Weekly Project-W HSE Report RPCO 19th To 25th March 2023
Weekly Project-W HSE Report RPCO 19th To 25th March 2023
Date: 26/03/2023
AGENDA
HS&E STATISTICS
INCIDENT SUMMARY
KEY ISSUES
PROJECT RELATED UPDATES
WELFARE FACILITY
HSE BEST PRACTISE
ENVIRONMENTAL BEST PRACTISE
HSE MILESTONES & ACHIEVEMENTS
1 Week Look Ahead
5. NO. OF INCIDENT/ACCIDENT 0 1 1
Lagging Indicators
1.2
0.8
0.6
0.4
0.2
0
15-Feb
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
KEY ISSUES
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
INCIDENT SUMMARY
PACKAGE CONTRACTOR INCIDENT INCIDENT BRIEF DECRIPTION ROOT CAUSE ACTION STATUS
CLASSIFICATION DATE
A RPCO Property damage 15-02-23 Electric pole hit by unknown vehicle Poor Illumination
at incident
Hard
barriers
Close
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS
BENAN completed below task:
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
WELFARE FACILITY
CONTRACTOR TOTAL EMPLOYEE’S HSE TOILET RESTING SHELTER PRAYER AREA
NAME AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE
PHOTO PHOTO
RPCO - Soft barricades installed and rock fall signage been posted at Monolith
RPCO – Soft Barricading from vehicle movement area, workplace and pedestrian road (R1) for awareness & control .
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE
PHOTO PHOTO
RPCO - Pre-Task TBT conducted on daily basis by covering all topics related to
RPCO- Conducted medical Emergency drill with JASARA HSE/Project Team to activities at Wadi , Monolith & Golf area.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
ENVIRONMENTAL BEST PRACTISE
PHOTO PHOTO
RPCO – Daily transfer of General waste to main skip been practiced to RPCO – Daily water spraying at access road for dust Control maintained.
avoid accumulation of waste at construction site.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE
PHOTO
BENAN - Pre-Task TBT conducted on daily basis by covering the all topics BENAN – Barricading drilling area before start of activity & after completion of
work conducting housekeeping. Also, workers maintaining PPE’s during work
related to activities and Safe lifting at Monolith.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT MILESTONES/ACHIEVEMENTS
SN DESCRIPTION
RPCO -
Up to
• R2: Up to Station 1+200 Excavation and lowering access.
• R3 14+000 top of embankment backfill 30CM 1st layer of Subgrade
1. Material.
• Up to Station (14+175) spreading, grading, levelling and compacting
top of embankment backfill 30CM layer of Subgrade Material.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT MILESTONES/ACHIEVEMENTS
SN DESCRIPTION
BENAN
1.
BENAN
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
ONE WEEKS LOOK AHEAD
BENAN •
•
Submit the draft reports of Wadi Floor
Continue Drilling at Monolith area ( BH M126-BH M121-BH M114--BH M118- BH M104)
• Start Drilling on the Secondary Route
• Preliminary Geological Map
• Benchmarks
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
END OF REPORT
THANK YOU