The delay and the output slew of different arcs are shown below:
Arc Delay (ps) Output Slew at pin Z (ps)
A→Z 10 20
B→Z 20 5
C→Z 30 10
What will be the arrival time and the output slew at the pin Z when Graph Based Analysis
(GBA) is performed for the setup check or late-mode check?
Solution:
For setup or late check, maximum arrival time should be taken. Hence, arrival time at Z = 42
ps
For GBA, the maximum slew from any path is taken. The maximum slew is from A to Z. Its
value is 20 ps.
Hence, the correct answer is (c) Arrival Time = 42 ps Output Slew = 20 ps
Here, T_capture=T_launch=0 ps [Since, delay on clock path is only the wire delay, which must
be ignored, according to the question]
10. For the same question above, what is the hold slack at the timing end-point FF2/D?
Arrival time at FF2/D = CLK-to-Q delay of FF1 + delay of inverter G2 = 20 + 50 = 70 ps
Required time = hold time of FF2=10 ps
Hold Slack = Arrival time – Required time = 70 -10=60 ps.
Hence, the correct answer is (b) 60 ps.