Lookahead Plan
Lookahead Plan
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Overall Completion -P-2 0.8% 0.776% 0.776% 0.776% 0.668% 0.456% 0.371% 0.371% 0.302%
### P2 Segment-04 20-Aug-23 26-Nov-23 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.04% 0.00% 0.22% 0.25%
Segment-04 A Micro Pilling Works on Periphery (Slope) Area` Completed Completed Nos 16 16 0
Segment-04 1 Marking for Pile Locations Completed Completed Nos 16 16 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-04 2 Pile Drilling / Filling on slope area for 24'' FW Main Header Supports completed completed Nos 16 16 0 0 0 0
Segment-04 3 Installation of Precasted pile cap on Slope Area Completed Completed Nos 16 16 0 0 0 0
Segment-04 B Pipe Bridge Micro Pilling & Pile Cap works on Existing Bund Wall Completed Completed NOs 16 16 0
Segment-04 1 Marking for Pile Locations Completed Completed NOs 16 16 0 0 0 0
Segment-04 2 Excavation of Micro Pillling works Completed Completed NOs 16 16 0 0 0 0
Segment-04 3 Pile Drilling/Filling with Grouting Material till surface level Completed Completed NOs 16 16 0 0 0 0
Segment-04 4 Installation of Precasted Pile Cap 25 27-Oct-23 20-Nov-23 NOs 16 16 5 4 5 1 0 0 0 0 0 0 15 0
Segment-04 5 Backfilling/Compaction & Inspection 4 22-Nov-23 25-Nov-23 NOs 16 16 0 0 0 12 4 0 0 0 0 0 12 4
Segment-04 A Trench works-(Location East side & West Side) 45 27-Oct-23 10-Dec-23 NO 167 167
Segment-04 1 Existing Road Cutting - Trench Works completed completed M2 1158 1115 43 0 0 0
Segment-04 2 Removal of interlock tiles - Trench Works completed completed M2 216 216 0 0 0 0
Segment-04 3 Trail Pit - Trench Works completed completed M3 90 90 0 0 0 0
Segment-04 4 Removal of concrete blocks - Trench Works 15 27-Oct-23 10-Nov-23 M2 1158 1,097 61 28 28 0 0 0 0 0 0 0 0 56 0
Segment-04 5 Excavation - Trench Works 14 30-Oct-23 12-Nov-23 M3 4032 3,875 157 57 78 22 0 0 0 0 0 0 0 157 0
Segment-04 6 Installation of raft Foundation - Trench Works 14 2-Nov-23 15-Nov-23 NO 77 68 9 2 4 3 0 0 0 0 0 0 0 9 0
Segment-04 7 Rebar & Concrete works for raft connection - Trench Works 16 5-Nov-23 20-Nov-23 NO 79 66 13 0 5 6 2 0 0 0 0 0 0 13 0
Segment-04 8 Raft connection portion coating - Trench Works 33 8-Nov-23 10-Dec-23 NO 79 65 14 0 2 3 3 3 3 0 0 0 0 8 6
Segment-04 9 Installation of Trench - Trench Works 35 11-Nov-23 15-Dec-23 NO 152 128 24 0 0 5 5 5 5 4 0 0 0 10 14
Segment-04 10 Backfilling of Trench - Trench Works 37 14-Nov-23 20-Dec-23 M3 2553 1,139 1414 0 0 153 268 267 268 267 191 0 0 421 993
Segment-04 C Pipe Bridge works Foundation_ Out Side/Inside/RC 14 12-Nov-23 25-Nov-23 NO 2 0 2
Segment-04 1 Excavation - Pipe Bridge 4 27-Oct-23 30-Oct-23 Cum 480 221 259 194 0 0 0 0 0 0 0 0 0 194 0
Segment-04 2 Blinding / Water proofing - Pipe Bridge 12 30-Oct-23 10-Nov-23 Cum 5 0 5 3 2 0 0 0 0 0 0 0 0 5 0
Segment-04 3 Rebar, Shutter & Concrete works for Foundation - Pipe Bridge 20 1-Nov-23 20-Nov-23 Cum 56 0 56 9 19 20 8 0 0 0 0 0 0 56 0
Segment-04 4 Rebar, Shutter & Concrete works for Pedestal - Pipe Bridge 24 3-Nov-23 26-Nov-23 Cum 8.1 0 8.075 1 2 3 2 1 0 0 0 0 0 8 1
Segment-04 5 Concrete Protection Coating - Pipe Bridge 28 5-Nov-23 2-Dec-23 M2 92 0 92.16 0 20 23 23 23 4 0 0 0 0 66 27
Segment-04 6 Backfilling - Pipe Bridge 33 10-Nov-23 12-Dec-23 Cum 207 0 207.36 0 7 44 44 44 44 25 0 0 0 95 113
Segment-04 D Structural Works 23 13-Nov-23 5-Dec-23
Segment-04 1 Installation of Strutural Pipe Bridges 31 5-Nov-23 5-Dec-23 Nos 1 0 1 0 0 0 1 0 0.000 0 0 0 0 1 0
Segment-04 E Piping Works 57 27-Oct-23 22-Dec-23
Segment-04 1 Fabrication of Piping Spools 16 27-Oct-23 11-Nov-23 Spools 165 147 18 7 8 1 0 0 0 0 0 0 0 16 0
Segment-04 2 Delivery to MOT Yard 15 27-Oct-23 10-Nov-23 Spools 165 147 18 8 8 0 0 0 0 0 0 0 0 16 0
Segment-04 3 Erection of Piping Primary Supports 34 15-Nov-23 18-Dec-23 Nos 47 0 47 0 0 5 9 10 10 9 4 0 0 14 33
Segment-04 4 Erection of Piping Spools 31 19-Nov-23 19-Dec-23 Spools 165 0 165 0 0 0 32 38 37 37 21 0 0 32 133
Segment-04 5 Installation of Grooved Coupling 32 19-Nov-23 20-Dec-23 Nos 151 151 0 0 0 29 33 33 33 23 0 0 29 122
Segment-04 6 Hydrotesting/ Flushing 33 19-Nov-23 21-Dec-23 Lot 1 0 1 0 0 0 1 0 0 0 0 0 0 1 0
Segment-04 7 Installation of Gate Valves 34 19-Nov-23 22-Dec-23 Nos 8 8 0 0 0 2 2 1 2 1 0 0 2 6
Segment-04 8 Installation of Cover Slab - Trench Works 42 11-Nov-23 22-Dec-23 NO 138 138 0 0 23 23 23 23 23 23 0 0 46 92
Segment-04 F E & I Works 27 6-Nov-23 2-Dec-23 Lot 2 0 2
Segment-04 1 Cable trench excavation 22 6-Nov-23 27-Nov-23 Lot 3 0 3 0 1 1 1 0 0 0 0 0 0 3 0
Segment-04 2 Earthig works & Cable laying and Termination 4 29-Nov-23 2-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-04 G Cathodic Protection Works 9 21-Nov-23 29-Nov-23 Lot 2 0 2
Segment-04 3 Installation of Cathodic protection 9 21-Nov-23 29-Nov-23 Lot 2 0 2 0 0 0 1 1 0 0 0 0 0 1 1
Segment-04 I Reinstatement Works civil 11 18-Dec-23 28-Dec-23 Lot 2 0 2
Segment-04 1 Reinstatement of Interlocking walk way & Crash barriers 8 16-Nov-23 23-Nov-23 RM 194 0 194 0 0 49 145 0 0 0 0 0 0 194 0
Segment-04 2 Reinstatement of Bund wall side slope (at Large Inlet location) 9 18-Nov-23 26-Nov-23 SQM 24 0 24 0 0 0 19 5 0 0 0 0 0 19 5
Segment-04 J Mechanical Completion 4 29-Nov-23 2-Dec-23 Lot 2 0 2
Segment-04 1 Removal of exisitng Valves 2 27-Nov-23 28-Nov-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-04 2 Refurbishment of existing Valves 2 28-Nov-23 29-Nov-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-04 3 Installation of exisitng Valve with new 24" Pipe Header 2 29-Nov-23 30-Nov-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-04 4 Temporary spool arragement from exisitng Isolation Valve to the above Valve 2 30-Nov-23 1-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-04 5 Walkdown 2 1-Dec-23 2-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-04 6 Punchlist Clearance 2 2-Dec-23 3-Dec-23 Lot 1 0 1 0 0 0 0 0 1 0 0 0 0 0 1
Segment-04 7 Dossier Submission 2 3-Dec-23 4-Dec-23 Lot 1 0 1 0 0 0 0 0 1 0 0 0 0 0 1
Segment-04 8 Achieve MC 2 4-Dec-23 5-Dec-23 Lot 1 0 1 0 0 0 0 0 1 0 0 0 0 0 1
Page 1 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
### P2 Segment-05 63 25-Sep-23 26-Nov-23 0 0.27% 0.34% 0.41% 0.48% 0.54% 0.61% 0.68% 0.75% 0.80% 0.00% 1.50% 3.38%
Segment-05 A Micro Piling Works Completed Completed 0
Segment-05 1 24" Header Line Micro pile completed completed NO 57 57 0 0 0 0
Segment-05 2 Pipe Bridge Micorpiles completed completed NO 6 6 0 0 0 0
Segment-05 3 Pipe Support / Goal Post Micorpiles completed completed NO 5 5 0 0 0 0
Segment-05 B Pile cap installation 23 27-Oct-23 18-Nov-23 NO 30 30
Segment-05 1 24" Header Line pile cap On bund -17 11-Dec-23 23-Nov-23 NO 26 24 2 0 0 0 2 0 0 0 0 0 0 2 0
Segment-05 2 Instalaltion of Precasted Pile Cap - Pipe Bridge -17 13-Dec-23 25-Nov-23 NO 2 0 2 0 0 0 0 2 0 0 0 0 0 0 2
Segment-05 3 Instalaltion of Precasted Pile Cap - Pipe Bridge -17 15-Dec-23 27-Nov-23 NO 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-05 3 Pipe Support/Goal Post Foundation On Bund -16 16-Dec-23 29-Nov-23 NO 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-05 C Installation of Trench - Trench Works 36 27-Oct-23 1-Dec-23 NO 65 65
Segment-05 1 Existing Road Cutting - Trench Works 49 25-Sep-23 12-Nov-23 M2 210 203 7 1 1 0 0 0 0 0 0 0 0 2 0
Segment-05 2 Removal of interlock tiles - Trench Works Completed Completed M2 210 210 0 0 0 0
Segment-05 3 Trail Pit - Trench Works 52 2-Oct-23 22-Nov-23 M3 120 108 12 2 2 1 1 0 0 0 0 0 0 6 0
Segment-05 4 Removal of concrete blocks - Trench Works 55 4-Oct-23 27-Nov-23 M2 210 207 3 1 2 0 0 0 0 0 0 0 0 3 0
Segment-05 5 Excavation - Trench Works 53 5-Oct-23 26-Nov-23 M3 1380 929 451 60 59 60 59 17 0 0 0 0 0 238 17
Segment-05 6 Installation of raft Foundation - Trench Works 57 6-Oct-23 1-Dec-23 NO 64 23 41 5 5 5 5 5 0 0 0 0 0 20 5
Segment-05 7 Rebar & Concrete works for raft connection - Trench Works 58 6-Oct-23 2-Dec-23 NO 65 14 51 6 6 6 6 7 0 0 0 0 0 24 7
Segment-05 8 Raft connection portion coating - Trench Works 58 7-Oct-23 3-Dec-23 NO 63 15 48 6 5 6 6 6 1 0 0 0 0 23 7
Segment-05 9 Installation of Trench - Trench Works 58 12-Oct-23 8-Dec-23 NO 167 51 116 14 14 14 14 14 14 0 0 0 0 56 28
Segment-05 10 Backfilling of Trench - Trench Works 52 19-Oct-23 9-Dec-23 M3 1928 77 1851 249 249 249 250 249 249 35 0 0 0 997 533
Segment-05 D In side Sleepers Baby Sleeper 7 1-Dec-23 7-Dec-23 0
Segment-05 1 Excavation - In side Sleepers 48 12-Oct-23 28-Nov-23 NOS 30 15 15 3 2 2 2 1 0 0 0 0 0 9 1
Segment-05 2 Blinding / Water proofing - In side Sleepers 47 14-Oct-23 29-Nov-23 NOS 30 16 14 2 2 2 2 1 0 0 0 0 0 8 1
Segment-05 3 Layout and Installation of Foundation - In side Sleepers 43 19-Oct-23 30-Nov-23 NOS 30 11 19 4 3 3 3 2 0 0 0 0 0 13 2
Segment-05 4 Concrete Protection Coating - In side Sleepers 42 21-Oct-23 1-Dec-23 NOS 30 0 30 5 5 5 5 5 0 0 0 0 0 20 5
Segment-05 5 Backfilling - In side Sleepers 41 23-Oct-23 2-Dec-23 NOS 30 0 30 5 5 6 5 5 0 0 0 0 0 21 5
Segment-05 E Pipe Bridge works_ Out Side 1 0
Segment-05 1 Excavation - Pipe Bridge 16 14-Oct-23 29-Oct-23 Cum 402 58 344 43 0 0 0 0 0 0 0 0 0 43 0
Segment-05 2 Blinding / Water proofing - Pipe Bridge 16 16-Oct-23 31-Oct-23 Cum 9 0 9 2 0 0 0 0 0 0 0 0 0 2 0
Segment-05 3 Rebar, Shutter & Concrete works for Foundation - Pipe Bridge 7 1-Nov-23 7-Nov-23 Cum 40 0 40 18 22 0 0 0 0 0 0 0 0 40 0
Segment-05 4 Rebar, Shutter & Concrete works for Pedestal - Pipe Bridge 6 9-Nov-23 14-Nov-23 Cum 5 0 5 0 2 3 0 0 0 0 0 0 0 5 0
Segment-05 5 Concrete Protection Coating - Pipe Bridge 6 11-Nov-23 16-Nov-23 NO 1 0 1 0 0 1 0 0 0 0 0 0 0 1 0
Segment-05 6 Backfilling - Pipe Bridge 5 13-Nov-23 17-Nov-23 Cum 357 0 357 0 0 357 0 0 0 0 0 0 0 357 0
Segment-05 F Structural Works 6 20-Nov-23 25-Nov-23 0
Segment-05 1 Installation of Strutural Pipe Bridges 5 20-Nov-23 24-Nov-23 Nos 3 0 3 0 0 0 3 0 0 0 0 0 0 3 0
Segment-05 2 Installation of Structural Pipe Supports 5 21-Nov-23 25-Nov-23 Nos 3 0 3 0 0 0 3 0 0 0 0 0 0 3 0
Segment-05 G Piping Works 46 27-Oct-23 11-Dec-23 Spools 246 246
Segment-05 1 Fabrication of Piping Spools 16 27-Oct-23 11-Nov-23 Spools 246 246 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-05 2 Delivery to MOT Yard 16 27-Oct-23 11-Nov-23 Spools 246 221 25 11 11 1 0 0 0 0 0 0 0 23 0
Segment-05 3 Erection of Piping Primary Supports 5 19-Nov-23 23-Nov-23 Nos 68 0 68 0 0 0 68 0 0 0 0 0 0 68 0
Segment-05 4 Erection of Piping Spools 9 21-Nov-23 29-Nov-23 Spools 246 0 246 0 0 0 110 136 0 0 0 0 0 110 136
Segment-05 5 Installation of Grooved Coupling 9 22-Nov-23 30-Nov-23 Nos 233 0 233 0 0 0 78 155 0 0 0 0 0 78 155
Segment-05 6 Hydrotesting/ Flushing 4 1-Dec-23 4-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-05 7 Installation of Gate Valves 5 1-Dec-23 5-Dec-23 Nos 26 0 26 0 0 0 0 6 20 0 0 0 0 0 26
Segment-05 8 Installation of Cover Slab - Trench Works 5 7-Dec-23 11-Dec-23 NO 51 0 51 0 0 0 0 0 21 30 0 0 0 0 51
Segment-05 H E & I Works 7 1-Dec-23 7-Dec-23 Lot 1 1
Segment-05 1 Cable trench excavation 5 1-Dec-23 5-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-05 2 Earthig works & Cable laying and Termination 6 2-Dec-23 7-Dec-23 Lot 1 0 1 0 0 0 0 0 1 0 0 0 0 0 1
Segment-05 I Cathodic Protection Works 4 8-Dec-23 11-Dec-23 Lot 1 1
Segment-05 3 Installation of Cathodic protection 4 8-Dec-23 11-Dec-23 Lot 1 0 1 0 0 0 0 0 1 0 0 0 0 0 1
Segment-05 K Passive fire protection 0 8-Dec-23 7-Dec-23 NOS 2 2
Segment-05 1 Installation of Passive fire protection for CS structure 6 2-Dec-23 7-Dec-23 NOS 2 0 2 0 0 0 0 0 2 0 0 0 0 0 2
Segment-05 L Reinstatement Works 8 4-Dec-23 11-Dec-23 0
Segment-05 1 Reinstatement of RCC Road at RCC Trenches locations 5 4-Dec-23 8-Dec-23 SQM 303 0 303 0 0 0 0 0 303 0 0 0 0 0 303
Segment-05 2 Reinstatement of Interlocking walk way & Crash barriers 5 6-Dec-23 10-Dec-23 SQM 194 0 194 0 0 0 0 0 117 77 0 0 0 0 194
Segment-05 3 Reinstatement of Bund wall side slope (at Micro Piling & Cap location) 6 6-Dec-23 11-Dec-23 SQM 200 0 200 0 0 0 0 0 100 100 0 0 0 0 200
Segment-05 I Mechanical Completion 1 0
Page 2 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 3 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Segment-12 11 Installation of Cover Slab - Trench Works 11 24-Nov-23 4-Dec-23 NO 167 0 167 0 0 0 16 106 45 0 0 0 0 16 151
Segment-12 J E & I Works 29 20-Nov-23 18-Dec-23 0
Segment-12 1 Cable trench excavation 29 20-Nov-23 18-Dec-23 Lot 4 0 4 0 0 0 1 1 1 1 0 0 0 1 3
Segment-12 2 Earthig works & Cable laying and Termination 10 12-Dec-23 21-Dec-23 Lot 1 0 1 0 0 0 0 0 0 1 0 0 0 0 1
Segment-12 M Reinstatement Works 13 10-Dec-23 22-Dec-23 0
Segment-12 1 Reinstatement of Interlocking walk way & Crash barriers 13 10-Dec-23 22-Dec-23 Lot 1 0 1 0 0 0 0 0 0 1 0 0 0 0 1
Segment-12 N Mechanical Completion 12 15-Dec-23 26-Dec-23 0
Segment-12 1 Removal of exisitng Valves 1 15-Dec-23 15-Dec-23 Lot 1 0 1 0 0 0 0 0 0 1 0 0 0 0 1
Segment-12 2 Refurbishment of existing Valves 2 15-Dec-23 16-Dec-23 Lot 1 0 1 0 0 0 0 0 0 1 0 0 0 0 1
Segment-12 3 Installation of exisitng Valve with new 24" Pipe Header 3 16-Dec-23 18-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 1 0 0 0 1
Segment-12 4 Temporary spool arragement from exisitng Isolation Valve to the above Valve 3 18-Dec-23 20-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 1 0 0 0 1
Segment-12 5 Walkdown 2 21-Dec-23 22-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 1 0 0 0 1
Segment-12 6 Punchlist Clearance 2 23-Dec-23 24-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
Segment-12 7 Dossier Submission 1 25-Dec-23 25-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
Segment-12 8 Achieve MC 1 26-Dec-23 26-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
Segment-12 O PRE COMM & RFC 11 18-Dec-23 28-Dec-23 0
Segment-12 1 Boxup/ Reinstatement 3 18-Dec-23 20-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 1 0 0 0 1
Segment-12 2 Leaktest 4 20-Dec-23 23-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 1 0 0 0 1
Segment-12 3 RFC walkdown 2 23-Dec-23 24-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
Segment-12 4 Punch closeout 2 24-Dec-23 25-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
Segment-12 5 RFC Dossier submission 2 25-Dec-23 26-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
Segment-12 6 Dossier approval/ Achieve RFC 2 26-Dec-23 27-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
Segment-12 7 SEGis ready for Commissioning 2 27-Dec-23 28-Dec-23 Lot 1 0 1 0 0 0 0 0 0 0 0 1 0 0 1
P2 Segment-12A 70 10-Sep-23 18-Nov-23 0 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.02% 0.00% 0.13% 0.15%
Segment-12A A Micro Piling works on Bund Wall for Pipe Bridge area Completed Completed 0
Segment-12A B Construction of Pipe Bridge (1no.) & Pipe Supports (3nos.) Completed Completed Nos 6 6 0
Segment-12A 2 Blinding / Water proofing - Pipe Bridge Completed Completed CUM 120 120 0 0 0 0
Segment-12A 3 Rebar, Shutter & Concrete works for Foundation - Pipe Bridge Completed Completed CUM 120 120 0 0 0 0
Segment-12A 4 Rebar, Shutter & Concrete works for Pedestal - Pipe Bridge Completed Completed CUM 120 120 0 0 0 0
Segment-12A 5 Concrete Protection Coating - Pipe Bridge Completed Completed Nos 120 120 0 0 0 0
Segment-12A 4 Rebar,Shutter & Concrete for foundation - Outside Sleeper 12 27-Oct-23 7-Nov-23 Nos 14 10 4 2 1 0 0 0 0 0 0 0 0 3 0
Segment-12A 5 Rebar,Shutter & Concrete for Pedestal - Outside Sleeper 10 29-Oct-23 7-Nov-23 Nos 14 10 4 3 1 0 0 0 0 0 0 0 0 4 0
Page 4 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Segment-12A 2 Earthig works & Cable laying and Termination 11 11-Oct-23 21-Oct-23 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-12A 1 Reinstatement of Bund wall side slope (at Sleeper Raft Location) 6 13-Nov-23 18-Nov-23 Nos 9 0 9 0 0 8 1 0 0 0 0 0 0 9 0
Segment-12A I Tie in 1 0
Segment-12A 1 SEGto be made Ready for connection with Exisitng 2 14-Nov-23 15-Nov-23 Nos 1 0 1 0 0 1 0 0 0 0 0 0 0 1 0
Segment-12A 3 Installation of exisitng Valve with new 24" Pipe Header 2 20-Nov-23 21-Nov-23 Lot 1 0 1 0 0 0 1 0 0 0 0 0 0 1 0
Segment-12A 4 Temporary spool arragement from exisitng Isolation Valve to the above Valve 2 22-Nov-23 23-Nov-23 Lot 1 0 1 0 0 0 1 0 0 0 0 0 0 1 0
### P2 Segment-31A 56 18-Oct-23 12-Dec-23 0 0.04% 0.04% 0.04% 0.04% 0.01% 0.00% 0.18% 0.01%
Segment-31A A Outside Sleepers (6 Nos) Pre Cast completed completed 0
Segment-31A 1 Excavation - Outside Sleeper completed completed Nos 6 6 0 0 0 0
Segment-31A 2 Blinding / Water proofing - Outside Sleeper completed completed Nos 6 6 0 0 0 0
Segment-31A 3 Installation of Precast - Outside Sleeper completed completed Nos 6 6 0 0 0 0
Segment-31A 4 Concrete Protection Coating - Outside Sleeper completed completed Nos 6 6 0 0 0 0
Segment-31A 5 Backfilling - Outside Sleeper completed completed Nos 6 6 0 0 0 0
Segment-31A B Outside Sleepers (Cast in situ)3 nos 0
Segment-31A 1 Excavation - Outside Sleeper completed completed NO 2 2 0 0 0 0
Segment-31A 2 Blinding - Outside Sleeper completed completed NO 2 2 0 0 0 0
Segment-31A 3 Water proofing - Outside Sleeper completed completed NO 2 2 0 0 0 0
Segment-31A 4 Rebar,Shutter & Concrete for foundation - Outside Sleeper completed completed NO 2 2 0 0 0 0
Segment-31A 5 Rebar,Shutter & Concrete for Pedestal - Outside Sleeper completed completed NO 2 2 0 0 0 0
Segment-31A 6 Concrete Protection Coating - Outside Sleeper completed completed NO 2 2 0 0 0 0
Segment-31A 7 Backfilling - Outside Sleeper completed completed NO 2 2 0 0 0 0
Segment-31A C Construction of Asphalt Road Crossing at 3 Locations 1 0
Segment-31A 1 Excavation for Pipe Installation 26 18-Oct-23 12-Nov-23 Nos 2 0 2 1 0 0 0 0 0 0 0 0 0 1 0
Segment-31A 2 Backfilling/Compaction & Inspection 11 7-Nov-23 17-Nov-23 Nos 2 0 2 0 1 1 0 0 0 0 0 0 0 2 0
Segment-31A 3 Installation of Precasted Cover Slabs 21 8-Nov-23 28-Nov-23 Nos 2 0 2 0 1 0 1 0 0 0 0 0 0 2 0
Segment-31A D Piping Works 1 0
Segment-31A 1 Fabrication of Piping Spools 10 27-Oct-23 5-Nov-23 Spools 78 78 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-31A 2 Delivery to MOT Yard 16 27-Oct-23 11-Nov-23 Spools 78 70 8 3 4 0 0 0 0 0 0 0 0 7 0
Segment-31A 3 Erection of Piping Primary Supports -5 27-Nov-23 21-Nov-23 Nos 14 0 14 0 0 7 7 0 0 0 0 0 0 14 0
Segment-31A 4 Erection of Piping Spools 8 14-Nov-23 21-Nov-23 Spools 78 10 68 0 0 34 34 0 0 0 0 0 0 68 0
Segment-31A 5 Installation of Grooved Coupling 6 17-Nov-23 22-Nov-23 Nos 69 69 0 0 12 57 0 0 0 0 0 0 69 0
Segment-31A 6 Hydrotesting/ Flushing 2 22-Nov-23 23-Nov-23 TP 1 0 1 0 0 0 1 0 0 0 0 0 0 1 0
Segment-31A 7 Installation of New 4nos. Butterfly Valves at PRV Station 2 23-Nov-23 24-Nov-23 Nos 4 0 4 0 0 0 4 0 0 0 0 0 0 4 0
Segment-31A 8 Installation of Gate Valves 3 23-Nov-23 25-Nov-23 Nos 9 0 9 0 0 0 6 3 0 0 0 0 0 6 3
Segment-31A 9 Backfilling/Compaction & Inspection 7 26-Nov-23 2-Dec-23 Nos 200 0 200 0 0 0 0 172 28 0 0 0 0 0 200
Page 5 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 6 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Segment-44 4 Temporary spool arragement from exisitng Isolation Valve to the above Valve 1 7-Dec-23 7-Dec-23 Lot 1 0 1 0 0 0 0 0 1 0 0 0 0 0 1
Segment-44 5 Walkdown 1 8-Dec-23 8-Dec-23 Lot 1 0 1 0 0 0 0 0 1 0 0 0 0 0 1
Segment-44 6 Punchlist Clearance 1 9-Dec-23 9-Dec-23 Lot 1 0 1 0 0 0 0 0 0 1 0 0 0 0 1
Segment-44 7 Dossier Submission 1 10-Dec-23 10-Dec-23 Lot 1 0 1 0 0 0 0 0 0 1 0 0 0 0 1
Segment-44 8 Achieve MC 1 11-Dec-23 11-Dec-23 Lot 1 0 1 0 0 0 0 0 0 1 0 0 0 0 1
Page 7 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 8 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Segment-50 3 Installation of exisitng Valve with new 24" Pipe Header 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-50 4 Temporary spool arragement from exisitng Isolation Valve to the above Valve 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-50 5 Walkdown 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-50 6 Punchlist Clearance 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-50 7 Dossier Submission 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-50 8 Achieve MC 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Page 9 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Segment-30B 1 Reinstatment of Existing GRE U/G Pipes at Sleepr locations (Blinded with end caps) 6 5-Dec-23 10-Dec-23 Nos 19 0 19 0 0 0 0 0 13 6 0 0 0 0 19
Page 10 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 11 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Segment-21 4 Rebar,Shutter & Concrete for foundation - Outside Sleeper 16 15-Oct-23 30-Oct-23 NO 4 0 4 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 5 Rebar,Shutter & Concrete for Pedestal - Outside Sleeper 16 18-Oct-23 2-Nov-23 NO 4 0 4 1 0 0 0 0 0 0 0 0 0 1 0
Segment-21 6 Concrete Protection Coating - Outside Sleeper 18 22-Oct-23 8-Nov-23 NO 4 0 4 1 1 0 0 0 0 0 0 0 0 2 0
Segment-21 7 Backfilling - Outside Sleeper 18 23-Oct-23 9-Nov-23 NO 4 0 4 1 1 0 0 0 0 0 0 0 0 2 0
Segment-21 C Trench works-(Location East side & West Side) 1 0
Segment-21 1 Existing Road Cutting - Trench Works 9 4-Oct-23 12-Oct-23 M2 1020 768 252 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 2 Removal of interlock tiles - Trench Works 11 4-Oct-23 14-Oct-23 M2 390 390 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 3 Trail Pit - Trench Works 13 4-Oct-23 16-Oct-23 M3 90 70 20 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 4 Removal of concrete blocks - Trench Works 13 4-Oct-23 16-Oct-23 M2 1020 826 194 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 5 Excavation - Trench Works 26 4-Oct-23 29-Oct-23 M3 5052 4,144 908 69 0 0 0 0 0 0 0 0 0 69 0
Segment-21 6 Installation of raft Foundation - Trench Works 26 12-Oct-23 6-Nov-23 NO 89 27 62 16 7 0 0 0 0 0 0 0 0 23 0
Segment-21 7 Rebar & Concrete works for raft connection - Trench Works 25 13-Oct-23 6-Nov-23 NO 88 0 88 25 10 0 0 0 0 0 0 0 0 35 0
Segment-21 8 Raft connection portion coating - Trench Works 27 13-Oct-23 8-Nov-23 NO 88 0 88 23 16 0 0 0 0 0 0 0 0 39 0
Segment-21 9 Installation of Trench - Trench Works 30 15-Oct-23 13-Nov-23 NO 167 0 167 39 39 16 0 0 0 0 0 0 0 94 0
Segment-21 10 Backfilling of Trench - Trench Works 21 25-Oct-23 14-Nov-23 M3 3013 0 3013 1004 1005 573 0 0 0 0 0 0 0 2582 0
Segment-21 11 Installation of Cover Slab - Trench Works 20 27-Oct-23 15-Nov-23 NO 126 0 126 44 44 31 0 0 0 0 0 0 0 119 0
Segment-21 D Micro Piling works on Bund Wall for Pipe Bridge area 1 0
Segment-21 1 Pipe Bridge - Outside Bund 9 1-Oct-23 9-Oct-23 NO 16 0 16 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 E Pipe Bridge works_ Out Side 1 0
Segment-21 1 Excavation - Pipe Bridge 13 7-Oct-23 19-Oct-23 Cum 341.6 3 338.6 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 2 Blinding / Water proofing - Pipe Bridge 10 12-Oct-23 21-Oct-23 Cum 1.5 0 1.485 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 3 Rebar, Shutter & Concrete works for Foundation - Pipe Bridge 9 17-Oct-23 25-Oct-23 Cum 12.8 0 12.75 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 4 Rebar, Shutter & Concrete works for Pedestal - Pipe Bridge 7 21-Oct-23 27-Oct-23 Cum 3 0 3 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 5 Concrete Protection Coating - Pipe Bridge 5 28-Oct-23 1-Nov-23 NO 1 0 1 1 0 0 0 0 0 0 0 0 0 1 0
Segment-21 6 Backfilling - Pipe Bridge 6 2-Nov-23 7-Nov-23 Cum 119 0 119 40 79 0 0 0 0 0 0 0 0 119 0
Segment-21 F Structural Works 1 0
Segment-21 1 Installation of Strutural Pipe Bridges 4 9-Nov-23 12-Nov-23 Nos 1 0 1 0 1 0 0 0 0 0 0 0 0 1 0
Segment-21 2 Installation of Structural Pipe Supports 4 11-Nov-23 14-Nov-23 Nos 3 0 3 0 0 3 0 0 0 0 0 0 0 3 0
Segment-21 G Piping Works 1 0
Segment-21 1 Fabrication of Piping Spools 45210 10-Oct-23 Spools 102 -102 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 2 Delivery to MOT Yard 45215 15-Oct-23 Spools 64 -64 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 1 Erection of Piping Primary Supports 13 12-Nov-23 24-Nov-23 Nos 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 2 Erection of Piping Spools 8 14-Nov-23 21-Nov-23 Spools 136 0 136 0 0 68 68 0 0 0 0 0 0 136 0
Segment-21 3 Installation of Grooved Coupling 7 16-Nov-23 22-Nov-23 Nos 128 0 128 0 0 37 91 0 0 0 0 0 0 128 0
Segment-21 4 Hydrotesting/ Flushing 3 22-Nov-23 24-Nov-23 Lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 5 Installation of Gate Valves 4 22-Nov-23 25-Nov-23 Nos 7 0 7 0 0 0 6 1 0 0 0 0 0 6 1
Segment-21 H E & I Works 1 0
Segment-21 1 Cable trench excavation 5 26-Nov-23 30-Nov-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-21 2 Earthig works & Cable laying and Termination 3 30-Nov-23 2-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-21 I Cathodic Protection Works 1 0
Segment-21 3 Installation of Cathodic protection 8 30-Nov-23 7-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-21 K Reinstatement Works 1 0
Segment-21 1 Reinstatement of Interlocking walk way & Crash barriers 6 1-Dec-23 6-Dec-23 RM 194 0 194 0 0 0 0 33 161 0 0 0 0 0 194
Segment-21 2 Reinstatement of Bund wall side slope (at Large Inlet location) 10 2-Dec-23 11-Dec-23 SQM 24 0 24 0 0 0 0 0 17 7 0 0 0 0 24
Segment-21 L Mechanical Completion 12 4-Dec-23 15-Dec-23 0
Segment-21 1 Removal of exisitng Valves 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 2 Refurbishment of existing Valves 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 3 Installation of exisitng Valve with new 24" Pipe Header 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 4 Temporary spool arragement from exisitng Isolation Valve to the above Valve 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 5 Walkdown 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 6 Punchlist Clearance 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 7 Dossier Submission 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 8 Achieve MC 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 M PRE COMM & RFC 1 0
Segment-21 1 Boxup/ Reinstatement 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 2 Leaktest 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 3 RFC walkdown 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 4 Punch closeout 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 5 RFC Dossier submission 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 6 Dossier approval/ Achieve RFC 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-21 7 SEGis ready for Commissioning 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
### P2 Segment-26 44 04-Oct-23 16-Nov-23 0 0.002166 0.29% 0.36% 0.43% 0.51% 0.58% 0.65% 0.72% 0.79% 0.87% 0.22% 1.59% 3.61%
Segment-26 A Outside Sleepers (Precast) 1 0
Segment-26 1 Excavation - Outside Sleeper 17 5-Oct-23 21-Oct-23 Nos 4 0 4 0 0 0 0 0 0 0 0 0 0 0 0
Segment-26 2 Blinding / Water proofing - Outside Sleeper 17 10-Oct-23 26-Oct-23 Nos 4 0 4 0 0 0 0 0 0 0 0 0 0 0 0
Segment-26 3 Installation of Precast - Outside Sleeper 19 15-Oct-23 2-Nov-23 Nos 4 0 4 1 0 0 0 0 0 0 0 0 0 1 0
Page 12 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 13 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Segment-29 1 Reinstatment of Existing GRE U/G Pipes at Sleepr locations (Blinded with end caps) 6 21-Dec-23 26-Dec-23 Nos 19 0 19 0 0 0 0 0 0 0 7 12 0 0 19
Page 14 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 15 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 16 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
P2 SEG39-82MTR UG NETWORK 41 25-Oct-23 04-Dec-23 0 0.04% 0.04% 0.04% 0.04% 0.04% 0.02% 0.00% 0.16% 0.06%
Segment-39 Pipe Supports Founation 16 27-Oct-23 11-Nov-23 No 3 0 3
Segment-39 Excavation - Pipe Supports 6 27-Oct-23 1-Nov-23 No 3 0 3 2 0 0 0 0 0 0 0 0 0 2 0
Segment-39 Blinding - Pipe Supports 15 26-Oct-23 9-Nov-23 No 3 0 3 1 1 0 0 0 0 0 0 0 0 2 0
Segment-39 Water proofing - Pipe Supports 3 27-Oct-23 29-Oct-23 No 3 0 3 2 0 0 0 0 0 0 0 0 0 2 0
Segment-39 4 Rebar, Shutter & Concrete works for Pedestal - Pipe Bridge 4 30-Oct-23 2-Nov-23 No 3 0 3 3 0 0 0 0 0 0 0 0 0 3 0
Segment-39 5 Concrete Protection Coating - Pipe Bridge 5 1-Nov-23 5-Nov-23 No 3 0 3 2 1 0 0 0 0 0 0 0 0 3 0
Segment-39 6 Backfilling - Pipe Bridge 4 3-Nov-23 6-Nov-23 No 3 0 3 1 2 0 0 0 0 0 0 0 0 3 0
Segment-39 A U/G piping works.-82RM 1 0
Segment-39 1 Excavation - 10 27-Oct-23 5-Nov-23 RM 82 20 62 43 12 0 0 0 0 0 0 0 0 55 0
Segment-39 2 Formation and levelling 6 7-Nov-23 12-Nov-23 RM 82 0 82 0 55 27 0 0 0 0 0 0 0 82 0
Segment-39 E Piping Works 1 0
Segment-39 1 Erection of Piping Primary Supports 45233 2-Nov-23 Nos 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 2 Erection of Piping Spools 8 5-Nov-23 12-Nov-23 Spools 33 0 33 0 25 8 0 0 0 0 0 0 0 33 0
Segment-39 3 Installation of Grooved Coupling 8 7-Nov-23 14-Nov-23 Nos 34 0 34 0 17 17 0 0 0 0 0 0 0 34 0
Segment-39 4 Hydrotesting/ Flushing 3 15-Nov-23 17-Nov-23 lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 5 Installation of Gate Valves 1 Nos 4 4 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 F E & I Works 1 0
Segment-39 1 Cable trench excavation 6 16-Nov-23 21-Nov-23 Lot 1 0 1 0 0 1 0 0 0 0 0 0 0 1 0
Segment-39 2 Cable laying and Termination 2 21-Nov-23 22-Nov-23 Lot 1 0 1 0 0 0 1 0 0 0 0 0 0 1 0
Segment-39 3 Earthig works 1 28-Nov-23 28-Nov-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-39 G Cathodic Protection Works 1 0
Segment-39 3 Installation of Cathodic protection 6 23-Nov-23 28-Nov-23 Lot 1 0 1 0 0 0 1 0 0 0 0 0 0 1 0
Segment-39 H Reinstatement Works 1 0
Segment-39 1 Reinstatment of Existing GRE U/G Pipes at Sleepr locations (Blinded with end caps) 8 19-Nov-23 26-Nov-23 Nos 19 0 19 0 0 0 15 4 0 0 0 0 0 15 4
Segment-39 I Mechanical Completion 14 20-Nov-23 3-Dec-23 0
Segment-39 1 Removal of exisitng Valves 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 2 Refurbishment of existing Valves 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 3 Installation of exisitng Valve with new 24" Pipe Header 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 4 Temporary spool arragement from exisitng Isolation Valve to the above Valve 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 5 Walkdown 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 6 Punchlist Clearance 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 7 Dossier Submission 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-39 8 Achieve MC 1 Lot 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
### P2 SEG43 41 25-Oct-23 04-Dec-23 0 0.06% 0.06% 0.06% 0.06% 0.06% 0.02% 0.00% 0.22% 0.08%
Segment-43 B Outside Sleepers (Cast in situ) 1 NOS 1 0
Segment-43 1 Excavation - Outside Sleeper 11 25-Oct-23 4-Nov-23 NO 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-43 2 Blinding - Outside Sleeper 12 27-Oct-23 7-Nov-23 NO 1 0 1 0 0 0 0 0 0 0 0 0 0 0 0
Segment-43 3 Water proofing - Outside Sleeper 12 30-Oct-23 10-Nov-23 NO 1 0 1 1 0 0 0 0 0 0 0 0 0 1 0
Segment-43 4 Rebar,Shutter & Concrete for foundation - Outside Sleeper 13 1-Nov-23 13-Nov-23 NO 1 0 1 1 0 0 0 0 0 0 0 0 0 1 0
Segment-43 5 Rebar,Shutter & Concrete for Pedestal - Outside Sleeper 14 3-Nov-23 16-Nov-23 NO 1 0 1 1 0 0 0 0 0 0 0 0 0 1 0
Segment-43 6 Concrete Protection Coating - Outside Sleeper 13 5-Nov-23 17-Nov-23 NO 1 0 1 0 1 0 0 0 0 0 0 0 0 1 0
Segment-43 7 Backfilling - Outside Sleeper 12 7-Nov-23 18-Nov-23 NO 1 0 1 0 1 0 0 0 0 0 0 0 0 1 0
Segment-43 E Piping Works 1 0
Segment-43 4 Erection of Piping Spools 6 7-Nov-23 12-Nov-23 Spools 11 0 11 0 8 3 0 0 0 0 0 0 0 11 0
Segment-43 5 Installation of Grooved Coupling 6 9-Nov-23 14-Nov-23 Nos 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-43 6 Hydrotesting/ Flushing 3 15-Nov-23 17-Nov-23 lot 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Segment-43 F E & I Works 1 0
Segment-43 1 Cable trench excavation 10 16-Nov-23 25-Nov-23 Lot 1 0 1 0 0 1 0 0 0 0 0 0 0 1 0
Segment-43 2 Cable laying and Termination 6 21-Nov-23 26-Nov-23 Lot 1 0 1 0 0 0 1 0 0 0 0 0 0 1 0
Segment-43 3 Earthig works 5 28-Nov-23 2-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-43 G Cathodic Protection Works 1 0
Segment-43 3 Installation of Cathodic protection 6 27-Nov-23 2-Dec-23 Lot 1 0 1 0 0 0 0 1 0 0 0 0 0 0 1
Segment-43 H Reinstatement Works 1 0
Segment-43 1 Reinstatment of Existing GRE U/G Pipes at Sleepr locations (Blinded with end caps) 6 28-Nov-23 3-Dec-23 Nos 19 0 19 0 0 0 0 13 6 0 0 0 0 0 19
Page 17 of 18
MOT CONSTRUCTION SCHEDULE - PRIORITY - 2 Weekly Distribution Monthly Distribution
Priority SEG
Sr. Activity Forecast Forecast UOM Scope Prev. This Cum. Bal. 27-Oct 3-Nov 10-Nov 17-Nov 24-Nov 1-Dec 8-Dec 15-Dec 22-Dec 29-Dec Oct-23 Nov-23 Dec-23
Nos Start Finish Week Week Comp
Page 18 of 18