of the water depth, the wave type is Airy for the regular waves and JONSWAP
for the irregular waves. The wave input is the maximum wave height from each direction,
measured from the individual trough to crest height. Additionally, some metocean data
give the significant wave height instead of the maximum wave height. In this case,
according to DNV-RP-H103, the significant wave height needs to be multiplied by 1.89
as a factor that depends on the peak shape parameter in the JONSWAP spectrum [34].
Table 4.2 shows the data on wave height and period from the Stones field. The data are
from one specific month that has the lowest wave height among other months. May, as
the month with the lowest wave height, will be the recommended month for installing the
riser. In contrast, the wave data for Jack St. Malo are shown in Table 4.3. The data are
taken from the average one-year wave height since the waves are relatively calm
throughout the year.
28
EG59F9 – Individual Project in Subsea Engineering
Stones
May
Direction to Wave Name
Parameter
Hs (m) Hmax (m) Tp(s)
North (N) Wave-N 2.29 4.32 8
North East (NE) Wave-NE 2.29 4.32 8
East ( E) Wave-E 2.29 4.32 8
South East (SE) Wave-SE 3.81 7.2 9
South (S) Wave-SE 3.81 7.2 9
South West (SW) Wave-SW 0.76 1.44 6
West (W) Wave-W 0.76 1.44 6
North West (NW) Wave-NW 2.29 4.32 8
4.1.2.4 Currents
For the installation study, the one-year return period current is suitable for the analysis.
However, the velocity still should represent the vertical profile of the extreme velocity,
since as the sea gets deeper the velocity will get lower. The current data for Stones and
Jack St. Malo are shown in the Table 4.4 and Table 4.5, respectively.
29
EG59F9 – Individual Project in Subsea Engineering
31
EG59F9 – Individual Project in Subsea Engineering
drive. Moreover, the winch has a 10 m specified length and 100,000 kN stiffness of the
winch wire. Third, the tower and the riser are modelled as line in flexible linear elements
with steel material properties. The difference between the tower and the riser besides the
geometry is the line type and the connection for each line end point. The tower is modelled
as the general line type; both line points are connected to the vessel. Furthermore, the
riser is modelled as a homogeneous pipe such that one end of the line is anchored to the
seabed and the other end is connected to the winch but still free moving.
The contact between the riser and the tower assumes that the riser is located inside the
tower and the tower acts as a tensioner that holds the riser. In addition, the riser hang-off
angle depends on the tower inclination, which needs to be configured. The overall model
can be seen in Figure 4.4.
33
EG59F9 – Individual Project in Subsea Engineering
4.3.1 Loadcase
34
EG59F9 – Individual Project in Subsea Engineering
35
EG59F9 – Individual Project in Subsea Engineering
CHAPTER FIVE
STONES
M I N I M U M WA L L T H I C K N E S S
18.27 mm
16 inch 18.71 mm
19.09 mm
19.77 mm
15.99 mm
14 inch 16.37 mm
16.70 mm
17.30 mm
14.56 mm
12 inch 14.91 mm
15.21 mm
15.76 mm X120
12.27 mm
12.57 mm X100
10 inch 12.82 mm
13.28 mm
X90
9.85 mm
8 inch 10.09 mm
10.29 mm
10.66 mm X80
J A C K S T. M A L O
M I N I M U M WA L L T H I C K N E S S
16.31 mm
16 inch 16.57 mm
16.76 mm
17.09 mm
14.27 mm
14 inch 14.49 mm
14.67 mm
14.96 mm
13.00 mm
12 inch 13.20 mm
13.36 mm
13.62 mm
X120
10.96 mm
11.13 mm X100
10 inch 11.26 mm
11.48 mm
8.79 mm
X90
8 inch 8.93 mm
9.04 mm
9.21 mm X80
This condition will have a big effect on the cost, especially when a very long SCR is
required.
1
0.9 Jack St. Malo
0.8 Stones
0.7
8 inch 10 inch 12 inch 14 inch 16 inch Allowable Limit
Diameter
The maximum allowed wall thickness depends on the diameter and thickness ratio for the
LCC check, which is 15 ≤ ≤ 45 [12]. Therefore, the maximum wall thickness
equals the diameter divided by 15, as shown in Figure 5.4
M A X I M U M WA L L T H I C K N E S S
16 inch 27.09 mm
14 inch 23.71 mm
12 inch 21.59 mm
10 inch 18.20 mm
8 inch 14.61 mm
37
EG59F9 – Individual Project in Subsea Engineering
The post-processing analysis begins with the regular wave analysis results, which are
more conservative compared to the irregular wave analysis. It uses the ERW fabrication
method and 0.015 for the ovality for all the material grades and cases. After that, if in one
particular grade there are some cases that have more than one for the stress utilisation,
those cases will be analysed in irregular waves and with the ERW fabrication method and
0.015 ovality. Finally, if the results from the irregular wave analysis still exceed the
maximum stress utilisation allowed, the fabrication method will be changed to the
seamless and take 0.01 as the ovality. A material grade is taken as feasible when it has
less than one as the stress utilisation.
3,099 kN
3000 10 inch
2,216 kN
12 inch
2000
1,077 kN 14 inch
1000
16 inch
0
MATERIAL GRADE
38
EG59F9 – Individual Project in Subsea Engineering
Figure 5.6 shows the maximum bending strain in the SCR. Based on DNV-OS-F101, the
strain has to be less than 0.4. In the Stones field, the highest strain is 0.31, which occurs
at the sagbend section. Hence, the strains in the Stones field in all cases are below the
limit.
0.3 10 inch
0.25
12 inch
0.2
0.15 14 inch
0.1 16 inch
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
Allowable Limit
CASE
2.5
2
X80
1.5
X90
1 X100
0.5 X120
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
Allowable Limit
CASE
39
EG59F9 – Individual Project in Subsea Engineering
current to the west based on Appendix A. These currents and waves hit the port or
starboard side of the vessel. In addition, Figure 5.9 shows that, even using the seamless
fabrication method and better ovality, the result is still above the allowable limit. Thus,
an 8 inch SCR with the X-120 material grade is only feasible in the Stones field if the
vessel can control the heading to prevent the waves from hitting the port or the starboard
side of the vessel.
2
X80
1.5 X90
1 X100
X120
0.5 Allowable Limit
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
CASE
1.10 1.08
1.00 1.03
0.96 0.95 ERW, 0.015 Ovality
0.90 0.91 0.90
Seamless, 0.01 Ovality
0.80
CASE 9 CASE 11 CASE 12 Allowable Limit
CASE
Figure 5.9 - 8 inch SCR Irregular Wave Post Processing Result in Stones
5.2.1.2 10 Inch SCR Stress Utilisation
It can be seen from Figure 5.10, that the regular wave analysis for the 10 inch SCR has
only some of the cases using X-120 material grade with a stress utilisation below one.
Moreover, the lower grades of this diameter are clearly not feasible in this field. The cases
that do not pass for the X-120 material grade are analysed using the irregular waves,
which are cases 7, 8, 9, 10, 11, 12, and 16, with stress utilisation values of 1.03, 1.03,
1.09, 1.05, 1.17, and 1.09, respectively
40
EG59F9 – Individual Project in Subsea Engineering
2
X80
1.5 X90
1 X100
X120
0.5
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
Allowable Limit
CASE
2
X80
1.5 X90
1 X100
X120
0.5
Allowable Limit
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
CASE
41
EG59F9 – Individual Project in Subsea Engineering
Figure 5.12 - 10 inch SCR Irregular Wave Post Processing Result in Stones
5.2.1.3 12 Inch, 14 Inch, and 16 Inch Stress Utilisation
Since a 10 inch SCR is not feasible in the Stones field, higher diameters will also not be
feasible in this field. The 12 inch, 14 inch, and 16 inch SCR regular wave analysis results
are shown in Figure 5.13, Figure 5.14, and Figure 5.15, respectively. In addition, none of
the cases for these diameters has a stress utilisation less than one, even in the highest
material grade and using seamless fabrication. As an option for this specific
environmental condition and water depth, using flexibles or adding a buoyancy module
to decrease the stress can be used if the project requires a bigger SCR.
3.5
3
2.5 X80
2 X90
1.5 X100
1
X120
0.5
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
Allowable Limit
CASE
42
EG59F9 – Individual Project in Subsea Engineering
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
Allowable Limit
CASE
3
2.5 X80
2
X90
1.5
X100
1
0.5 X120
CASE10
CASE11
CASE12
CASE13
CASE14
CASE15
CASE16
CASE17
CASE18
CASE19
CASE20
CASE21
CASE22
CASE23
CASE24
CASE1
CASE2
CASE3
CASE4
CASE5
CASE6
CASE7
CASE8
CASE9
Allowable Limit
CASE
43
EG59F9 – Individual Project in Subsea Engineering
2,231 kN
10 inch
2000 1,588 kN
1,077 kN 12 inch
1000 14 inch
0 16 inch
MATERIAL GRADE
0.25 10 inch
0.2
0.15 12 inch
0.1
0.05 14 inch
0
16 inch
Allowable Limit
CASE
44
EG59F9 – Individual Project in Subsea Engineering
8 inch SCR Regular Wave Analysis Stress Utilisation in Jack St. Malo
1.2
STRESS UTILISATION
1
X80
0.8
X90
0.6
X100
0.4
X120
Allowable Limit
CASE
Figure 5.18 - 8 inch SCR Regular Wave Analysis in Jack St. Malo
Figure 5.19 shows the overall result from the irregular wave analysis. To be more specific
in some cases, the results are shown in Figure 5.20. Within two SCR conditions, only
SCRs with seamless construction and 0.01 ovality pass the limitation criteria for the X-
80 material grade. Furthermore, there are a several of critical cases that have a stress
utilisation close to the limitation criteria according to Appendix A. These cases mostly
occur when the waves and current hit the vessel from the port beam, starboard, port bow,
and starboard bow directions. Hence, it is recommended to position the vessel’s bow
facing the incoming wave direction for safer operation.
8 inch SCR Irregular Wave Analysis Stress Utilisation in Jack St. Malo
1.1
STRESS UTILISATION
1
0.9
0.8 X80
0.7 X90
0.6
X100
0.5
0.4 x120
Allowable Limit
CASE
Figure 5.19 - 8 inch SCR Irregular Wave Analysis in Jack St. Malo
45
EG59F9 – Individual Project in Subsea Engineering
CASE
Figure 5.20 - 8 inch SCR Irregular Wave Post Processing Result in Jack St. Malo
5.2.2.2 10 Inch SCR Stress Utilisation
According to Figure 5.21, material grade X-80 for the 10 inch diameter is not feasible in
this operation because all the cases are above the stress utilisation limit. Different with
X-80, material grades above X-90 are feasible for this operation, as the highest standard
utilisation is 0.84. For X-90 itself, there are five cases that have exactly one as the stress
utilisation and are still feasible. However, to increase confidence in the operation, these
five cases are analysed using the irregular wave analysis, as shown in Figure 5.22.
1.2
1 X80
0.8 X90
0.6 X100
0.4 X120
Allowable Limit
CASE
Figure 5.21 - 10 inch SCR Regular Wave Analysis in Jack St. Malo
Figure 5.22 shows that, according to the irregular wave analysis, all the cases for material
grade X-90 are below the allowable limit. In addition, the calculation is done with the
ERW fabrication factor and 0.015 ovality. Hence, the X-90 material grade and above are
feasible. The highest stress utilisation factor for X-90 is 0.97, which is close to the
allowable limit. Hence, to reduce the stress utilisation, seamless riser and lower ovality
can be used as an option. The stress utilisation comparison between ERW and seamless
46
EG59F9 – Individual Project in Subsea Engineering
SCRs is shown in Figure 5.23. There is around a 0.04 reduction in stress utilisation for
the seamless riser, but from the economic point of view, it will increase the cost of
fabrication.
10 inch SCR Irregular Wave Analysis Stress Utilisation in Jack St. Malo
1.3
STRESS UTILISATION
1.2
1.1
1
0.9 X80
0.8 X90
0.7
0.6 X100
0.5
0.4 X120
Allowable Limit
CASE
Figure 5.22 - 10 inch SCR Irregular Wave Analysis in Jack St. Malo
1.05
1.00
0.97 0.97 0.97 0.97 0.97
0.95
0.93 0.93 0.93 0.93 0.93 ERW, 0.015 Ovality
0.90
0.85 Seamless, 0.01 Ovality
0.80 Allowable Limit
Case 2 Case 5 Case 8 Case 11 Case 14
CASE
Figure 5.23 - 10 inch SCR Irregular Wave Post Processing Result in Jack St. Malo
47
EG59F9 – Individual Project in Subsea Engineering
1.4
1.2 X80
1
0.8 X90
0.6 X100
0.4 X120
Allowable Limit
CASE
Figure 5.24 - 12 inch SCR Regular Wave Analysis in Jack St. Malo
For the X-90 material grade, five cases are analysed in irregular waves. These cases have
a 180 degree wave and current heading to the vessel’s bow based on Appendix A. The
results from the irregular wave analysis are shown in Figure 5.25, and those for different
configuration results are shown in Figure 5.26. These figures show that case 1, case 4,
case 7, case 10, and case 13 have a stress utilisation of less than one with both the ERW
and seamless fabrication methods. However, seamless SCRs still give better stress
utilisation factors than the ERW. Thus, for 12 inch SCRs in the Jack St. Malo field, the
X-90 material grade is acceptable for both ERW and seamless SCR. Nevertheless, the
vessel’s bow must always head towards the waves’ incoming direction.
1.4
1.2
1 X80
0.8
0.6 X90
0.4
X100
0.2
0 X120
Allowable Limit
CASE
Figure 5.25 - 12 inch SCR Irregular Wave Analysis in Jack St. Malo
48
EG59F9 – Individual Project in Subsea Engineering
Figure 5.26 - 12 inch SCR Irregular Wave Post Processing Result in Jack St. Malo
1.6
1.4
1.2 X80
1 X90
0.8
X100
0.6
0.4 X120
Allowable Limit
CASE
Figure 5.27 - 14 inch SCR Regular Wave Analysis in Jack St. Malo
The irregular wave analysis is conducted for the X-100 material grade for some cases
apart from the 180 degree wave and current direction. From Figure 5.28, the results of
irregular wave analysis show that all cases for X-100 material grade are acceptable for
the installation due to the stress utilisation. In addition, in Figure 5.29 shows that both the
ERW and seamless fabrication methods can be used for this riser.
49
EG59F9 – Individual Project in Subsea Engineering
1.4
1.2
X80
1
X90
0.8
0.6 X100
0.4 X120
Allowable Limit
CASE
Figure 5.28 - 14 inch SCR Irregular Wave Analysis in Jack St. Malo
1.00
0.95
ERW, 0.015 Ovality
0.90 0.87 0.87 0.88 0.88
0.84 Seamless, 0.01 Ovality
0.85 0.84 0.84 0.84 0.84
0.84 0.84 0.84 0.84 Allowable Limit
0.80 0.80 0.80 0.80 0.80 0.80
Case 2 Case 3 Case 5 Case 6 Case 9 Case 11 Case 12 Case 14 Case 15
CASE
Figure 5.29 - 14 inch SCR Irregular Wave Post Processing Result in Jack St. Malo
50
EG59F9 – Individual Project in Subsea Engineering
1.7
1.5
1.3 X80
1.1
X90
0.9
0.7 X100
0.5
X120
Allowable Limit
CASE
Figure 5.30 - 16 inch SCR Regular Wave Analysis in Jack St. Malo
5.2.3 Overall SCR Feasibility in the Gulf of Mexico
Table 5.1, Table 5.2, Table 5.3, and Table 5.4 show the feasibility of the SCRs in the Gulf
of Mexico. Table 5.1 and Table 5.2 describe the requirements for specific directions for
the vessel heading, while Table 5.3 and Table 5.4 describe the specific requirements for
the riser fabrication methods. In all the tables, the red colour means that these particular
diameter and grades are not feasible for the installation, and the grey colour means that
there is no analysis in those cases. Moreover, for Table 5.1 and Table 5.2, the orange
colour means that the installation method can be done with a specific vessel heading,
while the blue one means that the installation can be done in all directions. In Table 5.3
and Table 5.4, the purple colour means that both seamless and ERW SCRs are feasible
with the maximum ovality of 0.015. Finally, the yellow colour means that the SCR should
be seamless with 0.01 ovality to be feasible for installation.
STONES
REGULAR WAVE ANALYSIS IRREGULAR WAVE ANALYSIS
Outside
Nominal Size MATERIAL GRADE
Diameter
X80 X90 X100 X120 X80 X90 X100 X120
8 inch 219.1 mm
10 inch 273.1 mm
12 inch 323.9 mm
14 inch 355.6 mm
16 inch 406.4 mm
51
EG59F9 – Individual Project in Subsea Engineering
Table 5.2 - Wave and Current Direction Constraints for Jack St. Malo
STONES
REGULAR WAVE ANALYSIS IRREGULAR WAVE ANALYSIS
Outside
Nominal PSize MATERIAL GRADE
Diameter
X80 X90 X100 X120 X80 X90 X100 X120
8 inch 219.1 mm
10 inch 273.1 mm
12 inch 323.9 mm
14 inch 355.6 mm
16 inch 406.4 mm
JACK ST.MALO
REGULAR WAVE ANALYSIS IRREGULAR WAVE ANALYSIS
Outside
Nominal Size MATERIAL GRADE
Diameter
X80 X90 X100 X120 X80 X90 X100 X120
8 inch 219.1 mm
10 inch 273.1 mm
12 inch 323.9 mm
14 inch 355.6 mm
16 inch 406.4 mm
To summarize, only 8 inch SCRs with X-120 material grade feasible to be installed in the
Stones field. However, this SCR needs to be installed with a specific vessel heading. In
contrast, for the Jack St Malo field, all diameters are feasible to be installed, with the
minimum grade X-80 for 8 inches, X-90 for 12 and 14 inches, X-100 for 14 inches, and
X-120 for 16 inches. However, for 12 inch X-90 SCRs, the vessel needs a specific
heading, and for 8 inch X-80 SCRs, the fabrication needs to be seamless.
52
EG59F9 – Individual Project in Subsea Engineering
CHAPTER SIX
6.1 CONCLUSION
As mentioned in the beginning of the report, the project objective is to analyse the
feasibility of the SCR installation in ultra-deep water fields in the Gulf of Mexico. The J-
lay method is applied as the installation method and a vessel with the characteristic based
in Pathfinder was used for the analysis. However, the results are valid for all similar vessel
capable for this J-lay installation in the Gulf of Mexico.
Moreover, two fields are reviewed, which are Stones and Jack St. Malo. These fields have
different water depth: 2,914 m for Stones and 2,134 m for Jack St.Malo. Hence, they are
classified as ultra-deep water. The static and dynamic analysis are done in the Orcaflex
10.0 installation software using the Airy wave theory for the regular wave analysis and
JONSWAP wave theory for the irregular wave analysis.
53
EG59F9 – Individual Project in Subsea Engineering
The J-lay method is feasible for the ultra-deep water with several SCR variations and
vessel conditions in each field. In the Stones field, the SCR size is limited to the 8
inch nominal diameter and X-120 material grade. For the Jack St. Malo field, the
SCR size that can be installed is from the 8 inch to 16 inch nominal diameter, with
X-80 for the 8 inch, X-90 for the 10 and 12 inch, and X-100 for the 14 inch and 16
inch.
The seamless fabrication method will give lower stress utilisation compared to ERW.
There is one case in which the seamless SCR is required: an 8 inch X-80 SCR for the
Jack St. Malo field.
The vessel heading position also affects the installation operation. Some cases require
specific vessel headings. For the 8 inch X-120 SCR in Stones, the vessel needs to
avoid waves coming to the port and starboard of the vessel, while for 12 inch X-90
in Jack St. Malo, the vessel’s bow needs to be facing the waves’ incoming direction.
6.2 RECOMMENDATIONS
For a feasibility study, every aspect needs to be reviewed, especially for an extreme
environment like that of the GOM. The more cases are analysed, the more comprehensive
results are gained and can be more applicable for future projects. Thus, some suggestions
for this analysis are as follows:
The Gulf of Mexico is classified as a field that has extreme weather conditions such
as storms and the eddy current effects. Hence, the case with storms and eddy current
effects needs to be analysed further.
The other failure mode that needs to be assessed is fatigue. Fatigue happens because
of cyclic loads, which with later affect the SCR performance. In addition, fatigue is
associated with VIV (vortex induced vibration), which is induced by the interaction
between the structure and the fluid flow. VIV also needs to be assessed to know the
needs of the VIV suppression device on the SCR to eliminate the effect of VIV.
The SCR analysed is a simple SCR without any specific coating or insulation.
However, in a real project, the SCR will have a special coating or needs to be installed
not in empty condition; Therefore, SCRs with more realistic conditions need to be
assessed.
54
EG59F9 – Individual Project in Subsea Engineering
A flat seabed is assumed in Orcaflex, but sometimes in the Gulf of Mexico, the
seabed is uneven. It might cause residual stress on the SCR. Thus, the seabed needs
to be precisely defined in the simulation.
A financial comparison between ultra-high-strength material SCRs and flexibles
should be conducted since the flexible is widely used in the Gulf of Mexico but costs
more than the traditional SCR. With the financial comparison, the cost-saving details
can be known.
55
EG59F9 – Individual Project in Subsea Engineering
REFERENCES
[2] U.S.A, Chevron, “Jack/ St. Malo Expanding Chevron's Reach in the deepwater U.S
Gulf of Mexico,” Oil & Gas Journal, 2014.
[3] H.-G. Hillenbrand, M. Graf and C. Kalwa, “Development and Production of High
Strength Pipeline Steels,” in International Symposium Niobium, Florida, 2001.
[5] J.-Y. Yoo, S.-S. Ahn, D.-H. Seo, W.-H. Song and K.-B. Kang, “New Development of
High Grade X80 to X120 Pipeline Steels,” Materials and Manufacturing Processes,
vol. 26, pp. 154-160, 2011.
[6] S. W. I. &. Steel, “World Iron Steel,” 7 June 2017. [Online]. Available:
http://www.worldironsteel.com/news/x90-pipeline-gear-up-for-the-third-west-east-g-
5982880.html. [Accessed 1 August 2017].
[7] CNPC International Departement, “2014 Annual Report,” China National Petroleum
Corporation, Beijing, 2014.
[8] Y. Bai and Q. Bai, “Steel Catenary Risers,” in Subsea Pipelines and Risers,
Amsterdam, Elsevier, 2005, pp. 437-441.
[9] R. Hejazi and M. Kimiaei, “Equivalent linear soil stiffness in fatigue design of steel
catenary risers,” Ocean Engineering, vol. 111, pp. 493-507, 2016.
56
EG59F9 – Individual Project in Subsea Engineering
[12] Det Norske Veritas AS, Offshore Standard DNV-OS-F101: Subsea Pipeline System,
DNV, 2013.
[13] S. A. Hatton and N. Wilis, “OTC-8607-MS: Steel Catenary Risers for Deepwater
Enviroments,” in Offshore Technology Conference, Houston, 1998.
[14] J. O. Oladimeji, C. V. Ossia and J. U. Okoli, “On the Structural Integrity of S-Lay
Method of Pipeline Installtion,” American Journal of Mechanical Engineering, vol. 4,
no. 4, pp. 124-130, 2016.
[15] S. Kyriakides and E. Corona, “Offshore Facilities and Pipeline Installation Method,”
in Mechanics of Offshore Pipelines, Volume 1: Buckling and Collapse, Oxford,
Elsevier, 2007, pp. 15-43.
[16] D. Perinet and I. Frazer, “OTC-18669-MS: J-lay and Steep S-lay: Complementary
Tools for Ultradeep Water,” in Offshore Technology Conference, Houston, 2007.
[17] Y. Bai and Q. Bai, “Design of Deepwater Risers,” in Subsea Pipelines and Risers,
Amsterdam, Elsevier, 2005, pp. 401-411.
[20] Secretariat of the World Meteological Organization, Guide to Wave Analysis and
Foecasting (second edition), Geneva: World Meteological Organization, 1990.
[22] R. Staff, “Analysis: U.S. to Reap Fruits of Deepwater Labor,” Rigzone, 26 March
2006. [Online]. Available:
57
EG59F9 – Individual Project in Subsea Engineering
http://www.rigzone.com/news/oil_gas/a/90122/analysis_us_to_reap_fruits_of_deepw
ater_labor. [Accessed 8 August 2017].
[24] Shell, “The Stones Development, A New Vision in the Ultra-Deepwater Gulf of
Mexico,” Oil and Gas Journal, 2016.
[25] E. Jahanshahi , Control Solutions for Multiphase Flow: Linear and Nonlinear
Approaches to Anti-Slug Control, Norway: Norwegian University of Science and
Technology, 2013.
[27] “Jack / St Malo Deepwater Oil Project, Gulf of Mexico, United States of America,”
Offshore Technology, [Online]. Available: http://www.offshore-
technology.com/projects/jackstmalodeepwaterp/. [Accessed 2017 July 29].
[28] K. Bhalla, L. Gong and D. P. Huey, “JSM IWOCS Umbilical Analysis-Phase VIIII,”
Stress Engineering Service, Houston, 2012.
[30] American Petroleum Institute, Specification for Line Pipe, ANSI/API Spesification 5L,
Washington: American Petroleum Institute, 2008.
58
EG59F9 – Individual Project in Subsea Engineering
[34] Det Norske Veritas, Recommended Practice DNV-RP-H103 : Modelling and Analysis
of Marine Operation, Det Norske Veritas, 2011.
59
EG59F9 – Individual Project in Subsea Engineering
APPENDICES
STONES
Wave Current Wave Current
Load Direction Load Direction
Combination Combination
Case Case
Angle Vessel Wave Current Angle Vessel Wave Current
1 180 Bow Wave-W Current-E 13 180 Bow Wave-E Current-W
Port Bow Port Bow
2 225 Starboard Wave-W Current-E 14 225 Starboard Wave-E Current-W
Bow Bow
Port Port
Beam Beam Wave-E Current-W
3 270 Wave-W Current-E 15 270
Starboard Starboard
4 180 Bow Wave-SW Current-NE 16 180 Bow Wave-NE Current-SW
Port Bow Port Bow
5 225 Starboard Wave-SW Current-NE 17 225 Starboard Wave-NE Current-SW
Bow Bow
Port Port
6 270 Beam Wave-SW Current-NE 18 270 Beam Wave-NE Current-SW
Starboard Starboard
7 180 Bow Wave-S Current-N 19 180 Bow Wave-N Current-S
Port Bow Port Bow
8 225 Starboard Wave-S Current-N 20 225 Starboard Wave-N Current-S
Bow Bow
Port Port
9 270 Beam Wave-S Current-N 21 270 Beam Wave-N Current-S
Starboard Starboard
10 180 Bow Wave-SE Current-NW 22 180 Bow Wave-NW Current-SE
Port Bow Port Bow
11 225 Starboard Wave-SE Current-NW 23 225 Starboard Wave-NW Current-SE
Bow Bow
Port Port
12 270 Beam Wave-SE Current-NW 24 270 Beam Wave-NW Current-SE
Starboard Starboard
60
EG59F9 – Individual Project in Subsea Engineering
61
EG59F9 – Individual Project in Subsea Engineering
Figure 1 - Screenshot of Maximum Bending Moment of 10 inch SCR in Jack St. Malo
Field (Current-1, Wave, 225 deg)
Figure 2 - Screenshot of Maximum Top Tension of 10 inch SCR in Jack St. Malo Field
(Current-1, Wave, 225 deg)
62
EG59F9 – Individual Project in Subsea Engineering
63
APPENDIX-D: WALL THICKNESS SUMMARY
Table 3 - Minimum Wall Thickness Summary
64
Table 4 - Vertical Stability Check Results
65
APPENDIX-E: J-LAY SIMULATION IN STONES
Table 5 - J-Lay Simulation Results in Stones
1 180 Wave-W Current-E 14.91 167.58 14.17 185.89 345298.92 29060.05 0.19 1092.11 1.82 1.46 1.21 0.85
2 225 Wave-W Current-E 14.91 167.58 14.41 178.80 340337.02 29223.01 0.18 1091.70 1.78 1.42 1.18 0.83
3 270 Wave-W Current-E 14.91 167.58 15.46 167.93 332727.58 29962.48 0.17 1097.18 1.71 1.37 1.14 0.80
4 180 Wave-SW Current-NE 14.91 167.58 13.86 189.23 347639.23 28840.54 0.19 1091.74 1.84 1.47 1.22 0.86
5 225 Wave-SW Current-NE 14.91 167.58 14.22 180.34 341417.63 29089.47 0.18 1091.46 1.79 1.43 1.19 0.83
6 270 Wave-SW Current-NE 14.91 167.58 15.52 167.91 332712.62 30005.50 0.17 1097.19 1.71 1.37 1.14 0.80
7 180 Wave-S Current-N 14.91 167.58 27.69 212.32 363802.01 38519.10 0.22 1287.68 1.98 1.58 1.32 0.92
8 225 Wave-S Current-N 14.91 167.58 27.69 212.32 363802.01 38519.10 0.22 1287.68 2.02 1.62 1.35 0.95
9 270 Wave-S Current-N 14.91 167.58 36.10 257.08 395135.27 44405.39 0.24 1473.01 2.31 1.85 1.54 1.08
10 180 Wave-SE Current-NW 14.91 167.58 25.79 218.75 368306.99 37195.10 0.22 1285.29 2.02 1.61 1.34 0.94
8INCH MAY IRREGULAR 11 225 Wave-SE Current-NW 14.91 167.58 48.88 215.32 365900.48 53354.10 0.27 1462.65 2.04 1.64 1.36 0.96
12 270 Wave-SE Current-NW 14.91 167.58 49.14 213.61 364704.87 53537.88 0.24 1474.05 2.03 1.63 1.35 0.95
13 180 Wave-E Current-W 14.91 167.58 14.95 199.13 354571.51 29601.11 0.20 1154.20 1.90 1.52 1.26 0.88
14 225 Wave-E Current-W 14.91 167.58 14.15 183.57 343677.99 29044.14 0.19 1107.99 1.80 1.45 1.20 0.84
15 270 Wave-E Current-W 14.91 167.58 20.63 178.72 340285.34 33580.45 0.18 1214.48 1.78 1.42 1.18 0.83
16 180 Wave-NE Current-SW 14.91 167.58 14.09 216.17 366499.69 28998.91 0.22 1152.23 2.00 1.60 1.33 0.93
17 225 Wave-NE Current-SW 14.91 167.58 13.53 191.04 348908.24 28611.41 0.20 1106.55 1.85 1.48 1.23 0.86
18 270 Wave-NE Current-SW 14.91 167.58 21.25 178.21 339924.08 34017.02 0.18 1214.36 1.77 1.42 1.18 0.83
19 180 Wave-N Current-S 14.91 167.58 15.71 188.97 347456.50 30132.86 0.19 1155.78 1.84 1.47 1.22 0.86
20 225 Wave-N Current-S 14.91 167.58 14.84 178.77 340315.96 29529.61 0.18 1109.29 1.78 1.42 1.18 0.83
21 270 Wave-N Current-S 14.91 167.58 20.30 179.21 340629.00 33346.25 0.18 1214.15 1.78 1.42 1.18 0.83
66
22 180 Wave-NW Current-SE 14.91 167.58 15.71 188.97 347456.50 30132.86 0.19 1155.78 1.84 1.47 1.22 0.86
23 225 Wave-NW Current-SE 14.91 167.58 14.84 178.77 340315.96 29529.61 0.18 1109.29 1.78 1.42 1.18 0.83
24 270 Wave-NW Current-SE 14.91 167.58 20.30 179.21 340629.00 33346.25 0.18 1214.15 1.78 1.42 1.18 0.83
1 180 Wave-W Current-E 21.43 357.58 20.46 390.83 732711.58 41834.38 0.21 1609.54 2.11 1.69 1.40 0.98
2 225 Wave-W Current-E 21.43 357.58 20.73 378.25 723908.83 42024.65 0.20 1608.95 2.07 1.66 1.38 0.96
3 270 Wave-W Current-E 21.43 357.58 22.25 358.28 709927.01 43085.57 0.19 1618.19 2.00 1.60 1.33 0.93
4 180 Wave-SW Current-NE 21.43 357.58 20.04 396.55 736720.10 41538.37 0.21 1608.99 2.13 1.70 1.42 0.99
5 225 Wave-SW Current-NE 21.43 357.58 20.48 380.97 725814.55 41844.81 0.21 1608.63 2.08 1.66 1.38 0.97
6 270 Wave-SW Current-NE 21.43 357.58 22.33 358.24 709902.19 43142.30 0.19 1618.20 2.00 1.60 1.33 0.93
7 180 Wave-S Current-N 21.31 356.21 25.46 437.37 776160.64 45184.91 0.24 1906.48 2.27 1.82 1.51 1.06
8 225 Wave-S Current-N 21.31 356.21 55.13 437.37 807782.44 65949.69 0.24 1906.48 2.44 1.95 1.62 1.13
9 270 Wave-S Current-N 21.31 356.21 68.72 472.54 763918.34 75461.99 0.26 2214.95 2.21 1.77 1.47 1.03
10 180 Wave-SE Current-NW 21.31 356.21 23.69 447.41 785266.24 43943.09 0.24 1904.98 2.32 1.86 1.54 1.08
11 225 Wave-SE Current-NW 21.31 356.21 51.97 512.67 814018.74 63736.99 0.28 2182.85 2.47 1.98 1.64 1.15
10 INCH MAY IRREGULAR 12 270 Wave-SE Current-NW 21.31 356.21 69.07 472.44 761945.46 75710.49 0.26 2216.28 2.20 1.77 1.47 1.03
13 180 Wave-E Current-W 21.43 357.58 21.91 413.72 748736.05 42847.76 0.22 1698.72 2.37 1.90 1.58 1.10
14 225 Wave-E Current-W 21.43 357.58 20.42 386.21 729482.42 41801.66 0.21 1631.40 2.09 1.68 1.39 0.97
15 270 Wave-E Current-W 21.43 357.58 29.57 378.74 724252.19 48205.91 0.20 1792.47 2.07 1.66 1.38 0.96
16 180 Wave-NE Current-SW 21.31 356.21 20.50 483.32 795702.54 41709.26 0.24 1695.33 2.47 1.98 1.64 1.15
17 225 Wave-NE Current-SW 21.43 357.58 19.56 399.57 738830.31 41205.60 0.22 1629.35 2.14 1.71 1.42 0.99
18 270 Wave-NE Current-SW 21.43 357.58 30.19 377.83 723612.16 48641.50 0.20 1791.85 2.07 1.65 1.37 0.96
19 180 Wave-N Current-S 21.43 357.58 22.97 396.82 736904.71 43589.62 0.21 1702.21 2.13 1.70 1.42 0.99
20 225 Wave-N Current-S 21.43 357.58 21.40 378.05 723766.93 42492.00 0.20 1633.08 2.07 1.65 1.38 0.96
21 270 Wave-N Current-S 21.43 357.58 29.29 379.32 724659.84 48013.44 0.20 1792.22 2.07 1.66 1.38 0.96
22 180 Wave-NW Current-SE 21.43 357.58 22.97 396.82 736904.71 43589.62 0.21 1702.21 2.13 1.70 1.42 0.99
23 225 Wave-NW Current-SE 21.43 357.58 21.40 378.05 723766.93 42492.00 0.20 1633.08 2.07 1.65 1.38 0.96
67
24 270 Wave-NW Current-SE 21.43 357.58 29.29 379.32 724659.84 48013.44 0.20 1792.22 2.07 1.66 1.38 0.96
1 180 Wave-W Current-E 29.19 652.16 27.97 705.68 1331345.64 57052.30 0.23 2244.02 2.94 2.35 1.95 1.36
2 225 Wave-W Current-E 29.19 652.16 28.27 685.90 1317500.89 57263.60 0.22 2243.68 2.89 2.31 1.92 1.33
3 270 Wave-W Current-E 29.19 652.16 30.30 653.36 1294722.88 58686.06 0.21 2258.74 2.80 2.24 1.86 1.29
4 180 Wave-SW Current-NE 29.19 652.16 27.44 714.35 1337419.61 56680.95 0.23 2243.30 2.97 2.37 1.97 1.37
5 225 Wave-SW Current-NE 29.19 652.16 27.94 690.02 1320388.60 57030.42 0.22 2243.26 2.90 2.32 1.92 1.34
6 270 Wave-SW Current-NE 29.19 652.16 30.40 653.30 1294685.18 58752.00 0.21 2258.71 2.80 2.24 1.86 1.29
7 180 Wave-S Current-N 29.19 652.16 54.86 779.63 1383116.62 75879.50 0.25 2675.00 3.15 2.52 2.09 1.45
8 225 Wave-S Current-N 29.19 652.16 54.86 779.63 1383116.62 75879.50 0.25 2675.00 3.15 2.52 2.09 1.45
9 270 Wave-S Current-N 29.19 652.16 111.79 827.06 1416312.11 115728.31 0.27 3097.66 3.29 2.63 2.18 1.52
10 180 Wave-SE Current-NW 29.19 652.16 51.51 794.20 1393312.93 73530.82 0.26 2670.82 3.19 2.55 2.12 1.47
11 225 Wave-SE Current-NW 29.19 652.16 105.31 889.78 1460221.62 111193.07 0.29 3066.76 3.48 2.78 2.31 1.60
12 270 Wave-SE Current-NW 29.19 652.16 112.16 826.86 1416173.77 115983.47 0.27 3099.30 3.29 2.63 2.18 1.52
12 INCH MAY REGULAR
13 180 Wave-E Current-W 29.19 652.16 30.29 739.85 1355268.39 58674.90 0.24 2358.26 3.04 2.43 2.02 1.40
14 225 Wave-E Current-W 29.19 652.16 27.96 697.79 1325824.91 57046.60 0.23 2274.64 2.92 2.33 1.94 1.35
15 270 Wave-E Current-W 29.19 652.16 40.27 686.58 1317978.58 65660.57 0.22 2501.08 2.89 2.31 1.92 1.33
16 180 Wave-NE Current-SW 29.19 652.16 28.79 782.98 1385461.73 57629.72 0.25 2351.36 3.16 2.53 2.10 1.46
17 225 Wave-NE Current-SW 29.19 652.16 26.84 718.61 1340400.11 56264.50 0.23 2272.59 2.98 2.38 1.98 1.37
18 270 Wave-NE Current-SW 29.19 652.16 41.32 685.08 1316925.57 66396.17 0.22 2499.12 2.88 2.31 1.91 1.33
19 180 Wave-N Current-S 29.19 652.16 31.58 715.09 1337938.35 59581.11 0.23 2364.29 2.97 2.37 1.97 1.37
20 225 Wave-N Current-S 29.19 652.16 29.08 685.77 1317408.93 57833.49 0.22 2277.02 2.89 2.31 1.92 1.33
21 270 Wave-N Current-S 29.19 652.16 39.92 687.53 1318641.14 65421.60 0.22 2501.66 2.89 2.31 1.92 1.33
22 180 Wave-NW Current-SE 29.19 652.16 31.58 715.09 1337938.35 59581.11 0.23 2364.29 2.97 2.37 1.97 1.37
23 225 Wave-NW Current-SE 29.19 652.16 29.08 685.77 1317408.93 57833.49 0.22 2277.02 2.89 2.31 1.92 1.33
24 270 Wave-NW Current-SE 29.19 652.16 39.92 687.53 1318641.14 65421.60 0.22 2501.66 2.89 2.31 1.92 1.33
14 INCH MAY REGULAR 1 180 Wave-W Current-E 34.76 909.13 33.39 978.86 1852530.43 68007.52 0.24 2714.42 2.60 2.08 1.73 1.21
68
2 225 Wave-W Current-E 34.76 909.13 33.68 953.39 1834701.98 68213.41 0.23 2713.63 2.55 2.05 1.70 1.19
3 270 Wave-W Current-E 34.76 909.13 36.27 910.71 1804823.65 70027.21 0.22 2733.31 2.48 1.99 1.65 1.15
4 180 Wave-SW Current-NE 34.76 909.13 32.79 989.73 1860140.11 67584.76 0.24 2713.55 2.62 2.09 1.74 1.21
5 225 Wave-SW Current-NE 34.76 909.13 33.30 958.62 1838361.43 67945.37 0.24 2713.14 2.56 2.05 1.70 1.19
6 270 Wave-SW Current-NE 34.76 909.13 36.38 910.65 1804778.21 70102.52 0.22 2733.27 2.48 1.99 1.65 1.15
7 180 Wave-S Current-N 34.76 909.13 63.41 1076.21 1920675.39 89024.15 0.26 3250.21 2.77 2.22 1.84 1.28
8 225 Wave-S Current-N 34.76 909.13 63.41 1076.21 1920675.39 89024.15 0.26 3250.21 2.77 2.22 1.84 1.28
9 270 Wave-S Current-N 34.76 909.13 130.27 1129.70 1958116.20 135823.26 0.28 3729.58 2.86 2.29 1.90 1.33
10 180 Wave-SE Current-NW 34.76 909.13 59.62 1093.62 1932861.27 86369.63 0.27 3245.56 2.80 2.24 1.86 1.30
11 225 Wave-SE Current-NW 34.76 909.13 123.63 1211.54 2015401.55 131179.19 0.30 3724.13 3.01 2.41 2.00 1.40
12 270 Wave-SE Current-NW 34.76 909.13 130.33 1129.78 1958171.75 135864.99 0.28 3731.31 2.86 2.29 1.90 1.33
13 180 Wave-E Current-W 34.76 909.13 36.14 1021.21 1882173.94 69935.03 0.25 2856.89 2.67 2.14 1.78 1.24
14 225 Wave-E Current-W 34.76 909.13 33.38 967.88 1844842.89 67998.13 0.24 2752.74 2.58 2.06 1.72 1.20
15 270 Wave-E Current-W 34.76 909.13 48.85 953.50 1834773.48 78833.34 0.23 3014.83 2.55 2.05 1.70 1.19
16 180 Wave-NE Current-SW 34.76 909.13 34.44 1075.48 1920161.57 68741.83 0.26 2849.76 2.77 2.21 1.84 1.28
17 225 Wave-NE Current-SW 34.76 909.13 32.08 994.44 1863431.87 67090.86 0.24 2750.08 2.62 2.10 1.75 1.22
18 270 Wave-NE Current-SW 34.76 909.13 50.12 951.67 1833492.46 79721.56 0.23 3013.61 2.55 2.04 1.70 1.18
19 180 Wave-N Current-S 34.76 909.13 37.60 991.34 1861266.74 70957.82 0.24 2861.34 2.62 2.10 1.74 1.22
20 225 Wave-N Current-S 34.76 909.13 34.75 953.44 1834731.97 68960.89 0.23 2755.21 2.55 2.05 1.70 1.19
21 270 Wave-N Current-S 34.76 909.13 48.06 954.65 1835580.72 78280.11 0.23 3014.97 2.56 2.05 1.70 1.19
22 180 Wave-NW Current-SE 34.76 909.13 37.60 991.34 1861266.74 70957.82 0.24 2861.34 2.62 2.10 1.74 1.22
23 225 Wave-NW Current-SE 34.76 909.13 34.75 953.44 1834731.97 68960.89 0.23 2755.21 2.55 2.05 1.70 1.19
24 270 Wave-NW Current-SE 34.76 909.13 48.06 954.65 1835580.72 78280.11 0.23 3014.97 2.56 2.05 1.70 1.19
1 180 Wave-W Current-E 44.30 1457.24 42.72 1558.83 2962277.56 86789.46 0.26 3550.95 2.93 2.35 1.95 1.36
16 INCH MAY REGULAR 2 225 Wave-W Current-E 44.30 1457.24 42.93 1522.25 2936675.93 86937.72 0.25 3548.26 2.89 2.31 1.92 1.34
3 270 Wave-W Current-E 44.30 1457.24 46.01 1459.45 2892714.85 89092.66 0.24 3576.14 2.81 2.25 1.87 1.30
69
4 180 Wave-SW Current-NE 44.30 1457.24 41.99 1573.95 2972865.82 86280.27 0.26 3549.85 2.95 2.36 1.96 1.37
5 225 Wave-SW Current-NE 44.30 1457.24 42.47 1529.63 2941836.41 86610.13 0.25 3547.65 2.90 2.32 1.93 1.34
6 270 Wave-SW Current-NE 44.30 1457.24 46.13 1459.37 2892655.56 89171.96 0.24 3576.06 2.81 2.25 1.87 1.30
7 180 Wave-S Current-N 44.30 1457.24 76.55 1699.94 3061057.54 110467.77 0.28 4244.18 3.11 2.49 2.07 1.44
8 225 Wave-S Current-N 44.30 1457.24 76.55 1699.94 3061057.54 110467.77 0.28 4244.18 3.11 2.49 2.07 1.44
9 270 Wave-S Current-N 44.30 1457.24 160.40 1773.71 3112691.83 169166.10 0.29 4936.31 3.20 2.56 2.13 1.48
10 180 Wave-SE Current-NW 44.30 1457.24 72.26 1723.13 3077290.35 107466.87 0.28 4239.19 3.14 2.51 2.09 1.45
11 225 Wave-SE Current-NW 44.30 1457.24 149.77 1882.26 3188681.30 161720.52 0.31 4971.81 3.35 2.68 2.22 1.55
12 270 Wave-SE Current-NW 44.30 1457.24 160.49 1773.76 3112731.23 169229.17 0.29 4939.30 3.20 2.56 2.13 1.48
13 180 Wave-E Current-W 44.30 1457.24 45.57 1617.60 3003417.42 88785.28 0.27 3735.49 3.01 2.41 2.00 1.39
14 225 Wave-E Current-W 44.30 1457.24 42.60 1541.94 2950452.98 86706.63 0.25 3597.61 2.91 2.33 1.94 1.35
15 270 Wave-E Current-W 44.30 1457.24 62.52 1519.84 2934987.73 100644.60 0.25 3926.64 2.88 2.31 1.92 1.34
16 180 Wave-NE Current-SW 44.30 1457.24 43.55 1692.24 3055668.95 87370.30 0.28 3729.12 3.10 2.48 2.06 1.43
17 225 Wave-NE Current-SW 44.30 1457.24 40.87 1578.98 2976382.57 85494.18 0.26 3594.15 2.96 2.37 1.97 1.37
18 270 Wave-NE Current-SW 44.30 1457.24 64.14 1517.55 2933379.55 101782.70 0.25 3926.52 2.88 2.31 1.92 1.34
19 180 Wave-N Current-S 44.30 1457.24 48.54 1578.12 2975782.19 90860.11 0.26 3740.28 2.96 2.37 1.96 1.37
20 225 Wave-N Current-S 44.30 1457.24 44.69 1523.61 2937626.36 88164.26 0.25 3600.53 2.89 2.31 1.92 1.34
21 270 Wave-N Current-S 44.30 1457.24 61.51 1521.32 2936020.32 99939.50 0.25 3925.50 2.89 2.31 1.92 1.34
22 180 Wave-NW Current-SE 44.30 1457.24 48.54 1578.12 2975782.19 90860.11 0.26 3740.28 2.96 2.37 1.96 1.37
23 225 Wave-NW Current-SE 44.30 1457.24 44.69 1523.61 2937626.36 88164.26 0.25 3600.53 2.89 2.31 1.92 1.34
24 270 Wave-NW Current-SE 44.30 1457.24 61.51 1521.32 2936020.32 99939.50 0.25 3925.50 2.89 2.31 1.92 1.34
70
APPENDIX-F: J-LAY SIMULATION IN JACK ST. MALO
Table 6 - J-Lay Simulation Results in Jack St. Malo
MSd TOP
STATIC DYNAMIC Ssd (kN) STRAIN
(kN.m) TENSION LCC CHECK
CONDITION CASE DIRECTION WAVE CURRENT
Nominal SE ME SE ME
Diameter (kN) (kN.m) (kN) (kN.m) X80 X90 X100 X120
1 180 Wave Current-1 29.20 108.41 45.33 139.29 236701.20 69219.11 0.42 949.63 0.90 0.72 0.60 0.42
2 225 Wave Current-1 29.01 107.94 73.12 172.54 259369.09 88436.69 0.49 1076.78 1.04 0.83 0.69 0.49
3 270 Wave Current-1 29.01 107.94 72.83 172.61 259418.47 88233.72 0.49 1069.43 1.04 0.83 0.69 0.49
4 180 Wave Current-2 29.20 108.41 45.24 139.54 236877.19 69160.69 0.43 949.27 0.90 0.72 0.60 0.43
5 225 Wave Current-2 29.01 107.94 72.36 172.72 259490.45 87901.37 0.49 1076.04 1.04 0.83 0.69 0.49
6 270 Wave Current-2 29.01 107.94 71.74 172.81 259556.55 87466.52 0.49 1068.71 1.04 0.83 0.69 0.49
7 180 Wave Current-3 29.20 108.41 45.13 139.93 237151.38 69079.76 0.43 949.10 0.91 0.73 0.60 0.43
1
8" Year Irregular 8 225 Wave Current-3 29.01 107.94 70.97 172.88 259603.80 86932.16 0.49 1074.87 1.04 0.83 0.69 0.49
Wave
9 270 Wave Current-3 29.01 107.94 74.96 155.99 247785.32 89724.94 0.45 1067.83 0.97 0.78 0.65 0.45
10 180 Wave Current-4 29.20 108.41 45.02 140.36 237450.32 69003.49 0.43 948.67 0.91 0.73 0.61 0.43
11 225 Wave Current-4 29.01 107.94 74.84 155.83 247669.21 89641.72 0.45 1073.39 0.97 0.78 0.65 0.45
12 270 Wave Current-4 29.01 107.94 74.62 155.59 247504.19 89487.51 0.45 1066.84 0.97 0.77 0.65 0.45
13 180 Wave Current-5 29.20 108.41 45.02 140.87 237805.06 69006.07 0.43 948.14 0.91 0.73 0.61 0.43
14 225 Wave Current-5 29.01 107.94 74.33 155.27 247279.14 89279.97 0.45 1071.56 0.96 0.77 0.64 0.45
15 270 Wave Current-5 29.01 107.94 73.93 154.86 246988.37 88999.60 0.45 1065.48 0.96 0.77 0.64 0.45
1 180 Wave Current-1 54.00 259.00 101.00 314.49 552696.20 140036.00 0.57 1398.86 1.21 0.97 0.81 0.57
2 225 Wave Current-1 42.50 240.31 102.85 348.90 552791.02 126559.87 0.57 1587.89 1.21 0.97 0.81 0.57
3 270 Wave Current-1 42.50 240.31 123.95 346.46 551084.44 141335.05 0.56 1578.74 1.21 0.97 0.80 0.56
1 4 180 Wave Current-2 42.50 240.31 65.65 295.26 515238.20 100523.53 0.51 1398.70 1.08 0.87 0.72 0.51
10" Year Irregular
Wave 5 225 Wave Current-2 42.50 240.31 102.50 348.99 552848.50 126314.84 0.57 1586.82 1.21 0.97 0.81 0.57
6 270 Wave Current-2 42.50 240.31 123.71 346.01 550767.34 141164.98 0.56 1577.99 1.20 0.97 0.80 0.56
7 180 Wave Current-3 42.50 240.31 65.58 296.00 515756.22 100474.31 0.51 1398.37 1.08 0.87 0.72 0.51
8 225 Wave Current-3 42.50 240.31 101.96 349.25 553036.32 125938.59 0.57 1585.45 1.21 0.97 0.81 0.57
71
9 270 Wave Current-3 42.50 240.31 123.42 345.46 550381.35 140960.99 0.56 1577.03 1.20 0.96 0.80 0.56
10 180 Wave Current-4 42.50 240.31 65.52 296.81 516327.42 100431.34 0.51 1397.86 1.09 0.87 0.72 0.51
11 225 Wave Current-4 42.50 240.31 101.27 349.53 553232.27 125456.61 0.57 1583.79 1.21 0.97 0.81 0.57
12 270 Wave Current-4 42.50 240.31 123.09 344.85 549956.33 140730.93 0.56 1575.92 1.20 0.96 0.80 0.56
13 180 Wave Current-5 42.50 240.31 65.46 297.87 517066.36 100391.44 0.51 1397.11 1.09 0.87 0.73 0.51
14 225 Wave Current-5 42.50 240.31 100.41 349.87 553469.69 124850.55 0.57 1581.65 1.21 0.97 0.81 0.57
15 270 Wave Current-5 42.50 240.31 122.62 344.08 549415.14 140403.03 0.56 1574.46 1.20 0.96 0.80 0.56
1 180 Wave Current-1 59.43 453.05 70.10 498.10 930386.20 125378.12 0.57 1974.68 1.23 0.98 0.82 0.57
2 225 Wave Current-1 59.42 452.95 161.37 646.04 1033811.08 189251.97 0.68 2231.47 1.46 1.17 0.98 0.68
3 270 Wave Current-1 59.42 452.95 162.58 615.92 1012728.88 190097.70 0.66 2219.98 1.41 1.13 0.94 0.66
4 180 Wave Current-2 59.43 453.05 69.76 430.50 883066.20 125140.12 0.53 1974.11 1.13 0.91 0.75 0.53
5 225 Wave Current-2 59.42 452.95 161.03 645.90 1033714.15 189009.21 0.68 2230.41 1.46 1.17 0.97 0.68
6 270 Wave Current-2 59.42 452.95 162.31 615.33 1012315.99 189906.42 0.66 2219.11 1.41 1.13 0.94 0.66
7 180 Wave Current-3 59.43 453.05 69.23 430.71 883213.20 124769.12 0.53 1972.75 1.13 0.91 0.75 0.53
1
12" Year Irregular 8 225 Wave Current-3 59.42 452.95 89.66 541.60 960702.90 139057.08 0.60 1972.75 1.29 1.04 0.86 0.60
Wave
9 270 Wave Current-3 59.42 452.95 162.00 614.58 1011790.76 189693.27 0.66 2218.07 1.41 1.13 0.94 0.66
10 180 Wave Current-4 59.43 453.05 68.94 502.40 933396.20 124566.12 0.58 1973.22 1.23 0.99 0.82 0.58
11 225 Wave Current-4 59.42 452.95 160.24 645.40 1033361.03 188459.01 0.68 2227.47 1.46 1.17 0.97 0.68
12 270 Wave Current-4 59.42 452.95 161.65 613.83 1011267.54 189447.48 0.66 2216.85 1.41 1.13 0.94 0.66
13 180 Wave Current-5 59.43 453.05 68.84 504.60 934936.20 124496.12 0.58 1972.32 1.24 0.99 0.83 0.58
14 225 Wave Current-5 59.42 452.95 159.77 645.08 1033142.40 188132.00 0.68 2225.46 1.46 1.17 0.97 0.68
15 270 Wave Current-5 59.42 452.95 161.19 612.92 1010626.70 189121.20 0.66 2215.33 1.41 1.13 0.94 0.66
1 180 Wave Current-1 71.34 639.86 106.31 752.09 1348047.49 166020.31 0.66 2385.65 1.43 1.14 0.95 0.66
2 225 Wave Current-1 73.08 649.51 163.00 862.99 1282182.99 190393.46 0.74 2685.43 1.31 1.05 0.87 0.74
1 3 270 Wave Current-1 73.08 649.51 162.60 863.24 1282357.01 190109.74 0.72 2674.87 1.31 1.05 0.87 0.72
14" Year Irregular
Wave 4 180 Wave Current-2 71.34 639.86 106.22 752.86 1348589.27 165958.10 0.67 2384.82 1.43 1.14 0.95 0.67
5 225 Wave Current-2 73.08 649.51 161.22 864.77 1283425.20 189146.21 0.74 2684.23 1.31 1.05 0.88 0.74
6 270 Wave Current-2 73.08 649.51 160.24 865.74 1284105.31 188460.74 0.72 2674.12 1.32 1.05 0.88 0.72
72
7 180 Wave Current-3 71.34 639.86 106.18 754.61 1349811.64 165935.04 0.67 2382.84 1.43 1.15 0.95 0.67
8 225 Wave Current-3 71.34 639.86 106.18 754.61 1349811.64 165935.04 0.67 2382.84 1.43 1.15 0.95 0.67
9 270 Wave Current-3 73.08 649.51 164.97 815.79 1249140.49 191768.92 0.72 2673.03 1.26 1.01 0.84 0.72
10 180 Wave Current-4 71.34 639.86 106.05 756.50 1351138.59 165844.14 0.67 2383.14 1.43 1.15 0.95 0.67
11 225 Wave Current-4 73.08 649.51 164.82 815.42 1248881.30 191661.65 0.74 2681.26 1.26 1.01 0.84 0.74
12 270 Wave Current-4 73.08 649.51 164.59 814.95 1248552.69 191505.13 0.72 2671.69 1.26 1.01 0.84 0.72
13 180 Wave Current-5 71.34 639.86 106.02 758.91 1352822.52 165817.47 0.67 2382.58 1.44 1.15 0.96 0.67
14 225 Wave Current-5 73.08 649.51 164.29 814.44 1248192.50 191295.14 0.74 2679.42 1.26 1.01 0.84 0.74
15 270 Wave Current-5 73.08 649.51 163.87 813.73 1247699.41 191001.37 0.72 2670.20 1.25 1.01 0.84 0.72
1 180 Wave Current-1 92.51 1046.26 137.58 1208.67 2189474.23 215085.26 0.77 3108.60 1.65 1.32 1.10 0.77
2 225 Wave Current-1 92.51 1046.26 238.93 1389.61 2316128.56 286029.74 0.84 3520.99 1.82 1.46 1.21 0.84
3 270 Wave Current-1 92.51 1046.26 240.30 1339.95 2281366.55 286994.87 0.82 3497.38 1.77 1.42 1.18 0.82
4 180 Wave Current-2 92.51 1046.26 137.67 1210.15 2190507.77 215150.45 0.77 3106.92 1.65 1.32 1.10 0.77
5 225 Wave Current-2 92.51 1046.26 238.47 1389.85 2316297.33 285709.07 0.84 3519.08 1.82 1.46 1.21 0.84
6 270 Wave Current-2 92.51 1046.26 240.02 1339.10 2280768.91 286797.26 0.82 3496.35 1.77 1.42 1.18 0.82
7 180 Wave Current-3 92.51 1046.26 137.86 1213.02 2192516.92 215281.76 0.77 3105.11 1.65 1.32 1.10 0.77
1
16" Year Regular 8 225 Wave Current-3 92.51 1046.26 137.86 1213.02 2192516.92 215281.76 0.77 3105.11 1.65 1.32 1.10 0.77
Wave
9 270 Wave Current-3 92.51 1046.26 239.60 1338.07 2280047.69 286501.86 0.82 3494.28 1.77 1.42 1.18 0.82
10 180 Wave Current-4 92.51 1046.26 137.73 1215.99 2194598.52 215190.70 0.77 3104.12 1.65 1.32 1.10 0.77
11 225 Wave Current-4 92.51 1046.26 237.35 1390.46 2316722.90 284926.70 0.84 3514.84 1.82 1.46 1.21 0.84
12 270 Wave Current-4 92.51 1046.26 239.16 1336.99 2279293.46 286193.92 0.82 3491.87 1.77 1.42 1.18 0.82
13 180 Wave Current-5 92.51 1046.26 137.43 1218.48 2196338.32 214983.14 0.77 3102.71 1.66 1.33 1.10 0.77
14 225 Wave Current-5 92.51 1046.26 236.66 1390.72 2316902.78 284445.97 0.84 3512.22 1.82 1.46 1.21 0.84
15 270 Wave Current-5 92.51 1046.26 238.59 1335.81 2278468.86 285793.04 0.82 3489.11 1.77 1.41 1.18 0.82
73
APPENDIX-G : WALL THICKNESS BUCKLING CHECK
74
Figure 6 - Wall Thickness Check Spreadsheet Part.2
75
APPENDIX-H : LOAD CONTROLLED CONDITION CHECK
76
Figure 8 - LCC Check Spreadsheet Part. 2
77
Figure 9 - LCC Check Spreadsheet Part. 3
78