0% found this document useful (0 votes)
56 views

Checklists For Testing and Commissioning of Switchgear

This document is a checklist for testing and commissioning medium-voltage switchgear. It includes sections to record measurements and test results for busbar torque tests, busbar contact resistance, circuit breaker contact resistance, current transformers, and their insulation resistance, polarity, winding resistance, and ratio tests. Signatures are included to verify tests were witnessed and approved.

Uploaded by

kevin
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views

Checklists For Testing and Commissioning of Switchgear

This document is a checklist for testing and commissioning medium-voltage switchgear. It includes sections to record measurements and test results for busbar torque tests, busbar contact resistance, circuit breaker contact resistance, current transformers, and their insulation resistance, polarity, winding resistance, and ratio tests. Signatures are included to verify tests were witnessed and approved.

Uploaded by

kevin
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 18

CHECK LIST FOR: Form No:

MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00


( TESTING & COMMISSIONING REPORT)
Page : 1 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

BUSBAR TORQUE TEST

Temp:…..…. ºC

PANEL No.

REMARKS
R Y B

INSTRUMENT NAME:…………………………………………………………………………………...

SERIAL NO :…………………………………………………………………………………..

CALIBRATION DATE: ………………………………………………………………………………….

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 2 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

BUS BAR CONTACT RESISTANCE MEASUREMENT

Applied Current : 100 A DC Temp :………ºC

MEASURED RESISTANCE IN MICRO OHMS


PANEL N0. REMARKS
R Y B

INSTRUMENT NAME :………………………………………………………………………………….

SERIAL NO :…………………………………………………………………………………..

CALIBRATION DATE: …………………………………………………………………………………..

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 3 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

CIRCUIT BREAKER CONTACT RESISTANCE MEASUREMENT

Applied Current: 100 A DC Temp:………ºC

MEASURED RESISTANCE IN µΩ
PANEL N0. CB Serial No. REMARKS
R Y B

INSTRUMENT NAME :………………………………………………………………………………….

SERIAL NO :…………………………………………………………………………………..

CALIBRATION DATE: …………………………………………………………………………………..

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 4 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

CURRENT TRANSFORMER

Panel No. :

Name plate rating details of the equipment

Type Insulation level :

Serial No R: Y: B:

Core Class VK/VA Ratio Used for

a) Insulation Resistance Measurement : ( 500 V megger )


Temp:…........ºC

Test IR Value Measurement in Ω


CT cores combination & R Phase Y Phase B Remarks
Test point Phase
Core-1 1S1 to Earth

Core-2 2S1 to Earth

b) Polarity Test :

Secondary
CT Cores R Y B
Terminals
Core-1 1S1 to 1S2 & 1S3

Core-2 2S1 to 2S2 & 2S3

c) Winding Resistance Test :


Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 5 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

CT Core Phase Terminals Resistance Remarks

1S1 – 1S2
R
1S1 – 1S3
1S1 – 1S2
1
Y 1S1 – 1S3
1S1 – 1S2
B
1S1 – 1S3
2S1 – 2S2
R
2S1 – 2S3
2S1 – 2S2
2 Y
2S1 – 2S3
2S1 – 2S2
B
2S1 – 2S3

d) Ratio Test :

Applied
Measured Measured Secondary Current in A
Core No Actual Ratio Primary
Terminals R Y B
current in A
1S1 -1S2
1
1S1 – 1S3

2S1 – 2S2
2
2S1 – 2S3

INSTRUMENT NAME :………………………………………………………………………………….

SERIAL NO :………………………………………………………………………………….

CALIBRATION DATE: …………………………………………………………………………………..

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 6 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

FUNCTIONAL CHECKS
11 kV Circuit Breaker Local Operations & Interlocks

ITEM TO
WHAT TO CHECK COMMENTS REMARKS
CHECK

BREAKER - CAN RACK IN & OUT SMOOTHLY


- EARTH SWITCH CANNOT BE CLOSED
- VCB CLOSED: BKR CANNOT BE RACK OUT
SERVICE
POSTION - VCB OPENED: BKR CAN BE RACK OUT
- MAIN DOOR CANNOT BE OPENED
- VCB CAN BE CLOSED
- VCB CLOSED: BKR CANNOT BE RACKED IN
TEST
POSITION - CONTROL PLUG CAN BE REMOVED
- EARTH SWITCH CAN BE CLOSED

INTERMEDIATE
- VCB CANNOT BE CLOSED
POSITION

- CAN OPEN & CLOSE SMOOTHLY


EARTH SWITCH
- PADLOCK FACILITY PROVIDED

CB PLUG - WITH OUT CB PLUG CB NOT POSSIBLE TO RACK IN


VT SHUTTER
- SMOOTH OPENING & CLOSING
PT SHUTTERS
CB ON/OFF BY -ON COMMAND
ELECTRICAL
COMMAND -OFF COMMAND

CB ON/OFF
-ON & OFF CHECKED
MANUAL

INSTRUMENT NAME :………………………………………………………………………………….

SERIAL NO :………………………………………………………………………………….

CALIBRATION DATE: ………………………………………………………………………………….

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 7 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

VOLTAGE TRANSFORMER

TYPE :

RATED VOLTAGE :

RATIO :

OUTPUT (VA) :

PURPOSE :

SERIAL No. : R……………………….Y………………………B…………………….

YEAR OF MANUFT :

INSULATION, RATIO, POLARITY & RESISTANCE TEST

1. INSULATION TEST ( )

MEGGER
WINDING R Y B
(V)
PRIMARY TO EARTH 5000

PRIMARY TO SECONDARY-1 1000

PRIMARY TO SECONDARY-2 1000

SECONDAY -1 TO EARTH 500

SECONDAY -1 TO EARTH 500

SECONDAY -1 TO SECONDARY - 2 500

a) Polarity Test :

Secondary
CT Cores R Y B
Terminals
Core-1 a1 – n1

Core-2 a2 – n2

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 8 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

VOLTAGE TRANSFORMER
3. RATIO CHECK:

APPLIED PRIMARY MEASURED MEASURED


PHASE
VOLTAGE (V) VOLTAGE (V) ON VOLTAGE (V) ON
PRIMARY
SECONDARY-1 SECONDARY-2

RY

YB

BR

RN

YN

BN

4. VT WINDING RESISTANCE: TEMP:……. ºC

PHASE PRIMARY(K) SECONDARY-1 (m) SECONDARY-2 (m)


R

INSTRUMENT NAME:………………………………………………………………………………….

SERIAL NO :………………………………………………………………………………….

CALIBRATION DATE: …………………………………………………………………………………

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 9 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

PROTECTION RELAY TESTING


RELAY DETAILS

TYPE :……………………. MAKE :………………………………

AUX. VOLTS :……………V SERIAL NO :…………………………

GENERAL INSPECTION AND CHECKS

Sl.No. Checks Result

1 Installation and wiring correct to relevant drawings

2 Model number or rating information is correct

3 Output contacts are operating properly

4 LED Indication operation

a. Measurement:

CT RATIO :……………………………

Phase Phase R Phase Y Phase B Earth

Current Injected(A)
Current displayed
on Relay(A)

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 10 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

b. O/C & E/F Function


Characteristic Curve = NI
Setting Current Is> Pickup Current Drop off Current
Phase Remarks
Amps. Amps Amps.

R 1.0
Y 1.0
B 1.0
E/F 1.0

Characteristic Curve = NI
Setting Injected =2 x Is Injected=5 x Is
TMS
Phase Current
(A) Expected Time Sec. Actual Time Sec. Expected Time Sec. Actual Time Sec.
R 1.0 0.1
Y 1.0 0.1
B 1.0 0.1
E/F 1.0 0.1

C . Testing definite time stages

High set stage I >>

Test element Relay setting Current injected


Time setting (Sec) Operating time (Sec)
I >> (A) (A)

R 1 2

Y 1 2

B 1 2

E/F 1 2
Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 11 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

d. Final settings for O/C & E/F Function

Setting Injected =2 x Is Injected=5 x Is


TMS
Phase Current
(A) Expected Time Sec. Actual Time Sec. Expected Time Sec. Actual Time Sec.
R
Y
B
E/F

INSTRUMENT NAME:…………………………………………………………..………………………….

SERIAL NO :……………………………………………………………………………………….

CALIBRATION DATE: ………………………………………………………………………………….……

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 12 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

HIGH VOLTAGE TEST

1. INSULATION RESISTANCE TEST

Test Voltage: 5 kV DC Ambient Temp:………ºC

Voltage Applied Between BEFORE HV ( Ω) AFTER HV ( Ω)


R to Y+B+ Earth

Y to R+B+ Earth

B to R+Y+ Earth

2. HIGH VOLTAGE TEST

Applied Voltage: 22.4 kV AC for 60 SEC

Voltage Applied Between Leakage Current (mA) Result

R to Y+B+ Earth

Y to R+B+Earth

B to R+Y+Earth

INSTRUMENT NAME:………………………………………………………………………………….

SERIAL NO :…………………………………………………………………………………

CALIBRATION DATE: …………………………………………………………………………………

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 13 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

PRIMARY INJECTION TEST ON CT CIRCUIT

PRIMAR
CT RATIO PHASES Y ENTER DETAILS OF MEASURING POINTS AND PHASES
& PUROSE INJECTED CURREN
SWGR SWGR
T (Amps)
TERMINAL BLOCK - SA1 SWITCH

CORE -1 X311 X312 X313 X314 2 6 10 1


Ratio -
R–E

Metering R–Y

R–B

PRIMAR
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES Y
&
INJECTED CURREN
PUROSE SWGR SWGR.
T (Amps)

AMMETER DISPLAY

CORE -1 R Y B
Ratio - R–E

R–Y
Metering
R–B

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 14 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

PRIMARY INJECTION TEST ON CT CIRCUIT

PRIMARY
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES INJECTED CURRENT
& PUROSE (Amps) SWGR
SWGR
TERMINAL BLOCK TEST PLUG
X301 X302 X303 X304 1/22 23/24 25/26 27/28
CORE -2
Ratio - R–E

PROT. R–Y

R–B

PRIMARY
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES INJECTED CURRENT
& PUROSE (Amps) SWGR
SWGR
RELAY RELAY DISPLAY
49 51 53 56 R Y B N
CORE -2
Ratio - R–E

PROT. R–Y

R–B

INSTRUMENT NAME:………………………………………………………………………………….

SERIAL NO :………………………………………………………………………………….

CALIBRATION DATE: …………………………………………………………………………………

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 15 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

PRIMARY INJECTION TEST ON CT CIRCUIT

PRIMARY
CT RATIO
PHASES INJECTED CURRENT ENTER DETAILS OF MEASURING POINTS AND PHASES
& PUROSE (Amps) SWGR SWGR
TERMINAL BLOCK - TEST PLUG
X301 X302 X303 X304 21/22 23/24 25/26 27/28
CORE -1
Ratio - R–E

Protection. R–Y

R–B

PRIMARY ENTER DETAILS OF MEASURING POINTS AND PHASES


CT RATIO
PHASES INJECTED CURRENT
& PUROSE (Amps) SWGR SWGR

RELAY RELAY DISPLAY

49 51 53 56 R Y B N
CORE -1
Ratio -
R–E

Protection R–Y

R–B

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 16 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

PRIMAR Y INJECTION TEST ON CT CIRCUIT

PRIMARY
CT RATIO
PHASES INJECTED CURRENT ENTER DETAILS OF MEASURING POINTS AND PHASES
& PUROSE (Amps) SWGR SWGR
TERMINAL BLOCK - SA1(SELECTOR SWITCH)
X311 X312 X313 X314 2 6 10 1
CORE -2
Ratio - R–E

Metering R–Y

R–B

PRIMARY
CT RATIO ENTER DETAILS OF MEASURING POINTS AND PHASES
PHASES INJECTED CURRENT
& PUROSE (Amps)
SWGR

AMMETR DISPLAY

R Y B N
CORE -2
Ratio -
R–E

Metering R–Y

R–B

INSTRUMENT NAME:………………………………………………………………………………….

SERIAL NO :…………………………………………………………………………………

CALIBRATION DATE: …………………………………………………………………………………

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 17 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

VOLTMETER FUNCTIONAL TEST

1. INSTRUMENT DETAILS

MAKE :…………………………….

RANGE : ………………………………..

MODEL/TYPE :…………………………….

VT RATIO :…………………………….

2. SECONDARY INJECTION

Expected Measured
Applied Voltage
Sl. No. Reading (KV) Reading (KV) % Error
(V)
[s] [ns]
1
2
3
4
5

(ns – s)
% Error = --------------------- x 100
(Full scale value)

3. EQUIPMENT USED :

INSTRUMENT NAME
MAKE / MODEL SERIAL NO. CAL DUE DATE

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :


CHECK LIST FOR: Form No:
MEDIUM-VOLTAGE SWITCHGEAR TESTING AND COMMISSIONING Rev. No : 00
( TESTING & COMMISSIONING REPORT)
Page : 18 of 17
SUBCONTRACTOR CONTRACTOR
X
SECTION OF WORK: Electrical LOCATION:
LEVEL: WIR No.:

Tested By : Supplier/Sub-contractor Witnessed By Contractor Witnessed By Consultant Approved By : Client

Signature : Signature : Signature : Signature :

Name : Name : Name : Name :

Date : Date : Date : Date :

You might also like