Temporary Works
Temporary Works
CHRIS BRIDGES
Temporary Works
Construction
Contractor
Alternatives/Concepts
Design
ContractorsPreferences
Objective
Role
• What
Available
Different
Full-time
Groundwater
are solutions
the
presence
material?
temporary
level available?
required?
works required for?
• Duration
Available
Do
Frequent
Surcharges
nothing?
ofsite
plant?
temporary
visits? works?
• Over-arching
Instrumentation
Preferred / non-preferred
Durability contractual
& monitoring
requirements?
sub-contractor?
• Partial factors / factors of safety
• Construction sequencing
• Interaction with permanent works
Risks
• Time
• Reliance on third party information
• Lack of information
• Consequence of failure
• Cost
Pile & Crane Platforms
Pile & Crane Platforms
• BR 470
Detailed loads for load cases to be
provided by rig contractor/supplier.
Based on Meyerhof – footing
punching through a dense sand layer
over a soft clay.
Examples in BR 470.
Pile & Crane Platforms
Must haves:
• Information on ground conditions (test pits)
• Crane/pile rig loadings etc
• Information on material to form platform
Excavations
• Batters
• Sheet piles
• Cutter soil mixing
• Soil nails
• Rock support – dowels, bolts
• Piles – contiguous, secant, soldier piles, ground anchors
(temporary & permanent)
Excavations – Soil Nails
Excavations – Soil Nails
Shored Mechanically Stabilised Earth (SMSE) Walls
RSS
Soil Nails
Shored Mechanically Stabilised Earth (SMSE) Walls
Excavations – Temporary Ground Anchors
Excavations
Guangxi
“A stitch in time”
Nicholl Highway 2004
What Happened?
KEDRON BROOK
Phase 2
Phase 1
Kedron Brook Cut-and-cover Structure
Contractors Requirements
Flood Wall built on
Phase 1 Slab
DIVERTED ON TO THE
KEDRON BROOK
PHASE 1 ROOF SLAB
PHASE 2
PHASE 1
KEDRON BROOK
Interface
between Phases
1 and 2
Kedron Brook Cut-and-cover Structure
Contractors Preferences
• CSM
• Sheet piles - adopted
• Soil nails – partially adopted
• Soldier piles
Kedron Brook Cut-and-cover Structure
Design
• Flood risk (RL5m normal flow to
RL9m flood)
• Analysis undertaken included
design of sheet piles, rock anchors
and walers
• Excavation required below shallow
rockhead
• Rock socket used for temporary
stability until toe anchor installed
• Permits excavation to below toe of
wall. Socket then redundant
• Reused sheet piles, steel walers
for phase 2
Kedron Brook Cut-and-cover Structure
Construction Sequence
Kedron Brook Cut-and-cover Structure
Construction Sequence
Kedron Brook Cut-and-cover Structure
Construction Sequence
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 1
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
Construction – Phase 2
Kedron Brook Cut-and-cover Structure
March 2010
Kedron Brook Cut-and-cover Structure
March 2010
Kedron Brook Cut-and-cover Structure
August 2010
Kedron Brook Cut-and-cover Structure
October 2011
Kedron Park Hotel Tunnels
Contractors Requirements
• Cut-and-cover tunnel
• Cut required to in excess of Kedron Park
30m depth with final Hotel
South Wall
Eastern Side
Name: Stiff Clay Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 25 °
30 30
Proof of concept.
Surcharge (Unit Weight): 32 kN/m³
20 20
Stiff Clay
Elevation (mRL)
• Detailed design incorporating 15 15
phases.
-5 -5
0 5 10 15 20 25 30 35 40 45 50 55 60 65
Distance
Kedron Park Hotel Tunnels
Design - Layout
Kedron Park Hotel Tunnels
Design – South Wall Elevation
Kedron Park Hotel Tunnels
Design – East Wall Elevation
Kedron Park Hotel Tunnels
Design – Section
Kedron Park Hotel Tunnels
Design – Tower Crane
Kedron Park Hotel Tunnels
Design – Construction Sequence
Kedron Park Hotel Tunnels
Design - Instrumentation
Kedron Park Hotel Tunnels
Design – Analysis 0 5 10 15 20 25 30 35 40 45 50 55 60 65
35 35
South Wall
Eastern Side
Name: Stiff Clay Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 25 °
30 30
Name: Hard Clay Unit Weight: 21 kN/m³ Cohesion: 5 kPa Phi: 28 °
Name: VLS - LS Siltstone Unit Weight: 22 kN/m³ Cohesion: 22.5 kPa Phi: 30 °
Name: MS Siltstone Unit Weight: 22 kN/m³ Cohesion: 200 kPa Phi: 40 °
1.333
25 25
Surcharge (Unit Weight): 32 kN/m³
20 20
Stiff Clay
Elevation (mRL)
15 15
Hard Clay
10 10
5 5
VLS - LS Siltstone
0 0
MS Siltstone
-5 -5
0 5 10 15 20 25 30 35 40 45 50 55 60 65
Distance
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Design – Analysis
Kedron Park Hotel Tunnels
Kedron Park Hotel Tunnels
Kedron Park Hotel Tunnels
Construction Role
• Full time
• Record progress during
construction
• Mapping of face to
correlate testing
• Observe testing
• Record groundwater
• Site photography
• ITP sign off
• Site instructions
Kedron Park Hotel
Tunnels
Construction Sequence
Kedron Park Hotel Tunnels
Construction Role
Kedron Park Hotel Tunnels
Construction Role
East Wall
North Wall
Kedron Park Hotel Tunnels
Construction Role
GRP Nails
East Wall
Kedron Park Hotel Tunnels
Construction Role
Western End
Kedron Park Hotel Tunnels
Construction Role
Kedron Park Hotel Tunnels
Construction Role
0.140
Bridges, 2012
0.040 Unpublished
dh/H = 0.5%
dh = 4H/1000
0.000 dh = H/1000
0 5 10 15 20 25 30 35
Wall Height, H (m)
Wall Height vs Nail Length
(Published Results)
35
30
0
0 2 4 6 8 10 12 14 16 18 20
Nail Length (m)
Kedron Park Hotel Tunnels
Completed Structure
• Two year design life, 4 month
construction (nail wall).
• 18m deep excavation with further 10m
deep piled wall below