SEPM MCQ - Priyadarshani
SEPM MCQ - Priyadarshani
3) Which of the following is involved in the system planning and designing phase of the
Software Development Life Cycle (SDLC)?
a) Sizing
b) Parallel run
c) Specification freeze
d) All of the above
5) Which of the following prototypes does not associated with Prototyping Model?
a) Domain Prototype
b) Vertical Prototype
c) Horizontal Prototype
d) Diagonal Prototype
Answer: d) Diagonal Prototype
Explanation: There is nothing as such called Diagonal Prototype; however, the rest other
options do make sense.
11) Which of the following models doesn't necessitate defining requirements at the earliest in
the lifecycle?
a) RAD & Waterfall
b) Prototyping & Waterfall
c) Spiral & Prototyping
d) Spiral & RAD
12) When the user participation isn't involved, which of the following models will not result in
the desired output?
a) Prototyping & Waterfall
b) Prototyping & RAD
c) Prototyping & Spiral
d) RAD & Spiral
Answer: b) Prototyping & RAD
Explanation: The Prototyping model necessitates user participation as when a prototype is
created or designed, whereas, in the case of RAD, user participation is required in all four
phases.
13) Which of the following model will be preferred by a company that is planning to deploy an
advanced version of the existing software in the market?
a) Spiral
b) Iterative Enhancement
c) RAD
d) Both (b) and (c)
Answer: d) Both (b) and (c)
Explanation: None.
14) Arrange the following activities for making a software product by utilizing 4GT.
I. Design strategy
II. Transformation into product
III. Implementation
IV. Requirement gathering
a) 4, 1, 3, 2
b) 4, 3, 2, 1
c) 1, 2, 3, 4
d) 1, 4, 2, 3
Answer: a) 4, 1, 3, 2
Explanation: The sequence of activities mentioned in option c represents the Fourth
Generation Techniques(4GT) Model.
15) Which of the following is an example of Black Box and Functional Processing?
a) First Generation Language
b) Second Generation Language
c) Third Generation Language
d) Fourth Generation Language
Answer: d) Fourth Generation Language
Explanation: Functional processing or testing is commonly known as black-box testing,
where the existing contents are almost unknown, so anything could be demonstrated as a
black box. Hence the functionality of a black box can be defined in terms of inputs and outputs.
Answer: b) False
Explanation: The fourth-generation programming languages are more programmer-friendly
and helpful in augmenting the program's efficiency as it uses English words and phrases. It
increases the programmer's productivity by enabling them to engage in the software
development life cycle.
18) Which of the following is the main advantage of deploying a 4GT model for producing
small-scale products, programs, and applications?
a) The productivity of software engineers is improved.
b) The time required for developing software is reduced.
c) CASE tools and code generators help the 4GT model by providing a credible solution to
their problems.
d) None of the above.
20) Which of the following falls under the category of software products?
a) Firmware, CAD
b) Embedded, CAM
c) Customized, Generic
d) CAD, Embedded
Answer: a) True
Explanation: For systems with long life, software maintenance cost is higher than that of the
software development cost.
22) Which of the following activities of the generic process framework delivers a feedback
report?
a) Deployment
b) Planning
c) Modeling
d) Construction
Answer: a) Deployment
Explanation: The deployment phase is the last phase of the software development life cycle in
which the software product is delivered to its end-user, who further assesses its performance
and revert back with the feedback if anything is required or missing as per the formulated
evaluation.
Answer: b) Reusability
Explanation: None.
25) The RUP can be defined based on three main perspectives, i.e., static, dynamic & practice.
What is the purpose of static perspective?
a) It recommends some good practices that be included while carrying out the process.
b) It displays all the enacted process activities.
c) It portrays the phases that the model has entered over a specific time.
d) All of the above.
26) Which one of the following activities is not recommended for software processes in
software engineering?
a) Software Evolution
b) Software Verification
c) Software Testing & Validation
d) Software designing
27) Arrange the following activities to form a general software engineering process model.
I. Manufacture
II. Maintain
III. Test
IV. Install
V. Design
VI. Specification
a) 6, 5, 1, 3, 4, 2
b) 1, 2, 4, 3, 6, 5
c) 6, 1, 4, 2, 3, 5
d) 1, 6, 5, 2, 3, 4
Answer: a) 6, 5, 1, 3, 4, 2
Explanation: None.
29) On what basis is plan-driven development different from that of the software development
process?
a) Based on the iterations that occurred within the activities.
b) Based on the output, which is derived after negotiating in the software development
process.
c) Based on the interleaved specification, design, testing, and implementation activities.
d) All of the above
30) Which of the following activities is not applicable to agile software development?
a) Producing only the essential work products.
b) Utilizing the strategy of incremental product delivery.
c) Abolishing the project planning and testing.
d) All of the above
31) Which of the following framework activities are carried out in Adaptive Software
Development (ASD)?
a) Assumption, Association, Learning
b) The investigation, Strategy, Coding
c) Requirements gathering, Adaptive cycle planning, Iterative development
d) All of the above
32) The __________ model helps in representing the system's dynamic behavior.
a) Object Model
b) Context Model
c) Behavioral Model
d) Data Model
33) Model-driven engineering is nothing but a theoretical concept. It can never be transmuted
into a working/executable code.
a) True
b) False
Answer: b) False
Explanation: Model-driven engineering is a software development approach that represents
the system as a set model, which can be easily altered into an executable code.
34) The __________ and __________ are the two major dimensions encompassed in the Spiral
model.
a) Diagonal, Perpendicular
b) Perpendicular, Radial
c) Angular, diagonal
d) Radial, Angular
35) Which of the following technique is involved in certifying the sustained development of
legacy systems?
a) Reengineering
b) Forward engineering
c) Reverse engineering
d) Reverse engineering and Reengineering
36) An erroneous system state that results in an unexpected system behavior is acknowledged
as?
a) System failure
b) Human error or mistake
c) System error
d) System fault
37) What is the name of the approach that follows step-by-step instructions for solving a
problem?
a) An Algorithm
b) A Plan
c) A List
d) Sequential Structure
Answer: a) An Algorithm
Explanation: An algorithm is a precise step-by-step technique that takes an input instance (of
the given problem) as input(s) and produces output for the problem instance.
38) Which of the following word correctly summarized the importance of software design?
a) Quality
b) Complexity
c) Efficiency
d) Accuracy
Answer: a) Quality
Explanation: The quality of a functional software functional depicts how well it can conform
with or adapts to a given design based on functional requirements or specifications.
Answer: c) All the functions represented in the DFD are mapped to a module structure
Explanation: The module structure depicts the architecture of the software.
41) What does a directed arc or line signify?
a) Data Flow
b) Data Process
c) Data Stores
d) None of the above
42) What does a data store symbol in the Data Flow Diagram signify?
a) Logical File
b) Physical File
c) Data Structure
d) All of the above
Answer: d) All of the above
Explanation: A logical file can be a data structure or physical file on the disk or vice versa.
a) Effort
b) Cost
c) Efficiency
d) All of the above
Answer: c) Efficiency
Explanation: Efficiency can never be measured as it is an indirect measure of the SE process.
Answer: a) To evaluate the ongoing project's status and track possible risks.
Explanation: None.
45) What is the main intent of project metrics?
a) For strategic purposes
b) To minimize the development schedule.
c) To evaluate the ongoing project's quality on a daily basis
d) To minimize the development schedule and evaluate the ongoing project's quality on a
daily basis
Answer: d) To minimize the development schedule and evaluate the ongoing project's quality
on a daily basis
Explanation: A project metric refers to a quantifiable measure of the degree to which a
system, component, or process owns a certain trait.
46) Name the graphical practice that depicts the meaningful changes that occurred in metrics
data.
a) Function point analysis
b) Control Chart
c) DRE (Defect Removal Efficiency)
d) None of the above
47) Which parameters are essentially used while computing the software development cost?
a) Hardware and Software Costs
b) Effort Costs
c) Travel and Training Costs
d) All of the above
48) Which of the following is an incorrect activity for the configuration management of a
software system?
a) Change management
b) System management
c) Internship management
d) Version management
49) The project planner examines the statement of scope and extracts all-important software
functions, which is known as
a) Planning process
b) Decomposition
c) Association
d) All of the mentioned
Answer: b) Decomposition
Explanation: None.
50) Which of the following Is not considered as an option for achieving reliable cost and effort
estimation?
a) The ability to translate the size estimate into human effort, calendar time, and dollars
b) Use relatively simple decomposition techniques to generate project cost and effort
estimates.
c) Base estimates on similar projects that have already been completed
d) Use one or more empirical models for software cost and effort estimation
Answer: a) The ability to translate the size estimate into human effort, calendar time, and
dollars
Explanation: None.
51) Which of the following does not complement the decomposition techniques but offers a
potential estimation approach for their impersonal growth?
a) Empirical estimation models
b) Decomposition techniques
c) Automated estimation tools
d) Both empirical estimation models and automated estimation tools
52) Which of the following is not included in the total effort cost?
a) Costs of lunch time food
b) Costs of support staff
c) Costs of networking and communications
d) Costs of air conditioning and lighting in the office space
53) Which of the following model has a misconception that systems are built by utilizing
reusable components, scripts, and database programs?
a) The reuse model
b) An early designed model
c) An application-composition model
d) A post architecture model
54) Which of the following is used to predict the effort as a function of LOC or FP?
a) COCOMO
b) FP-based estimation
c) Both COCOMO and FP-based estimation
d) Process-based estimation
Answer: c) Both COCOMO and FP-based estimation
Explanation: Both COCOMO and FP-based estimation is used to calculate the effort by
utilizing the empirically derived formulas.
55) Once the requirements are stabilized, the basic architecture of the software can be
established. Which of the following version of the COCOMO model conforms to the given
statement?
a) Application composition model
b) Post-architecture-stage model
c) Early design stage model
d) All of the above
56) Which of the following threatens the quality and timeliness of the produced software?
a) Business risks
b) Potential risks
c) Technical risks
d) Known risks
57) Which of the following refers to the systematic attempt, which is implemented to ascertain
the threats to any project plan?
a) Performance risk
b) Risk identification
c) Risk projection
d) Support risk
Answer: b) RTCADO-178B
Explanation: RTCADO-178B is the most popular aviation standard, which has been altered to
a defacto standard.
Q2. Effective software ___ focuses on the four Ps: people, product, process, and project.
1. Planning
2. Control
3. Project management
4. All of the mentioned above
Answer: C) Project management
Explanation:
The four Ps of effective software project management are people, product, process, and
project. The order isn't random. Managers who lose sight of the fact that software engineering
is a deeply human endeavor will never be successful in project management.
Q3. Project managers plan, monitor, and control the work of a team of ____.
1. Software engineers
2. Management activities
3. Project management
4. None of the mentioned above
Answer: A) Software engineers
Explanation:
A team of software engineers is managed by project managers, who plan, monitor, and
regulate their work. The relationship between business and software specialists is
coordinated by senior management.
Q5. ____ is a people-intensive activity, and for this reason, competent practitioners often make
poor team leaders.
1. Project management
2. Management activities
3. Software engineers
4. All of the mentioned above
Answer: A) Project management
Explanation:
Because project management is such a people-intensive activity, competent practitioners
frequently make lousy team leaders. They simply lack the correct blend of interpersonal skills.
Q6. A good ___ must take charge of the project.
1. Software engineers
2. Planning
3. Project manager
4. All of the mentioned above
Answer: C) Project manager
Explanation:
The project must be managed by a good project manager. They must have the courage to take
command when necessary and the confidence to trust good technical experts to act on their
intuition.
Q8. A software team can avoid frustration if it is given as much responsibility for ___ as
possible.
1. Management
2. Planning
3. Decision making
4. None of the mentioned above
Answer: C) Decision making
Explanation:
If a software team is given as much decision-making authority as feasible, it can minimize
frustration. Understanding the product to be developed, the people doing the job, and
allowing the team to choose the process model can all help to avoid an ineffective process.
Q9. A software project manager is confronted with a dilemma at the very beginning of a ____.
1. Project manager
2. Software project
3. Software planning
4. None of the mentioned above
Answer: B) Software project
Explanation:
At the start of a software project, a software project manager is faced with a dilemma.
Quantitative estimates and a well-organized strategy are needed, yet solid data is absent.