Method Statement For Public Address System T&C
Method Statement For Public Address System T&C
___________________________________________________________________
A method statement is a document that sets out how a task will be completed and the health, safety, and environmental
(HSE) control measures to be adopted and followed. A method statement should identify any OH&S hazards and
Environmental aspects or impact that may be present in the task and the HSE precautions that need to be taken to deal
with them. It should state whether the works will interface with activities of any other contractor on site.
Contents:
1.0 Introduction
2.0 Scope of Works
3.0 Sequence and method of works
4.0 Programme
5.0 Competency and Training
6.0 Emergency Procedures
7.0 Supervision
8.0 Monitoring of the Works
9.0 Environmental
10.0 PPE Required
11.0 Tools & Equipment's
12.0 References/Codes
Page 1 of 8
Method Statement For Testing Commissioning Of Public Address System
___________________________________________________________________
b. Name of Project:
c. Type of work being Ground work Steel fixing Formwork Concreting MEPCladdingMasonry
conducted: carpentryScaffolding ExcavationLifting OperationsSteel worksPre cast
other:
2.0 SCOPE OF
WORKS a. Description of the work: TESTING COMMISSIONING OF PUBLIC ADDRESS SYSTEM
3.0 SEQUENCE & a. How GENERAL HSE Control measures for each
METHOD OF the task / 1.1 INTRODUCTION step:
WORK work is to The purpose of this document is to detail the
be done testing & commissioning procedures for the project. a) TOOL BOX TALK with
in a foremen and workers
The procedure relates to the requirements for before starting job.
logical
sequence the Public Address System testing and b) Use Personal protective
step by commissioning equipment (PPE)
steps
1.2 PERSONNEL AND RESPONSIBILITIES
Present at each and every test will be any of the
following personnel:
Commissioning Engineer :
Specialist Supplier shall be responsible for the
correct testing of equipment and to ensure that
records are accurate and legible.
He is also responsible to ensure that this procedure
is followed. In addition, it is also his responsibility to
ensure that all documentation is available, test
sheets are accurately completed and issued to the
Client and that all coordination is carried out prior
to testing and commissioning commences.
Client’s/Consultant’s Representative:
Unless otherwise agreed, the Client’s/Consultant’s
representative shall be Mechanical Engineer (site
Page 2 of 8
Method Statement For Testing Commissioning Of Public Address System
___________________________________________________________________
representative) and /or designated members of
staff. Their attendance whether continuous or
periodic shall normally be required during testing
and commissioning and shall be mutually agreed
with the Contractor as necessary.
1.3 DOCUMENTATION
Prior to any testing and commissioning the
following documentation will
be available for inspection by any attendee of the
testing and
commissioning team:
a) Pre-commissioning test sheets
b) This procedure for testing and commissioning
c) All relevant drawings & Schedules
d) All relevant material submittals
e) Test and commissioning checklist
1.5 PRE-REQUISITES
The following items are prerequisites to the
commencement of testing and
commissioning:
a) A notice of testing and commissioning shall have
been issued and a provisional testing and
commissioning program shall have been agreed
with the site representative.
b) All Equipment’s connected to the systems have
to be commissioned, tested and approved prior
testing of the special systems. Eg. Like VFDs, MCCs,
Sprinkler, Etc.
c) Completion of all pre-commissioning test.
d) Approval of snag items/clearance of items
affecting testing and commissioning.
e) The system has been installed as per approved
shop drawings.
f) All related electrical, mechanical and LV Systems
equipment’s are installed, completed and ready to
Page 3 of 8
Method Statement For Testing Commissioning Of Public Address System
___________________________________________________________________
accept electrical power.
g) A written confirmation from the installer and the
engineer that the equipment to operate is ready
and fit.
Commissioning Checks
After assembly, all major equipment’s together are
to be site tested to establish the workability of the
system at site.
Following tests are to be performed at site:
Insulation resistance, HV test for cables.
Rated output power.
Performance of PAGE and PRIVATE
channels for all equipment in the entire
Public Address System.
Proper functioning of auto-changeover unit.
Test to ensure that db level of
announcement at any station by its own
handset shall be lower than announcement
at the same station by any other handset.
We shall perform all site tests as per the Field
Quality Plan. During contract stage we shall furnish
details of these tests & the standards to which
these conform for purchaser’s approval.
Functional Test
b. Working hours; is there b. Night work: No Yes (if yes, is there good lighting , does permission required before
any night work involved. work starts describe actions to be taken)
c. Are there critical dates to c. Critical Dates: No Yes (give dates & constraints if any)
be achieved, milestones
etc: (any constraints from the All testing and commissioning should be done before the end of
programme)
d. Are there any interface d. No Yes(give details)
with other contractor that
overlap?
5.0 COMPETENCY a. All personnel involved in a. Yes No (if no see safety department)
& TRAINING the work are trained &
competent;
b. Any special trained b. No Yes(give details of training required)
personnel required for the Operating and maintenance training for the operators
task? (i.e. confined space etc)
6.0 EMERGENCY a. Are all personnel aware a. YES NO(If No, work not to start until all are aware of the emergency procedure)
PROCEDURES of the site emergency
procedures?
b. Is there a requirement for b. NO YES(If Yes, work not to start until all are aware of the emergency procedure)
specialised emergency Describe emergency procedures to be used :
considerations? (such as
confined space rescue etc.)
Page 6 of 8
Method Statement For Testing Commissioning Of Public Address System
___________________________________________________________________
c. Are there adequate first c. YES NO(If NO, work not to start until first aiders are available)
aiders on site?
7.0 SUPERVISION a. Is there good supervision a. Describe the level of the supervision for the task:
for the task? (Name of supervisor, charge hand / foremen).
Construction Manager :
Sr. QA/QC Engineer.:
Sr. Electrical Engineer:
Sr. Safety Eng. :
T&C Engineer:
Electrical Supervisor:
b. Is there a need for full b. NO YES(If Yes, work not to start until supervision is in place)
time supervision due to the Describe how the supervisor will control task:
level of risk?
MUST BE ONE FOREMAN & SITE ENGINEER SUPERVISING FULL TIME
WITH WORKERS
8.0 MONITORING a. Describe the a. Describe the level of monitoring for the task:
OF THE WORKS arrangements for
monitoring of the task? Testing & Commissioning agents from the consultant shall
(Who, frequency of be monitoring the testing & commissioning works.
monitoring, actions from
the monitoring, recording
of monitoring)
9.0 a. Are there any a. Describe the environmental impact / issue for the task and how are you
ENVIRONMENTAL environmental impacts / going to control it:
issues when conducting the
task, and include how will o All the off cuts of material will be collected and taken to the
you control these impacts / environmental waste separation area for recycling purposes. Waste
issues? material will be forwarded to the MASDAR recycling centre by Al
Fara’a environmental workers.
o All packaging materials will be removed from the site and maintain
safe and tidy workplace.
o Any lubricants will be stored within a dedicated chemical store.
MSDS data must be available at all times for perusal by HSE
manager, environmental manager and independent auditors. Any
chemicals used must formally assessed by manager sustainability
prior to use.
10.0 PPE a. Tick the relevant PPE Hard Hat Safety Boots High Visibility Vest Gloves Goggles
REQUIREMENTS required to conduct the
Face mask
task
Page 7 of 8
Method Statement For Testing Commissioning Of Public Address System
___________________________________________________________________
b. Is there any requirement NO YES(If Yes, list specialised PPE)
for specialised PPE? If so list
them and ensure all are
trained on the PPE.
11.0 Tools and
equipment • Meggar
• Multimeter
• Clamp multimeter
Page 8 of 8