BL Check List
BL Check List
1-General:
2‐ Pre‐Analysis Checks
Y/N/NA The Project Information (ID, Name, Company name, etc) are Proper/according to Specs
Project Must Finish By is blank
Default Activity Type is set to "TASK"
Default Pecent Complete type is set to "Physical" or as Specs
Critical Path is Defined as the longest path or as Specs
3‐ Calendars Checks
4‐ Schedule Checks
5‐ Cost Loading
Major costs are broken down and assigned on the appropriate task
The Total budgeted cost are equal to contract award amount
Cost on Procurement activities are loaded on the end of the activity
Early activities are not excessively front loaded
7- Update
8- Constructual
9- Activites
Project title:
Contractor: Date of submission:
Date of Contract signature: Date of site handing over:
1‐ Pre‐Analysis Checks
The Project Information (ID, Name, Company name, etc) are Proper/according to Specs
Project Must Finish By is blank
2- Calendars
All Calendars are "Project" NOT "Global"
Constrcution,Weather, Procurement, Review and Approval activities calendars are proper
All Calendars are 7/D or as specs
All calendars have the project and company names
3- Schedule
Data Date is equal to contract award date or according to SPECS
The schdule depicts all project's scope
WBSs are grouped well
4- Milestones
All Contractual Milestones are indicated and met
All interim milestones are not constrained, unless the contract directs otherwise
Contract Award milestone is constrained to award date
5- Activities
Verify WBS system
Default Activity Type is set to "TASK"
Default Percent Complete type is set to "Duration" or as Specs
All Activites have clear and descriptive naming
All BOQ items are included into schedule activities
lags are not used instead of an activity
Number of critical activities are within Specs limits
Check the Schedule LOG
Constrains are optimum used, type of const.
Mendatory Constraints are NOT used
Normal Activities are free from date/float constraints
All Owner activities are represented
Activities assigned as Owner responsibility are correctly assigned
All procurement (specially long lead items) activities are represented
Turnover and Closeout activities are represented
Engineering and Procurment Activities are tied to construction