Weekly Project-W HSE Report RPCO 19th To 25th March 2023

Uploaded by

abhinav dj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
150 views

Weekly Project-W HSE Report RPCO 19th To 25th March 2023

Uploaded by

abhinav dj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 17

PROJECT-W

WEEKLY HSE REPORT


Prepared by: Abhinav.D.J

Date: 26/03/2023
AGENDA

HS&E STATISTICS
INCIDENT SUMMARY
KEY ISSUES
PROJECT RELATED UPDATES
WELFARE FACILITY
HSE BEST PRACTISE
ENVIRONMENTAL BEST PRACTISE
HSE MILESTONES & ACHIEVEMENTS
1 Week Look Ahead

PROJECT-W ADVANCE WORK PACKAGE-A


HS&E Statistics
SL.NO FIGURES WEEK PROJECT TO DATE (PTD) YEAR TO DATE (YTD)

1. TOTAL MANPOWER 1356 6602 6602

2. TOTAL MAN-HOUR 13560 66020 66020

3. SAFE MAN-HOURS WORKED WITHOUT LTI 13560 66020 66020

4. NO. OF NEAR MISS REPORTED 3 15 15

5. NO. OF INCIDENT/ACCIDENT 0 1 1

6. TOTAL NO. OF LOST TIME INJURY (LTI) REPORTED 0 0 0

7. NO. OF SAFETY TRAINING CONDUCTED 1 6 6

8. NO. OF SAFETY OBSERVATION REPORTED 0 40 40

9. NO OF HSE INSPECTION CONDUCTED 1 11 11

10. NO. OF SAFETY MEETING’S CONDUCTED 1 10 10

11. NO. OF EMERGENCY DRILL 1 1 1

12. NO. OF MANAGEMENT WALKTHROUGH 1 12 12

13. NO. OF SAFETY AUDIT 0 1 1


PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HS&E Statistics
SL.NO FIGURES WEEK PROJECT TO DATE (PTD) YEAR TO DATE (YTD)

14. NO. OF WEEKLY TOOLBOX SESSION 1 9 9

15. NO. OF ENVIRONMENTAL INCIDENT/ACCIDENT 0 0 0

16. NO. OF ENVIRONMENTAL INSPECTION 1 4 4

17. NO. OF ENVIRONMENTAL OBSERVATION 0 2 2

Lagging Indicators
1.2

0.8

0.6

0.4

0.2

0
15-Feb

LTI Motor Vehicle Incident LTI Motor Vehicle Incident


Property Damage Fire Property Damage Fire
Total Recordable Incident Rate Total Recordable Incident Rate

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
KEY ISSUES

SN CONTRACTOR KEY ISSUES ACTION TAKEN

• Interference from Local residence & over speeding, camels wanderings


on workplace/project area.
1 RPCO • Mosque to be provided at offices area.
In Progress of rectification

2 BENAN • Internet not established


• Medical items as per checklist is missing (Need to be provided)
In Progress of rectification

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
INCIDENT SUMMARY

PACKAGE CONTRACTOR INCIDENT INCIDENT BRIEF DECRIPTION ROOT CAUSE ACTION STATUS
CLASSIFICATION DATE

A RPCO Property damage 15-02-23 Electric pole hit by unknown vehicle Poor Illumination
at incident
Hard
barriers
Close

location/ Lack of installed


protection barriers Assigned
security
guard/
flagman
at
entrance

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS

RPCO completed below task:


1. • Fence-1A: (4+075 to 4+840) 255 posts installed, and foundation concreted PHOTO
with 8 CUM (Total = 881 Posts Installed).
• Fence–1A: (6+200 to 6+800) Clearing / Grading.
• R1: (0+680 to 0+700) alignment access works.
• Station (14+400 to 14+650) spreading, grading, levelling and compacting
SINGLE 30 cm layer of Subgrade Material.
• Station (11+800 to 12+000) spreading, grading, levelling and compacting 1st
backfill 30CM layer of Subgrade Material.
• Station (14+050 to 14+175) spreading, grading, levelling and compacting
top of embankment backfill 30CM layer of Subgrade Material.
• Importing Subgrade Material to Site using 14 Dump Trucks: (qty = 20 trips
= 480 CUM).
• R2: (0+800 to 1+200) Excavation and lowering access.
• R2: (0+000 to 0+250) spreading, grading, levelling and compacting 1st
BACKFILL 30CM layer.
• (14+175 to 14+400) FDT for top of embankment backfill 30CM 1st layer of
Subgrade Material.
• FDT Re-test for Subgrade Materials at sta. 13+300 to 14+000 (Hole no. 10
& 11)
• FDT for Road backfill, graded, levelled, and compacted at stations 14+175
to 14+400
• 7 days concrete cylinder testing for fence 2 C25 MPA.
• Fresh Concrete Testing of Fence A1 Footing Concreting from Sta. 4+075
to 4+840

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS
BENAN completed below task:

• Continue drilling in BH M 106 ( total depth 42 m) from 36 m to 42


2. m.
• Disassembling the rig in BH M106 and moving to BH M118.
• Moving the rig in BH M 129 to BH M 126.
• Moving the rig in BH M 109 to BH M 114.
• Moving the rig in BH M 103 to BH M 121.

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
WELFARE FACILITY
CONTRACTOR TOTAL EMPLOYEE’S HSE TOILET RESTING SHELTER PRAYER AREA
NAME AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED

RPCO 161 3/3 6/6 6/6 1/3


BENAN 39 2/3 8/3 0/3 1/2

• RPCO – To provide prayer Rooms


• BENAN – Need to work on provision of Welfare facility & Waste Skips due to multiple location of work at Plateau , Wadi & Fence 2 area.

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE

PHOTO PHOTO

RPCO - Soft barricades installed and rock fall signage been posted at Monolith
RPCO – Soft Barricading from vehicle movement area, workplace and pedestrian road (R1) for awareness & control .

way provided at both sides of service road

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE

PHOTO PHOTO

RPCO - Pre-Task TBT conducted on daily basis by covering all topics related to
RPCO- Conducted medical Emergency drill with JASARA HSE/Project Team to activities at Wadi , Monolith & Golf area.

practice and handling of Medical Emergency at work site .

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
ENVIRONMENTAL BEST PRACTISE

ENVIRONMENTAL BEST PRACTISE ENVIRONMENTAL BEST PRACTISE

PHOTO PHOTO

RPCO – Daily transfer of General waste to main skip been practiced to RPCO – Daily water spraying at access road for dust Control maintained.
avoid accumulation of waste at construction site.

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE

PHOTO

BENAN - Pre-Task TBT conducted on daily basis by covering the all topics BENAN – Barricading drilling area before start of activity & after completion of
work conducting housekeeping. Also, workers maintaining PPE’s during work
related to activities and Safe lifting at Monolith.

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT MILESTONES/ACHIEVEMENTS

SN DESCRIPTION

RPCO -
Up to
• R2: Up to Station 1+200 Excavation and lowering access.
• R3 14+000 top of embankment backfill 30CM 1st layer of Subgrade
1. Material.
• Up to Station (14+175) spreading, grading, levelling and compacting
top of embankment backfill 30CM layer of Subgrade Material.

• Fence1A Started from airport security fence and reached up to


2.
station 6+000 Installed the posts and concreted.

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
PROJECT MILESTONES/ACHIEVEMENTS

SN DESCRIPTION
BENAN

• Site clinic & Communication devices has been setup

1.

BENAN

• 29 BH from 30 BH wadi floor has been completed


2. • 9 of 30 BH on Monolith Phase 1 has been completed & 4 progress.

• Fencing of Helipad & security gate is completed.

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
ONE WEEKS LOOK AHEAD

CONTRACTOR NAME ONE WEEKS LOOK AHEAD


RPCO • R2 –25% Excavation and Starting the delivery of back fill material.
• R3- Shall Apply the full subgrade up to Station 15+500.
• Fence 2- Chain link up to station 8+000 shall be complete.
• Fence 1A –Concrete Posts up to 7+000.

BENAN •

Submit the draft reports of Wadi Floor
Continue Drilling at Monolith area ( BH M126-BH M121-BH M114--BH M118- BH M104)
• Start Drilling on the Secondary Route
• Preliminary Geological Map
• Benchmarks

PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From March 19th Mar 25th, 2023
END OF REPORT