Daily

The document outlines the daily activities from July 19th to August 8th. Key activities included: 1) Inspecting and working on electrical infrastructure like meter rooms and watch towers across several buildings. 2) Meeting with various partners like SEEPZ, JE, ADANI to discuss electrical work and address issues. 3) Drafting plans and estimates for proposed work like layouts, booster pumps, and search light installations. 4) Preparing documentation like forms, lists, reports to support the electrical work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views5 pages

Daily

The document outlines the daily activities from July 19th to August 8th. Key activities included: 1) Inspecting and working on electrical infrastructure like meter rooms and watch towers across several buildings. 2) Meeting with various partners like SEEPZ, JE, ADANI to discuss electrical work and address issues. 3) Drafting plans and estimates for proposed work like layouts, booster pumps, and search light installations. 4) Preparing documentation like forms, lists, reports to support the electrical work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Tuesday 19/07

 Filled the MB of ADANI electricity bill.


 Visted meter room of SDF1 for inspection of the work given.
 Jointly discussion with SEEPZ, JE, and specific unit holders for removal of non-essential cables
and repair the damaged panel box.
 Looked for the elevation near the Gt no. 3, for water supply issue at SEEPZ++.

Wednesday 20/07

 Draft elevation layout for the SEEPZ++ was made.


 Discussed with DE & AE the less pressure supply of of water in SEEPZ++ premises.
 The layout of 108 pole inprocess.
 Visted Meter room of SDF1, Wing A. The live wire of supplier is yet to be removed by ADANI.
 Rearranging and removing unwanted electrical appliances in A wing of SDF 1 is completed upto
90%.
 Typed the Office note for Rele Madam, topic related to filmcity.

Thursday 21/07

 Assisted Pritesh Sir, with water report submission of 27/06 - 29/06.


 Jointly with SEEPZ, JE, visited the Site work going on at SDF 1 B wing.
 Work of SDF 1 of both wings has been completed upto 85%.
 Soon after completion of 15% work, thoroughly cleanly of the meter room will be done for
further work.

Friday 22/07

 Site work in SDF 2 A wing ground floor has been started.


 Visited Plot Neysa for checking wether the slope given by contour is same on site.
 Jointly visiting SDF 1 with SEEPZ, JE, for any query from unit holders.
 Assisted Pritesh Sir, with waterbill report as this was due date.
Monday 25/07

 Layout of 108 poles has been in process and completed upto 85%.
 Jointly with ADANI Engineer, SEEPZ JE & Supervisor of Jay Bhagwan visited SDF 1 A wing for any
further removal of live wire and redundant panel box.
 Also visited lift room on the terrace to inspect for any repair/remove of panel and wires.
 Assisted Pritesh Sir, with water recepit made list of bank statement written down with consumer
number.
 Made excel sheet of cheque acknowledgement for bank.

Tuesday 26/07

 Unloading of all the search light near all the Watch Tower.
 One system consisited of three different spare units/boxes.
 Main unit i.e. unit containing mototr system is kept down near watch tower and two other spare
unit are kept in cabin of watch tower.
 Visited Meter room site with SEEPZ, JE, SDF A wing Ground & First floor is 95% completed.
 Draft diagram of Booster pump was submitted to Rele Madam.

Wednesday 27/07

 Visited SEEPZ++ site with Civil, JE, for inspection of pipe runnning through SEEPZ++ area.
 Further discussion was made DE Sir & AE Madam about the requirement of instrument.
 No meter room work was conducted toady as occassion of gutteri.
 Showed the watch tower site to hydra crane owner to further conduct the work.

Thursday 28/07

 Visited meter room site with SEEPZ, JE, ADANI and agency are jointly working togehter to get
everything in meter room cleaned up.
 So far 97% of work is done in SDF 1 A wing.
 Made rough estimate of the booster pump to be installed near SEEPZ ++.
 Discussed with DE and AE about the estimate.
 To conclude site has to be visited again to measure pipe circumference, whether pipe is DI or CI,
and roadside measurement.
Friday 29/07

 Visited all the watch tower to dismantle the old flood light on watch tower.
 Checked the foundation and whether the bolt of previous light matches new one.
 Meter room work of SDF 2 A wing is completed by agency, site visit along with SEEPZ, JE &
ADANI Supervisor is remaining.
 SDF 1 is nearly completed upto 97%. The work remaining is 3% should be done by supplier i.e.
ADANI will be completing the work at Saturday and Sunday.
Tuesday 02/08

 Visited site with wadkar


 Lifted all the search light with Hydarulic crane and placed it on top.
 Removed and kept down the old dismantled search light at base of watch tower.
 Meter room work is in progress.
 SDF 2 B wing agency work is ongoing as instructed.

Wednesday 03/08

 Visited meter room of SDF 2 A wing and as inspected and further more cables were removed.
 MB format was typed for the GJ 2 complex. As instructed by Pimple Sir.
 Meter reading entry was done in excel sheet from MB.
 Looked through Estimate of PWD SSR, CSR, DSR for the preparation of DPR of Gate 2 & 3.

Thursday 04/08

 Completed in draft the MB work of GJ 2 Complex.


 Visited site with SEEPZ, JE, of meter room to discuss scope of work at meter room under unit
holders.
 Site visit was not possible because of health issue.

Friday 05/08

 Visited watch tower near SDF 3 with SEEPZ, JE to see the installation of Search Light on tower.
 Visited meter room site with agency worker to discuss with unit holders about scope of work
under their authority.
 Listed all the Non DSR electrical items for the Gate 2 & 3. Made the PDF copy for further
attachment.
 Visited both the watch tower of which the installation and commissioning is completed.
Monday 08/08

 Visited Meter room site of SDF 1 for final review.


 5 queries were found and they were informed to SEEPZ authority for actions.
 List of electrical items for Gate 2 & 3 were found in PWD CSR and CPWD DSR.