Time Management Lecture 6
Time Management Lecture 6
Its key benefit is that it breakdown work packages into activities that
provides a basis for estimating, scheduling, executing, monitoring and
controlling the project work.
OPA
a) Lessons learned.
b) Standardized processes.
c) Any template for of schedule activity list.
d) Existing formal & informal activity planning related
policies, procedures, guidelines and scheduling
methodology.
1
10/22/2019
ROLLING WAVE PLANNING •It includes the activity identifier and a scope
It is a form of progressive elaboration and an iterative
planning technique.
of work description for each activity in
• Short term/ Immediate work – Detail Planning sufficient detail to ensure that project team
• Long term/ Future work – High level planning without much details
members understand what work is required to
EXPERT JUDGMENT be completed.
DIFFERENCE BETWEEN WBS & ACTIVITY LIST WBS & THE ACTIVITY LIST
A WBS is a list of the components of the deliverable. Creating a WBS involves lot of communication between customer, key
stakeholders and project team and Project Manager is responsible to
An Activity List is a list of the activities we will engage cascade the entire project scope in the form of deliverable oriented WBS.
in during the project.
We should make WBS first followed by the Activity List. Activity List which is a main component of Work Package and it is best
The creation of the WBS and the Activity List are a prepared by the actual team members who will be doing the work.
turning point in project planning. The WBS is created as
the finest level detail of defined project scope. It
completes our work on scope planning & prepares us to
plan all nine other areas of project management,
including time. The first step in detailed time & cost
estimation is the creation of Activity List.
A good WBS makes the transition from scope
planning to time planning easy. Once we know
clearly what we are making, it is easy to
plan how we will make it.
2
10/22/2019
3
10/22/2019
ACTIVITY LIST # 2: HOME REPAIR HOBBYIST APPROACH ACTIVITY LIST # 3: BUY MATERIAL & OUTSOURCE LABOR
1. Buy all items on the to-do list, including pre-cut, pre-stained
shelves.
1. Buy all items on the to-do list, including pre-cut, pre-stained
2. Measure locations in the wall for the wall mounts. shelves.
3. Mark locations of the screw holes. 2. Hire a carpenter to install the shelves.
4. Check screw hole locations with a level.
3. Housekeeping with own resources.
5. Drill 6 holes, and place 6 anchors in walls.
4. Pay the carpenter.
6. Mount 2 adjustable wall mounts with 6 screws, screws set loosely.
7. Tighten all screws.
8. Attach braces to wall mounts.
9. Check braces with a level.
10. Place shelves on braces.
11. Clean up.
4
10/22/2019
Its key benefit is that it defines the logical sequence of work to obtain
the greatest efficiency given all project constraints.
5
10/22/2019
6
10/22/2019
7
10/22/2019
DEPENDENCY DETERMINATION
Mandatory
Discretionary
External
Internal
8
10/22/2019
9
10/22/2019
Sequence Activities
Exercise!
Consider the following series of activities in a business
planning to launch a new product:
Activities
Commence Production
10
10/22/2019
Below are all the activities that john needs to plan, to complete
foundation of the house. These by themselves look sequential, but
there are some dependencies. These will come to light when he
prepares the network diagram.
11