Puncak Alam Housing SDN BHD (Formerly Known As Bukit Cerakah Development SDN BHD) V Menta Construction SDN BHD & Anor
Puncak Alam Housing SDN BHD (Formerly Known As Bukit Cerakah Development SDN BHD) V Menta Construction SDN BHD & Anor
B
COURT OF APPEAL (PUTRAJAYA) — CIVIL APPEAL NO W-02–517
OF 2010
ABDUL MALIK ISHAK, AZAHAR MOHAMED AND ANANTHAM
KASINATHER JJCA
18 JANUARY 2013
C
The appellant was the developer of a housing project in which the first
respondent was appointed as the main earthworks contractor. The first
respondent was the second respondent’s nominated subcontractor. The
I appellant alleged that there was an embankment failure in Phase 3B. Two years
after the alleged embankment failure, the first respondent’s solicitors issued a
notice pursuant to s 218(1)(e) of the Companies Act 1965 for the sums due
and owing by the appellant to the first respondent for the works carried out in
the project. The appellant agreed to pay the sum of RM11,498,788.12 as
288 Malayan Law Journal [2014] 1 MLJ
A (7) The first respondent had carried out its works under the contracts. The
works were accepted by the appellant through two methods: testing and
certification process. The appellant even issued its final certificate for
payment and the certificate of making good defects. But the first
respondent was not paid the balance sums due to it under the certificates
B (see para 58).
(8) The allegations of fraud and conspiracy were based on the facts known to
the appellant prior to entering the settlement agreement. It could not be
denied that the first respondent had carried out substantial works for the
C benefit of the appellant and the first respondent had been kept out of the
funds since 2002. The appellant had benefitted and enjoyed the fruits of
the first respondent’s labour (see para 59).
Notes
For cases on effect of novation, see 3(3) Mallal’s Digest (4th Ed, 2013 Reissue)
paras 5697–5699.
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 291
A For cases on payment, see 3(2) Mallal’s Digest (4th Ed, 2013 Reissue) paras
3645–3648.
For cases on settlement agreement, see 3(2) Mallal’s Digest (4th Ed, 2013
Reissue) paras 2995–2997.
B Cases referred to
Ang Hiok Seng @ Ang Yeok Seng v Yim Yut Kiu (personal representative of the estate
of Chan Weng Sun, deceased) [1997] 2 MLJ 45, FC (refd)
Charles Rickards LD v Oppenhaim [1950] 1 KB 616, CA (refd)
Datuk Jagindar Singh & Ors v Tara Rajaratnam [1986] 1 MLJ 105, PC (refd)
C Hotel Royal Ltd Bhd v Tina Travel & Agencies Sdn Bhd [1990] 1 MLJ 21, HC
(refd)
Davie v Magistrates of Edinburgh 1953 SC 34 (refd)
Kah Seng Construction Sdn Bhd v Selsin Development Sdn Bhd [1996] MLJU
359; [1997] 1 CLJ Supp 448, HC (refd)
D Kamal Kant Paliwal v Smt Prakash Devi Paliwal and others AIR 1976 Raj 79,
HC (refd)
Knowles v Roberts (1888) 38 Ch D 263, CA (refd)
Lian Keow Sdn Bhd (in liquidation) & Anor v Overseas Credit Finance (M) Sdn
Bhd & Ors [1988] 2 MLJ 449, SC (refd)
E Low v Bouverie [1891] 3 Ch 82, CA (refd)
Lyl Hooker Sdn Bhd v Tevanaigam Savisthri & Anor [1987] 2 MLJ 52, SC (refd)
M and R (minors) (sexual abuse: expert evidence), Re [1996] 4 All ER 239, CA
(refd)
M/s RC Thakkar v (The Bombay Housing Board by its successors) now The Gujarat
F Housing Board AIR 1973 Guj 34 (refd)
MBf Finance Bhd v Sri-Hartamas Dvpt Sdn Bhd [1992] 1 CLJ 160, HC (refd)
Malayan Plant (Pte) Ltd v Moscow Narodny Bank Ltd [1980] 2 MLJ 53, PC
(refd)
Malaysian International Merchant Bankers Bhd v Datuk Mohd Salleh & Anor
G [1988] 1 CLJ (Rep) 786, HC (refd)
Mawar Awal (M) Sdn Bhd v Kepong Management Sdn Bhd & Anor [2005] 6
MLJ 132, HC (refd)
Morgan Guaranty Trust Co of New York v Lian Seng Properties Sdn Bhd [1991] 1
MLJ 95, SC (refd)
H PT Anekapangan Dwitama v Far East Food Industries Sdn Bhd [1995] 1 MLJ
21, HC (refd)
Pioneer Concrete (M) Sdn Bhd v Celini Corp Sdn Bhd [1998] 3 MLJ 810, HC
(refd)
Plumley v Horrell (1869) 20 LT 473 (refd)
I Sunshine Securities (Pte) Ltd, Re; Sunshine Securities (Pte) Ltd & Anor v Official
Receiver and Liquidator of Mosbert Acceptance Ltd [1978] 1 MLJ 57, CA
(refd)
W J Alan & Co Ltd v El Nasr Export & Import Co [1972] 2 All ER 127, CA
(refd)
292 Malayan Law Journal [2014] 1 MLJ
Wei Giap Construction Co (Pte) Ltd v Intraco Ltd [1979] 2 MLJ 4 (refd) A
William Derry, JC Wakefield, MM Moore, J Pethick and SJ Wilde v Sir Henry
William Peek, Baronet (1889) 14 App Cas 337, HL (refd)
Legislation referred to
Companies Act 1965 s 218(1)(e), (2) B
Contracts Act 1950 ss 17, 17(d), (e), 19, 63
Evidence Act 1950
Specific Relief Act 1950 ss 30, 34(1)(a)
Appeal from: Civil Suit No S2–22–241 of 2002 (High Court, Kuala Lumpur) C
Robert Low (Tan Chong Lii with him) (Ranjit Ooi & Robert Low) for the
appellant.
C Sri Kumar (Chetan Jethwani with him) (Kumar Partnership) for the first
respondent. D
Faizal Hassan bin Abdul Hamid (Edlin Ghazali & Associates) for the second
respondent.
[1] This was an appeal against the decision of the High Court in dismissing
the appellant’s claim and entering judgment on the first respondent’s
counterclaim after a full trial. F
[2] The appellant’s claim before the High Court was for the rescission of a
settlement agreement on the grounds of conspiracy, fraud and for breach of
contract. G
A [5] Now, the first respondent was appointed as the main earthworks
contractor for the development in Phase 3A and Phase 3B.
[6] In regard to Phase 3B, the first respondent was the second respondent’s
nominated subcontractor. The appellant agreed to make all payments that were
B due under the Phase 3B contract directly to the first respondent. Evidence wise,
there is no direct contractual relationship between the appellant and the first
respondent in respect of the works that were carried out in Phase 3B. The letter
dated 1 April 1999 from the appellant to the second respondent appointing the
first respondent as the nominated subcontractor can be seen at the first
C respondent’s core bundle at Tab 1. That letter was worded as follows:
E --------------------------------------------------------------------------------------------------
In accordance with Clause 28 of the Conditions of Contract, you are hereby
instructed to accept the Tender for the above-mentioned subcontract Works from
Menta Construction Sdn Bhd, who has been nominated to execute and complete
the said subcontract Road and Drainage Works for the total sum of Ringgit
F Malaysia: Eleven Million Six Hundred Seventy Seven Thousand Eight Hundred
and Ten (RM11,677,810.00).
The above-mentioned firm shall become Nominated subcontractor and you shall be
required to enter into a formal subcontract with the said firm.
G The subcontract documents will be prepared and you shall be notified when they are
ready to be signed by you and the Nominated subcontractor.
The Nominated subcontractor has undertaken to commence the subcontract Works
within two (2) weeks from the date of receipt of your Official Order and to complete
the whole of the subcontract Works within Twelve (12) Months from the date of Site
H Possession.
All correspondence i.e. letters, instructions and the like issued by the
Superintending Officer whether directly or indirectly to you relating to subcontract
Works shall be deemed to have been served to you and taken effect thereof by the
Nominated subcontractor in so far as it related to the proper execution and
I completion of the NSC works.
You are hereby required to provide all necessary Supervision and Administration of
the Nominated subcontractor’s Works including co-ordination with the Employer
and the S.O. to ensure the timely completion of the Works and compliance with the
provisions of the Contract.
294 Malayan Law Journal [2014] 1 MLJ
Please prepare the necessary Letter of Acceptance and Documents for the execution A
of both the contracts.
[7] Another significant letter from the appellant to the first respondent dated
1 April 1999 agreeing to make payment to the first respondent as reflected at
B
the first respondent’s core bundle at Tab 2 was worded in this way:
PROPOSED CONSTRUCTION AND COMPLETION OF EARTHWORKS
AND MAIN DRAINAGE WORKS FOR CADANGAN PEMBANGUNAN
BERSEPADU PUNCAK ALAM Dl ATAS LOT PT. 1929 AND PT. 1935,
LADANG FELDA BUKIT CHERAKAH, MUKIM JERAM DAN IJOK, C
DAERAH KUALA SELANGOR, SELANGOR DARUL EHSAN (PHASE 3B)
- Direct Payment To Nominated subcontractors
--------------------------------------------------------------------------------------------------
With reference to the above, we hereby confirmed and agreeable to make all interim D
payments direct to MENTA CONSTRUCTION SDN BHD as the Nominated
subcontractor of the above-referred works of all amounts which have been certified
by the Superintending Officer.
E
[8] It is appropriate to mention that the contractual commencement date for
Phase 3A was on 9 November 1998 and for Phase 3B was on 1 April 1999. In
this connection, it is ideal to refer to the first respondent’s core bundle at Tab 3
exhibiting the letter of acceptance for Phase 3A showing the commencement
date to be on 9 November 1998 and that would be the date of site possession.
F
This would be followed by the letter of acceptance showing the
commencement date to be on 1 April 1999 as the date of site possession as seen
at the first respondent’s core bundle at Tab 4.
[9] The certificate of practical completion for Phase 3A showed that the first G
respondent completed the works for Phase 3A on 15 January 2000 and the
defects liability period for Phase 3A was set to end on 15 January 2001.
[10] While the certificate of practical completion for Phase 3B showed that
the first respondent completed the works for Phase 3B on 31 March 2000 and H
the defects liability period for Phase 3B was set to end on 31 March 2001.
[11] Sometime in the year 2000, the appellant alleged that there was an
embankment failure in Phase 3B.
I
[12] The certificate of final account addressed to the first respondent for
Phase 3A showed the sum of RM22,753,755.25 as the amount due to the
contractor as seen in the first respondent’s core bundle at Tab 7. While the
certificate of final account issued for Phase 3B and addressed to the first
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 295
[13] And the certificate of making good defects were also issued for both
Phase 3A and Phase 3B upon conclusion of the defects liability period.
B
[14] On 17 January 2002, two years after the alleged embankment failure,
the first respondent’s solicitors issued a notice pursuant to s 218(1)(e) of the
Companies Act 1965 for the sum of RM10,498,788.12 plus interest of
RM1,321,245.91 being sums due and owing by the appellant to the first
C
respondent for the works carried out in Phase 3A and Phase 3B. The inability
of the company to pay its debts is very common and it is often used as a ground
to obtain a winding up order. And the inability to pay is usually proved by
service of a statutory notice under s 218(2) of the Companies Act 1965 or by
other proof of insolvency. The law books are replete with authorities on this
D
point. Any creditor who has not been paid has the right to file a petition for
winding up whatever his other motives may be (Morgan Guaranty Trust Co of
New York v Lian Seng Properties Sdn Bhd [1991] 1 MLJ 95, (SC)). And the test
of commercial insolvency is quite simple: the inability of the company to meet
its current debts as they fall due. However, such a company may have
E
substantial wealth which cannot be immediately realised, yet the company is
still ‘unable to pay its debts’ as they fall due (Re Sunshine Securities (Pte) Ltd;Re
Sunshine Securities (Pte) Ltd; Sunshine Securities (Pte) Ltd & Anor v Official
Receiver and Liquidator of Mosbert Acceptance Ltd [1978] 1 MLJ 57 (CA); Wei
Giap Construction Co (Pte) Ltd v Intraco Ltd [1979] 2 MLJ 4; Malayan Plant
F
(Pte) Ltd v Moscow Narodny Bank Ltd [1980] 2 MLJ 53 (PC); Hotel Royal Ltd
Bhd v Tina Travel & Agencies Sdn Bhd [1990] 1 MLJ 21; MBf Finance Bhd v
Sri-Hartamas Dvpt Sdn Bhd [1992] 1 CLJ 160 at p 169; Lian Keow Sdn Bhd (in
liquidation) & Anor v Overseas Credit Finance (M) Sdn Bhd & Ors [1988] 2
MLJ 449 at p 454 (SC); PT Anekapangan Dwitama v Far East Food Industries
G
Sdn Bhd [1995] 1 MLJ 21 at p 29; and Pioneer Concrete (M) Sdn Bhd v Celini
Corp Sdn Bhd [1998] 3 MLJ 810 at p 814).
[15] Now, as a result of the 218 notice, the appellant and the first respondent
H entered into negotiations wherein the appellant agreed to pay the sum of
RM11,498,788.12 as settlement of the first respondent’s claim. It is this
settlement agreement dated 5 February 2002 that formed the backbone of the
present appeal to us.
[17] By letter dated 7 March 2002 as seen in the first respondent’s core
bundle at Tab 15, just one day before the second instalment was due, the
296 Malayan Law Journal [2014] 1 MLJ
[18] On 8 March 2002, the appellant then commenced this action against
the first and second respondents as well as the third defendant in the High D
Court.
ANALYSIS
[19] The main plank of the appellant’s claim before the High Court was that E
the appellant would not have entered into the settlement agreement but for the
alleged fraud and conspiracy of the first and second respondents. The alleged
conspiracy concerned the alleged concealment of the defective earthworks.
[21] The High Court further held that the expert report of Soil Instruments I
(M) Sdn Bhd was only confined to the area where the embankment failure took
place and it was insufficient, standing on its own, to conclude that defective
works occurred over the entire project area. The High Court also held that
there was absolutely no evidence of fraud but only suspicion that shrouded the
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 297
17. In this case, the ground is that the compromise ought to be set aside
B because it was obtained by fraud. The particulars of fraud relied upon were
set out. The plaintiff portrayed itself as the victim of a fraud who would
not have entered into the compromise if it had known the facts. The
plaintiff ’s argument is not without its problems. The plaintiff was aware of
the slope failure in year 2000. It had occurred in 1999. The plaintiff had
C engaged Soil Instruments (M) Sdn Bhd to undertake a soil investigation in
November 2001, the results of which were available in a report to the
plaintiff at the end of November. The plaintiff proposed settlement, and a
settlement was agreed to on 5/2/2002. The first payment under the
settlement was paid the next day. Only the day before the second payment
due on 8/3/2002, a month later, did the plaintiff refuse payment and
D proceeded to purport to rescind the settlement agreement, alleging the use
of unsuitable materials and fraud.
18. As to fraud, it is trite law that fraud requires a standard of proof higher
than a balance of probabilities. There is not much in the way of evidence
of actual wrongdoing, except they appeared to have worked on the same
E site and the result was the embankment failure. I confine the description
to ‘embankment failure’ for that is the only area where failure was a
certainty. The consultant’s report upon which the plaintiff ’s actions was
founded, and specifically pleaded in this case and quoted above, contains
limitations. Engineers are cautious persons and it is always necessary to
F read equally carefully their carefully chosen words.
19. Firstly, the statement ‘Taking this embankment failure area as
representative of the total development area …’ shows the consulting
engineer applied his findings from the embankment failure area to the rest
of the area for which, one might recall, there was no failure. Secondly, the
G words ‘… with the observed surface conditions throughout the site …’
means that in respect of the other areas where there was no failure, he
relied upon the observed surface conditions only. The consulting engineer
concluded ‘… there is strong evidence suggesting that misrepresentation
of the actual soil density value and compaction quality is prevalent
throughout the entire development area’. He would only go so far as to use
H
the words ‘suggesting’ and ‘misrepresentation’ but did not say the strong
evidence ‘showed’ or ‘proved’ or that the misrepresentation of the actual
soil density value and compaction quality were such they breached the
contract specifications. The reason for caution in the language is for the
obvious reason his review was conducted a considerable time after the
I performance of the contract and the embankment failure.
20. I would conclude that the report of the consulting engineer is not
unequivocal and the evidence to support the plaintiff ’s claim as to
unsuitable materials is therefore inconclusive, and as to fraud it is
non-existent. There is precious little, other than suspicion, to justify
298 Malayan Law Journal [2014] 1 MLJ
[22] Since the appellant had failed to prove conspiracy and fraud, the High
Court rightly dismissed the appellant’s claim and allowed the first respondent’s
C
counterclaim to enforce the settlement agreement.
[23] There was a compromise between the appellant and the first respondent
by way of a settlement agreement and that ended the suit between the parties.
Public policy demands that there should be an end to litigation and the parties D
should be held to their bargains. Lord Romilly MR in Plumley v Horrell (1869)
20 LT 473, aptly said:
The Master of the Rolls said that when an agreement was entered into for a
compromise, one would suppose, prima facie, that the case was not to be tried over
again. E
[25] And the proposal for settlement was accepted by the first respondent H
through its solicitor’s letter dated 5 February 2002 addressed to the appellant as
seen at Tab 13 of the first respondent’s core bundle. It is this letter dated
5 February 2002 that gave rise to a complete settlement agreement between the
appellant and the first respondent. Put in another way, the letter dated
5 February 2002 crystallised the settlement agreement between the parties. I
And that ended the dispute between the parties. In the words of Bowen LJ in
Knowles v Roberts (1888) 38 Ch D 263, at p 272:
As soon as you have ended a dispute by a compromise you have disposed of it.
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 299
A [26] It was argued on behalf of the appellant that the compromise should be
set aside because of fraud. Section 17 of the Contracts Act 1950 lays down five
different acts which may constitute fraud and for convenience that section is
now reproduced verbatim:
B 17 ‘Fraud’.
‘Fraud’ includes any of the following acts committed by a party to a contract, or with
his connivance, or by his agent, with intent to deceive another party thereto or his
agent, or to induce him to enter into the contract:
(a) the suggestion, as to a fact, of that which is not true by one who does not
C believe it to be true;
(b) the active concealment of a fact by one having knowledge of belief of the
fact;
(c) a promise made without any intention of performing it;
D (d) any other act fitted to deceive; and
(e) any such act or omission as the law specially declares to be fraudulent.
[29] In our judgment, there was no evidence of fraud perpetrated by the first
respondent that entitled the appellant to rescind the settlement agreement
dated 5 February 2002. We are in full accord with the decision of the High
300 Malayan Law Journal [2014] 1 MLJ
Court that the embankment failure occurred two years before the settlement A
agreement was agreed upon by the appellant and the first respondent.
[30] It is trite law that a high standard of proof is required where fraud is
alleged. Lord Keith of Kinkel, delivering the judgment of the Privy Council, in
B
Datuk Jagindar Singh & Ors v Tara Rajaratnam [1986] 1 MLJ 105, at p 110,
aptly said:
… that the standard of proof of fraud in civil proceedings was the criminal standard
of proof beyond reasonable doubt.
C
[31] In the same vein, Mohd Azmi FCJ writing for the Federal Court in Ang
Hiok Seng @ Ang Yeok Seng v Yim Yut Kiu (personal representative of the estate of
Chan Weng Sun, deceased) [1997] 2 MLJ 45, at p 61, succinctly said:
D
The definition of ‘fraud’, read in conjunction with the authorities, leads us to the
conclusion that where the fraud alleged in civil proceedings is based on a criminal
offence, the criminal burden of proof beyond reasonable doubt must be applied. But
where the fraud alleged is purely civil in nature, there is no reason why the civil
burden should not apply.
E
[32] Now, before the High Court, the appellant alleged that the first
respondent and the third defendant had conspired to defraud the appellant by
issuing false and misleading soil density tests. And the appellant claimed that its
consent to the settlement agreement was vitiated by the fraud of the first F
respondent and the third defendant acting in conspiracy. In order to appreciate
the appellant’s submissions, it would be ideal to examine the evidence that was
led before the High Court and the following evidence was disclosed:
(a) that the soil density testing was supervised, controlled and monitored by G
the appellant’s own supervising officer by the name of Encik Sihat bin
Md Salleh (‘DW5’) as well as by the third defendant. In his witness
statement by way of an affidavit, DW5 testified as follows:
3.Q: Apakah skop tugas En. Sihat berkenaan dengan projek kerja-kerja
tanah atas Fasa 3A dan 3B projek pembangunan plaintif di Bukit H
Cerakah?
A: Skop tugas saya sebagai Senior Clerk (of ) Works adalah menjalankan
pengawasan ke atas kontraktor kerja-kerja tanah sebagaimana yang
terdapat di dalam kontrak dokumen dan adalah mengikut arahan
I
Superintending Officer.
4.Q: Apakah tugas En. Sihat berkenaan ujian pemampatan tanah di atas
tapak Fasa 3A dan 3B?
A: Tugas saya adalah untuk menyelia ujian pemampatan tanah dari
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 301
G
(h) as demonstrated the former employee of the appellant, DW5, gave
evidence in favour of the first respondent. He confirmed that he or his
assistant would witness the soil testing and would in fact select the site for
the soil density testing to take place. He further confirmed that the soil
testing was done in his presence or that of his subordinate;
H (i) the appellant was aware of the embankment failure two years before the
first respondent made its counterclaim;
(j) and notwithstanding the embankment failure, the appellant further
issued the certificate of making good defects at the end of the defects
I liability period;
(k) the appellant was aware of the outcome of the soil investigation report by
its own expert in the person of Dr Mohd Asbi bin Othman (‘PW4’) well
before entering into the settlement agreement with the first respondent.
According to PW4, he had informed the plaintiff of his views
306 Malayan Law Journal [2014] 1 MLJ
A A: No.
Q: You didn’t check that?
A: No, I did not. Well, I mean you see, the loading is only limited to a
certain area within the embankment, but the settlement and the
B creep and the tacky cracks that we saw all at the embankment and
more widespread even in areas where there’s no logging.
Q: And you did not take any photographs of those?
A: We have photographs.
C
(l) and notwithstanding what PW4 had testified under cross-examination,
the appellant agreed to enter into the settlement agreement;
(m) the expert report of the first respondent’s witness by the name of Dr Gue
See Sew (‘DW3’) concluded that the embankment failure was caused by
D
soil erosion and poor drainage on the slope. In his expert report, DW3
had this to say (see Tab 26 of the first respondent’s core bundle):
(1) The title of the EAR report does not tally well with the objective of
the report which is mainly to assess the quality of earthwork in
F relation to the occurrence of embankment failure at Phase 3B.
Investigation of slope failure should cover the following:
(i) Design of slopes.
(ii) Improper construction including compaction of fill.
G (iii) Loading or disturbance from adjacent construction activities.
(iv) Lack of maintenance on drains and slope.
(v) Erosion.
(2) All in-situ density tests were carried out on the embankment that has
H a localised slip or failure. This area represent 21/2% of the overall
filled area of Phase 3B (See Appendix 1). Most of the in-situ density
tests were conducted on the embankment slope which is also outside
the boundary of the development as shown in Appendix 2. Based on
in-situ density tests done solely in this area, the EAR report further
I concludes that the fill on the whole site of Phase 3B is defective. (It)
is imprudent to generalise and conclude the whole site based on the
test results at only one area. There is also no evidence to show the
misrepresentation of the actual soil density value and compaction
quality throughout the development area prepared by Contractor,
Menta Construction Sdn Bhd.
308 Malayan Law Journal [2014] 1 MLJ
(3) Low density of the fill could have been disturbed due to the water A
seepage as shown in Trial Pit Log TP2.
(4) The slope failure was due to erosion. Evidence of choked and silted
drain would result in water overflowing the drain during heavy
downpour and caused erosion and finally the failed slope.
B
(n) it must be borne in mind that the appellant raised for the first time the
question of the sufficiency of the works only after the second payment
under the settlement agreement became due.
C
[33] Both PW4 and DW3 are expert witnesses and an expert evidence is
admissible under our Evidence Act 1950 because it is relevant and it has a high
probative value in relation to the issues raised in the case. The duty of an expert
witness, according to the case of Davie v Magistrates of Edinburgh 1953 SC 34,
at p 40, is to assist the judge in this way:
D
Their duty is to furnish the judge or jury with the necessary scientific criteria for
testing the accuracy of their conclusions, so as to enable the judge or jury to form
their own independent judgment by the application of these criteria to the facts
proved in evidence.
E
[34] But the ultimate decision is for the judge to decide and that all questions
of relevance and weight are for the judge alone (Re M and R (minors) (sexual
abuse: expert evidence) [1996] 4 All ER 239 at p 253 (CA)). In the context of the
present appeal, the High Court rightly assessed the expert evidence and came to
F
a correct decision.
[35] The appellant heavily relied on the first engineering assessment report
(‘the first EAR report’) that was prepared by Perunding ZNR in an attempt to
rescind the settlement agreement. It is our judgment that the first EAR report G
is unsafe and cannot be relied upon to establish fraud for the following reasons:
(a) that the soil investigation report which forms the basis of the first EAR
report was localised to the embankment failure on Phase 3B. This means
that the testing that was carried out for the purpose of preparing this
report was carried out in and around the area where the embankment H
failed. This fact is very important and cannot be overlooked for four main
reasons:
(i) that the area where the embankment failed is located outside the
boundary of the property belonging to the appellant; I
(ii) that the area where the embankment failed represents only 2.5% of
the overall fill area of Phase 3B and, calculation wise, if the total fill
area for Phase 3A is taken into account, that figure will be
significantly smaller;
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 309
A (iii) that the appellant’s expert failed to take into account the damaging
effect of construction and piling works near the embankment as
contributing to the embankment failure in Phase 3B; and
(iv) that the appellant’s expert did not take into account the design of the
B slope and the poor maintenance of the drainage near the slope as well
as the erosion;
(b) Ng Wai Yoong/Daniel Ng (‘PW1’) who carried out the soil investigation
report on which the first EAR report was based admitted that the soil
investigation that was conducted by him was not representative of the
C
entire Phase 3B (see the cross-examination of PW1 as seen at Tab 17 of
the first respondent’s core bundle); and
(c) The first EAR report relied on another soil investigation report and this
other report was not produced at the trial.
D
[36] A second engineering assessment report (‘the second EAR report’) was
also relied upon by the appellant. The second EAR report was commissioned in
February 2002 which was after the refusal to pay the second instalment of the
E settlement agreement. It was submitted by learned counsel for the first
respondent that the second EAR report was designed to bolster the appellant’s
claim of fraud. It is our judgment that the second EAR report cannot be used
to complain about the soil testing that was undertaken at the project bearing in
mind that the second EAR report was also not representative of the entire scope
F of works because the full half of the trial pits that was used as a basis to form the
conclusion in the second EAR report was carried out on those areas designated
as ‘kawasan lapang’. The evidence also showed that the first respondent was
entitled to use materials such as palm oil tree trunks and boulders, that were
otherwise unsuitable, for backfill on the ‘kawasan lapang’. Under
G cross-examination, Wan Husin bin Wan Embong (‘PW5’) testified as to the use
of boulders in this way (see p 480 of the first respondent’s core bundle):
Q: Now, so far as the boulders are concerned there was a general instruction
that boulders could be used on vacant sites and roads - under vacant sites
and roads. Is that right?
H
A: Vacant sites and roads.
Q: For Phase 3A and 3B?
A : Yes.
I Q: You recall this?
A: That one was discussed, ya.
Q: It was discussed?
A: It was discussed on this issue.
310 Malayan Law Journal [2014] 1 MLJ
Q: This is for both Phases because I think you only referred to documents A
relating to 3A, but I want to know that it is for both?
A: Ya, he is in charge of both Phases, ya.
[37] In regard to the usage of palm oil tree trunks, PW5 testified under B
cross-examination in this way (see p 482 of the first respondent’s core bundle):
Q: Now, with regard to this chipping, did you ever describe what you wanted
or what you meant by chipping in your instructions of the palm trunks?
C
A: The understanding was the tree trunk has to be cut into small pieces - yes.
Q: But no discussion took place and how small that they had to be?
A: I have to check on that. I can’t remember whether there is or not. But
definitely it has to be cut off.
D
Q: They have to be cut but
A: They have to be cut into small pieces.
Q: Cut into pieces about 20 cm or so – 40 cm?
A: The intention would be cut into small pieces – I have to check whether I E
can’t remember whether we discussed on the sizes or not. But they have to
be in small enough sizes so that we have no void between.
Q: That would be no void between?
A: No void between. F
[38] And the dumping of oil palm trunks at the ‘kawasan lapang’ was further
emphasised by PW5 at pp 484–485 of the first respondent’s core bundle:
Q: Can you look at under 30th April and 1st–29th or 30th April the site G
clearing and dumping of oil palm trunks at kawasan lapang. So it was
reported? It was brought to the attention of En. Badrul and was approved
by the clerk (of ) works at the bottom? Is that correct?
A: Yes, yes.
H
Q: Can I take you now to 1224/1223 rather, the same Bundle. Again this is
yet another weekly report and that also brings it to the attention of - so it
was brought to the attention of En. Badrul then? They were dumping oil
palm trunks at the KL3 phase. You look at 20/5/1999. KL3 of course
kawasan lapang, is it not, KL is abbreviation for kawasan lapang. Is that
right? I
A: Ya.
[39] Based on these salient facts, the High Court was entitled to come to the
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 311
A conclusion that the expert reports provided by the appellant were fraught with
fanciful speculation and were insufficiently substantiated.
[40] We must reiterate that the courts must be slow and cautious in deciding
whether to interfere with settlement agreements entered by the parties. Since
B
time immemorial, the principle has always been that there must be a finality to
disputes between the parties. The following facts must be put to the forefront:
(a) that the appellant was represented at the negotiations for settlement by its
executive director who was also a qualified lawyer;
C
(b) that despite being put on notice in regard to the embankment failure and
the alleged defective works, the appellant nevertheless entered into the
settlement agreement; and
(c) flowing from all these, the appellant paid out its first instalment under the
D settlement agreement.
[41] It is part and parcel of our judgment that the appellant’s claim was
cleverly designed to merely raise the spectre of fraud in order to avoid its
obligations under the settlement agreement. An illusion of fraud cannot fulfil
E
the standard of proof as required by the law. Here, the appellant failed to prove
fraud beyond reasonable doubt.
G [43] Furthermore, all the interim payments were made between the
appellant and the first respondent. It is apparent that the appellant and the first
respondent had excluded the second respondent in all negotiations leading to
the execution of the settlement agreement. And all the discussions, meetings
and negotiations during and after the construction works were concluded
H between the appellant and the first respondent only. Even Tan Choon Hock
(‘DW1’) in his evidence under cross-examination testified that the second
respondent was not involved in Phase 3A and did not do any work for Phase
3B.
I [44] The role of the second respondent in this project was merely as a main
contractor ‘on paper’ only. It was the appellant who had instructed the second
respondent to appoint the first respondent as the nominated subcontractor for
Phase 3B. And that all matters during the construction were dealt with by the
appellant and the first respondent to the exclusion of the second respondent.
312 Malayan Law Journal [2014] 1 MLJ
With this kind of arrangement between the appellant and the first respondent, A
the contract that was initially awarded to the second respondent as the main
contractor had been novated. And there existed a new, separate and binding
contract between the appellant and the first respondent to the exclusion of the
second respondent.
B
[45] It is appropriate to state that the novation was not objected to by any
party including the second respondent. The subsequent conduct of the
appellant and the first respondent further showed that they had entered into
the settlement agreement. There are no two ways about it. C
[46] By virtue of s 63 of the Contracts Act 1950, the second respondent had
been discharged from any contractual obligation under the original
appointment. In its original text, s 63 of the Contracts Act 1950 enacts as
D
follows:
[47] Salleh Abas LP in Lyl Hooker Sdn Bhd v Tevanaigam Savisthri & Anor
[1987] 2 MLJ 52, at p 53 aptly described ‘novation’ in these erudite terms:
F
Novation is a new contract. It extinguishes rights and obligations under the old
contract for which the new contract is made. Being a new contract, there must be
consent by all parties and there must be consideration, and rights and obligations
under it are not those transferred from the old contract which is already
extinguished (see Chitty on Contract, Vol 1, (1983 Ed), at paras 1315–1316).
G
[48] Gunn Chit Tuan J (as he then was) in Malaysian International Merchant
Bankers Bhd v Datuk Mohd Salleh & Anor [1988] 1 CLJ (Rep) 786, at p 792
explained the meaning of ‘novation’ in this way:
H
Novation, no doubt, is an act whereby, with the consent of all parties, a new contract
is substituted for an existing contract and the latter is discharged. Usually, but not
necessarily, a novation takes the form of the introduction of a new party to the new
contract and the discharge of a person who was party to the old contract.
I
[49] Low Hop Bing J (later JCA) in Kah Seng Construction Sdn Bhd v Selsin
Development Sdn Bhd [1996] MLJU 359; [1997] 1 CLJ Supp 448, at p 454 had
this to say about ‘novation’:
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 313
A Pollock & Mulla in Indian Contract and Specific Relief Acts (10th Ed), p 501 sets out
the requirements that must be satisfied before a party can successfully show that a
contract has been varied pursuant to s 63, viz:
(a) firstly, the variation of the contract may be shown by express agreement;
and
B
(b) secondly, if variation is to come about by a course of conduct, the variation
was intended and understood by both parties.
The burden is on the plaintiff to establish that the above requirements are fulfilled
in order to bring about the operation of the principles of novation.
C
[50] Abdul Malik bin Ishak J (now JCA) in Mawar Awal (M) Sdn Bhd v
Kepong Management Sdn Bhd & Anor [2005] 6 MLJ 132, at p 150 made
reference to ‘novation’ in this way:
D (38) It is ideal to mention that s 63 of the Contracts Act 1950 on novation is of wider
import. Indeed this was the view held by Visu Sinnadurai J in Polygram Records Sdn
Bhd v The Search [1994] 3 MLJ 127; [1994] 3 CLJ 806; [1994] 3 AMR 2060 and
I certainly share his view. His Lordship Visu Sinnadurai J in that case aptly said:
G
[51] Halsbury’s Laws of England, Vol 8, (3rd Ed), defined ‘novation’ in this
way:
Novation is, in effect, a form of assignment in which, by the consent of all parties,
a new contract is substituted for an existing contract. Usually, but not necessarily, a
H
new person becomes party to the new contract, and some person who was party to
the old contract is discharged from further liability. The introduction of a new party
prevents the new contract from being a mere accord without satisfaction, and thus
affords a defence to any action upon the old contract.
I For novation to ensue there must be not only the substitution of some other
obligation for the original one, but also the intention or animus novandi.
[52] Next, it was argued that the appellant’s claim was barred by estoppel and
acquiescence. It is trite law that when one party conducts himself in such a
314 Malayan Law Journal [2014] 1 MLJ
fashion as to lead the other party to believe that he has been given a unilateral A
waiver of performance of a particular part of the contract, then the party who
is relying on that conduct is entitled to claim such a waiver. Lord Denning MR
in W J Alan & Co Ltd v El Nasr Export & Import Co [1972] 2 All ER 127 (CA),
writing a separate judgment had this to say about ‘waiver’ at p 140 of the report:
B
The principle of waiver is simply this: if one party, by his conduct, leads another to
believe that the strict rights arising under the contract will not be insisted on,
intending that the other should act on that belief, and he does act on it, then the first
party will not afterwards be allowed to insist on the strict legal rights when it would
be inequitable for him to do so: see Plasticmoda Societa Per Azioni v Davidsons
(Manchester) Ltd [1952] 1 Lloyd’s Rep 527 at p 539 per Denning LJ. C
[55] Here, factually speaking, the appellant took the following steps through
the supervising officer which constituted estoppel in every sense of the word: G
(a) having issued and paid out on the interim certificates for work done;
(b) having issued the certificate of practical completion;
(c) having issued the certificate of making good defects; and
H
(d) having issued the statement of final account.
[56] In addition to the above, the appellant had taken the following steps in
order to ensure that the work was sufficiently carried out to its satisfaction:
I
(a) that DW5 was empowered to and did in fact carry out compaction
testing during the course of the works;
(b) that DW5 monitored and witnessed the compaction testing that was
carried out on the site while the progress of the works was ongoing;
Puncak Alam Housing Sdn Bhd (formerly known as Bukit
Cerakah Development Sdn Bhd) v Menta Construction Sdn
[2014] 1 MLJ Bhd & Anor (Abdul Malik Ishak JCA) 315
A (c) when DW5 was dissatisfied with the nature of the works, he would direct
rectification and further testing;
(d) the first respondent provided the progress reports of the works that were
carried out and discussions with the appellant’s representatives at site
B
meetings were held at regular intervals; and
(e) after the certificate of making good defects was issued to the first
respondent, no further complaints were raised regarding the sufficiency
of work and the quality of materials until after the second payment was
due under the settlement agreement.
C
[57] All the facts adumbrated above coupled with the settlement agreement
and the subsequent payment of the first instalment can only lead to only one
conclusion: that the appellant must be estopped from claiming that there were
defective works under the original agreement.
D
CONCLUSION
E
[58] We have perused through the evidence with a fine toothcomb and we
have also mulled through the evidence at great length. The facts as narrated
revealed that the first respondent had carried out its works under the contracts.
And the first respondent even carried out the testing of the works under the
F watchful eye of the appellant’s representatives. The works were accepted by the
appellant through two methods: testing and certification process. The
appellant even issued its final certificate for payment and the certificate of
making good defects. But the first respondent was not paid the balance sums
due to it under the certificates. And when the first respondent threatened to
G wind up the appellant for non-payment, the appellant quickly entered into the
settlement agreement. The appellant proceeded to partly perform its
obligations to pay under the settlement agreement. And when the time came to
pay the second instalment under the settlement agreement, the appellant
alleged fraud and conspiracy and refused to pay.
H
[59] In our judgment, the allegations of fraud and conspiracy were based on
the facts known to the appellant prior to entering the settlement agreement. It
cannot be denied that the first respondent had carried out substantial works for
the benefit of the appellant and the first respondent had been kept out of the
I funds since 2002. The appellant had benefitted and enjoyed the fruits of the
first respondent’s labour.
and the first respondent and the second respondent secured RM700,000 for A
allowing the first respondent to play a major role in this case. Even the
settlement agreement concerned the appellant and the first respondent to the
exclusion of the second respondent.
[61] For these varied reasons, we dismissed the appeal of the appellant with B
costs of RM50,000 in favour of the first respondent and RM10,000 in favour
of the second respondent. We affirmed the decision of the High Court. Deposit
to be refunded to the appellant.