2019 09 20 Stormwater Report
2019 09 20 Stormwater Report
DESIGN CALCULATIONS
Prepared for
Revised:
August 21, 2019
September 20, 2019
Table of Contents
Table of Contents 2
Summary 3
Peak Rate Summary 3
Stormwater on site is managed through the use of 7 –225’ long x 36” diameter polyethylene pipes that
fully store the 2, 10, and 25 year storm flow and slowly release the water into the nearby drop inlet.
High groundwater and poor soils restrict the feasibility of onsite infiltration of stormwater, however an
infiltration basin is proposed provide recharge for new impervious area. A 1” diameter orifice at the
bottom of the weir placed inside of the proposed outlet structure controls the flow, with a 6” diameter
orifice acting as the emergency overflow. Calculations show peak flow rates post construction to be
lower for the 2, 10, 25, and 100 year storms.
This analysis was prepared to demonstrate Compliance with the Massachusetts Stormwater
Management Regulations and the Town of Pembroke Rules and Regulations for Stormwater
Management.
The calculations have been performed for the 2, 10, 25, 100-year 24 hour storm event, using the
HydroCAD computer program. This computer program is based upon the Soils Conservation Service
(SCS) TR-20 and TR-55 computer models and uses the SCS Curvilinear Unit rainfall distribution.
The following summary details a reduction in Peak Rate runoff. Values are in cubic feet per second.
2P
8R 2S
6S Pipe Storage
1P
ADS Pipe 0S Post-CB2
Pre-CB1
CB1
Post-Street
7S
Pre-Street 0P
Post-Total
8S
6P
Pre-CB2
Pre-Total
Subcat Reach Pond Link Routing Diagram for 345 Oak Drainage
Prepared by Grady Consulting, LLC, Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC
345 Oak Drainage
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 2
Area CN Description
(sq-ft) (subcatchment-numbers)
58,152 79 50-75% Grass cover, Fair, HSG C (0S, 1S, 2S, 3S, 4S, 5S, 6S, 7S, 8S)
24,001 98 Paved parking, HSG C (0S, 3S, 5S, 7S)
2,546 98 Roofs, HSG C (3S, 7S)
1,643 98 Unconnected pavement, HSG C (3S, 5S, 7S)
2,400 98 Unconnected roofs, HSG C (4S)
88,742 86 TOTAL AREA
345 Oak Drainage
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 3
Reach 8R: ADS Pipe Avg. Flow Depth=0.05' Max Vel=2.72 fps Inflow=0.03 cfs 2,561 cf
8.0" Round Pipe n=0.012 L=27.0' S=0.0519 '/' Capacity=2.98 cfs Outflow=0.03 cfs 2,560 cf
Pond 2P: Pipe Storage Peak Elev=86.26' Storage=4,628 cf Inflow=1.97 cfs 5,927 cf
Outflow=0.03 cfs 2,561 cf
Total Runoff Area = 88,742 sf Runoff Volume = 14,752 cf Average Runoff Depth = 1.99"
65.53% Pervious = 58,152 sf 34.47% Impervious = 30,590 sf
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 6
Runoff = 0.32 cfs @ 12.05 hrs, Volume= 900 cf, Depth= 1.70"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
0.36 Runoff
0.34 0.32 cfs
0.32 Type III 24-hr
0.3
2-Year Rainfall=3.40"
0.28
0.26
Runoff Area=6,350 sf
0.24 Runoff Volume=900 cf
0.22 Runoff Depth=1.70"
Flow (cfs)
0.2
Flow Length=64'
0.18
0.16 Slope=0.1000 '/'
0.14 Tc=2.9 min
0.12
CN=82
0.1
0.08
0.06
0.04
0.02
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 7
Runoff = 0.20 cfs @ 12.11 hrs, Volume= 647 cf, Depth= 1.49"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
Runoff
0.21
0.20 cfs
0.2
0.19 Type III 24-hr
0.18 2-Year Rainfall=3.40"
0.17
0.16 Runoff Area=5,213 sf
0.15
Runoff Volume=647 cf
0.14
0.13 Runoff Depth=1.49"
Flow (cfs)
0.12
0.11
Flow Length=165'
0.1 Tc=7.5 min
0.09
0.08
CN=79
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 8
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
0.022 Runoff
0.021 0.02 cfs
0.02
0.019 Type III 24-hr
0.018 2-Year Rainfall=3.40"
0.017
0.016 Runoff Area=420 sf
0.015
0.014 Runoff Volume=52 cf
0.013
Runoff Depth=1.49"
Flow (cfs)
0.012
0.011 Flow Length=20'
0.01
0.009 Slope=0.1000 '/'
0.008
0.007
Tc=1.3 min
0.006 CN=79
0.005
0.004
0.003
0.002
0.001
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 9
Runoff = 1.33 cfs @ 12.05 hrs, Volume= 3,895 cf, Depth= 2.54"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
Runoff
1.33 cfs
Type III 24-hr
2-Year Rainfall=3.40"
Runoff Area=18,392 sf
1 Runoff Volume=3,895 cf
Runoff Depth=2.54"
Flow (cfs)
Flow Length=171'
Tc=3.7 min
CN=92
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 11
Runoff = 0.32 cfs @ 12.00 hrs, Volume= 830 cf, Depth= 2.26"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
0.36 Runoff
0.34 0.32 cfs
0.32 Type III 24-hr
0.3
2-Year Rainfall=3.40"
0.28
0.26
Runoff Area=4,400 sf
0.24 Runoff Volume=830 cf
0.22 Runoff Depth=2.26"
Flow (cfs)
0.2
Flow Length=35'
0.18
0.16 Tc=0.2 min
0.14 CN=89
0.12
0.1
0.08
0.06
0.04
0.02
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 12
Runoff = 0.66 cfs @ 12.07 hrs, Volume= 2,032 cf, Depth= 2.54"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
Runoff
0.7 0.66 cfs
0.65 Type III 24-hr
0.6 2-Year Rainfall=3.40"
0.55 Runoff Area=9,597 sf
0.5 Runoff Volume=2,032 cf
0.45 Runoff Depth=2.54"
Flow (cfs)
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 13
Runoff = 0.22 cfs @ 12.12 hrs, Volume= 747 cf, Depth= 1.49"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
0.24 Runoff
0.23 0.22 cfs
0.22
0.21
Type III 24-hr
0.2 2-Year Rainfall=3.40"
0.19
0.18 Runoff Area=6,022 sf
0.17
0.16
Runoff Volume=747 cf
0.15
0.14
Runoff Depth=1.49"
Flow (cfs)
Runoff = 1.66 cfs @ 12.12 hrs, Volume= 5,534 cf, Depth= 1.77"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
Runoff
1.66 cfs
Type III 24-hr
2-Year Rainfall=3.40"
Runoff Area=37,415 sf
Runoff Volume=5,534 cf
Runoff Depth=1.77"
Flow (cfs)
1 Flow Length=263'
Slope=0.0250 '/'
Tc=8.1 min
CN=83
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 15
Runoff = 0.04 cfs @ 12.05 hrs, Volume= 116 cf, Depth= 1.49"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 2-Year Rainfall=3.40"
0.026
0.024 Flow Length=28'
0.022
0.02
Slope=0.0250 '/'
0.018 Tc=3.1 min
0.016
0.014 CN=79
0.012
0.01
0.008
0.006
0.004
0.002
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 16
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth > 0.95" for 2-Year event
Inflow = 0.03 cfs @ 19.50 hrs, Volume= 2,561 cf
Outflow = 0.03 cfs @ 19.51 hrs, Volume= 2,560 cf, Atten= 0%, Lag= 0.3 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Max. Velocity= 2.72 fps, Min. Travel Time= 0.2 min
Avg. Velocity = 2.44 fps, Avg. Travel Time= 0.2 min
Inflow
0.032 0.03 cfs Outflow
0.03 Inflow Area=32,389 sf 0.03 cfs
0.028 Avg. Flow Depth=0.05'
0.026
Max Vel=2.72 fps
0.024
8.0"
0.022
Round Pipe
0.02
n=0.012
Flow (cfs)
0.018
0.016 L=27.0'
0.014 S=0.0519 '/'
0.012 Capacity=2.98 cfs
0.01
0.008
0.006
0.004
0.002
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 18
Inflow Area = 44,372 sf, 49.70% Impervious, Inflow Depth > 1.12" for 2-Year event
Inflow = 0.52 cfs @ 12.06 hrs, Volume= 4,159 cf
Primary = 0.52 cfs @ 12.06 hrs, Volume= 4,159 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
0.52 cfs Primary
0.55 0.52 cfs Inflow Area=44,372 sf
0.5
0.45
0.4
0.35
Flow (cfs)
0.3
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 19
Inflow Area = 37,602 sf, 56.13% Impervious, Inflow Depth > 1.02" for 2-Year event
Inflow = 0.22 cfs @ 12.11 hrs, Volume= 3,207 cf
Primary = 0.22 cfs @ 12.11 hrs, Volume= 3,207 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
0.24 0.22 cfs Primary
0.23 0.22 cfs Inflow Area=37,602 sf
0.22
0.21
0.2
0.19
0.18
0.17
0.16
0.15
0.14
Flow (cfs)
0.13
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 20
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth = 2.20" for 2-Year event
Inflow = 1.97 cfs @ 12.06 hrs, Volume= 5,927 cf
Outflow = 0.03 cfs @ 19.50 hrs, Volume= 2,561 cf, Atten= 99%, Lag= 446.7 min
Primary = 0.03 cfs @ 19.50 hrs, Volume= 2,561 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs / 3
Peak Elev= 86.26' @ 19.50 hrs Surf.Area= 4,814 sf Storage= 4,628 cf
Plug-Flow detention time= 706.9 min calculated for 2,560 cf (43% of inflow)
Center-of-Mass det. time= 586.7 min ( 1,380.6 - 793.9 )
Inflow
1.97 cfs Primary
2 Inflow Area=32,389 sf
Peak Elev=86.26'
Storage=4,628 cf
Flow (cfs)
0.03 cfs
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 22
Inflow Area = 44,370 sf, 19.24% Impervious, Inflow Depth = 1.73" for 2-Year event
Inflow = 1.91 cfs @ 12.12 hrs, Volume= 6,396 cf
Primary = 1.91 cfs @ 12.12 hrs, Volume= 6,396 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
1.91 cfs Primary
2 1.91 cfs Inflow Area=44,370 sf
Flow (cfs)
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 2-Year Rainfall=3.40"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 23
Inflow Area = 4,400 sf, 54.55% Impervious, Inflow Depth = 2.26" for 2-Year event
Inflow = 0.32 cfs @ 12.00 hrs, Volume= 830 cf
Outflow = 0.01 cfs @ 15.96 hrs, Volume= 758 cf, Atten= 97%, Lag= 237.3 min
Discarded = 0.01 cfs @ 15.96 hrs, Volume= 758 cf
Primary = 0.00 cfs @ 0.00 hrs, Volume= 0 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 97.42' @ 15.96 hrs Surf.Area= 1,329 sf Storage= 507 cf
Plug-Flow detention time= 582.8 min calculated for 758 cf (91% of inflow)
Center-of-Mass det. time= 539.1 min ( 1,342.5 - 803.3 )
Inflow
0.32 cfs Outflow
0.36
Inflow Area=4,400 sf Discarded
Primary
0.34 Peak Elev=97.42'
0.32
0.3
Storage=507 cf
0.28
0.26
0.24
0.22
Flow (cfs)
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06 0.01 cfs
0.04 0.01 cfs
0.00
0.02 cfs
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 25
Reach 8R: ADS Pipe Avg. Flow Depth=0.05' Max Vel=2.88 fps Inflow=0.03 cfs 3,149 cf
8.0" Round Pipe n=0.012 L=27.0' S=0.0519 '/' Capacity=2.98 cfs Outflow=0.03 cfs 3,148 cf
Pond 2P: Pipe Storage Peak Elev=86.81' Storage=7,287 cf Inflow=2.89 cfs 8,955 cf
Outflow=0.03 cfs 3,149 cf
Total Runoff Area = 88,742 sf Runoff Volume = 23,346 cf Average Runoff Depth = 3.16"
65.53% Pervious = 58,152 sf 34.47% Impervious = 30,590 sf
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 26
Runoff = 0.54 cfs @ 12.04 hrs, Volume= 1,488 cf, Depth= 2.81"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
0.6
Runoff
0.55
0.54 cfs
Type III 24-hr
0.5
10-Year Rainfall=4.70"
0.45 Runoff Area=6,350 sf
0.4 Runoff Volume=1,488 cf
Runoff Depth=2.81"
0.35
Flow (cfs)
Flow Length=64'
0.3
Slope=0.1000 '/'
0.25 Tc=2.9 min
0.2 CN=82
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 27
Runoff = 0.34 cfs @ 12.11 hrs, Volume= 1,106 cf, Depth= 2.55"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
Runoff
0.36 0.34 cfs
0.34 Type III 24-hr
0.32
0.3
10-Year Rainfall=4.70"
0.28 Runoff Area=5,213 sf
0.26 Runoff Volume=1,106 cf
0.24
Runoff Depth=2.55"
0.22
Flow (cfs)
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
0.038 Runoff
0.036 0.03 cfs
0.034 Type III 24-hr
0.032
0.03
10-Year Rainfall=4.70"
0.028 Runoff Area=420 sf
0.026 Runoff Volume=89 cf
0.024
0.022
Runoff Depth=2.55"
Flow (cfs)
Runoff = 1.95 cfs @ 12.05 hrs, Volume= 5,819 cf, Depth= 3.80"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
Runoff
2
1.95 cfs
Type III 24-hr
10-Year Rainfall=4.70"
Runoff Area=18,392 sf
Runoff Volume=5,819 cf
Runoff Depth=3.80"
Flow (cfs)
Flow Length=171'
1 Tc=3.7 min
CN=92
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 31
Runoff = 0.49 cfs @ 12.00 hrs, Volume= 1,278 cf, Depth= 3.49"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
Runoff
0.49 cfs
0.5
Type III 24-hr
0.45 10-Year Rainfall=4.70"
0.4 Runoff Area=4,400 sf
Runoff Volume=1,278 cf
0.35
Runoff Depth=3.49"
Flow (cfs)
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 32
Runoff = 0.96 cfs @ 12.07 hrs, Volume= 3,036 cf, Depth= 3.80"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
Runoff
1 0.96 cfs
Type III 24-hr
10-Year Rainfall=4.70"
Runoff Area=9,597 sf
Runoff Volume=3,036 cf
Runoff Depth=3.80"
Flow (cfs)
Flow Length=160'
Slope=0.0200 '/'
Tc=5.1 min
CN=92
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 33
Runoff = 0.38 cfs @ 12.12 hrs, Volume= 1,277 cf, Depth= 2.55"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
0.42 Runoff
0.4 0.38 cfs
0.38 Type III 24-hr
0.36
0.34 10-Year Rainfall=4.70"
0.32 Runoff Area=6,022 sf
0.3
0.28
Runoff Volume=1,277 cf
0.26 Runoff Depth=2.55"
Flow (cfs)
0.24
Flow Length=197'
0.22
0.2 Tc=8.3 min
0.18 CN=79
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 34
Runoff = 2.71 cfs @ 12.11 hrs, Volume= 9,054 cf, Depth= 2.90"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
3 Runoff
2.71 cfs
Type III 24-hr
10-Year Rainfall=4.70"
Runoff Area=37,415 sf
2
Runoff Volume=9,054 cf
Runoff Depth=2.90"
Flow (cfs)
Flow Length=263'
Slope=0.0250 '/'
Tc=8.1 min
1 CN=83
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 35
Runoff = 0.07 cfs @ 12.05 hrs, Volume= 198 cf, Depth= 2.55"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 10-Year Rainfall=4.70"
Runoff
0.075 0.07 cfs
0.07 Type III 24-hr
0.065 10-Year Rainfall=4.70"
0.06
Runoff Area=933 sf
0.055
Runoff Volume=198 cf
0.05
Runoff Depth=2.55"
0.045
Flow (cfs)
0.04
Flow Length=28'
0.035 Slope=0.0250 '/'
0.03 Tc=3.1 min
0.025 CN=79
0.02
0.015
0.01
0.005
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 36
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth > 1.17" for 10-Year event
Inflow = 0.03 cfs @ 21.14 hrs, Volume= 3,149 cf
Outflow = 0.03 cfs @ 21.15 hrs, Volume= 3,148 cf, Atten= 0%, Lag= 0.3 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Max. Velocity= 2.88 fps, Min. Travel Time= 0.2 min
Avg. Velocity = 2.57 fps, Avg. Travel Time= 0.2 min
Inflow
0.038 0.03 cfs Outflow
0.036 Inflow Area=32,389 sf 0.03 cfs
0.034 Avg. Flow Depth=0.05'
0.032
0.03 Max Vel=2.88 fps
0.028 8.0"
0.026
Round Pipe
0.024
n=0.012
Flow (cfs)
0.022
0.02 L=27.0'
0.018
0.016
S=0.0519 '/'
0.014 Capacity=2.98 cfs
0.012
0.01
0.008
0.006
0.004
0.002
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 38
Inflow Area = 44,372 sf, 49.70% Impervious, Inflow Depth > 1.58" for 10-Year event
Inflow = 0.86 cfs @ 12.06 hrs, Volume= 5,831 cf
Primary = 0.86 cfs @ 12.06 hrs, Volume= 5,831 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
0.95 0.86 cfs Primary
0.9 0.86 cfs Inflow Area=44,372 sf
0.85
0.8
0.75
0.7
0.65
0.6
0.55
Flow (cfs)
0.5
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 39
Inflow Area = 37,602 sf, 56.13% Impervious, Inflow Depth > 1.36" for 10-Year event
Inflow = 0.37 cfs @ 12.11 hrs, Volume= 4,254 cf
Primary = 0.37 cfs @ 12.11 hrs, Volume= 4,254 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
0.4 0.37 cfs Primary
0.38 0.37 cfs Inflow Area=37,602 sf
0.36
0.34
0.32
0.3
0.28
0.26
0.24
Flow (cfs)
0.22
0.2
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 40
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth = 3.32" for 10-Year event
Inflow = 2.89 cfs @ 12.06 hrs, Volume= 8,955 cf
Outflow = 0.03 cfs @ 21.14 hrs, Volume= 3,149 cf, Atten= 99%, Lag= 545.0 min
Primary = 0.03 cfs @ 21.14 hrs, Volume= 3,149 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs / 3
Peak Elev= 86.81' @ 21.14 hrs Surf.Area= 4,774 sf Storage= 7,287 cf
Plug-Flow detention time= 725.7 min calculated for 3,149 cf (35% of inflow)
Center-of-Mass det. time= 587.1 min ( 1,371.3 - 784.3 )
Inflow
2.89 cfs Primary
3 Inflow Area=32,389 sf
Peak Elev=86.81'
Storage=7,287 cf
2
Flow (cfs)
0.03 cfs
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 42
Inflow Area = 44,370 sf, 19.24% Impervious, Inflow Depth = 2.85" for 10-Year event
Inflow = 3.14 cfs @ 12.11 hrs, Volume= 10,530 cf
Primary = 3.14 cfs @ 12.11 hrs, Volume= 10,530 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
3.14 cfs Primary
3.14 cfs Inflow Area=44,370 sf
3
2
Flow (cfs)
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 10-Year Rainfall=4.70"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 43
Inflow Area = 4,400 sf, 54.55% Impervious, Inflow Depth = 3.49" for 10-Year event
Inflow = 0.49 cfs @ 12.00 hrs, Volume= 1,278 cf
Outflow = 0.02 cfs @ 14.14 hrs, Volume= 949 cf, Atten= 96%, Lag= 128.0 min
Discarded = 0.01 cfs @ 14.14 hrs, Volume= 850 cf
Primary = 0.01 cfs @ 14.14 hrs, Volume= 100 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 97.61' @ 14.14 hrs Surf.Area= 1,433 sf Storage= 781 cf
Plug-Flow detention time= 568.7 min calculated for 949 cf (74% of inflow)
Center-of-Mass det. time= 482.5 min ( 1,273.7 - 791.2 )
Inflow
0.49 cfs Outflow
Inflow Area=4,400 sf Discarded
Primary
0.5
Peak Elev=97.61'
Storage=781 cf
0.45
0.4
0.35
Flow (cfs)
0.3
0.25
0.2
0.15
Reach 8R: ADS Pipe Avg. Flow Depth=0.05' Max Vel=2.98 fps Inflow=0.04 cfs 3,553 cf
8.0" Round Pipe n=0.012 L=27.0' S=0.0519 '/' Capacity=2.98 cfs Outflow=0.04 cfs 3,552 cf
Pond 2P: Pipe Storage Peak Elev=87.27' Storage=9,369 cf Inflow=3.51 cfs 11,277 cf
Outflow=0.04 cfs 3,553 cf
Total Runoff Area = 88,742 sf Runoff Volume = 29,510 cf Average Runoff Depth = 3.99"
65.53% Pervious = 58,152 sf 34.47% Impervious = 30,590 sf
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 46
Runoff = 0.69 cfs @ 12.04 hrs, Volume= 1,916 cf, Depth= 3.62"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
0.75 Runoff
0.69 cfs
0.7
Type III 24-hr
0.65
25-Year Rainfall=5.60"
0.6
Runoff Area=6,350 sf
0.55
Runoff Volume=1,916 cf
0.5
Runoff Depth=3.62"
0.45
Flow (cfs)
0.4
Flow Length=64'
0.35
Slope=0.1000 '/'
0.3
Tc=2.9 min
0.25 CN=82
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 47
Runoff = 0.44 cfs @ 12.11 hrs, Volume= 1,444 cf, Depth= 3.32"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
0.48 Runoff
0.46 0.44 cfs
0.44 Type III 24-hr
0.42
0.4 25-Year Rainfall=5.60"
0.38
0.36
Runoff Area=5,213 sf
0.34 Runoff Volume=1,444 cf
0.32
0.3 Runoff Depth=3.32"
0.28
Flow (cfs)
0.26
Flow Length=165'
0.24 Tc=7.5 min
0.22
0.2 CN=79
0.18
0.16
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 48
Runoff = 0.04 cfs @ 12.02 hrs, Volume= 116 cf, Depth= 3.32"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
Runoff
0.048
0.046 0.04 cfs
0.044 Type III 24-hr
0.042
0.04 25-Year Rainfall=5.60"
0.038
0.036 Runoff Area=420 sf
0.034
0.032
Runoff Volume=116 cf
0.03 Runoff Depth=3.32"
Flow (cfs)
0.028
0.026 Flow Length=20'
0.024
0.022 Slope=0.1000 '/'
0.02
0.018
Tc=1.3 min
0.016 CN=79
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 49
Runoff = 2.37 cfs @ 12.05 hrs, Volume= 7,168 cf, Depth= 4.68"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
Runoff
2.37 cfs
Type III 24-hr
25-Year Rainfall=5.60"
2 Runoff Area=18,392 sf
Runoff Volume=7,168 cf
Runoff Depth=4.68"
Flow (cfs)
Flow Length=171'
Tc=3.7 min
CN=92
1
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 51
Runoff = 0.60 cfs @ 12.00 hrs, Volume= 1,595 cf, Depth= 4.35"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
Runoff
0.65
0.60 cfs
0.6 Type III 24-hr
0.55 25-Year Rainfall=5.60"
0.5 Runoff Area=4,400 sf
0.45 Runoff Volume=1,595 cf
0.4
Runoff Depth=4.35"
Flow (cfs)
0.35
Flow Length=35'
Tc=0.2 min
0.3
CN=89
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 52
Runoff = 1.17 cfs @ 12.07 hrs, Volume= 3,740 cf, Depth= 4.68"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
Runoff
1.17 cfs
Type III 24-hr
25-Year Rainfall=5.60"
1 Runoff Area=9,597 sf
Runoff Volume=3,740 cf
Runoff Depth=4.68"
Flow (cfs)
Flow Length=160'
Slope=0.0200 '/'
Tc=5.1 min
CN=92
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 53
Runoff = 0.50 cfs @ 12.12 hrs, Volume= 1,668 cf, Depth= 3.32"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
0.55 Runoff
0.50 cfs
0.5
Type III 24-hr
0.45 25-Year Rainfall=5.60"
Runoff Area=6,022 sf
0.4
Runoff Volume=1,668 cf
0.35
Runoff Depth=3.32"
Flow (cfs)
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 54
Runoff = 3.46 cfs @ 12.11 hrs, Volume= 11,604 cf, Depth= 3.72"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
Runoff
3.46 cfs
Type III 24-hr
25-Year Rainfall=5.60"
3
Runoff Area=37,415 sf
Runoff Volume=11,604 cf
Runoff Depth=3.72"
Flow Length=263'
Flow (cfs)
2
Slope=0.0250 '/'
Tc=8.1 min
CN=83
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 55
Runoff = 0.09 cfs @ 12.05 hrs, Volume= 258 cf, Depth= 3.32"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 25-Year Rainfall=5.60"
0.1 Runoff
0.095
0.09 cfs
0.09 Type III 24-hr
0.085 25-Year Rainfall=5.60"
0.08
0.075 Runoff Area=933 sf
0.07 Runoff Volume=258 cf
0.065
0.06
Runoff Depth=3.32"
Flow (cfs)
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth > 1.32" for 25-Year event
Inflow = 0.04 cfs @ 21.83 hrs, Volume= 3,553 cf
Outflow = 0.04 cfs @ 21.83 hrs, Volume= 3,552 cf, Atten= 0%, Lag= 0.2 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Max. Velocity= 2.98 fps, Min. Travel Time= 0.2 min
Avg. Velocity = 2.65 fps, Avg. Travel Time= 0.2 min
Inflow
0.04 cfs Outflow
0.042
Inflow Area=32,389 sf 0.04 cfs
0.04
0.038 Avg. Flow Depth=0.05'
0.036
0.034 Max Vel=2.98 fps
0.032 8.0"
0.03
0.028 Round Pipe
0.026
n=0.012
Flow (cfs)
0.024
0.022 L=27.0'
0.02
0.018
S=0.0519 '/'
0.016 Capacity=2.98 cfs
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 58
Inflow Area = 44,372 sf, 49.70% Impervious, Inflow Depth > 1.90" for 25-Year event
Inflow = 1.11 cfs @ 12.06 hrs, Volume= 7,029 cf
Primary = 1.11 cfs @ 12.06 hrs, Volume= 7,029 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
1.11 cfs Primary
1.11 cfs Inflow Area=44,372 sf
1
Flow (cfs)
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 59
Inflow Area = 37,602 sf, 56.13% Impervious, Inflow Depth > 1.59" for 25-Year event
Inflow = 0.47 cfs @ 12.11 hrs, Volume= 4,997 cf
Primary = 0.47 cfs @ 12.11 hrs, Volume= 4,997 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
0.47 cfs Primary
0.5 0.47 cfs Inflow Area=37,602 sf
0.45
0.4
0.35
0.3
Flow (cfs)
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 60
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth = 4.18" for 25-Year event
Inflow = 3.51 cfs @ 12.06 hrs, Volume= 11,277 cf
Outflow = 0.04 cfs @ 21.83 hrs, Volume= 3,553 cf, Atten= 99%, Lag= 586.1 min
Primary = 0.04 cfs @ 21.83 hrs, Volume= 3,553 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs / 3
Peak Elev= 87.27' @ 21.83 hrs Surf.Area= 4,209 sf Storage= 9,369 cf
Plug-Flow detention time= 738.0 min calculated for 3,553 cf (32% of inflow)
Center-of-Mass det. time= 587.7 min ( 1,366.9 - 779.2 )
Inflow
3.51 cfs Primary
Inflow Area=32,389 sf
Peak Elev=87.27'
3 Storage=9,369 cf
Flow (cfs)
0.04 cfs
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 62
Inflow Area = 44,370 sf, 19.24% Impervious, Inflow Depth = 3.66" for 25-Year event
Inflow = 4.02 cfs @ 12.11 hrs, Volume= 13,531 cf
Primary = 4.02 cfs @ 12.11 hrs, Volume= 13,531 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
4.02 cfs Primary
4.02 cfs Inflow Area=44,370 sf
4
3
Flow (cfs)
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 25-Year Rainfall=5.60"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 63
Inflow Area = 4,400 sf, 54.55% Impervious, Inflow Depth = 4.35" for 25-Year event
Inflow = 0.60 cfs @ 12.00 hrs, Volume= 1,595 cf
Outflow = 0.08 cfs @ 12.48 hrs, Volume= 1,243 cf, Atten= 87%, Lag= 28.3 min
Discarded = 0.01 cfs @ 12.48 hrs, Volume= 874 cf
Primary = 0.07 cfs @ 12.48 hrs, Volume= 369 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 97.65' @ 12.48 hrs Surf.Area= 1,449 sf Storage= 827 cf
Plug-Flow detention time= 453.8 min calculated for 1,242 cf (78% of inflow)
Center-of-Mass det. time= 374.5 min ( 1,159.6 - 785.1 )
Inflow
0.60 cfs Outflow
Inflow Area=4,400 sf Discarded
Primary
0.65
Peak Elev=97.65'
0.6
Storage=827 cf
0.55
0.5
0.45
0.4
Flow (cfs)
0.35
0.3
0.25
0.2
0.08 cfs
0.15
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 65
Reach 8R: ADS Pipe Avg. Flow Depth=0.11' Max Vel=4.79 fps Inflow=0.19 cfs 6,187 cf
8.0" Round Pipe n=0.012 L=27.0' S=0.0519 '/' Capacity=2.98 cfs Outflow=0.19 cfs 6,186 cf
Pond 2P: Pipe Storage Peak Elev=87.73' Storage=11,054 cf Inflow=4.57 cfs 14,934 cf
Outflow=0.19 cfs 6,187 cf
Total Runoff Area = 88,742 sf Runoff Volume = 39,302 cf Average Runoff Depth = 5.31"
65.53% Pervious = 58,152 sf 34.47% Impervious = 30,590 sf
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 66
Runoff = 0.93 cfs @ 12.04 hrs, Volume= 2,601 cf, Depth= 4.92"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
1 Runoff
0.93 cfs
Type III 24-hr
100-Year Rainfall=7.00"
Runoff Area=6,350 sf
Runoff Volume=2,601 cf
Runoff Depth=4.92"
Flow (cfs)
Flow Length=64'
Slope=0.1000 '/'
Tc=2.9 min
CN=82
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 67
Runoff = 0.61 cfs @ 12.11 hrs, Volume= 1,992 cf, Depth= 4.58"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
Runoff
0.65
0.61 cfs
0.6 Type III 24-hr
0.55 100-Year Rainfall=7.00"
0.5 Runoff Area=5,213 sf
0.45 Runoff Volume=1,992 cf
0.4
Runoff Depth=4.58"
Flow (cfs)
Flow Length=165'
0.35
Tc=7.5 min
0.3
CN=79
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 68
Runoff = 0.06 cfs @ 12.02 hrs, Volume= 160 cf, Depth= 4.58"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
Runoff
0.065 0.06 cfs
0.06 Type III 24-hr
0.055 100-Year Rainfall=7.00"
0.05 Runoff Area=420 sf
0.045
Runoff Volume=160 cf
0.04
Runoff Depth=4.58"
Flow (cfs)
Flow Length=20'
0.035
Slope=0.1000 '/'
0.03
Tc=1.3 min
0.025
CN=79
0.02
0.015
0.01
0.005
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 69
Runoff = 3.02 cfs @ 12.05 hrs, Volume= 9,280 cf, Depth= 6.05"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
Runoff
3.02 cfs
3 Type III 24-hr
100-Year Rainfall=7.00"
Runoff Area=18,392 sf
Runoff Volume=9,280 cf
2
Runoff Depth=6.05"
Flow (cfs)
Flow Length=171'
Tc=3.7 min
CN=92
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 71
Runoff = 0.78 cfs @ 12.00 hrs, Volume= 2,093 cf, Depth= 5.71"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
0.85 Runoff
0.8
0.78 cfs
0.75
Type III 24-hr
0.7 100-Year Rainfall=7.00"
0.65 Runoff Area=4,400 sf
0.6 Runoff Volume=2,093 cf
0.55
Runoff Depth=5.71"
0.5
Flow (cfs)
Flow Length=35'
0.45
0.4
Tc=0.2 min
0.35 CN=89
0.3
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 72
Runoff = 1.50 cfs @ 12.07 hrs, Volume= 4,842 cf, Depth= 6.05"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
Runoff
1.50 cfs
Type III 24-hr
100-Year Rainfall=7.00"
Runoff Area=9,597 sf
Runoff Volume=4,842 cf
1 Runoff Depth=6.05"
Flow (cfs)
Flow Length=160'
Slope=0.0200 '/'
Tc=5.1 min
CN=92
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 73
Runoff = 0.68 cfs @ 12.12 hrs, Volume= 2,301 cf, Depth= 4.58"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
0.75 Runoff
0.7
0.68 cfs
Type III 24-hr
0.65
100-Year Rainfall=7.00"
0.6
0.55
Runoff Area=6,022 sf
0.5
Runoff Volume=2,301 cf
0.45
Runoff Depth=4.58"
Flow (cfs)
0.4
Flow Length=197'
0.35
Tc=8.3 min
0.3 CN=79
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 74
Runoff = 4.62 cfs @ 12.11 hrs, Volume= 15,676 cf, Depth= 5.03"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
5 Runoff
4.62 cfs
Type III 24-hr
100-Year Rainfall=7.00"
4
Runoff Area=37,415 sf
Runoff Volume=15,676 cf
Runoff Depth=5.03"
3
Flow Length=263'
Flow (cfs)
Slope=0.0250 '/'
Tc=8.1 min
2
CN=83
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 75
Runoff = 0.13 cfs @ 12.05 hrs, Volume= 356 cf, Depth= 4.58"
Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Type III 24-hr 100-Year Rainfall=7.00"
0.14 Runoff
0.13
0.13 cfs
Type III 24-hr
0.12
100-Year Rainfall=7.00"
0.11
Runoff Area=933 sf
0.1
Runoff Volume=356 cf
0.09
Runoff Depth=4.58"
Flow (cfs)
0.08
Flow Length=28'
0.07
Slope=0.0250 '/'
0.06 Tc=3.1 min
0.05 CN=79
0.04
0.03
0.02
0.01
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 76
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth > 2.29" for 100-Year event
Inflow = 0.19 cfs @ 14.97 hrs, Volume= 6,187 cf
Outflow = 0.19 cfs @ 14.98 hrs, Volume= 6,186 cf, Atten= 0%, Lag= 0.2 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Max. Velocity= 4.79 fps, Min. Travel Time= 0.1 min
Avg. Velocity = 2.98 fps, Avg. Travel Time= 0.2 min
Inflow
0.21 0.19 cfs Outflow
0.2 0.19 cfs Inflow Area=32,389 sf
0.19
0.18 Avg. Flow Depth=0.11'
0.17 Max Vel=4.79 fps
0.16
0.15 8.0"
0.14 Round Pipe
0.13
n=0.012
Flow (cfs)
0.12
0.11 L=27.0'
0.1
0.09 S=0.0519 '/'
0.08 Capacity=2.98 cfs
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 78
Inflow Area = 44,372 sf, 49.70% Impervious, Inflow Depth > 2.96" for 100-Year event
Inflow = 1.50 cfs @ 12.06 hrs, Volume= 10,939 cf
Primary = 1.50 cfs @ 12.06 hrs, Volume= 10,939 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
1.50 cfs Primary
1.50 cfs Inflow Area=44,372 sf
1
Flow (cfs)
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 79
Inflow Area = 37,602 sf, 56.13% Impervious, Inflow Depth > 2.61" for 100-Year event
Inflow = 0.64 cfs @ 12.11 hrs, Volume= 8,178 cf
Primary = 0.64 cfs @ 12.11 hrs, Volume= 8,178 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
0.7 0.64 cfs Primary
0.64 cfs Inflow Area=37,602 sf
0.65
0.6
0.55
0.5
0.45
Flow (cfs)
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 80
Inflow Area = 32,389 sf, 65.16% Impervious, Inflow Depth = 5.53" for 100-Year event
Inflow = 4.57 cfs @ 12.06 hrs, Volume= 14,934 cf
Outflow = 0.19 cfs @ 14.97 hrs, Volume= 6,187 cf, Atten= 96%, Lag= 174.8 min
Primary = 0.19 cfs @ 14.97 hrs, Volume= 6,187 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs / 3
Peak Elev= 87.73' @ 14.97 hrs Surf.Area= 2,843 sf Storage= 11,054 cf
Plug-Flow detention time= 578.6 min calculated for 6,185 cf (41% of inflow)
Center-of-Mass det. time= 448.9 min ( 1,221.8 - 772.9 )
Inflow
5 4.57 cfs Primary
Inflow Area=32,389 sf
Peak Elev=87.73'
4 Storage=11,054 cf
3
Flow (cfs)
0.19 cfs
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 82
Inflow Area = 44,370 sf, 19.24% Impervious, Inflow Depth = 4.96" for 100-Year event
Inflow = 5.39 cfs @ 12.11 hrs, Volume= 18,333 cf
Primary = 5.39 cfs @ 12.11 hrs, Volume= 18,333 cf, Atten= 0%, Lag= 0.0 min
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Inflow
6 5.39 cfs Primary
5.39 cfs Inflow Area=44,370 sf
5
4
Flow (cfs)
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
345 Oak Drainage Type III 24-hr 100-Year Rainfall=7.00"
Prepared by Grady Consulting, LLC Printed 9/20/2019
HydroCAD® 10.00-21 s/n 09955 © 2018 HydroCAD Software Solutions LLC Page 83
Inflow Area = 4,400 sf, 54.55% Impervious, Inflow Depth = 5.71" for 100-Year event
Inflow = 0.78 cfs @ 12.00 hrs, Volume= 2,093 cf
Outflow = 0.24 cfs @ 12.24 hrs, Volume= 1,716 cf, Atten= 70%, Lag= 14.2 min
Discarded = 0.01 cfs @ 12.24 hrs, Volume= 904 cf
Primary = 0.23 cfs @ 12.24 hrs, Volume= 812 cf
Routing by Stor-Ind method, Time Span= 0.00-36.00 hrs, dt= 0.01 hrs
Peak Elev= 97.70' @ 12.24 hrs Surf.Area= 1,480 sf Storage= 911 cf
Plug-Flow detention time= 345.9 min calculated for 1,715 cf (82% of inflow)
Center-of-Mass det. time= 275.1 min ( 1,052.9 - 777.8 )
Inflow
0.78 cfs Outflow
Inflow Area=4,400 sf Discarded
Primary
0.85
0.8
Peak Elev=97.70'
0.75 Storage=911 cf
0.7
0.65
0.6
0.55
Flow (cfs)
0.5
0.45
0.4
0.35 0.24 cfs
0.3
0.25
0.23 cfs
0.2
0.15
0.1 0.01 cfs
0.05
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
Time (hours)
Section II
Stormwater Management
♦ STANDARD #1 No New Stormwater Conveyances
The proposed development proposes no new stormwater conveyances that discharge untreated
stormwater off-site or cause down gradient erosion.
BASIN
Total Proposed
Retained volume below Nyloplast yard drain emergency outlet = 798 cf
Purpose: To calculate the water quality flow rate (WQF) over a given site area. In this situation the WQF is
derived from the first 1" of runoff from the contributing impervious surface.
Reference: Massachusetts Dept. of Environmental Protection Wetlands Program / United States Department of
Agriculture Natural Resources Conservation Service TR-55 Manual
Procedure: Determine unit peak discharge using Figure 1 or 2. Figure 2 is in tabular form so is preferred. Using
the tc, read the unit peak discharge (qu) from Figure 1 or Table in Figure 2. qu is expressed in the
following units: cfs/mi2/watershed inches (csm/in).
where:
Q = flow rate associated with first 1" of runoff
qu = the unit peak discharge, in csm/in.
A = impervious surface drainage area (in square miles)
WQV = water quality volume in watershed inches (1" in this case)
Rainfall
Percent Rainfall Cumulative Total Flowrate Treated Flowrate Incremental
Intensity1
Volume1 Rainfall Volume (cfs) (cfs) Removal (%)
(in/hr)
0.02 9.3% 9.3% 0.01 0.01 9.0
0.04 9.5% 18.8% 0.02 0.02 9.1
0.06 8.7% 27.5% 0.03 0.03 8.3
0.08 10.1% 37.6% 0.03 0.03 9.6
0.10 7.2% 44.8% 0.04 0.04 6.8
0.12 6.0% 50.8% 0.05 0.05 5.6
0.14 6.3% 57.1% 0.06 0.06 5.9
0.16 5.6% 62.7% 0.07 0.07 5.2
0.18 4.7% 67.4% 0.08 0.08 4.3
0.20 3.6% 71.0% 0.09 0.09 3.3
0.25 8.2% 79.1% 0.11 0.11 7.3
0.50 14.9% 94.0% 0.22 0.22 12.3
0.75 3.2% 97.3% 0.32 0.32 2.4
1.00 1.2% 98.5% 0.43 0.43 0.8
1.50 0.7% 99.2% 0.65 0.65 0.4
2.00 0.8% 100.0% 0.86 0.86 0.3
0.00 0.0% 100.0% 0.00 0.00 0.0
0.00 0.0% 100.0% 0.00 0.00 0.0
0.00 0.0% 100.0% 0.00 0.00 0.0
0.00 0.0% 100.0% 0.00 0.00 0.0
0.00 0.0% 100.0% 0.00 0.00 0.0
90.6
Removal Efficiency Adjustment2 = 6.5%
Predicted % Annual Rainfall Treated = 93.5%
Predicted Net Annual Load Removal Efficiency = 84.2%
1 - Based on 10 years of rainfall data from NCDC station 736, Blue Hill, Norfolk County, MA
2 - Reduction due to use of 60-minute data for a site that has a time of concentration less than 30-minutes.
Massachusetts Department of Environmental Protection
Bureau of Resource Protection - Wetlands Program
In addition to all plans and supporting information, the Stormwater Report must include a brief narrative
describing stormwater management practices, including environmentally sensitive site design and LID
techniques, along with a diagram depicting runoff through the proposed BMP treatment train. Plans are
required to show existing and proposed conditions, identify all wetland resource areas, NRCS soil types,
critical areas, Land Uses with Higher Potential Pollutant Loads (LUHPPL), and any areas on the site
where infiltration rate is greater than 2.4 inches per hour. The Plans shall identify the drainage areas for
both existing and proposed conditions at a scale that enables verification of supporting calculations.
As noted in the Checklist, the Stormwater Management Report shall document compliance with each of
the Stormwater Management Standards as provided in the Massachusetts Stormwater Handbook. The
soils evaluation and calculations shall be done using the methodologies set forth in Volume 3 of the
Massachusetts Stormwater Handbook.
To ensure that the Stormwater Report is complete, applicants are required to fill in the Stormwater Report
Checklist by checking the box to indicate that the specified information has been included in the
Stormwater Report. If any of the information specified in the checklist has not been submitted, the
applicant must provide an explanation. The completed Stormwater Report Checklist and Certification
must be submitted with the Stormwater Report.
1
The Stormwater Report may also include the Illicit Discharge Compliance Statement required by Standard 10. If not included in
the Stormwater Report, the Illicit Discharge Compliance Statement must be submitted prior to the discharge of stormwater runoff to
the post-construction best management practices.
2
For some complex projects, it may not be possible to include the Construction Period Erosion and Sedimentation Control Plan in
the Stormwater Report. In that event, the issuing authority has the discretion to issue an Order of Conditions that approves the
project and includes a condition requiring the proponent to submit the Construction Period Erosion and Sedimentation Control Plan
before commencing any land disturbance activity on the site.
Note: Because stormwater requirements vary from project to project, it is possible that a complete
Stormwater Report may not include information on some of the subjects specified in the Checklist. If it is
determined that a specific item does not apply to the project under review, please note that the item is not
applicable (N.A.) and provide the reasons for that determination.
A complete checklist must include the Certification set forth below signed by the Registered Professional
Engineer who prepared the Stormwater Report.
9/20/2019
Signature and Date
Checklist
Project Type: Is the application for new development, redevelopment, or a mix of new and
redevelopment?
New development
Redevelopment
Credit 1
Credit 2
Credit 3
Use of “country drainage” versus curb and gutter conveyance and pipe
Treebox Filter
Grass Channel
Green Roof
Other (describe):
Standard 3: Recharge
Required Recharge volume reduced through use of the LID site Design Credits.
Sizing the infiltration, BMPs is based on the following method: Check the method used.
Runoff from all impervious areas at the site discharging to the infiltration BMP.
Runoff from all impervious areas at the site is not discharging to the infiltration BMP and calculations
are provided showing that the drainage area contributing runoff to the infiltration BMPs is sufficient to
generate the required recharge volume.
Recharge BMPs have been sized to infiltrate the Required Recharge Volume.
Recharge BMPs have been sized to infiltrate the Required Recharge Volume only to the maximum
extent practicable for the following reason:
Site is comprised solely of C and D soils and/or bedrock at the land surface
Property includes a M.G.L. c. 21E site or a solid waste landfill and a mounding analysis is included.
1
80% TSS removal is required prior to discharge to infiltration BMP if Dynamic Field method is used.
The infiltration BMP is used to attenuate peak flows during storms greater than or equal to the 10-
year 24-hour storm and separation to seasonal high groundwater is less than 4 feet and a mounding
analysis is provided.
Documentation is provided showing that infiltration BMPs do not adversely impact nearby wetland
resource areas.
Standard 4: Water Quality
is within soils with a rapid infiltration rate (greater than 2.4 inches per hour)
involves runoff from land uses with higher potential pollutant loads.
The Required Water Quality Volume is reduced through use of the LID site Design Credits.
Calculations documenting that the treatment train meets the 80% TSS removal requirement and, if
applicable, the 44% TSS removal pretreatment requirement, are provided.
LUHPPLs are located at the site and industry specific source control and pollution prevention
measures have been proposed to reduce or eliminate the exposure of LUHPPLs to rain, snow, snow
melt and runoff, and been included in the long term Pollution Prevention Plan.
All exposure has not been eliminated and all BMPs selected are on MassDEP LUHPPL list.
The LUHPPL has the potential to generate runoff with moderate to higher concentrations of oil and
grease (e.g. all parking lots with >1000 vehicle trips per day) and the treatment train includes an oil
grit separator, a filtering bioretention area, a sand filter or equivalent.
Redevelopment Project
A Construction Period Pollution Prevention and Erosion and Sedimentation Control Plan must include the
following information:
Narrative;
Construction Period Operation and Maintenance Plan;
Names of Persons or Entity Responsible for Plan Compliance;
Construction Period Pollution Prevention Measures;
Erosion and Sedimentation Control Plan Drawings;
Detail drawings and specifications for erosion control BMPs, including sizing calculations;
Vegetation Planning;
Site Development Plan;
Construction Sequencing Plan;
Sequencing of Erosion and Sedimentation Controls;
Operation and Maintenance of Erosion and Sedimentation Controls;
Inspection Schedule;
Maintenance Schedule;
Inspection and Maintenance Log Form.
A Construction Period Pollution Prevention and Erosion and Sedimentation Control Plan containing
the information set forth above has been included in the Stormwater Report.
Plan showing the location of all stormwater BMPs maintenance access areas;
The Long-Term Pollution Prevention Plan includes measures to prevent illicit discharges;
Source of Funding:
Operation and Maintenance of this stormwater management system will be the responsibility
of the property owner to include its successor and/or assigns, as the same may appear on record
with the appropriate register of deeds.
During Construction:
Construction activities shall follow the Construction Sequence shown on the approved plans.
During periods of active construction the stormwater management system shall be inspected on a
weekly basis and within 24 hours of a storm event of greater than ½”. Maintenance tasks shall be
performed monthly or after significant rainfall events of 1” of rain or greater. During construction,
silt-laden runoff shall be prevented from entering the drainage system and off-site properties.
Temporary swales shall be constructed as needed during construction to direct runoff to sediment
traps. Infiltration systems and subsurface storage systems shall not be placed in service until after
the installation of base course pavement and vegetative stabilization of the areas contributing to the
systems.
During dewatering operations, all water pumped from the dewatering shall be directed to a “dirt
bag” pumped sediment removal system (or approved equal) as manufactured by ACF
Environmental. Water from construction dewatering activities should not be directed into any of
the existing or proposed stormwater management facilities system unless it is fully treated prior to
discharge. The unit shall be placed on a crushed stone blanket. Disposal of such “dirt bag” shall
occur when the device is full and can no longer effectively filter sediment or allow water to pass at
a reasonable flow rate. Disposal of this unit shall be the responsibility of the contractor and shall
be as directed by the owner in accordance with applicable local, state, and federal guidelines and
regulations.
All erosion and sedimentation control measures shall be in place prior to the commencement of
any site work or earthwork operations, and shall be maintained during construction, and shall
remain in place until all site work is complete and ground cover is established.
2019-05-3
All exposed soils not to be paved shall be stabilized as soon as practical. Seed mixes shall only be
applied during appropriate periods as recommended by the seed supplier, typically May 1 to
October 15. Any exposed soils that cannot be stabilized by vegetation during these dates shall be
stabilized with hay bales, hay mulch, check dams, jute netting or other acceptable means.
Once each structure is in place, it should be maintained in accordance with the procedures
described in the post-construction Operations and Maintenance Plan.
During dry periods where dust is created by construction activities the following control measures
should be implemented.
Sprinkling – The contractor may sprinkle the ground along haul roads and traffic areas until
moist.
Vegetative cover – Areas that are not expected to be disturbed regularly may be stabilized
with vegetative cover.
Mulch – Mulching can be used as a quick and effective means of dust control in recently
disturbed areas.
Spray on chemical soil treatments may be utilized. Application rates shall conform to
manufacturers recommendations.
Illicit Discharges
Illicit discharges to the stormwater management system are discharges that are not entirely
comprised of stormwater. Illicit discharges are prohibited from the stormwater management
system and the stormwater management system shall be inspected for illicit discharges annually.
STORMWATER MANAGEMENT
BEST MANAGEMENT PRACTICES
INSPECTION SCHEDULE AND EVALUATION CHECKLIST – CONSTRUCTION PHASE
PROJECT LOCATION: 345 Oak Street, Pembroke Latest Revision: May 30, 2019
Best Inspection Date Inspector Minimum Cleaning/ Date of Performed Water Level
Management Frequency Inspected Maintenance and Repair Cleaning/Repair By in
Practice (1) Key Items to Needed Detention
Check yes/no System
List items
Silt socks & After every
swales and major storm
silt traps event
Dewatering Daily-
Operations during
actual
dewatering
Temporary Daily or as
Construction needed.
Entrance
(1) Refer to the Massachusetts Stormwater Management, Volume Two: Stormwater Technical Handbook for
recommendations regarding frequency for inspection and maintenance of specific BMPs.
Limited or no use of sodium chloride salts, fertilizers or pesticides recommended. Slow release fertilizer recommended.
Other notes:(Include deviations from: Con Com Order of Conditions, PB Approval, Construction Sequence and Approved Plan)
OPERATION AND MAINTENANCE PLAN
PROPOSED DRAINAGE SYSTEM – POST CONSTRUCTION
345 Oak Street, Assessors Map F15-38
Pembroke, Massachusetts
Owner:
Champion Builders Inc.
P.O. Box #1414
Duxbury, MA 02331
Contact: (781) 585-4114 Email: [email protected]
Party Responsible for Operation and Maintenance:
After construction is complete the owner will be the party responsible for operation and maintenance
of the drainage system. When the property is conveyed, the new owner will be the party responsible
for operation and maintenance.
Source of Funding:
Operation and Maintenance of this stormwater management system will be the responsibility of the
owner.
The 1” diameter orifice should be kept clear of debris, and should be inspected quarterly to ensure no
blockage exists. Standing water in the storage pipes is an indicator of such a blockage.
Illicit Discharges
Illicit discharges to the stormwater management system are discharges that are not entirely
comprised of stormwater. Illicit discharges are prohibited from the stormwater management
system and the stormwater management system shall be inspected for illicit discharges
annually.
This Standard prohibits illicit discharges to stormwater management systems. The stormwater
management system is the system for conveying, treating, and infiltrating stormwater on-site,
including stormwater best management practices and any pipes intended to transport stormwater to the
groundwater, a surface water, or municipal separate storm sewer system. Illicit discharges to the
stormwater management system are discharges that are not entirely comprised of stormwater.
Notwithstanding the foregoing, an illicit discharge does not include discharges from the following
activities or facilities: firefighting, water line flushing, landscape irrigation, uncontaminated
groundwater, potable water sources, foundation drains, air conditioning condensation, footing drains,
individual resident car washing, flows from riparian habitats and wetlands, dechlorinated water from
swimming pools, water used for street washing and water used to clean residential buildings without
detergents.
For additional information, refer to Performance Standards and Guidelines for Stormwater Management in Massachusetts,
published by the Department of Environmental Protection.
STORMWATER MANAGEMENT
BEST MANAGEMENT PRACTICES
PROJECT LOCATION: 345 Oak Street, Pembroke Latest Revision January 23, 2019
Best Inspection Date Inspector Minimum Cleaning/ Date of Performed Water
Management Frequency Inspected Maintenance Repair Cleaning/ By Level in
Practice (1) and Key Needed Repair Drainage
Items to yes/no System
Check List items
Outlet Once per
Structure year
(1) Refer to the Massachusetts Stormwater Management, Volume Two: Stormwater Technical Handbook for
recommendations regarding frequency for inspection and maintenance of specific BMPs.
(2) records shall be kept for a minimum of three years.
Limited or no use of sodium chloride salts, fertilizers or pesticides recommended. Slow release fertilizer recommended.
Other notes:(Include deviations from: Con Com Order of Conditions, PB Approval, Construction Sequence and Approved Plan)
L~X|XQÿQfÿeSSQÿT}SXWXÿTQOPMOMT LMNOPQORSTUVSPSWXQTY
\ÿZ2)*+$5ÿ'/5$7672'/50ÿ&2ÿ1.(.+$5ÿ12+ÿ&.[$ÿ.&ÿ
l+*/5*75 #$&)7.%+.2/ /2+ÿ*ÿ5$+$77$/+;
mÿnÿa$*3ÿi124 a729.5$&ÿ/2ÿ%$*3ÿ:124ÿ*++$/'*+.2/ \ÿ^2(%*+.-1$ÿ4.+,ÿ&'-&'7:*)$ÿ&+27(ÿ57*./ÿ
oÿnÿk$),*76$ a729.5$&ÿ/2ÿ672'/54*+$7ÿ7$),*76$ \ÿ&^* 8&+$(&;
/ÿ-$ÿ'&$5ÿ:27ÿ7$+72:.++./6ÿ&(*11ÿ'7-*/ÿ12+&ÿ
pÿnÿqllÿk$(29*1mrsÿqllÿ7$(29*1ÿ)7$5.+ÿ4,$/ÿ 4,$7$ÿ1*76$7ÿ_`a&ÿ*7$ÿ/2+ÿ:$*&.-1$;
'&$5ÿ:27ÿ%7$+7$*+($/+;ÿÿ_$)*'&$ÿ \ ÿa7 29.5$ÿ%7$+7$*+($/+ÿ2:ÿ7'/2::ÿ-$:27$ÿ.+ÿ.&ÿ
2:ÿ+,$.7ÿ1.(.+$5ÿ$::$)+.9$/$&&ÿ*/5ÿ \ÿb*1&..91$8ÿ7*$)5)ÿ$+2&ÿ&2$+5,ÿ$:27ÿ7_`a
5$ &;
ÿ(*./+$/*/)$;
&+27*6$ÿ)*%*).+80ÿ5$$%ÿ&'(%ÿ)*+),ÿ \ÿZ2/6$9.+8ÿ.&ÿ,.6,ÿ4. +,ÿ%72%$7ÿ(*./+$/*/)$;
-*&./&ÿ7$)$.9$ÿ)7$5.+ÿ:27ÿ7$(29./6ÿ
qllÿ2/18ÿ.:ÿ+,$8ÿ*7$ÿ'&$5ÿ:27ÿ
%7$+7$*+($/+ÿ*/5ÿ5$&.6/$5ÿ*&ÿ2::n cX TOMNOPQORSTUdXeXQOQXfPTY
\ÿZ.(.+$5ÿ%211'+*/+ÿ7$(29*1;
1./$ÿ&8&+$(&; \ÿbg%$/&.9$ÿ+2ÿ./&+*11ÿ*/5ÿ(*./+*./0ÿ7$&'1+./6ÿ./ÿ
rÿnÿt.6,$7ÿ k$)2(($/5$5ÿ*&ÿ%7$+7$*+($/+ÿ
a211'+*/+ÿ _`a;ÿu1+,2'6,ÿ%729.5$&ÿ&2($ÿ&%.11ÿ \ÿ,h2 .6,ÿ)2&+ÿ%$7ÿ'/.+ÿ*7$*ÿ+7$*+$5;
ÿ*-.1.+8ÿ+2ÿ)2/+721ÿ921'($ÿ2:ÿ&+27(4*+$7
Z2*5./6 )2/+721ÿ)*%*-.1.+80ÿ*ÿ5$$%ÿ&'(%ÿ \ ÿi7 $ j'$/+ÿ(*./+$/*/)$ÿ.&ÿ$&&$/+.*1
)*+),ÿ-*&./ÿ(*8ÿ/2+ÿ-$ÿ'&$5ÿ./ÿ
%1*)$ÿ2:ÿ*/ÿ2.1ÿ67.+ÿ&$%*7*+27ÿ27ÿ&*/5ÿ */5ÿ'2..71$ÿ*&/ÿ%57ÿ26%7$$*7ÿ&5$.&%2&*1ÿ2:ÿ+7*%%$5ÿ&$5.($/+ÿ
\ ÿk$ j
:.1+$7ÿ:27ÿ1*/5ÿ'&$&ÿ+,*+ÿ,*9$ÿ+,$ÿ \ÿb/+7*%($/+ÿ,*[*75ÿ:27ÿ*(%,.-.*/&ÿ*/5ÿ2+,$7ÿ
%2+$/+.*1ÿ+2ÿ6$/$7*+$ÿ7'/2::ÿ4.+,ÿ
,.6,ÿ)2/)$/+7*+.2/&ÿ2:ÿ2.1ÿ*/5ÿ67$*&$ÿ &(*11ÿ*/.(*1&
&'),ÿ*&!ÿ,.6,n./+$/&.+8n'&$ÿ%*73./6ÿ f||QOPQÿ{SefNO|ÿWWXXSPXST
12+&0ÿ6*&ÿ&+*+.2/&0ÿ:1$$+ÿ&+27*6$ÿ \ÿq2+*1ÿl'&%$/5$5ÿl21.5&ÿqllÿnÿmrsÿ:27ÿ
*7$*&0ÿ9$,.)1$ÿ*/5v27ÿ$j'.%($/+ÿ 7$6'1*+278ÿ%'7%2&$&
(*./+$/*/)$ÿ*/5ÿ&$79.)$ÿ*7$*&;
wÿnÿÿ#.&),*76$&ÿ `*8ÿ-$ÿ'&$5ÿ*&ÿ%7$+7$*+($/+ÿ_`a;ÿÿ h' \ ÿ +7.$/+&ÿh.+726$/0ÿ%,2&%,27'&ÿnÿ
/&'::.).$/+ÿ5*+*
/$*7ÿ27ÿ+2ÿ /2+ÿ*/ÿ*5$j'*+$ÿ&%.11ÿ)2/+721ÿ5$9.)$ÿ \ÿ`$ +*1&ÿ)2%%$70ÿ1$*50ÿ[./)0ÿ)*5(.'(ÿnÿ
^7.+.)*1ÿu7$*& :27ÿ5.&),*76$&ÿ/$*7ÿ27ÿ+2ÿ)7.+.)*1ÿ / &' ::.).$/+ÿ5*+*
*7$*&; \ÿa*+,26$/&ÿ)21.:27(0ÿ$ÿ)21.ÿnÿ/&'::.).$/+ÿ
xÿzÿ t.6,18ÿ&'.+*-1$; 5*+*
{SMSNS|f}eSPQ 0123413256ÿ89 ÿÿ63ÿÿÿ512ÿÿÿÿÿ5ÿ
5U51UÿV2ÿ1ÿWXYZ2Y1[ÿVÿ\]ÿ^5Y2
?@##@#
!" #
$%&'()*ÿ,%-*& ./,0ÿ*-1(&ÿ'(0ÿ2(30
45(3%ÿ,%-*& ./,0ÿ*-1(&ÿ'(0ÿ2(30ÿ/0ÿ67(%(8(0ÿ*7(ÿ9('*7ÿ/:ÿ
9('/&-*&ÿ-&ÿ;0(3*(0ÿ*73%ÿ/0ÿ(<,35ÿ*/ÿ/%(ÿ735:ÿ
*7(ÿ9('*7ÿ:0/1ÿ*7(ÿ=/**/1ÿ/:ÿ*7(ÿ-%8(0*ÿ/:ÿ*7(ÿ
5/6(&*ÿ'-'(ÿ-%ÿ*7(ÿ=3&-%>
AB @Cÿ @"E
I55ÿ9(('ÿ&,1'ÿ)3*)7ÿ=3&-%&ÿ1,&*ÿ-%)5,9(ÿ7//9&>ÿ./0ÿJ3&&K-;7632ÿ'0/L()*&Mÿ)/%&,5*ÿ*7(ÿN*/0163*(0ÿ
K3%9=//Oÿ:/0ÿK-;7632&ÿ3%9ÿP0-9;(&ÿ:/0ÿ7//9ÿ0(<,-0(1(%*&>
FQ(G9HÿC #@
,)(ÿ$1'(08-/,&ÿN,0:3)(
R-&)/%%()*ÿ0//:*/'ÿ3%9ÿ%/%S0//:*/'ÿ0,%/::
T(;(*3*(9ÿ.-5*(0ÿN*0-'
0123413256ÿ89 ÿÿ63ÿÿÿ512ÿÿÿÿÿ5ÿ
ÿÿ !"#ÿ$%&' 1020G.1.2/ÿA>2/->96Lÿÿ\29./ÿG-0/.6ÿ72678.ÿI0-V72Gÿ
G0-0G.6ÿ0-.ÿA;--.2/9Hÿ-.T;7-.8ÿ/>ÿF0=.ÿ1;AFÿ61099.-ÿ
>I.272G6ÿ/F02ÿ/F>6.ÿ8.6A-7<.8ÿF.-.72Lÿÿ
&!()ÿ*)&"!&+'% E>ÿ-.A.7=.ÿ/F.ÿ[abÿ-.1>=09ÿA-.87/YÿF>>86ÿ1;6/ÿ
3ÿ,-./-.0/1.2/ <.ÿ;6.8ÿ72ÿ8..Iÿ6;1IÿA0/AFÿ<06726Lÿÿÿc>>86ÿ096>ÿ
3ÿ5.678.2/709ÿ6;<87=767>26 F.9IÿA>2/072ÿ>79ÿ6I7996LÿS066c7GFQ0Hÿ10Hÿ726/099ÿ
3ÿ?@@7A. A0/AFÿ<06726ÿQ7/F>;/ÿF>>86ÿI->=78.8ÿ/F.Hÿ0-.ÿ
3ÿ5./079 8.67G2.8YÿA>26/-;A/.8Yÿ>I.-0/.8Yÿ028ÿ1072/072.8ÿ
%&B'ÿ+'%&CD!&+'% 72ÿ0AA>-802A.ÿQ7/Fÿ/F.ÿS066ÿc7GFQ0HÿO/>-1Q0/.-ÿ
3ÿEF.ÿA>2/-7<;/72Gÿ8-0720G.ÿ0-.0ÿ/>ÿ02Hÿ8..Iÿ c028<>>VL
6;1IÿA0/AFÿ<0672ÿ6F>;98ÿ2>/ÿ.JA..8ÿKÿ0A-.ÿ>@ÿ \26/099ÿ/F.ÿQ..IÿF>9.ÿ0<>=.ÿ/F.ÿ>;/9./ÿI7I.Lÿ_.=.-ÿ
71I.-=7>;6ÿA>=.-L
3ÿM.67G2ÿ028ÿA>26/-;A/ÿ8..Iÿ6;1IÿA0/AFÿ<06726ÿ06ÿ 7<206-/-0.999Lÿ/F.ÿQ..IÿF>9.ÿ72ÿ/F.ÿ<>//>1ÿ>@ÿ/F.ÿA0/AFÿ<0672ÿ
>@@N972.ÿ6H6/.16L
3ÿO7P.ÿ/F.ÿ8-0720G.ÿ0-.0ÿ6>ÿ/F0/ÿ/F.ÿ@9>Qÿ-0/.ÿ8>.6ÿ &!ÿ+'%!D&'!%
2>/ÿ.JA..8ÿ/F.ÿA0I0A7/Hÿ>@ÿ/F.ÿ729./ÿG-0/.Lÿ
3ÿM7=.-/ÿ.JA.66ÿ@9>Q6ÿ/>ÿ02>/F.-ÿRS,ÿ72/.28.8ÿ Xÿ I->I>2.2/ÿ10Hÿ2>/ÿ<.ÿ0<9.ÿ/>ÿ726/099ÿ0ÿ8..Iÿ6;1Iÿ
/>ÿ1../ÿ/F.ÿQ0/.-ÿT;02/7/Hÿ-.T;7-.1.2/6ÿUI.0Vÿ 3/ÿAM.
A 0 Fÿ<0672ÿ<.A0;6.ÿ>@d
I/Fÿ/>ÿ<.8->AVe
-0/.ÿ0//.2;0/7>2Wÿ>-ÿ/>ÿ0ÿ6/>-1ÿ8-072ÿ6H6/.1Lÿ
X2ÿ>@@N972.ÿ8.67G2ÿ.2F02A.6ÿI>99;/02/ÿ-.1>=09ÿ 33ÿÿc7 GFÿG->;28Q0/.-e
.@@7A7.2AHYÿ<.A0;6.ÿ7/ÿI-.=.2/6ÿ/F.ÿ-.6;6I.267>2ÿ 3ÿ,- ?/
.6.2A.ÿ>@ÿ;/797/7.6eÿ>-
F.-ÿ67/.ÿA>287/7>26ÿ/F0/ÿ9717/ÿ8.I/Fÿ>@ÿ
>@ÿ6.871.2/6ÿ72ÿ90-G.ÿ6/>-16L .JA0=0/7>2ÿ<.A0;6.ÿ>@ÿ6/0<797/HL
S0V.ÿ/F.ÿ6;1Iÿ8.I/FÿU876/02A.ÿ@->1ÿ/F.ÿ<>//>1ÿ>@ÿ
/F.ÿ>;/9./ÿI7I.ÿ/>ÿ/F.ÿ<>//>1ÿ>@ÿ/F.ÿ<0672Wÿ0/ÿ9.06/ÿ f &'!''"
@>;-ÿ@../ÿ/71.6ÿ/F.ÿ8701./.-ÿ>@ÿ/F.ÿ>;/9./ÿI7I.ÿ028ÿ 5.G;90-ÿ1072/.202A.ÿ76ÿ.66.2/709LÿÿM..Iÿ6;1IÿA0/AFÿ
1>-.ÿ7@ÿ/F.ÿA>2/-7<;/72Gÿ8-0720G.ÿ0-.0ÿF06ÿ0ÿF7GFÿ <06726ÿ-.1072ÿ.@@.A/7=.ÿ0/ÿ-.1>=72GÿI>99;/02/6ÿ>29Hÿ
6.871.2/ÿ9>08LÿEF.ÿ17271;1ÿ6;1Iÿ8.I/Fÿ76ÿZÿ@../Lÿÿ 7@ÿ/F.Hÿ0-.ÿA9.02.8ÿ>;/ÿ@-.T;.2/9HLÿÿ?2.ÿ6/;8Hÿ@>;28ÿ
M>;<9.ÿA0/AFÿ<06726Yÿ/F>6.ÿQ7/Fÿ[ÿ729./ÿG-0/.6Yÿ10Hÿ /F0/ÿ>2A.ÿagbÿ>@ÿ/F.ÿ6;1Iÿ=>9;1.ÿ76ÿ@799.8Yÿ/F.ÿA0/AFÿ
-.T;7-.ÿ8..I.-ÿ6;1I6Lÿ\26/099ÿ/F.ÿ72=.-/ÿ>@ÿ/F.ÿ>;/9./ÿ <0672ÿ76ÿ2>/ÿ0<9.ÿ/>ÿ-./072ÿ0887/7>209ÿ6.871.2/6Lÿÿ
I7I.ÿ0/ÿ9.06/ÿZÿ@../ÿ@->1ÿ/F.ÿ<>//>1ÿ>@ÿ/F.ÿA0/AFÿ<0672ÿ
G-0/.L \26I.A/ÿ>-ÿA9.02ÿ8..Iÿ6;1Iÿ<06726ÿ0/ÿ9.06/ÿ@>;-ÿ/71.6ÿ
I.-ÿH.0-ÿ028ÿ0/ÿ/F.ÿ.28ÿ>@ÿ/F.ÿ@>970G.ÿ028ÿ62>QNÿ
EF.ÿ729./ÿG-0/.ÿ6.-=.6ÿ/>ÿI-.=.2/ÿ90-G.-ÿ8.<-76ÿ@->1ÿ -.1>=09ÿ6.06>26LÿO.871.2/6ÿ1;6/ÿ096>ÿ<.ÿ-.1>=.8ÿ
.2/.-72Gÿ/F.ÿ6;1ILÿÿE>ÿ<.ÿ.@@.A/7=.Yÿ/F.ÿG-0/.ÿ1;6/ÿ @>;-ÿ/71.6ÿI.-ÿH.0-ÿ>-ÿQF.2.=.-ÿ/F.ÿ8.I/Fÿ>@ÿ8.I>67/6ÿ
F0=.ÿ0ÿ6.I0-0/7>2ÿ<./Q..2ÿ/F.ÿG-0/.6ÿ>@ÿ>2.ÿ6T;0-.ÿ 76ÿG-.0/.-ÿ/F02ÿ>-ÿ.T;09ÿ/>ÿ>2.ÿF09@ÿ/F.ÿ8.I/Fÿ@->1ÿ
72AFÿ>-ÿ9.66LÿÿEF.ÿ729./ÿ>I.272G6ÿ1;6/ÿ2>/ÿ099>Qÿ@9>Q6ÿ /F.ÿ<>//>1ÿ>@ÿ/F.ÿ72=.-/ÿ>@ÿ/F.ÿ9>Q.6/ÿI7I.ÿ72ÿ/F.ÿ
G-.0/.-ÿ/F02ÿ]ÿA@6ÿ/>ÿ.2/.-ÿ/F.ÿ8..Iÿ6;1IÿA0/AFÿ<0672Lÿ <0672Lÿ\@ÿF028972Gÿ-;2>@@ÿ@->1ÿ9028ÿ;6.6ÿQ7/FÿF7GF.-ÿ
\@ÿ/F.ÿ729./ÿG-0/.ÿ76ÿ8.67G2.8ÿQ7/Fÿ0ÿA;-<ÿA;/Yÿ/F.ÿ I>/.2/709ÿI>99;/02/ÿ9>086ÿ>-ÿ876AF0-G72Gÿ-;2>@@ÿ2.0-ÿ
G-0/.ÿ1;6/ÿ-.0AFÿ/F.ÿ<0AVÿ>@ÿ/F.ÿA;-<ÿA;/ÿ/>ÿI-.=.2/ÿ >-ÿ/>ÿ0ÿA-7/7A09ÿ0-.0Yÿ1>-.ÿ@-.T;.2/ÿA9.0272Gÿ10Hÿ<.ÿ
<HI06672GLÿÿEF.ÿ729./ÿG-0/.ÿ1;6/ÿ<.ÿA>26/-;A/.8ÿ 2.A.660-HL
>@ÿ0ÿ8;-0<9.ÿ10/.-709ÿ028ÿ@7/ÿ/7GF/9Hÿ72/>ÿ/F.ÿ@-01.ÿ
6>ÿ7/ÿQ>2^/ÿ<.ÿ8769>8G.8ÿ<Hÿ0;/>1><79.ÿ/-0@@7ALÿEF.ÿ ÿ̀9016F.99ÿ<;AV./6ÿ0-.ÿ/HI7A099Hÿ;6.8ÿ/>ÿ-.1>=.ÿ
729./ÿG-0/.ÿ1;6/ÿ2>/ÿ<.ÿQ.98.8ÿ/>ÿ/F.ÿ@-01.ÿ6>ÿ/F0/ÿ 6.871.2/ÿ72ÿS0660AF;6.//6Lÿÿc>Q.=.-Yÿ=0A;;1ÿ
6.871.2/6ÿ10Hÿ<.ÿ.0679Hÿ-.1>=.8LÿÿE>ÿ@0A797/0/.ÿ /-;AV6ÿ0-.ÿ[email protected]<9.Yÿ<.A0;6.ÿ/F.Hÿ-.1>=.ÿ1>-.ÿ
1072/.202A.Yÿ/F.ÿ729./ÿG-0/.ÿ1;6/ÿ<.ÿI90A.8ÿ09>2Gÿ /-0II.8ÿ6.871.2/ÿ028ÿ6;I.-20/02/ÿ/F02ÿA9016F.996Lÿÿ
/F.ÿ->08ÿ6F>;98.-ÿ>-ÿA;-<ÿ972.ÿ-0/F.-ÿ/F02ÿ0ÿ/-0@@7Aÿ h0A;;172Gÿ76ÿ096>ÿ0ÿ6I..87.-ÿI->A.66ÿ028ÿ76ÿ9.66ÿ
902.Lÿÿÿ 97V.9Hÿ/>ÿ620Iÿ/F.ÿA06/ÿ7->2ÿF>>8ÿQ7/F72ÿ/F.ÿ8..Iÿ
6;1IÿA0/AFÿ<0672L
_>/.ÿ/F0/ÿQ7/F72ÿI0-V72GÿG0-0G.6Yÿ/F.ÿO/0/.ÿ,9;1<72Gÿ
`>8.ÿ-.G;90/.6ÿ729./ÿG-0/.6ÿ028ÿ>/F.-ÿ6/>-1Q0/.-ÿ
0123413256ÿ89 ÿÿ63ÿÿÿ512ÿÿÿÿÿ5ÿ
ÿ !"#$%ÿ&'$ÿ($&ÿ(ÿ&'$ÿ&((ÿ$!"!)ÿ#$$*ÿ
+,*ÿ&'ÿ-"!.ÿÿ/$!"!)ÿÿ#$$*ÿ+,*ÿ&'ÿ
-"!ÿ"&'"!ÿÿ%#ÿ"&'ÿ&"0$ÿ&%(("ÿ%ÿ$0$!ÿ"&'"!ÿ
ÿ*%1"!)ÿ&ÿ"ÿ#!)$%+2ÿ!#ÿÿ* "$ÿ#$&"ÿ,ÿ-$ÿ
!$$%ÿ&ÿ($)+%#ÿ %1$%.
&' +)'ÿ&'ÿ-"!ÿ#$-%"ÿ(&$!ÿ !&"!ÿ
!$!&%&"!ÿ(ÿ"ÿ!#ÿ'3%# +ÿ,&$%"ÿ+'ÿ
ÿ*$&%$+,ÿ'#%%- !ÿ!#ÿ,$&2ÿ4567ÿ
"("$ÿ&'$,ÿÿ"#ÿ&$.ÿÿ8!$ÿ&'$%$ÿ"ÿ
$0"#$!$ÿ&'&ÿ&'$ÿ'0$ÿ-$$!ÿ !&,"!&$#ÿ-ÿÿ
*"ÿ%ÿ&'$%ÿ,$!2ÿÿ4567ÿ# $ÿ! &ÿ%+&"!$ÿ
%$9+"%$ÿ&'ÿ-"!ÿ$!"!)ÿ&ÿ-$ÿ&$&$#ÿ-$(%$ÿ
#"* .ÿ/ !&,"!&$#ÿ&'ÿ-"!ÿ$!"!)ÿ,+&ÿ
-$ÿ$0+&$#ÿ"!ÿ %#!$ÿ"&'ÿ&'$ÿ:3%# +ÿ
;&$ÿ<$)+&"!2ÿ=>?ÿ/4<ÿ=?.???2ÿ!#ÿ'!#$#ÿÿ
'3%# +ÿ&$.ÿÿ
@!ÿ&'$ÿ-$!$ÿ(ÿ$0"#$!$ÿ(ÿ !&,"!&"!2ÿ&'ÿ
-"!ÿ$!"!)ÿ,ÿ-$ÿ&1$!ÿ&ÿÿ!#("ÿ%ÿ&'$%ÿ
(""&ÿ*$%,"&&$#ÿ-ÿ4567ÿ&ÿ$*&ÿ"#ÿ&$2ÿ
"&' +&ÿ!ÿ*%"%ÿ**%0ÿ-ÿ4567.ÿÿ: $0$%2ÿ
,$ÿ!#("ÿ%$9+"%$ÿ&'ÿ-"!ÿ$!"!)ÿ&ÿ-$ÿ
&$&$#ÿ-$(%$ÿ&'$ÿ%$ÿ$*&$#.
;"&'ÿ*%"%ÿ4567ÿ**%02ÿ&'ÿ-"!ÿ$!"!)ÿ
,ÿ-$ÿ+$#ÿÿ)%#"!)ÿ!#ÿ'*"!)ÿ,&$%"ÿ&ÿ
!#("ÿ+!#$%) "!)ÿ+%$ÿA$$ÿ<$0"$#ÿB+"#$"!$ÿ
(%ÿ5$&$%,"!"!)ÿ/+%$ÿ&"0"&"$ÿ&ÿ@!&"0$ÿ
8!"!$#ÿC!#("ÿD"&$Eÿ%ÿÿ#"ÿ 0$%ÿ&ÿ&"0$ÿ
!#(".ÿÿÿÿ4567ÿÿ$! +%)$ÿ&'$ÿ-$!$(""ÿ
%$+$ÿ(ÿ&'ÿ-"!ÿ$!"!)ÿ'$!$0$%ÿ* "-$.ÿÿÿ
F$!$(""ÿ<$+$ÿ5$&$%,"!&"!ÿ"ÿ%$9+"%$#ÿ(%ÿ+'ÿ
+$.ÿÿ
4567ÿ%$)+&"!ÿ*%'"-"&ÿ!#("ÿ(%,ÿ$*&"!)ÿ
,&$%"ÿ&'&ÿ !&"!ÿ(%$$G#%"!"!)ÿ"9+"#.ÿÿH!$ÿ
ÿ&ÿ%$, 0$ÿ"9+"#ÿ"ÿ&ÿ+$ÿÿ'#%+"ÿ"(&ÿ&%+1ÿ
#+%"!)ÿ$!"!)ÿ*$%&"!ÿÿ&'&ÿ&'$ÿ,&$%"ÿ!ÿ
-$ÿ#$!&$#ÿ&ÿ&'$ÿ"&$.ÿÿ(&$%ÿ#"!)ÿ,&$%"ÿ(%,ÿ
$0$%ÿ&'ÿ-"!ÿ"!&ÿÿ&%+12ÿ$$0&$ÿ&'$ÿ&%+1ÿ
ÿ&'&ÿ!ÿ(%$$G#%"!"!)ÿ"9+"#ÿ!ÿ(ÿ-1ÿ"!&ÿ
&'$ÿ&%+&+%$.ÿÿ@(ÿ&'$%$ÿ"ÿ! ÿ(%$$ÿ&$%ÿ"!ÿ&'$ÿ&%+12ÿ
&'$ÿ,&$%"ÿ,ÿ-$ÿ#$$,$#ÿ&ÿ-$ÿ+((""$!&ÿ#%.ÿÿ
H&'$%"$ÿ&'$ÿ&'ÿ-"!ÿ$!"!)ÿ,+&ÿ+!#$%) ÿÿ
7"!&ÿI"&$%ÿC"9+"#ÿJ$&.ÿÿB ÿ&ÿ.ÿ4.) 0K#$*K
%$$KK(&.# ÿ(%ÿ"!(%,&"!ÿ!ÿÿ(ÿ&'$ÿ
4567ÿ%$9+"%$,$!&ÿ*$%&"!"!)ÿ&ÿ&'$ÿ#"* ÿ(ÿ
&'ÿ-"!ÿ$!"!).
0123413256ÿ89 ÿÿ63ÿÿÿ512ÿÿÿÿÿ5ÿ
ENGINEERED SOLUTIONS
CDS Guide
Operation, Design, Performance and Maintenance
CDS® Design Basics
Using patented continuous deflective separation technology, the There are three primary methods of sizing a CDS system. The
CDS system screens, separates and traps debris, sediment, and Water Quality Flow Rate Method determines which model size
oil and grease from stormwater runoff. The indirect screening provides the desired removal efficiency at a given flow rate for a
capability of the system allows for 100% removal of floatables defined particle size. The Rational Rainfall Method™ or the and
and neutrally buoyant material without blinding. Flow and Probabilistic Method is used when a specific removal efficiency of
screening controls physically separate captured solids, and the net annual sediment load is required.
minimize the re-suspension and release of previously trapped
Typically in the Unites States, CDS systems are designed to
pollutants. Inline units can treat up to 6 cfs, and internally bypass
achieve an 80% annual solids load reduction based on lab
flows in excess of 50 cfs (1416 L/s). Available precast or cast-in-
generated performance curves for a gradation with an average
place, offline units can treat flows from 1 to 300 cfs (28.3 to
particle size (d50) of 125 microns (μm). For some regulatory
8495 L/s). The pollutant removal capacity of the CDS system has
environments, CDS systems can also be designed to achieve an
been proven in lab and field testing.
80% annual solids load reduction based on an average particle
size (d50) of 75 microns (μm) or 50 microns (µm).
Operation Overview
Stormwater enters the diversion chamber where the diversion Water Quality Flow Rate Method
weir guides the flow into the unit’s separation chamber and In some cases, regulations require that a specific treatment rate,
pollutants are removed from the flow. All flows up to the often referred to as the water quality design flow (WQQ), be
system’s treatment design capacity enter the separation chamber treated. This WQQ represents the peak flow rate from either
and are treated. an event with a specific recurrence interval, e.g. the six-month
storm, or a water quality depth, e.g. 1/2-inch (13 mm) of
Swirl concentration and screen deflection force floatables and
rainfall.
solids to the center of the separation chamber where 100% of
floatables and neutrally buoyant debris larger than the screen The CDS is designed to treat all flows up to the WQQ. At influent
apertures are trapped. rates higher than the WQQ, the diversion weir will direct most
flow exceeding the WQQ around the separation chamber. This
Stormwater then moves through the separation screen, under
allows removal efficiency to remain relatively constant in the
the oil baffle and exits the system. The separation screen remains
separation chamber and eliminates the risk of washout during
clog free due to continuous deflection.
bypass flows regardless of influent flow rates.
During the flow events exceeding the treatment design capacity,
Treatment flow rates are defined as the rate at which the CDS
the diversion weir bypasses excessive flows around the separation
will remove a specific gradation of sediment at a specific removal
chamber, so captured pollutants are retained in the separation
efficiency. Therefore the treatment flow rate is variable, based
cylinder.
on the gradation and removal efficiency specified by the design
engineer.
These intensities, along with the total drainage area and runoff
coefficient for each specific site, are translated into flow rates
using the Rational Rainfall Method. Since most sites are relatively
small and highly impervious, the Rational Rainfall Method is
appropriate. Based on the runoff flow rates calculated for each
intensity, operating rates within a proposed CDS system are
2
determined. Performance efficiency curve determined from full Two different gradations of silica sand material (UF Sediment
scale laboratory tests on defined sediment PSDs is applied to & OK-110) were used in the CDS performance evaluation. The
calculate solids removal efficiency. The relative removal efficiency particle size distributions (PSDs) of the test materials were
at each operating rate is added to produce a net annual pollutant analyzed using standard method “Gradation ASTM D-422
removal efficiency estimate. “Standard Test Method for Particle-Size Analysis of Soils” by a
certified laboratory.
Probabilistic Rational Method
The Probabilistic Rational Method is a sizing program Contech UF Sediment is a mixture of three different products produced
developed to estimate a net annual sediment load reduction for by the U.S. Silica Company: “Sil-Co-Sil 106”, “#1 DRY” and
a particular CDS model based on site size, site runoff coefficient, “20/40 Oil Frac”. Particle size distribution analysis shows that
regional rainfall intensity distribution, and anticipated pollutant the UF Sediment has a very fine gradation (d50 = 20 to 30 μm)
characteristics. covering a wide size range (Coefficient of Uniformity, C averaged
at 10.6). In comparison with the hypothetical TSS gradation
The Probabilistic Method is an extension of the Rational Method specified in the NJDEP (New Jersey Department of Environmental
used to estimate peak discharge rates generated by storm events Protection) and NJCAT (New Jersey Corporation for Advanced
of varying statistical return frequencies (e.g. 2-year storm event). Technology) protocol for lab testing, the UF Sediment covers a
Under the Rational Method, an adjustment factor is used to similar range of particle size but with a finer d50 (d50 for NJDEP
adjust the runoff coefficient estimated for the 10-year event, is approximately 50 μm) (NJDEP, 2003).
correlating a known hydrologic parameter with the target storm
event. The rainfall intensities vary depending on the return The OK-110 silica sand is a commercial product of U.S. Silica
frequency of the storm event under consideration. In general, Sand. The particle size distribution analysis of this material, also
these two frequency dependent parameters (rainfall intensity included in Figure 1, shows that 99.9% of the OK-110 sand is
and runoff coefficient) increase as the return frequency increases finer than 250 microns, with a mean particle size (d50) of 106
while the drainage area remains constant. microns. The PSDs for the test material are shown in Figure 1.
These intensities, along with the total drainage area and runoff
coefficient for each specific site, are translated into flow rates
using the Rational Method. Since most sites are relatively small
and highly impervious, the Rational Method is appropriate. Based
on the runoff flow rates calculated for each intensity, operating
rates within a proposed CDS are determined. Performance
efficiency curve on defined sediment PSDs is applied to calculate
solids removal efficiency. The relative removal efficiency at each
operating rate is added to produce a net annual pollutant
removal efficiency estimate.
3
to SSC removal for any particle size gradation, assuming the Maintenance
particles are inorganic sandy-silt. Figure 2 shows CDS predictive
The CDS system should be inspected at regular intervals and
performance for two typical particle size gradations (NJCAT
maintained when necessary to ensure optimum performance.
gradation and OK-110 sand) as a function of operating rate.
The rate at which the system collects pollutants will depend more
heavily on site activities than the size of the unit. For example,
unstable soils or heavy winter sanding will cause the grit chamber
to fill more quickly but regular sweeping of paved surfaces will
slow accumulation.
Inspection
Inspection is the key to effective maintenance and is easily
performed. Pollutant transport and deposition may vary from
year to year and regular inspections will help ensure that the
system is cleaned out at the appropriate time. At a minimum,
inspections should be performed twice per year (e.g. spring
and fall) however more frequent inspections may be necessary
Figure 2. CDS stormwater treatment predictive performance for in climates where winter sanding operations may lead to rapid
various particle gradations as a function of operating rate. accumulations, or in equipment washdown areas. Installations
should also be inspected more frequently where excessive
Many regulatory jurisdictions set a performance standard for
amounts of trash are expected.
hydrodynamic devices by stating that the devices shall be capable
of achieving an 80% removal efficiency for particles having a The visual inspection should ascertain that the system
mean particle size (d50) of 125 microns (e.g. Washington State components are in working order and that there are no
Department of Ecology — WASDOE - 2008). The model can blockages or obstructions in the inlet and separation screen.
be used to calculate the expected performance of such a PSD The inspection should also quantify the accumulation of
(shown in Figure 3). The model indicates (Figure 4) that the CDS hydrocarbons, trash, and sediment in the system. Measuring
system with 2400 micron screen achieves approximately 80% pollutant accumulation can be done with a calibrated dipstick,
removal at the design (100%) flow rate, for this particle size tape measure or other measuring instrument. If absorbent
distribution (d50 = 125 μm). material is used for enhanced removal of hydrocarbons, the level
of discoloration of the sorbent material should also be identified
5
Distance from Water Surface
Diameter Sediment Storage Capacity
to Top of Sediment Pile
CDS Model
ft m ft m y3 m3
Note: To avoid underestimating the volume of sediment in the chamber, carefully lower the measuring device to the top of the
sediment pile. Finer silty particles at the top of the pile may be more difficult to feel with a measuring stick. These finer particles
typically offer less resistance to the end of the rod than larger particles toward the bottom of the pile.
6
CDS Inspection & Maintenance Log
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
——————————————————————————————————————————————————————————
1. The water depth to sediment is determined by taking two measurements with a stadia rod: one measurement from the manhole opening to the
top of the sediment pile and the other from the manhole opening to the water surface. If the difference between these measurements is less
than the values listed in table 1 the system should be cleaned out. Note: to avoid underestimating the volume of sediment in the chamber,
the measuring device must be carefully lowered to the top of the sediment pile.
2. For optimum performance, the system should be cleaned out when the floating hydrocarbon layer accumulates to an appreciable thickness. In
the event of an oil spill, the system should be cleaned immediately.
7
SUPPORT
• Drawings and specifications are available at www.ContechES.com.
ENGINEERED SOLUTIONS
• Site-specific design support is available from our engineers.
800-338-1122
www.ContechES.com
The product(s) described may be protected by one or more of the following US patents: 5,322,629; 5,624,576; 5,707,527; 5,759,415; 5,788,848; 5,985,157; 6,027,639; 6,350,374; 6,406,218;
6,641,720; 6,511,595; 6,649,048; 6,991,114; 6,998,038; 7,186,058; 7,296,692; 7,297,266; related foreign patents or other patents pending.
2
alternative means for communication of program information (Braille, large print,
audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice
and TDD). To file a complaint of discrimination, write to USDA, Director, Office of
Civil Rights, 1400 Independence Avenue, S.W., Washington, D.C. 20250-9410 or
call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity
provider and employer.
3
Contents
Preface.................................................................................................................... 2
How Soil Surveys Are Made..................................................................................5
Soil Map.................................................................................................................. 8
Soil Map................................................................................................................9
Legend................................................................................................................10
Map Unit Legend................................................................................................ 11
Map Unit Descriptions.........................................................................................11
Plymouth County, Massachusetts...................................................................13
636B—Montauk-Urban land complex, 0 to 8 percent slopes...................... 13
References............................................................................................................15
4
How Soil Surveys Are Made
Soil surveys are made to provide information about the soils and miscellaneous
areas in a specific area. They include a description of the soils and miscellaneous
areas and their location on the landscape and tables that show soil properties and
limitations affecting various uses. Soil scientists observed the steepness, length,
and shape of the slopes; the general pattern of drainage; the kinds of crops and
native plants; and the kinds of bedrock. They observed and described many soil
profiles. A soil profile is the sequence of natural layers, or horizons, in a soil. The
profile extends from the surface down into the unconsolidated material in which the
soil formed or from the surface down to bedrock. The unconsolidated material is
devoid of roots and other living organisms and has not been changed by other
biological activity.
Currently, soils are mapped according to the boundaries of major land resource
areas (MLRAs). MLRAs are geographically associated land resource units that
share common characteristics related to physiography, geology, climate, water
resources, soils, biological resources, and land uses (USDA, 2006). Soil survey
areas typically consist of parts of one or more MLRA.
The soils and miscellaneous areas in a survey area occur in an orderly pattern that
is related to the geology, landforms, relief, climate, and natural vegetation of the
area. Each kind of soil and miscellaneous area is associated with a particular kind
of landform or with a segment of the landform. By observing the soils and
miscellaneous areas in the survey area and relating their position to specific
segments of the landform, a soil scientist develops a concept, or model, of how they
were formed. Thus, during mapping, this model enables the soil scientist to predict
with a considerable degree of accuracy the kind of soil or miscellaneous area at a
specific location on the landscape.
Commonly, individual soils on the landscape merge into one another as their
characteristics gradually change. To construct an accurate soil map, however, soil
scientists must determine the boundaries between the soils. They can observe only
a limited number of soil profiles. Nevertheless, these observations, supplemented
by an understanding of the soil-vegetation-landscape relationship, are sufficient to
verify predictions of the kinds of soil in an area and to determine the boundaries.
Soil scientists recorded the characteristics of the soil profiles that they studied. They
noted soil color, texture, size and shape of soil aggregates, kind and amount of rock
fragments, distribution of plant roots, reaction, and other features that enable them
to identify soils. After describing the soils in the survey area and determining their
properties, the soil scientists assigned the soils to taxonomic classes (units).
Taxonomic classes are concepts. Each taxonomic class has a set of soil
characteristics with precisely defined limits. The classes are used as a basis for
comparison to classify soils systematically. Soil taxonomy, the system of taxonomic
classification used in the United States, is based mainly on the kind and character
of soil properties and the arrangement of horizons within the profile. After the soil
5
Custom Soil Resource Report
scientists classified and named the soils in the survey area, they compared the
individual soils with similar soils in the same taxonomic class in other areas so that
they could confirm data and assemble additional data based on experience and
research.
The objective of soil mapping is not to delineate pure map unit components; the
objective is to separate the landscape into landforms or landform segments that
have similar use and management requirements. Each map unit is defined by a
unique combination of soil components and/or miscellaneous areas in predictable
proportions. Some components may be highly contrasting to the other components
of the map unit. The presence of minor components in a map unit in no way
diminishes the usefulness or accuracy of the data. The delineation of such
landforms and landform segments on the map provides sufficient information for the
development of resource plans. If intensive use of small areas is planned, onsite
investigation is needed to define and locate the soils and miscellaneous areas.
Soil scientists make many field observations in the process of producing a soil map.
The frequency of observation is dependent upon several factors, including scale of
mapping, intensity of mapping, design of map units, complexity of the landscape,
and experience of the soil scientist. Observations are made to test and refine the
soil-landscape model and predictions and to verify the classification of the soils at
specific locations. Once the soil-landscape model is refined, a significantly smaller
number of measurements of individual soil properties are made and recorded.
These measurements may include field measurements, such as those for color,
depth to bedrock, and texture, and laboratory measurements, such as those for
content of sand, silt, clay, salt, and other components. Properties of each soil
typically vary from one point to another across the landscape.
Observations for map unit components are aggregated to develop ranges of
characteristics for the components. The aggregated values are presented. Direct
measurements do not exist for every property presented for every map unit
component. Values for some properties are estimated from combinations of other
properties.
While a soil survey is in progress, samples of some of the soils in the area generally
are collected for laboratory analyses and for engineering tests. Soil scientists
interpret the data from these analyses and tests as well as the field-observed
characteristics and the soil properties to determine the expected behavior of the
soils under different uses. Interpretations for all of the soils are field tested through
observation of the soils in different uses and under different levels of management.
Some interpretations are modified to fit local conditions, and some new
interpretations are developed to meet local needs. Data are assembled from other
sources, such as research information, production records, and field experience of
specialists. For example, data on crop yields under defined levels of management
are assembled from farm records and from field or plot experiments on the same
kinds of soil.
Predictions about soil behavior are based not only on soil properties but also on
such variables as climate and biological activity. Soil conditions are predictable over
long periods of time, but they are not predictable from year to year. For example,
soil scientists can predict with a fairly high degree of accuracy that a given soil will
have a high water table within certain depths in most years, but they cannot predict
that a high water table will always be at a specific level in the soil on a specific date.
After soil scientists located and identified the significant natural bodies of soil in the
survey area, they drew the boundaries of these bodies on aerial photographs and
6
Custom Soil Resource Report
identified each as a specific map unit. Aerial photographs show trees, buildings,
fields, roads, and rivers, all of which help in locating boundaries accurately.
7
Soil Map
The soil map section includes the soil map for the defined area of interest, a list of
soil map units on the map and extent of each map unit, and cartographic symbols
displayed on the map. Also presented are various metadata about data used to
produce the map, and a description of each soil map unit.
8
Custom Soil Resource Report
70° 46' 12'' W
Soil Map
4663210
42° 6' 26'' N 42° 6' 26'' N
4663210
4663190
4663190
4663170
4663170
4663150
4663150
4663130
4663130
4663110
4663110
4663090
Soil Map may not be valid at this scale.
4663090
Miscellaneous Water This product is generated from the USDA-NRCS certified data as
Perennial Water of the version date(s) listed below.
Rock Outcrop
Soil Survey Area: Plymouth County, Massachusetts
Saline Spot Survey Area Data: Version 11, Sep 7, 2018
Sandy Spot
Soil map units are labeled (as space allows) for map scales
Severely Eroded Spot 1:50,000 or larger.
Sinkhole
Date(s) aerial images were photographed: Aug 26, 2014—Sep
Slide or Slip 4, 2014
Sodic Spot
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
10
Custom Soil Resource Report
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
11
Custom Soil Resource Report
An identifying symbol precedes the map unit name in the map unit descriptions.
Each description includes general facts about the unit and gives important soil
properties and qualities.
Soils that have profiles that are almost alike make up a soil series. Except for
differences in texture of the surface layer, all the soils of a series have major
horizons that are similar in composition, thickness, and arrangement.
Soils of one series can differ in texture of the surface layer, slope, stoniness,
salinity, degree of erosion, and other characteristics that affect their use. On the
basis of such differences, a soil series is divided into soil phases. Most of the areas
shown on the detailed soil maps are phases of soil series. The name of a soil phase
commonly indicates a feature that affects use or management. For example, Alpha
silt loam, 0 to 2 percent slopes, is a phase of the Alpha series.
Some map units are made up of two or more major soils or miscellaneous areas.
These map units are complexes, associations, or undifferentiated groups.
A complex consists of two or more soils or miscellaneous areas in such an intricate
pattern or in such small areas that they cannot be shown separately on the maps.
The pattern and proportion of the soils or miscellaneous areas are somewhat similar
in all areas. Alpha-Beta complex, 0 to 6 percent slopes, is an example.
An association is made up of two or more geographically associated soils or
miscellaneous areas that are shown as one unit on the maps. Because of present
or anticipated uses of the map units in the survey area, it was not considered
practical or necessary to map the soils or miscellaneous areas separately. The
pattern and relative proportion of the soils or miscellaneous areas are somewhat
similar. Alpha-Beta association, 0 to 2 percent slopes, is an example.
An undifferentiated group is made up of two or more soils or miscellaneous areas
that could be mapped individually but are mapped as one unit because similar
interpretations can be made for use and management. The pattern and proportion
of the soils or miscellaneous areas in a mapped area are not uniform. An area can
be made up of only one of the major soils or miscellaneous areas, or it can be made
up of all of them. Alpha and Beta soils, 0 to 2 percent slopes, is an example.
Some surveys include miscellaneous areas. Such areas have little or no soil
material and support little or no vegetation. Rock outcrop is an example.
12
Custom Soil Resource Report
Description of Montauk
Setting
Landform: Hills, ground moraines, recessionial moraines, drumlins
Landform position (two-dimensional): Backslope, shoulder, summit
Landform position (three-dimensional): Side slope, crest
Down-slope shape: Linear, convex
Across-slope shape: Convex
Parent material: Coarse-loamy over sandy lodgment till derived from gneiss,
granite, and/or schist
Typical profile
Ap - 0 to 4 inches: fine sandy loam
Bw1 - 4 to 26 inches: fine sandy loam
Bw2 - 26 to 34 inches: sandy loam
2Cd - 34 to 72 inches: gravelly loamy sand
Properties and qualities
Slope: 0 to 8 percent
Depth to restrictive feature: 20 to 39 inches to densic material
Natural drainage class: Well drained
Runoff class: Medium
Capacity of the most limiting layer to transmit water (Ksat): Very low to moderately
high (0.00 to 1.42 in/hr)
Depth to water table: About 18 to 37 inches
Frequency of flooding: None
Frequency of ponding: None
Salinity, maximum in profile: Nonsaline (0.0 to 1.9 mmhos/cm)
Available water storage in profile: Low (about 5.2 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 2e
Hydrologic Soil Group: C
Hydric soil rating: No
13
Custom Soil Resource Report
Minor Components
Scituate
Percent of map unit: 5 percent
Landform: Drumlins, hills, ground moraines
Landform position (two-dimensional): Summit, footslope, backslope
Landform position (three-dimensional): Crest, side slope
Down-slope shape: Linear, convex
Across-slope shape: Convex
Hydric soil rating: No
Udorthents, loamy
Percent of map unit: 5 percent
Landform position (three-dimensional): Tread
Down-slope shape: Linear
Across-slope shape: Linear
Hydric soil rating: No
14
References
American Association of State Highway and Transportation Officials (AASHTO).
2004. Standard specifications for transportation materials and methods of sampling
and testing. 24th edition.
American Society for Testing and Materials (ASTM). 2005. Standard classification of
soils for engineering purposes. ASTM Standard D2487-00.
Cowardin, L.M., V. Carter, F.C. Golet, and E.T. LaRoe. 1979. Classification of
wetlands and deep-water habitats of the United States. U.S. Fish and Wildlife
Service FWS/OBS-79/31.
Federal Register. July 13, 1994. Changes in hydric soils of the United States.
Federal Register. September 18, 2002. Hydric soils of the United States.
Hurt, G.W., and L.M. Vasilas, editors. Version 6.0, 2006. Field indicators of hydric
soils in the United States.
National Research Council. 1995. Wetlands: Characteristics and boundaries.
Soil Survey Division Staff. 1993. Soil survey manual. Soil Conservation Service.
U.S. Department of Agriculture Handbook 18. http://www.nrcs.usda.gov/wps/portal/
nrcs/detail/national/soils/?cid=nrcs142p2_054262
Soil Survey Staff. 1999. Soil taxonomy: A basic system of soil classification for
making and interpreting soil surveys. 2nd edition. Natural Resources Conservation
Service, U.S. Department of Agriculture Handbook 436. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053577
Soil Survey Staff. 2010. Keys to soil taxonomy. 11th edition. U.S. Department of
Agriculture, Natural Resources Conservation Service. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053580
Tiner, R.W., Jr. 1985. Wetlands of Delaware. U.S. Fish and Wildlife Service and
Delaware Department of Natural Resources and Environmental Control, Wetlands
Section.
United States Army Corps of Engineers, Environmental Laboratory. 1987. Corps of
Engineers wetlands delineation manual. Waterways Experiment Station Technical
Report Y-87-1.
United States Department of Agriculture, Natural Resources Conservation Service.
National forestry manual. http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/
home/?cid=nrcs142p2_053374
United States Department of Agriculture, Natural Resources Conservation Service.
National range and pasture handbook. http://www.nrcs.usda.gov/wps/portal/nrcs/
detail/national/landuse/rangepasture/?cid=stelprdb1043084
15
Custom Soil Resource Report
16
TECHNICAL NOTE
Pipe Flotation
TN 5.05
March 2016
Introduction
The light weight of high density polyethylene (HDPE) and polypropylene (PP) pipe make it desirable because of the
ease of handling and installation but this same benefit also makes these thermoplastic pipes prone to flotation. All pipe
products, such as concrete and corrugated metal, are prone to flotation under the right circumstances. In fact, all pipe
materials and other buried structures are subject to flotation. When the uplift on the pipe or structure exceeds the
downward force of the weight and load it carries, the pipe (or structure) will rise or heave. Where flotation is a
possibility, proper installation and/or anchoring of the pipe is critical. This document provides an analysis on minimum
cover heights required to prevent pipe flotation for thermoplastic pipe sizes 12”-60”. Buoyant force due to flowable fill is
also discussed.
Soil loads experienced by a pipe at varying water table depths (Wsoil) can be calculated from Equation 2. Figure 1
illustrates each of the three cases seen in field installations where buoyancy becomes a concern, and also clarifies all
of the parameters contained within Equation 2.
(a) Water table at pipe crown (b) Water table exceeds (c) Water table is at
pipe crown elevation ground surface
The typical weights (Wpipe) and average outside diameters are shown in Table 1.
Table 1
Approximate Weights of ADS Thermoplastic Pipe
Nominal Dual Wall Pipe Triple Wall
Nominal OD
Diameter Weight Pipe Weight
in. (mm)
in. (mm) lb/ft (kg/m) lb/ft (kg/m)
4 (100) 4.6 (117) 0.44 (0.6) N/A
6 (150) 7.0 (178) 0.85 (1.3) N/A
8 (200) 9.5 (241) 1.5 (2.2) N/A
10 (250) 12 (305) 2.1 (3.1) N/A
12 (300) 14.5 (368) 3.2 (4.7) N/A
15 (375) 18 (457) 4.6 (6.8) N/A
18 (450) 22 (559) 6.4 (9.5) N/A
24 (600) 28 (711) 11.0 (16.4) N/A
30 (750) 36 (914) 15.4 (22.9) 20.7 (30.8)
36 (900) 42 (1067) 19.8 (29.4) 24.2 (36.0)
42 (1050) 48 (1219) 26.4 (39.3) 31.9 (47.5)
48 (1200) 54 (1372) 31.3 (46.6) 41.8 (62.3)
60 (1500) 67 (1702) 45.2 (67.3) 55.0 (81.9)
N/A indicates the pipe is not available in the respective diameter
Figure 2
Forces Affecting Flotation
Table 2
Minimum Recommended Cover to Prevent Flotation of ADS Thermoplastic Pipe
Nominal Minimum Calculation Notes:
Diameter Cover 1. The pipe is assumed to be empty. This not only simplifies the
in. (mm) in. (mm) calculations but creates a condition that would encourage
flotation. Unless the system is constructed to be watertight,
4 (100) 3 (77) this condition would not likely be found in an actual
6 (150) 4 (102) installation.
8 (200) 5 (127) 2. The outside diameter of the corrugated pipe was used to
10 (250) 7 (178) determine soil and water displacement.
12 (300) 9 (228) 3. Saturated soil density used was 130 pcf which is typical for
many saturated soil mixtures. Soils of greater densities will
15 (375) 11 (280) reduce the chance of flotation.
18 (450) 13 (330) 4. The water table was assumed to be at the ground surface, as
24 (600) 17 (432) illustrated in Figure 1(c), simulating a fully saturated soil. This
30 (750) 22 (559) assumption creates a “worst case” condition to yield more
36 (900) 25 (635) conservative results.
5. The soil load prism shown in Figure 2(a) was used to
42 (1050) 29 (737)
determine soil weight.
48 (1200) 33 (838) 6. For structural purposes, a minimum cover of 12” (0.3m) shall
60 (1500) 40 (1016) apply for 4”-48” (100-1200mm) pipe, and 24” (0.6m) for 60”
(1500mm) pipe.
U 4.52 62.4 992.4 lb/ft
4
The water table is at top of grade, so Figure 1(c) applies. Since Hdry=0, the first term in
Equation 2 is eliminated:
The above calculations are conservative. The angle of internal friction of the soil, , and the coefficient of lateral earth
stress, Ko, are not accounted for in the above equations. These parameters are best left to the geotechnical engineer.
If these parameters are added to the above calculations, the depth of cover required would be reduced.
Anchoring Systems
In many instances pipe flotation may simply be addressed with adequate cover. In those situations where adequate
cover cannot be achieved, there are a number of acceptable alternate methods for restraining the pipe. Several
examples are shown in Figure 3.
Due to the variations in in-situ soil densities, water table heights, and the restraining force of the anchors, the Engineer
should evaluate the project-specific conditions to determine the required anchor type and spacing to prevent flotation.
The maximum spacing between anchor supports should not exceed 10 feet. In this manner, pipe is supported at each
joint and at the midpoint of each length of pipe to ensure adequate stabilization.
Figure 3
Pipe Stabilizing Alternatives
A
disp FF
U (5)
144
Due to the vast differences in the unit weights between water and flowable fill, uplift caused by flowable fill can be
greater than two times that of hydrostatic uplift. When backfilling with flowable fill, the pipe will float in the absence of
soil overburden, since the weight of the pipe will not offset the vertical uplift. Precautions must be taken to ensure the
pipe remains on its intended alignment and grade. This is commonly done by anchoring the pipe in place or placing
the flowable fill in incremental lifts. Refer to Technical Note 5.02: Flowable Fill Backfill for Thermoplastic Pipe for
common anchoring methods and additional technical information related to placing flowable fill as backfill.