PM 04 (1) Project Time Management
PM 04 (1) Project Time Management
Project Management
– Activity definition
– Activity sequencing
– Activity Resource estimating
– Activity duration estimating
– Schedule development
– Schedule control
1- Activity Definition
Project schedules grow out of the basic document that initiate a project
– Project charter includes start and end dates and budget information
– Scope statement and WBS help define what will be done
• Activity definition involves developing a more detailed WBS and supporting explanations to
understand all the work to be done so you can develop realistic duration estimates
activity identifier (ID), and activity label or name, activity description, predecessor
activities, successor activities, logical relationships
a technical writing team may begin editing the draft of a large SS=15
document 15 days after they begin writing it. SS+15
C 6 SBSC+2
D 9 B;SCSD+4
Sample AOA and PDM
Put the activity letter or name and duration estimate in the box
Basic Rules for Creating AOA Diagrams
Activity &
• Find all of the activities that start at node 1. i Duration
j
• Arrows imply logical precedence only. the length of the arrow have any
significance.
• Smaller numbers to the left Each activity has its unique number
Basic Rules for Creating AOA Diagrams
Merge: Activity C depends upon the Burst: Activities B and C both depend
completion of both Activities A & B upon the completion of Activity A
A B
C
A
B
C
A C
Cross: activities C and D both
depend upon the completion of
B
Activities A and B D
Basic Rules for Creating AOA Diagrams
(Dummy Activities)
Sometimes it is necessary to insert dummy activities (duration & resource zero) in
order to maintain the clarity of the diagram and the precedence relationships
between activities.
A C
Activity C depend upon the
completion of Activities A and B, Dummy
and activity D depend upon the B D
completion of Activity B
Dummy A
Networks may have only one initial
event (with no predecessor) and
only one terminal event (with no B
successor).
Basic Rules for Creating AOA Diagrams
(Dummy Activities)
Two tasks cannot share the same start and end node.
A A
Activity Predecessors
C A,B C
A -- 1 2 3 1 3 C 4
B -- B B
2 Dummy
Activity Predecessors
A -- 2
A
B
C
--
--
A 2
X ؟ X
1 B
X A 1 B Y 5 3 5 Y 6
Y A,B 3 C
C
Z B,C Z
Z
4
4
Example: Draw AOA
Activity A B C D E F G H I J K L
2 2
D A D
A
E B E 6
1 B 6 1
3 3
C F C F
J J
4 4
G G
K
K 9 7 9
H 7 H
5 5
L L
I I 8
8
Other Common Mistakes in Creating
AOA Diagrams
3
Loop Creating
1 2 5
Redundant Dummies 4
Activity Predecessors
A --
D
B -- 2 4
A G
C --
Remove F
D A B
E C 1 H J
5 7 8
F D
G D C
I
H A,B,C,F 3 6
I E E
J G,H,I
Example: Find Mistakes
I 22
K 25
13
A N
P L M
12 B Q
14 30 50
T V
C R S
F 45
G 40 U 52
20 D
21 H
W
E
A Comparison of AON and AOA
Network Conventions
Activity Meaning AOA AON
A B C D
E L P
E L P
E2
To speed up the work, the distance is E1 L2
divided into two 150 km sections and
each group of works is done in each L1 P2
section
P1
Continue Exercise #1
E1-3: Draw AON and AOA
A)Please draw the AOA of previous PDM
B) Please draw the AOA and PDM if the distance is divided into
three100 km sections and each group of work is done in each
section
Exercise #1
E1-4:Drawing Network
A: find Mistakes E
B F
J
J D
A G K M
H
K
A N
I L M L
N
C H
P
B
V
F I
C R T
S
U
D G
E
Continue Exercise #1
E1-4:Drawing Network
B: Give Your Idea!!
As we learnt, AOA networks Can only show finish-to-start dependencies and AON
networks Better at showing different types of dependencies.
Please give your idea to apply the different types of dependencies on AOA networks and
draw the relevant AOA and AON for the following dependencies:
Final Product
Combined part 1
Part C
Part B Part A
Continue Exercise #1
E1-5: Draw AOA
Production
Process: Activity Description
A Manufacturing Part A
Purchase Machine B Manufacturing Part B
C Manufacturing Part C
D Manufacturing Part D
manufacturing E Purchase Machine #1
F Purchase Machine #2
Activities:
G Purchase Machine #3
A1 Test Part A
Part Test B1 Test Part B
C1 Test Part C
D1 Test Part D
Assemble M1 Assemble Combined Part 1
M2 Assemble Combined Part 2
M Assemble final Product
Final Test t Final Test
Exercise #1
)E1-6: Draw AON (PN
در ﻣﻨﻄﻘﻪ اي 2واﺣﺪ ﻣﺴﻜﻮﻧﻲ ﻗﺮار اﺳﺖ ﺳﺎﺧﺘﻪ ﺷﻮد ﻛﻪ ﻓﻌﺎﻟﻴﺖ ﻫﺎي ﻻزم در ﻫﺮ واﺣﺪ ﺑﻪ ﺷﺮح ذﻳﻞ اﺳﺖ:
Continue Exercise #1
)E1-6: Draw AON (PN
F6S7=0 F1S2=0 -1ﺑﺎﻳﺪ ﻣﺤﻮﻃﻪ ﻗﺒﻞ از ﻗﺮار دادن ﻗﺎﻟﺒﻬﺎي ﺑﺘﻦ ﻳﺎ ﻟﻮﻟﻪ ﻫﺎي ﻓﺎﺿﻼب ﭘﺎك ﺷﻮد.
F6S8=0 F1S3=0
-2ﻟﻮﻟﻪ ﮔﺬاري ﻓﺎﺿﻼب ﺑﺎﻳﺪ ﺣﺪاﻗﻞ 2ﺳﺎﻋﺖ ﻗﺒﻞ از اﺗﻤﺎم ﻗﺮاردادن ﻗﺎﻟﺒﻬﺎي ﺑﺘﻦ ﺑﻪ
F8F7+2 F3F2+2
ﭘﺎﻳﺎن ﺑﺮﺳﺪ ) ﺗﺎ ﺑﺘﻮان ﻗﺎﻟﺒﻬﺎي آﺧﺮي را روي اﺗﺼﺎﻻت ﺑﻴﻦ ﺳﺎﺧﺘﻤﺎن و ﻟﻮﻟﻪ ﻫﺎي
)(F7F8-2 )(F2F3-2 ﺧﺎرﺟﻲ ﻗﺮار داد ( .
S7S9+7 -3ﺗﻨﻬﺎ ﭘﺲ از ﮔﺬﺷﺖ 7ﺳﺎﻋﺖ از ﺷﺮوع ﻗﺮاردادن ﻗﺎﻟﺒﻬﺎي ﺑﺘﻦ و ﻟﻮﻟﻪ ﮔﺬاري S2S4+7
S8S9+7 ﻓﺎﺿﻼب ﻣﻲ ﺗﻮان ﻧﺼﺐ ﻣﻴﻞ ﮔﺮد ﻫﺎي ﺑﺘﻨﻲ را ﺷﺮوع ﻛﺮد .اﻳﻨﻜﺎر ﻳﻚ ﺳﺎﻋﺖ ﺑﻌﺪ از S3S4+7
اﺗﻤﺎم ﻗﺮاردادن ﻗﺎﻟﺒﻬﺎي ﺑﺘﻦ ﺑﻪ اﺗﻤﺎم ﺑﺮﺳﺪ و ﻧﻤﻲ ﺗﻮاﻧﺪ ﻗﺒﻞ از اﺗﻤﺎم ﻟﻮﻟﻪ ﮔﺬاري
F8F9=0 F3F4=0
ﻓﺎﺿﻼب ﺗﻤﺎم ﺷﻮد
F7F9+1 F2F4+1
F9S10+2 F4S5+2 -4ﻗﺒﻞ از ﺷﺮوع ﺑﺘﻦ رﻳﺰي ﻻزم اﺳﺖ 2ﺳﺎﻋﺖ ﺻﺮف ﺑﺎزرﺳﻲ ﭼﻬﺎر ﻓﻌﺎﻟﻴﺖ اول ﺷﻮد .
ﻧﻜﺘﻪ :ﭼﻮن ﻻزم اﺳﺖ 4ﻓﻌﺎﻟﻴﺖ اول ﺗﻤﺎم ﺷﻮﻧﺪ و ﺳﭙﺲ 2ﺳﺎﻋﺖ وﻗﻔﻪ ﺑﻴﻔﺘﺪ ﻛﺎﻓﻲ اﺳﺖ اﻳﻦ وﻗﻔﻪ ﺑﻴﻦ ﭘﺎﻳﺎن ﻧﺼﺐ ﻣﻴﻞ ﮔﺮدﻫﺎ
) ﻛﻪ آﺧﺮﻳﻦ ﻓﻌﺎﻟﻴﺖ در ﺑﻴﻦ 4ﺗﺎي اول اﺳﺖ ( و ﺷﺮوع ﺑﺘﻦ رﻳﺰي اﻧﺠﺎم ﺷﻮد .
Continue Exercise #1
)E1-6: Draw AON (PN
F1S6=0 -5ﻛﺎرﮔﺮاﻧﻲ ﻛﻪ ﻛﺎرﻫﺎي ﭘﺎك ﻛﺮدن ﻣﺤﻮﻃﻪ و ﺷﻴﺐ ﺑﻨﺪي را اﻧﺠﺎم ﻣﻲ دﻫﻨﺪ
F4S9=0 ﺑﺎﻳﺪ ﻛﺎر ﺧﻮد را در ﻳﻚ واﺣﺪ ﺗﻤﺎم ﻛﻨﻨﺪ ﺳﭙﺲ ﺑﻪ واﺣﺪ دﻳﮕﺮ ﺑﺮوﻧﺪ .اﻳﻦ
ﻣﻮﺿﻮع در ﻣﻮرد ﻧﺼﺐ ﻣﻴﻞ ﮔﺮدﻫﺎي ﺑﺘﻨﻲ ﻧﻴﺰ ﺑﺎﻳﺪ رﻋﺎﻳﺖ ﺷﻮد ،وﻟﻲ ﻗﺮاردادن
F2S7-2ﻳﺎ
ﻗﺎﻟﺒﻬﺎي ﺑﺘﻦ در دو واﺣﺪ ﻣﻲ ﺗﻮاﻧﺪ ﺗﺎ 2ﺳﺎﻋﺖ ﺑﻄﻮر ﻫﻤﺰﻣﺎن ) ﻣﻮازي ( اﻧﺠﺎم
S2S7+10 ﺷﻮﻧﺪ .در ﻣﻮرد ﻛﺎرﻫﺎي ﺑﺘﻦ رﻳﺰي ﻧﻴﺰ ﺗﺎ 2ﺳﺎﻋﺖ ﻫﻤﺰﻣﺎﻧﻲ در دو واﺣﺪ
F5S10-2ﻳﺎ اﺷﻜﺎل ﻧﺪارد .اﻳﻦ ﻣﻘﺪار ﺑﺮاي ﻛﺎرﻫﺎي ﻟﻮﻟﻪ ﮔﺬاري ﻓﺎﺿﻼب 6ﺳﺎﻋﺖ اﺳﺖ .
S5S10+2
F3S8-6ﻳﺎ
S3S8+10