New Takt Book
New Takt Book
PROGRAMS PHASES
& PROJECTS
PATH OF
TAKT
PLANNING
TAKT TIME
CRITICAL FLOW
INTER- PRODUCTION
CONNECTIONS LAWS
BUFFERS
11
ALL CONSTRUCTION SCHEDULES SHOULD BE FORMATTED LIKE THIS:
Time=T
Location= X,Y,Z
Trades flowing = Flowing
RHYTHM
Work finishes
on a rhythm
Work starts
on a rhythm
Everything is balanced
to that rhythm
CONSISTENCY
LABOR MATERIALS INFORMATION
24
WE NEED TO DEFINE THE COMPONENTS OF THE TAKT CALCULATOR BEFORE
WE MOVE ON. THIS CALCULATOR WILL BE USED TO OPTIMIZE OUR PHASES.
32
NOW THAT WE HAVE THE ZONES LEVELED WE WILL LABEL THEM BY ZONE TYPE.
REMEMBER, WE HAVE THE FOLLOWING TYPES OF ZONES:
1. HORIZONTAL: HORIZONTAL FLOWS OF WORK.
2. VERTICAL: VERTICAL FLOWS OF WORK.
3. WORKABLE BACKLOG: WORK THAT IS READY TO BE WORKED ON BUT IS NOT A PART
OF THE PATH OF CRITICAL FLOW. IT IS USED TO ENABLE SWING CAPACITY WHICH IS
WHEN RESOURCES ARE SHARED BETWEEN AREAS WHEN ADDED HELP IS NEEDED.
VERTICAL FLOW
ALSO FLAGGED AREAS THAT MAY BE
CHOSEN AS VERTICAL FLOWS. ELEVATORS, 3
STAIRS, BATHROOMS, STACKED ELECTRICAL
ROOMS AND CHASES ARE EXAMPLE OF
VERTICAL FLOWS. 2
1
1
2
WORKABLE BACKLOG 3
LEVEL 1
HORIZONTAL Zone 1
FLOW PHASE Zone 2
Zone 3
1
VERTICAL 2
FLOW 3
WORKABLE PHASE 4
BACKLOG Elevator
42