Dynamic Compaction Operation Safety Training - ECT
Dynamic Compaction Operation Safety Training - ECT
12. Operator must aware rigger position all the time as well as
ACCESS – CHEC JV (PVT) LTD: EAST CONTAINER TERMINAL (PHASE 2) PROJECT
13. Operator and rigger must familiar with hand signal for
communication.
17. Rains creates wet and slippery ground, loose and landslides
situation. When the soil is loose and could cause danger to the
crane stability dynamic compaction works must be stopped.
Inspection points
Dynamic compaction hammer lifting point connected D
shekels & cable eye
Use only suitable wire ropes slings and never use damage wire
rope slings.
During lifting safe working load cannot exceed.
Regular inspection must be conducted.
If more than one wire rope sling is use in lifting need to pay
attention to the angle between the slings.
The distance between the cable’s clips shall be the same as
well the direction of installation should be correct.
ACCESS – CHEC JV (PVT) LTD: EAST CONTAINER TERMINAL (PHASE 2) PROJECT
A. Daily
B. Weekly
C. Monthly
D. No important
培训部门
培训时间/Date 年/Y 月/M 日/D
Taught By
ACCESS – CHEC JV (PVT) LTD: EAST CONTAINER TERMINAL (PHASE 2) PROJECT
参加人员/Attendees
10
11
12
13