Bfc31802chapter4sem220222023 Part1a
Bfc31802chapter4sem220222023 Part1a
Chapter 4
ROAD CONSTRUCTION
1
BFC 31802 HIGHWAY ENGINEERING
SITE INVESTIGATION
SITE INVESTIGATION
Site investigation is carried in most cases as a preliminary to new works.
This investigation will reveal the level of ground water and the
true state of sub-strata.
2
BFC 31802 HIGHWAY ENGINEERING
SITE INVESTIGATION
3
BFC 31802 HIGHWAY ENGINEERING
SITE INVESTIGATION
(1) Disposal
- e.g. in the case of spoil from cuts
(2) Acquisition
- e.g for large fill projects such as reclaimation
4
5
BFC 31802 HIGHWAY ENGINEERING
Ø ROUTE SURVEY
Ø SITE INVESTIGATION
https://youtu.be/aDe03CSlTSU
https://youtu.be/-Aw_5GPE9bo
6
BFC 31802 HIGHWAY ENGINEERING
Ø SITE CLEARANCE
Ø EARTHWORKS
7
BFC 31802 HIGHWAY ENGINEERING
8
BFC 31802 HIGHWAY ENGINEERING
Ø SUB-BASE CONSTRUCTION
https://youtu.be/e_5_8q8TDVc
9
BFC 31802 HIGHWAY ENGINEERING
Ø BASE CONSTRUCTION
10
BFC 31802 HIGHWAY ENGINEERING
11
BFC 31802 HIGHWAY ENGINEERING
ROAD IS COMPLETED.
12
BFC 31802 HIGHWAY ENGINEERING
SURFACE PREPARATION
Prime Coats
The granular base layer can be prepared with a prime coat if necessary. A prime coat
is a sprayed application of a cutback or emulsion asphalt applied to the surface of
untreated subgrade or base layers in order to (Asphalt Institute, 2001):
1. Fill the surface voids and protect the subbase from weather.
2. Stabilize the fines and preserve the subbase material.
3. Promote bonding to the subsequent pavement layers.
Tack Coats
A tack coat is a thin bituminous liquid asphalt, emulsion or cutback layer applied
between HMA pavement lifts to promote bonding. Adequate bonding between
construction lifts and especially between the existing road surface and an overlay is
critical in order for the completed pavement structure to behave as a single unit and
provide adequate strength. If adjacent layers do not bond to one another they
essentially behave as multiple independent thin layers.
14
BFC 31802 HIGHWAY ENGINEERING
EARTHWORKS
This process consists of clearing, grubbing and stripping in
road construction area. It also includes the demolition and
disposal of soils to a formation level (top of the sub grade).
15
BFC 31802 HIGHWAY ENGINEERING
EARTHWORKS
Excavation
Similarly a shrinkage factor is defined for the compaction of a soil at it's final destination:
EARTHWORKS
Earthmoving Equipment
19
Dump Truck
BFC 31802 HIGHWAY ENGINEERING
EARTHWORKS
Earthmoving Equipment
Shovel
21
22
BFC 31802 HIGHWAY ENGINEERING
23
BFC 31802 HIGHWAY ENGINEERING
The first stage in the production of the Mass Haul Diagram is the calculation of the cross
sectional areas of cut or fill at different points along the road.
1
Area = hb 2 h( nh )
2
= hb + nh2
= h(b + nh)
24
BFC 31802 HIGHWAY ENGINEERING
b
S nh
2
S n
b
S nh
2
S n
25
BFC 3042 HIGHWAY ENGINEERING
Example 1:
The table below shows ground levels and formation levels for a proposed
road construction. Embankments are to be built with side slopes of 1:2.5 and
cuttings with slopes of 1:3.0. The embankment crest width and cutting base
width is 13m. It may be assumed that the ground is horizontal across the
section.
26
40
35
30
25
GROUND LEVEL
20
FORMATION LEVEL
HEIGHT
15
10
0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600
-5
-10
CHAINAGE 27
BFC 31802 HIGHWAY ENGINEERING
(a) Construct a Mass Haul diagram for the project given the following:
Bulking Factor = 0.8
Shrinkage Factor = 1.0
28
BFC 31802 HIGHWAY ENGINEERING
29
(b) A river breaks up the project at chainage 1160m. Calculate the volumes of
waste material and borrow for this scenarios:
(i) Material cannot be moved across the river
30
BFC 31802 HIGHWAY ENGINEERING
River
Borrow = 68,000 m3
Waste = 38,000 m3
31
32
BFC 31802 HIGHWAY ENGINEERING
(b) A river breaks up the project at chainage 1160m. Calculate the volumes
of waste material and borrow for this scenarios:
(ii) A Bailey bridge is constructed allowing material to be transported across the river
33
BFC 31802 HIGHWAY ENGINEERING
Borrow = 30,000 m3
Waste = 0 m3
34
35
BFC 31802 HIGHWAY ENGINEERING
Borrow = 30,000 m3
Waste = 0 m3
36
BFC 31802 HIGHWAY ENGINEERING
37
BFC 31802 HIGHWAY ENGINEERING
SUBGRADE PREPARATION
The subgrade is the in-situ material upon which the pavement structure is placed.
Increasing the load-bearing capacity of the subgrade soil will most likely improve pavement
load-bearing capacity and thus, pavement strength and performance.
Additionally, greater subgrade structural capacity can result in thinner (but not excessively
thin) and more economical pavement structures.
The finished subgrade should meet elevations, grades and slopes specified in the contract
plans.
38
BFC 31802 HIGHWAY ENGINEERING
SUBGRADE PREPARATION
Subgrade Performance
39
BFC 31802 HIGHWAY ENGINEERING
SUBGRADE PREPARATION
Poor subgrade should be avoided if possible, but when it is necessary to build over weak soils
there are several methods used to improved subgrade performance:
40
BFC 31802 HIGHWAY ENGINEERING
SUBGRADE PREPARATION
If the subgrade ruts excessively under construction traffic it may cause premature
pavement rutting and will result in variable paving thicknesses.
(2) Remove all debris, large rocks, vegetation and topsoil from the area to be paved
These items either do not compact well or cause non-uniform compaction and mat
thickness.
(3) Treat the subgrade under the area to be paved with an approved herbicide
This will prevent or at least retard future vegetation growth, which could affect subgrade
support or lead directly to pavement failure.
41
BFC 31802 HIGHWAY ENGINEERING
SURFACE PREPARATION
Preparing the subgrade and granular base course for new pavement
Involves activities such as subgrade stabilization, over-excavation of poor
subgrade, applying a prime coat or compacting the subgrade.
42
BFC 31802 HIGHWAY ENGINEERING
SURFACE PREPARATION
COMPACTION
Compaction is the process by which the volume of air in an Hot Mix Asphalt (HMA) mixture is
reduced by using external forces to reorient the constituent aggregate particles into a more
closely spaced arrangement.
Inadequate compaction results in a pavement with decreased stiffness, reduced fatigue life,
accelerated aging/decreased durability, rutting, raveling, and moisture damage.
43
BFC 31802 HIGHWAY ENGINEERING
SURFACE PREPARATION
Compaction Equipment
There are three basic pieces of equipment available for HMA compaction:
(1) Paver screed
(2) Steel wheeled roller
(3) Pneumatic tire roller.
44
BFC 31802 HIGHWAY ENGINEERING
Quality assurance addresses the overall problem of obtaining the quality of a service, product,
or facility in the most efficient, economical, and satisfactory manner possible.
Quality control
Those quality assurance actions and considerations necessary to assess production and
construction processes so as to control the level of quality being produced in the end
product.
This concept of quality control typically includes sampling and testing by the contractor to
monitor the process but usually does not include acceptance sampling and testing by the
agency/owner.
45
BFC 31802 HIGHWAY ENGINEERING
Acceptance
Sampling, testing, and the assessment of test results to determine whether or not the quality
of produced material or construction is acceptable in terms of the specifications.
Independent assurance
A management tool that requires a third party, not directly responsible for process control or
acceptance, to provide an independent assessment of the product and/or the reliability of
test results obtained from process control and acceptance testing.
The results of independent assurance tests should not be used as a basis of product
acceptance.
46
BFC 3042 HIGHWAY ENGINEERING
47