Daily
Daily
Wednesday 20/07
Thursday 21/07
Friday 22/07
Layout of 108 poles has been in process and completed upto 85%.
Jointly with ADANI Engineer, SEEPZ JE & Supervisor of Jay Bhagwan visited SDF 1 A wing for any
further removal of live wire and redundant panel box.
Also visited lift room on the terrace to inspect for any repair/remove of panel and wires.
Assisted Pritesh Sir, with water recepit made list of bank statement written down with consumer
number.
Made excel sheet of cheque acknowledgement for bank.
Tuesday 26/07
Unloading of all the search light near all the Watch Tower.
One system consisited of three different spare units/boxes.
Main unit i.e. unit containing mototr system is kept down near watch tower and two other spare
unit are kept in cabin of watch tower.
Visited Meter room site with SEEPZ, JE, SDF A wing Ground & First floor is 95% completed.
Draft diagram of Booster pump was submitted to Rele Madam.
Wednesday 27/07
Visited SEEPZ++ site with Civil, JE, for inspection of pipe runnning through SEEPZ++ area.
Further discussion was made DE Sir & AE Madam about the requirement of instrument.
No meter room work was conducted toady as occassion of gutteri.
Showed the watch tower site to hydra crane owner to further conduct the work.
Thursday 28/07
Visited meter room site with SEEPZ, JE, ADANI and agency are jointly working togehter to get
everything in meter room cleaned up.
So far 97% of work is done in SDF 1 A wing.
Made rough estimate of the booster pump to be installed near SEEPZ ++.
Discussed with DE and AE about the estimate.
To conclude site has to be visited again to measure pipe circumference, whether pipe is DI or CI,
and roadside measurement.
Friday 29/07
Visited all the watch tower to dismantle the old flood light on watch tower.
Checked the foundation and whether the bolt of previous light matches new one.
Meter room work of SDF 2 A wing is completed by agency, site visit along with SEEPZ, JE &
ADANI Supervisor is remaining.
SDF 1 is nearly completed upto 97%. The work remaining is 3% should be done by supplier i.e.
ADANI will be completing the work at Saturday and Sunday.
Tuesday 02/08
Wednesday 03/08
Visited meter room of SDF 2 A wing and as inspected and further more cables were removed.
MB format was typed for the GJ 2 complex. As instructed by Pimple Sir.
Meter reading entry was done in excel sheet from MB.
Looked through Estimate of PWD SSR, CSR, DSR for the preparation of DPR of Gate 2 & 3.
Thursday 04/08
Friday 05/08
Visited watch tower near SDF 3 with SEEPZ, JE to see the installation of Search Light on tower.
Visited meter room site with agency worker to discuss with unit holders about scope of work
under their authority.
Listed all the Non DSR electrical items for the Gate 2 & 3. Made the PDF copy for further
attachment.
Visited both the watch tower of which the installation and commissioning is completed.
Monday 08/08