0% found this document useful (0 votes)
18 views

Pre-Start Up Check List1

Mitsubishi Electric Automation provides a pre-startup checklist for UPS systems to ensure a smooth startup. The checklist contains installation tasks that should be completed by the installing contractor prior to startup such as verifying wiring connections and power configurations match the UPS specifications. Customers are requested to review the checklist for their applicable equipment, confirm the tasks are complete, and return the form before the scheduled startup date so the technician has all necessary access and power will be available during startup. The customer representative is also highly recommended to attend operator training during startup.

Uploaded by

Luis Oropeza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views

Pre-Start Up Check List1

Mitsubishi Electric Automation provides a pre-startup checklist for UPS systems to ensure a smooth startup. The checklist contains installation tasks that should be completed by the installing contractor prior to startup such as verifying wiring connections and power configurations match the UPS specifications. Customers are requested to review the checklist for their applicable equipment, confirm the tasks are complete, and return the form before the scheduled startup date so the technician has all necessary access and power will be available during startup. The customer representative is also highly recommended to attend operator training during startup.

Uploaded by

Luis Oropeza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Mitsubishi Electric Automation, Inc.

UPS SYSTEMS GROUP

Pre-Start up Checklist
It is our goal to ensure a smooth and uneventful start up of your UPS System. In an effort to minimize the
impact of this essential procedure to your overall operations as well as to avoid incurring additional start up
charges, we have provided a checklist of items that should be performed by the installing contractor prior to the
actual start up date for the UPS. We kindly request that you review and complete the applicable tasks listed on
this form. When complete, please indicate in the appropriate spaces of the form and return to our office at the
number provided below before the start up date. It is highly recommended that the end user responsible for this
equipment be available to attend the operator training at the time of start up. Thank you.
OWNER / END USER INFORMATION:
Company name
Site contact Telephone # Fax #
Scheduled start up date Time
Facility address

EQUIPMENT INFORMATION:
UPS Model # UPS Serial #
INSTALLATION INFORMATION:
UPS / Battery Y N N/A
Is equipment installed in final location? ____ ____
Are the main input AC power wiring connections complete? ____ ____
Are the bypass input AC power wiring connections complete? ____ ____ ____
The supply voltage must match the UPS rating. Has this been verified? ____ ____
Phase rotation to the main and bypass inputs must be
clockwise (A-B-C). Has this been verified? ____ ____
Are the output AC power wiring connections complete? ____ ____
Are battery power/control wiring connections complete? ____ ____
Will input power to the UPS be available at the time of start up? ____ ____
Will technician have free and clear access to UPS at time of start up? ____ ____
Will customer representative be available for training at time of start up? ____ ____
Options
Is the Remote Status Alarm Panel (RSAP) installed? ____ ____ ____
Is the control wiring for RSAP installed? ____ ____ ____
Is the Maintenance Bypass System (MBS) cabinet installed? ____ ____ ____
Are the power/control connections to MBS cabinet complete? ____ ____ ____

Please return form to (Service Representative____________________________________________________


Attention:_______________________________________________ Fax #:___________________________

F75-02Y-SLSUPS-001*

You might also like