Earned Value Management
Earned Value Management
https://planergy.com/blog/earned-value-management/
1 / 12
corrective action before the entire project collapses or generates excess cost,
waste, or delays.
Compare this to traditional methods of tracking progress, and you’ll quickly see
why taking both project scheduling and budget into account is better than simply
relying on either.
For example, if a project is scheduled to take five months, and the project
manager’s only looking at elapsed time as a project completion metric, they might
consider the project to be 20% complete after a month has passed, even if only
10% of the work required has been completed. Without a clear understanding of
current project status and where it’s heading, disaster awaits.
EVM addresses this by formalizing processes and assigning value to every task, to
be assigned only once that task is completed. EVM standards used by the United
States Department of Defense (DOD) and set by the National Defense Industrial
Association (NDIA) have been codified since 1998 under the American National
Standard Institute Electronic Industries Association 748 Standard, also known as
the ANSI/EIA 748 standard.
A common approach is to break the total project into tasks that each receive a
value expressed as a percentage, with all the tasks and subtasks adding up to
100%.
If your project is, for example, updating the procurement department’s computers
and software, you might break it out like this:
https://planergy.com/blog/earned-value-management/
2 / 12
70% Primary Hardware Replacement
20% Software and Licensing Updates
10% Peripherals
Each completed task is added to the total earned value (EV) as it’s completed. So,
going back to our five-month timeframe, if you’ve managed to replace both
hardware and peripherals by the end of month four, you’ve completed 80% of the
work, producing earned value of 80% in 80% of the time allotted.
The percentages used to establish earned value are based on each task’s
percentage of the total project budget, or budget at completion (BAC). If, for
example, you have a project with only one task, and the budget for that task is
$7500, then the project’s BAC is also $7500.
Alternatively, if you had three tasks (like in our computer upgrade scenario), the
breakdown might look more like this:
Of course, the EV formulas alone aren’t quite enough to help you transform your
project management. They’re best executed within an earned value management
system (EVM system), which is a well-developed, focused application of the
formulas and their analyses to monitor and optimize your project as it happens,
ensuring optimal performance and lowest total cost in real time.
After all, hindsight may be 20/20, but knowing what went wrong is never quite as
satisfying, or profitable, as stopping it from happening altogether.
Once you understand what you’re looking for and how to measure progress,
https://planergy.com/blog/earned-value-management/
3 / 12
you’ll be ready to perform the actual calculations that determine specific
components of earned value—and manage your projects accordingly.
Planned Value (PV): The total budgeted costs for the project. PV is also known
as budgeted cost of work scheduled (BCWS) and is expressed as the portion of the
planned spend at any given point in the project.
Actual Costs (AC): The amount actually spent to complete tasks within the
project. Also known as actual cost of work performed (ACWP).
Earned Value (EV): Also called budgeted cost of work performed (BCWP), EV is
measured by multiplying the percentage of work completed by the total project
budget.
https://planergy.com/blog/earned-value-management/
4 / 12
Critical Earned Value Calculations
Once you understand what you’re looking for and how to measure progress, you’ll
be ready to perform the actual calculations that determine specific components of
earned value—and manage your projects accordingly.
Cost Variance (CV): A measurement of the difference between earned value and
the actual amount spent at any given point in the project. A negative CV value
indicates a task is over budget, a CV of zero indicates a task that’s on budget, and
a positive CV indicates a task that’s under budget.
Expressed as EV – AC = CV
Expressed as EV – PV = SV
Expressed as EV ÷ AC = CPI
https://planergy.com/blog/earned-value-management/
5 / 12
Expressed as EV ÷ PV = SPI
It’s important to note that these equations require analysis beyond crunching the
numbers. For example, a project could have several tasks ahead of schedule, but
over budget. Or the SPI for a given project could indicate more work has been
completed than planned, but all of the work completed so far is made up of non-
critical tasks that won’t necessarily carry the project to the finish line.
Project managers can use these calculations as the foundation for more complex
ones that reveal deeper insights into why (for example) a project is ahead of
schedule but over budget. This process is known as earned value analysis, or EVA.
If, for example, the project is experiencing an ongoing variance that will most
likely continue (e.g., supply chain disruption due to political conflict, disease,
etc.): BAC ÷ CPI = EAC
Finally, to take another example, if the budget was incorrectly estimated at the
beginning of the project: AC + ETC = EAC
Let’s say the peripheral replacement task of our computer update project
experiences a cost overrun of $2500 in month four of the five-month schedule.
The actual percentage of work completed is only 60% instead of the expected 80%
https://planergy.com/blog/earned-value-management/
6 / 12
in month four. This creates a CV of less than one, due to a one-time event such as
supply chain disruption caused by severe weather. Fortunately for the project,
that event can only affect performance and cost once.
An overrun of $2500 at month four, when the project should be 80% complete
(and therefore the peripheral task should have an EV of $8,000 based on ⅘ x
$10,000), but an actual EV of only $6,000 would result in an AC of $8,500.
$12,500 = EAC
Assuming no other delays or changes, the estimated actual cost of the peripheral
replacement portion of this project will be $12,500.
If the project will most likely continue to perform as it has up to this point: EAC –
AC = ETC
If the parameters have changed significantly, a new estimate is required and ETC
is equal to the new estimate determined by the changes made.
https://planergy.com/blog/earned-value-management/
7 / 12
A negative VAC indicates the amount of money required to finish the project as
planned.
A positive VAC indicates the surplus funds available after completing the project
as planned.
You’ll need $2,500 more than originally planned to complete the peripheral
replacement.
If the project must meet its original budget: (BAC – EV) ÷ (BAC – AC) = TCPI
If our project team doesn’t have access to additional funds, they need to find a
way to makeup the negative cost variance by improving efficiency.
2.6 = TCPI
In order to catch up and meet their budget and performance goals at the end of
month five, the peripheral replacement task will need to more than double its
https://planergy.com/blog/earned-value-management/
8 / 12
current efficiencies (260%).
If you’re focused on baking EVM into your project management, start with a
checklist of project essentials that will make it easier to track and manage tasks,
costs, and overall project performance.
https://planergy.com/blog/earned-value-management/
9 / 12
6. Contingency Planning (Budget and Schedule): Develop
complementary schemes to ensure task and project completion, with an
emphasis on minimal disruption or additional cost.
7. Ongoing Contingency Management: Monitor and extrapolate schedule
and cost contingency values in real time to ensure sufficient resources are
in place.
8. Actual Cost Calculations: Calculate AC using not only cost system data,
but estimated values from outstanding invoices (accruals).
9. Accurate EVM Reporting: EVM is only as effective as the techniques
used to monitor performance, budget, and scope. EVM works best when
reported progress is expressed quantitatively; peripherals installed, total
offices completed, etc.
10. Management Buy-in and Engagement: It’s essential to educate and
engage management and the C-Suite to trust the EVM process and focus
on the importance of accuracy and completeness in gaining useful
insights and improving decision making.
11. Plan to Succeed by Investing in the Right Software: A cloud-based,
versatile solution like Planergy helps ensure total data transparency, easy
contingency management for all your processes and workflows, and deep
analytics powered by artificial intelligence to ensure your earned value
management system is complete, accurate, and accessible.
https://planergy.com/blog/earned-value-management/
10 / 12
What’s your goal today?
1. Use Planergy to manage purchasing and accounts
payable
We’ve helped save billions of dollars for our clients through better spend
management, process automation in purchasing and finance, and reducing
financial risks. To discover how we can help grow your business:
https://planergy.com/blog/earned-value-management/
11 / 12
Related Posts
https://planergy.com/blog/earned-value-management/
12 / 12