Camalaniugan Temp Bridge Structural Analysis
Camalaniugan Temp Bridge Structural Analysis
APRIL 2021
INDEX
CHAPTER 1 CONSTRUCTION INTRODUCTION..................................................................................................- 3 -
1.1 CONSTRUCTION BRIEFING..............................................................................................................- 3 -
-3-
TOPOGRAPHY LAYERS
LAYER THINCKNESS
NAME SCOPE GEOLOGICAL TOP TO
TOP TO BOTTOM
CONDITION BOTTOM
CLIMATE FEATURES
ANNUAL AVERAGE
annual average temperature is about 27℃, high temperature and humidity
TEMPERATURE
-4-
2.2.4 TRANSPORTATION CONDITON
The surrounding road network in this area is well-developed, and the temporary construction site
transportation is convenient and close to Manila North Road, and the road is wide. Manila North Road is
directly connected to the AH26 National Highway to the north and to the starting point of the project on the
south, but from the starting point of the project to the main bridge It is necessary to build a construction
access road, and the transportation of heavy equipment and materials is generally more convenient.
The self-weight of the structure is considered in the calculation model according to 7.85t/m3
② Vehicle load
The passing vehicle loads considered for construction are: 10m³ concrete mixer truck with full load
(including concrete) 50T, 50T crawler crane, 280 type rotary drill (weight 85t), not passing at the same
time, considering the most unfavorable situation, so the calculated load is 85T According to the calculation
of rotary drilling, the load distribution is as follows: the crawler on the left is 170KN/m, and the crawler on
the right is 170KN/m.
The lateral distance between the wheels is 3.6m, and the track along the direction of the vehicle is
5m.
③ Crowd load
The bridge is 6m wide, and vehicle is planned to pass 5m in the middle and 1m wide pedestrian
passage on one side. The crowd load is 3.5KN/m2.
④ Water impact load
The calculated water level for construction is +3, the lower elevation of the bottom of the riverbed is -14.8,
the elevation of the trestle deck is +5.00, the maximum water depth is about 17.8m, the elevation of the
bottom of the steel trestle Bailey beam is +3.27, and the maximum height from the riverbed is 18.07m ,
The water level in twenty-five years is 0.27m from the bottom of Belle beam. Water impact force acting on
steel pipe piles during flood period (every 20 years):
Fw = KA (rv2/2g) (KN)
In the formula: r—the bulk density of water (KN/m3), r=10 (KN/m3)
v—there is no data of the once-in-20-year event, take the maximum flow rate in the 25-year event
(m/s), V=4.14 (m/s) in the flood evaluation data
A—Water blocking area (m2), steel pipe pile A1=17. 3x0.63=10.899m2
g—acceleration of gravity, g=10 (m/s2)
K-shape factor, circular structure, take K=0.8. Then: FW=77KN (steel pile).
3.1.4.1 SUBSTRUCTURE
1、PIPE PILES
MIN IN
NO LOCATION THICK DENSE
CLAY SAND HARD SILT GRAVE SOIL
SAND SAND
DEPTH
-8-
20#PIER 2 2 5-15 16-33 34-75
SIDE
15 21 70 85 280
4 FRICTION
END
140 380 1050-2340 1560 3000
FRICTION
21#PIER 2 3-6 7-22.5 23-75
SIDE
10 50 100 280
5 FRICTION
END
1240 1300-2770 1240-2700 3000
FRICTION
The specific calculation is as follows:
[ρ]=1/k(U∑f1L1+AR)
Where
[ρ]--the allowable bearing capacity of the pile KN;
U-----The perimeter of the cross section of the pile body m;
fi----The pile body passes through the ultimate friction resistance Kpa between each layer and the pile
body, check " Bridge Preliminary Investigation Report";
Li----thickness of each soil layer m;
A-----supporting area of pile bottom m2;
R-----Pile tip ultimate grinding resistance Kpa;
K----Safety factor, 2 is used in this design.
The pile foundation adopts φ630mm steel pipe pile, the calculated wall thickness is δ=8mm, and the pile
is settled by vibratory hammering. The perimeter of the pile U=1.9782m, and the pile end area
A=0.0156m2.
The maximum force of a single steel pipe pile is 768.6KN.
①17# Pier location
Enter the dense sand layer 4.5m, and the depth of soil is 15.5m
[ρ]= 1 U
2
f i
Li AR
1.9782 [15 2 (45 9) (4.5 x70) 0.0156 2010
1
2
=772KN
The load Pmax is greater than that of the steel pipe pile and the load can reach requirement.
②18# Pier location
Drive 6.5m into the dense sand layer, 14m deep into the soil
[ρ]= 1 U
2
f i
Li AR
-9-
1.9782 [24 2 (45 5.5) (6.5 x70) 0.0156 1880
1
2
=773KN
The load Pmax is greater than that of the steel pipe pile and the load can reach requirement.
③19# Pier position
10m into the dense sand layer, 14m deep into the soil
[ρ]= 1 U
2
f i
Li AR
1.9782 [16 3 (35 1) (66 x10) 0.0156 2630
1
2
=775.4KN
The load Pmax is greater than that of the steel pipe pile. fulfil requirements.
④20# Pier location
10m into the dense sand layer, 14m deep into the soil
[ρ]= 1 U
2
f i
Li AR
1.9782 [15 2 (21 2) (10 x70) 0.0156 2010
1
2
=794KN
The load Pmax is greater than that of the steel pipe pile. fulfil requirements.
⑤21# Pier location
6m into the clay layer, 12m deep into the soil
[ρ]= 1 U
2
f i
Li AR
1.9782 [10 2 (40 4) (6 x100) 0.0156 2100
1
2
=803KN
The load Pmax is greater than that of the steel pipe pile. fulfil requirements.
N
f
A
- 10 -
The calculated length of the Ф630×8mm steel pipe pile is 17m, the cross-sectional area A=156.3cm², the
moment of inertia Ix=Iy=75612.4cm4; the radius of gyration ix=22.0cm. The steel pipe pile is fixed at one
end and hinged at the other end, with a length factor of μ=1.
Slenderness ratio
λ=μL/i-=77
Check Appendix G to get a stability coefficient of 0.597, take the maximum reaction force of the steel pipe
pile 768kN, and calculate the following results, which meet the requirements of the specification.
From the above calculation results, the maximum stress of the steel pipe pile is 82.3MPa<190MPa, and
the stability of the steel pipe pile meets the requirements.
The max reaction force of pile top cross beam is 92.0Mpa<[σ]=215Mpa, which meet the reaction
requirement.
- 11 -
The maximum stress is 261Mpa<[σ]=310Mpa of the vertical rod at the top of the pile, which meets
the stress requirements
2、DEFORMATION
- 12 -
The maximum stress is 95.8Mpa<[σ]=210Mpa at the top of the end pile, which meets the stress
requirements.
The maximum stress of the distribution beam is 55Mpa<[σ]=215Mpa, which meets the stress
requirements.
- 13 -
The maximum stress of the transverse distribution beam is 46.2Mpa<[σ]=215Mpa, which meets the
stress requirements.
3.1.5 Stability Analysis of Trestle Bridge under Current Impact
During the construction period, the most unfavorable hydrological condition is calculated based on
the flood once in 25 years. The maximum water depth during the flood period of the trestle bridge area is
about 3+14.8=17. 3m, and the maximum water depth of the constant water level is about
0.5+14.8=15.3m. The maximum height of the riverbed is 3.27+14.8=17.98m.
Water impact force acting on steel pipe piles during flood period (every 25 years):
Fw = KA (rv2/2g) (KN)
In the formula: r—the bulk density of water (KN/m3), r=10 (KN/m3)
v—Velocity in 25 years (m/s), take V=4.14 (m/s)
A—Water blocking area of steel pipe pile (m2), A=17.3×0.63=10.9m2
g—acceleration of gravity, g=10 (m/s2)
K-shape factor, circular structure, take K=0.8.
then:
Maximum water resistance of a single steel pipe pile: Fw=9.2×1.4=74.7KN
The self-weight of the upper structure of the one-span trestle bridge: Q=202KN, uniformly arranged
on the load-bearing beam, and the uniformly distributed load is 37.4KN/m.
The impact force of the water flow is evenly distributed at 2/3 of the length of the steel pipe pile
below the water surface, and the uniform load is 7.4KN/m.
When considering the stability of the trestle under the impact of water flow, the lower part of the steel
pipe pile is regarded as a hinged structure, and the upper part is connected by the lower beam and
scissors to form a portal frame structure to jointly resist the impact of water flow and take the impact of
water flow during the flood period. Calculation is shown in the graph below:
- 14 -
The maximum stress of the steel pipe pile is 138Mpa<[σ]=215Mpa. The trestle structure can meet
the needs of anti-collapse by its own weight under the impact of water flow during the flood period. In
addition, considering the auxiliary drilling platform to the trestle, the trestle structure is safe under the
impact of water flow in the flood period.
- 15 -
3.2.1 ALL COMPONENTS CALCULATION RESULTS
1、PIPES PILE
Soil layer
1m 2-9m 9-16.5m 16.5-22.5m 22.5-40.5
thickness
ththck 1L1+AR)
[ρ]=1/k(U∑f
- 17 -
3、LONGITUDINAL BEAM
The maximum stress of the longitudinal beam is 156Mpa<[σ]=215Mpa, which meets the stress
requirements.
。
The maximum deflection is 11.4mm<[f]=6000/400=15mm, which meets the deflection requirements.
- 18 -
The maximum stress of the reverse channel steel is 181 Mpa<[σ]=215Mpa, which meets the stress
requirements.
- 19 -
crawler cranes, and concrete mixer trucks are allocated as follows: Rotary drilling and crawler cranes are
arranged in the drilling platform, and crawler cranes are arranged on the side of the platform.
3.3.5.1 SUBSTRUCTURE
1、PIPE PILE
WORK CONDITION 1
- 20 -
The maximum reaction force of the steel pipe pile is 638.7KN.
The maximum stress of the steel pipe pile is 56.2Mpa<[σ]=215Mpa, which meets the stress
requirements.
WORK CONDITION 2
- 21 -
The maximum reaction of the pipe pile is 638.7KN。
The maximum stress of the steel pipe pile is 61.4Mpa<[σ]=215Mpa, which meets the stress
requirements.
2. PILE TOP CROSS BEAM(WORK CONDITION HAS SLIGHT DIFFERENCE FROM WORK
CONDITON 1 AND 2)
The maximum stress of the pile top beam is 92.0Mpa<[σ]=215Mpa, which meets the stress
requirements
- 22 -
The maximum deflection is 3.95mm<[f]=3000/400=7.5mm, which meets the deflection requirements.
The maximum stress is 298Mpa<[σ]=310Mpa of the vertical rod at the top of the pile, which meets
the stress requirements
2.变形 DEFORMATION
The maximum stress is 258.8Mpa<[σ]=310Mpa for the vertical rod at the top of the pile, which meets
the stress requirements.
2. DEFORMATION
- 24 -
The maximum stress of the distribution beam is 90.8Mpa<[σ]=215Mpa, which meets the stress
requirements.
- 25 -
2、PILE TOP CROSS BEAM(CONDITION 2 AND CONDITION 2 DIFFERENCE IS SLIGHT)
The maximum stress of the beam at the top of the pile is 159.8Mpa<[σ]=215Mpa, which meets the
stress requirements.
- 26 -
The maximum stress is 287Mpa<[σ]=310Mpa for the chord beam at the top of the pier, which meets
the stress requirements.
2、DEFORMATION
- 27 -
The maximum stress of the distribution beam is 150Mpa<[σ]=215Mpa, which meets the stress
requirements.
The maximum stress of the transverse distribution beam is 36.2Mpa<[σ]=215Mpa, which meets the
stress requirements.
The minimum embedding depth of the steel casing is calculated according to the following formula::
(𝐻 + ℎ)𝛾𝑤 − 𝐻𝛾0
𝐿=
𝛾𝑑 − 𝛾𝑤
In the formula: L——embedded depth of protective tube (m);
H——The depth from the construction water level to the bed surface (m). According to the survey, the
construction water level is +1.00m, so H is taken as 15.735m;
- 28 -
h——The water head in the protective tube, that is, the difference between the water level in the
protective tube and the construction water level (m). Because the top elevation of the protective tube is
+4.50m, h is taken as 3.3m;
γw——The bulk density of the mud in the protective cylinder, which is taken as 11KN/m3;
γ0——The bulk density of water, which is 10KN/m3;
γd——the saturated bulk density of the soil layer of the outer bed of the protective tube, taken as
16KN/m3
Then the minimum embedding depth L of 21# pier steel protective tube is:
L=[(15.735+3.3)×11-15.735×10]/(16-11)=10.407m
In the formula: N——the exciting vibration force of the steel casing, which is taken as 1200KN;
A——The cross-sectional area of the steel protective tube, based on the above calculation, which is taken
as 834cm2;
Φ——stability coefficient of the axial force-bearing member, in the table Φ=0.89
Then N/(ΦA)=1200×10/(0.89×834)=16.17MPa<[б]=188 MPa, which meets the requirements.
CAO YUNGAN
FIELD OF EXPERTISE: STRUCTURAL
PRC No. STP-OCE-D-No. 2023-211
- 30 -
- 31 -