Lecture 3 Process Safety
Lecture 3 Process Safety
https://www.youtube.com/watch?v=goSEyGNfiPM
https://www.ispatguru.com/process-safety-and-its-management/
Process Safety Management - Standards
There are 3 key guidelines for process safety management with the same
scope of elements but differs in structure and integration.
• OSHA (14 elements).
• CCPS Risk-based process safety approach (20 elements).
• EI – Energy Institute (20 elements).
Elements Of Process Safety
• Element 1: Employee participation
• Element 2: Process Safety Information
• Element 3: Process Hazard Analysis
14
• Element 4: Operating Procedures
• Element 5: Safe work practices
• Element 6: Contractor control
• Element 7: Training
• Element 8: Pre-Start up Safety Review
• Element 9: Mechanical integrity
• Element 10: Management of Change
• Element 11: Emergency response planning
• Element 12: Trade secrets
• Element 13: Incident Investigation
• Element 14: Compliance audits
Elements Of Process Safety
Process Hazards Analysis - PHA
Process Hazards Analysis - PHA
Definition:
• Identifying, evaluating, and controlling the hazards of processes involving highly hazardous chemicals
Methodologies:
1. What-if/checklist
2. Hazard and operability study (HAZOP)
3. Hazards Identification Study (HAZID)
4. Failure mode and effects analysis (FMEA)
5. Fault tree analysis
HAZardous OPerability - HAZOP
Hazard and operability
study (HAZOP)
Definition:
• It is a structured and systematic examination of a complex planned or
existing process or operation in order to identify and evaluate problems
that may represent risks to personnel or equipment.
• The technique is based on breaking the overall complex design of the process
into a number of simpler sections called 'nodes' which are then individually
reviewed.
• The risk assessment is intended to help establish the risk picture. This will then be used in part to
assess the need for barriers in order to reduce risk to an acceptable level and allow specified
requirements to be met
FRA • FRA should not be considered as the basis to justify similar work in the future. Particular
activity and relevant conditions shall be assessed on a case-by-case basis.
Methodolog y
FRA Template
FRA – Action sheet template
Pre-Start-Up Safety Review - PSSR
What is the PSSR?
• An investigation into the process in question prior to introducing a highly hazardous
chemical to that process is a systematic and thorough examination of that process.
PSSR Scope
Contractor
Report
Leader Involvement
• In ideal risk management, a prioritization process is followed whereby the risks with the greatest loss
(or impact) and the greatest probability of occurring are handled first.
• Risks with a lower probability of occurrence and lower loss are handled in descending order.
• In practice the process of assessing overall risk can be difficult and balancing resources used to
mitigate between risks with a high probability of occurrence but lower loss, versus a risk with a high
loss but lower probability of occurrence can often be mishandled.
Risk Management
4. Mitigation or solution of risks using available technological, human and organizational resources
Process 2 - Risk Identification
• After establishing the context, the next step in the process of managing
risk is to identify potential risks.
• Risks are about events that, when triggered, cause problems or benefits.
• Hence, risk identification can start with the source of our problems and
those of our competitors (benefit), or with the problematic
consequences.
Process 3 - Risk Assessment
• Once risks have been identified, they must then be assessed as to their potential
severity of impact (generally a negative impact, such as damage or loss) and to the
probability of occurrence.
• These quantities can be either simple to measure, in the case of the value of a lost
building, or impossible to know for sure in the case of an unlikely event, the
probability of occurrence of which is unknown.
• Therefore, in the assessment process it is critical to make the best educated decisions
in order to properly prioritize the implementation of the risk management plan.
Process 4 – Potential Risk treatments
• Once risks have been identified and assessed, all techniques to manage
the risk fall into one or more of these four major categories:
• The risk management plan should propose applicable and effective security controls
for managing the risks.
MAJOR ACCIDENTS
• Major accidents are fires, explosions or releases of dangerous substances that
will cause death or serious injury; major damage to the structure or plant or loss
of stability; the collision of a helicopter; failure of life support systems for
diving operations; or any other event involving death or serious injury to five or
more people.
PERFORMANCE STANDARDS
• A Performance Standard is a qualitative or quantitative statement of the
performance required of a system or item of equipment for it to satisfactorily
fulfill its purpose.
• It is a requirement that Performance Standards should be established for all
SCEs.
VERIFICATION SCHEMES
• Verification schemes are written schemes implemented to confirm, or
otherwise, that SCEs are suitable and remain in good repair and
condition.
INDEPENDENT COMPETENT PERSONS
• Independent Competent Persons (ICPs) are required to carry out various functions under the
verification scheme to ensure that the process of managing risks associated with Major Accident
Hazards is working effectively.
• It is a requirement that ICPs must be sufficiently independent so as to be impartial and objective in
their judgment such that safety is not compromised.
• The role of the ICP can either be undertaken by a single organization or by a number of different
individuals or organizations considering separate aspects of the installation.
• In the latter case, however, greater coordination will be required by the duty holder to ensure that
all parts of the scheme have been adequately addressed and that interfaces are effectively managed.
• Although not mandatory, it is generally recommended that where multiple ICPs are employed, one
has an overseeing role.
IDENTIFICATION OF SCEs
Step 1
Step 2
PFEER:
Step 3 Prevention of Fire and
Explosion and
Emergency Response
Regulations
Step 4
Step 1 - Identify the major accident events on the installation
• This is carried out using a series of hazard identification techniques, involving both
qualitative and quantitative methods.
• The results from this process are generally recorded in a Hazard Register which
documents all of the potential major accident event scenarios on an installation and should
be documented in the safety case for the installation.
Step 2 - Identification of structures and plants which can cause, contribute
to, prevent or help recover from a major accident
• Duty holders will generally utilize lists of plant and equipment, extracted from their computerized
maintenance management systems, as the starting point for assessing which of the items on the list are
safety-critical.
• Approaches vary, but SCEs need to be defined at an appropriate level such that they have a direct
linkage to MAHs, and it is also clear whether or not an equipment item forms part of one or more
SCEs.
Step 3 - Identify PFEER Specified Plant
• Specified Plant is any of the plants of an installation that is provided:
1. To comply with Regulations 11(1)(a), 13, 15 and16 of the PFEER Regulations.
2. As a means of detecting fire and for detecting and recording accumulations of
flammable gases (as required by Regulation 10 of the PFEER Regulations).
3. Measures to combat fire and explosion as required by Regulation 12 of the PFEER
Regulations.
Step 4 - Prepare a record of items identified as SCEs
• It is important that the record of SCEs is maintained up to date, therefore the major
accident analyses and the list of SCEs should be reviewed periodically.
• The list should also be reviewed prior to the addition of new equipment or modification
of the existing plant.
Barrier Management
Important Terminologies
• Barrier: Technical, operational, and organizational elements that are intended individually
or collectively to reduce the possibility for a specific error, hazard, or accident to occur, or
which limit its harm/disadvantages.
• Barrier element: Technical, operational, or organizational measures or solutions which
play a part in realizing a barrier function.
• Barrier function: The task or role of a barrier. Examples include preventing leaks or
ignition, reducing fire loads, ensuring acceptable evacuation, and preventing hearing
damage.
• Barrier strategy: Result of a process that, on the basis of the risk picture, describes and
clarifies the barrier functions and elements to be implemented in order to reduce risk.
Important Terminologies
• Barrier management: Coordinated activities to establish and maintain barriers so that they
maintain their function at all times.
• Performance requirements: Verifiable requirements related to barrier element properties to
ensure that the barrier is effective. They can include such aspects as capacity, functionality,
effectiveness, integrity, reliability, availability, ability to withstand loads, robustness, expertise, and
mobilization time.
• Performance influencing factors: Conditions that are significant for the ability of barrier
functions and elements to perform as intended.
• Context: External and internal frame conditions must be taken into account in barrier
management.
Important Terminologies
• Major accident: A major accident means an acute incident such as a major spill, fire,
or explosion which immediately or subsequently entails multiple serious personal
injuries and/or loss of human lives, serious harm to the environment, and/or loss of
major financial assets.
Purpose Of Barrier Management
• The main purpose of barrier management is to establish and maintain barriers so that
the risk faced at any given time can be handled by preventing an undesirable incident
from occurring or by limiting the consequences should such an incident occur.
• Barrier management includes:
1. The processes
2. Systems
3. Solutions
4. Measures
Which must be in place to ensure the necessary risk reduction through the implementation
and follow-up of barriers.
Example for Barrier Functions at Different Levels
Barrier Management Model
THANK YOU