Part-A Merged
Part-A Merged
A
1.0 Earthworks Planning Criteria
The criteria for the planning of earthworks will be governed by the following considerations:
i) Assessment of the existing site condition on drainage patterns, type of soils, natural
topography, rainfall, existing vegetation and environmental features.
ii) Development of base plan to review the physical conditions of site and adjacent
areas. The site plan shall include topography of site, locations of the discharge
point, area of fill, conceptual temporary drain and sediment basin, existing land
use, slope and existing vegetation (if any).
iii) The procedure to be adopted in the control of earth movement and compaction.
iv) Methods to be adopted for the control of soil erosion and silting of existing
watercourse during earthworks by using sediment basins and earth drain.
v) Runoff management consideration.
vi) Complying with the requirements of the authority.
vii) Losses in soil volume due to shrinkage, compaction, consolidation, settlement and
washout should be considered.
Q = CiA
For a specific return period of T years, Q is the peak discharge in cubic meters per second
(m3/s), i is the average intensity of rainfall in millimetres per hour (mm/hr), A is the catchment
area in m2, C is the runoff coefficient.
The time of concentration is the time required for the water to flow from the most remote point
of the catchment to the point being investigated. For urban stormwater drains, the time of
concentration (tc) consists of the time required for runoff to flow over the ground surface to the
nearest drain (to), and the time of flow in the drain to the point under consideration (t d). This
defined as: tc = to + td. For the sizing of drains based on calculated flows from runoff estimation,
the Manning’s Equation shown below is used: Where,
All required additional fill will be imported and transported from the approved borrow site.
10.70m
1200
Y:\Staff-library\_New Projects\_Project 2014\1412_(PG)-Dalat School Overall D.T.L\2. C & S\Road & Drainage\3. Approval\JKR\2015-11-17_Comply JKR Comments\IMG_0001.jpg
600
600
300
1000 1000
5.90m
250 3000 300 3000 250
1000
700
R8-125
PLT
JURUTERA PERUNDING / CIVIL & STRUCTURAL ENGINEERS
CONSULTANCY (PG0175795-K)
NO. 5-2-5, HUNZA COMPLEX, JALAN GANGSA, ISLAND PARK, 11600 PENANG. MALAYSIA.
Tel : 04-6585410 , Fax : 04-6580410, email : [email protected]
PROFE
RA SI
TE
ON
U
JU R
AWAM
AL
Z:\Staff-library\_New Projects\_Project 2014\1412_(PG)-Dalat School Overall D.T.L\2. C & S\Road & Drainage\3. Approval\JKR\2015-11-17_Comply JKR Comments\pl sign.jpg
12610
.......................................................................
IR. TAN PENG LEAK MA A
B.Eng. (USM) M.I.E.M., P.Eng. (SPAN QP1968) LAYSI
Y:\Staff-library\_New Projects\_Project 2014\1412_(PG)-Dalat School Overall D.T.L\2. C & S\Road & Drainage\3. Approval\JKR\2015-11-17_Comply JKR Comments\IMG.jpg
BOUL
TAI
DERS
PAN
ISAN
GAR
e
Concret
AI
PANT
BOUL
DERS
AI
PANT
'BEACH
BOUL
COTTAGE'
DERS
G=5.8
PRL.=3.90m
AI G=0.4
PANT TANAH
BOUL
G=0.8
DERS
G=0.9
NTAI
AN PA
GARIS
PRL.=3.90m G=1.
8
PRL.=3.95m G=0.8
AY DORM
IVEW
EX. G
MEETIN
ROOM
PADANG
MM DR
. 6000
P.E.
EX. AGE
STOR
PROP
8
G=0.
1
STOR
0.8 G=1.
NEW
AGE
G= STOR
B
5
G=1.
TANAH
ERL.=11.60m 'GYMNASIUM'
4
G=0.
H
G=3.6
G=1.4 Asam
R ROAD Asam
EX. TA G=0.7
G=3.3
Asam
Pisang
G=1.1
ERL.=11.60m
G=1.7 Y:\Staff-library\_New Projects\_Project 2014\1412_(PG)-Dalat School Overall D.T.L\2. C & S\Road & Drainage\3. Approval\JKR\2015-11-17_Comply JKR Comments\IMG_0001.jpg
G=1.2 MH
B
G=4.9
Ketapang
G=3.1
G=1.5
(2.101Ha) G=0.8
Ketapang
DALAT INTERNATIONAL SCHOOL G=1.7
G=1.9
TL
CLF
G=3.4 BILIK DARJAH
G=0.8
ANJANG
BOLA KER GANG
Ketapang
G=1.8
GANG
GELANG
G=1.1
NANG
'
TENIS
ITORY
DORM RY
Ketapang
GELANG
'JAFF
G=1.8
RE
G=2.6
KOLAM
TG
10069m2 PADANG
TG
HUT
G=2.4
TAPA
KONK K
H RIT TAPAK STOR
UNAN
HUT
PORC
PERMAINAN
G=1.8 KANAK-KANAK
BANG
PORC
NEW MIOREY
SCHODDLE
H
ING'
BUILD OL
Sa
ERL.=1 G=3.gu
'2-ST
1.54m 4 Sagu
ERL.=11.52m EX. TA G=4.
R ROAD 4
G=1.5
PROP
Sagu TG
HOTEL SANDY BAY PARADISE . CARG=2.5 ERL.=1
PASagu
RK 1.68m TG
MH
'2-ST EX. CA
R
A
OR PARK TG
STUD EY TG
CENT ENT
10-12 RE'
G=7.0
POND
OK
SMH
MH
R ROAD .=11.40m
'CHA
ND
PEJABAT MH DORM LER
MH
MH ITOR
Y'
ERL
G=4.5 MH
G=1.4 TG
G=2.5 POND
OK
MH MH
MH
PERPUS
EX. TA
TAKAAN
TG
JA
LA
NT
G=2.4
R BAND
G=2.0
Y'
AR
DORM MEN
ITOR
DRY'
ROOM'
G=2.5
'ECK
'SENIO
'LAUN
BILIK DA
BILIK
DARJAH
RJA
6-7-8 H
3-4-5
G=2.0
ERL.=11.21m
TL
TESEN
SUB-STNB
BILIK DA G=1.9
RJAH NOTE :
MUSIC Y
2-3
TR
Aras bumi adalah berdasarkan dari BM no. P 0476 yang terletak di depan
'ELEMEN
'
Y'
G=1.3 Sekolah Antarabangsa DALAT, Jalan Tanjong Bungah. (RL. 11.847m LSD)
ITOR
DORM MEN
WOR ANCE
G=2.1
P'
'ECK
PAGAR KON
KSHO
EN
'ELEM
'MAINT
PEJALAN KAKI EN
MUSI TRY
C'
DARI BATU FERRINGHI LOH & LOH ARCHITECTS
CLF
STRY
INDUHOP
ART'
'S
G=2.0 G=1.7
JALAN
TA NJUNG
N GA N KAKI
PEJ
PLT
JURUTERA PERUNDING / CIVIL & STRUCTURAL ENGINEERS
CONSULTANCY (PG0175795-K)
G=1.7
PROFE
RA SI
KE GEOR
GETOWN TE O
NA
JUR
AWAM
L
Z:\Staff-library\_New Projects\_Project 2014\1412_(PG)-Dalat School Overall D.T.L\2. C & S\Road & Drainage\3. Approval\JKR\2015-11-17_Comply JKR Comments\pl sign.jpg
12610
.......................................................................
IR. TAN PENG LEAK MA A
B.Eng. (USM) M.I.E.M., P.Eng. (SPAN QP1968) L AY S I
Figure 1 Layout of Cut section.
Figure 6 3D View
Figure 7 3D View
Figure 8 Earthworks Input
The potential of soil to support loads is known as its bearing capacity, and it can withstand
loads with ease. The gross pressure at the base of the foundation at which soil fails is known as the
ultimate bearing capacity. There are a ton of theories available for calculating bearing capacity.
But Terzaghi's theory of bearing capacity trumps all the other theories. The bearing capacity of the
soil was determined in this project using Terzaghi's bearing capacity theory. Equation below can
be used to determine both the ultimate and allowable bearing capacities:
Where,
Qult = ultimate bearing capacity c = cohesion of soil
q = soil pressure
γ = unit weight of soil
Nc, Nq, Nγ= Terzaghi’s bearing capacity factors
Where,
qall = allowable bearing capacity
qult = ultimate bearing capacity
FOS = factor of safety (FOS = 3)
Although there were unsuitable soil data because the lab tests were not conducted, all the
information, parameters, and data about soils were derived from the typical value the typical soil
unit weight, indicated in Table 2.3.
The void ratio and dry unit weight taken using the typical value also by referring to Geotechnical
Engineering book. The values show in Figure 2.4 below.
Furthermore, the bearing capacity factors can be found in Figure 2.5 by assuming that the
friction angle for clay is equal to zero.
The ultimate bearing capacity calculated based on the clay soil which the parameter of clay as
shown in Table 2.6.
c’ 8m
Φ (°) 0
Nc 5.70
Nq 1.00
Nγ 0
Dry unit weight, γdry 16
Saturated unit weight, 19.86 KN/m2
Void ratio, e 0.65
Depth, D 2.55 m
Width, B 2.70 m
Df 4.00 m
CALCULATION BEARING CAPACITY OF SOIL
qall = qult/FOS
= 107.71 /3
= 35.9 kN/m²
Since the earth's subsurface is not flat right now, it is necessary to level the site, dig a hole,
and fill in the soil. The technique of moving soil from one place to another to level the ground is
called "cut and fill." Cutting is required to level the ground surface when the existing earth is higher
than the proposed ground level. The earth will then be filled to raise its ground level if the current
ground level is lower than the planned ground level. As a result, the conventional technique
suggested to produce a level or level ground surface is cut and fill.
The work required to accommodate the building platform cannot be completed by cut and
fill alone. Any movement of the earth disturbs natural compaction, and soil in this condition is
usually referred to as "fluffed" or "aerated." Before using the earth for foundations, it must be
compacted to prevent settling. Proper compaction is essential to prevent sinking earth, which can
lead to disastrous consequences like foundation damage.
In this construction project, the proposal level is 11.50 m which mean the soil level that
above need to cut and below 11.50 m need for backfilling of soil. There are several methods used
for determination on the volume of the cut and fill. For this project, Kubla Cubed are used to
determine the total volume of cut and fill. The advantage of using this software is the basis of the
estimate can be fully summarized on the construction drawing and allow a clearer summary of the
graphical summary is not for estimation. As with the Kubla Cube software, it provides an
approximate data, generate a 3D simulation.
Using Kubla Cubed Software to generate the cutting and filling volumes, it ended up with
we only fill due to all elevation points on the construction site is below the proposed level which
is 11.50 m.
The result that we found from the Kubla Cubed software is the fill volume should 196.47
m3, based on the result it appears there is a dark colour , this means there is a area below the
proposed level should cover, it noticed there is a dark red circle it represented a lake that has been
demolished in the site, the simulation results will be listed below:
Figure 2.1: Proposed level 2D
The gridline approach involves creating a uniform grid on a plan for the earthwork and
removing current and anticipated ground levels at each grid node. These numbers calculate the
typical cut or fill depth needed for each grid cell, multiply that depth by the cell area and then
calculate the volume needed for each cell. The total cut and fill volumes for the project can be
calculated by adding the volumes for each cell. The suggested average level is subtracted from the
present average cell level to get the cell depth of cut or fill. The resultant depth shows a fill or cut
depending shows a fill or cut depending on whether it is positive or negative.
The benefits of the grid approach include the ability to fully depict the estimated foundation
on the construction drawing and to provide a clearer explanation of the graphical summary. As
with the cross-section approach, the accuracy of the grid method depends on the size of the grid
cell. Nevertheless, applying the grid approach requires a great deal of time and effort.
The table shows the calculation of cut and fill of the earthwork. According to the table, the
total fill volume and cut volume required to achieve the proposed platform level of 11.5 m and the
building area are 196.47 m3 fill volume. Since there are only fill volume, there will be required
volume of soil from outside area to fill the site area.
No Exis ng Proposed Level Fill Cut Area Fill volume Cut Volume
Level (m) (m) (m2) (m3) (m3)
1 11.5 11.5 0.53 0.07 1747.8 196.47 5.14
4
2 11.4 11.5 0.53 0.07 1747.8 196.47 5.14
4
3 11.45 11.5 0.53 0.07 1747.8 196.47 5.14
4
4 11.4 11.5 0.53 0.07 1747.8 196.47 5.14
4
5 11.25 11.5 0.53 0.07 1747.8 196.47 5.14
4
6 11.3 11.5 0.53 0.07 1747.8 196.47 5.14
4
7 11.5 11.5 0.53 0.07 1747.8 196.47 5.14
4
8 11.42 11.5 0.53 0.07 1747.8 196.47 5.14
4
9 11.5 11.5 0.53 0.07 1747.8 196.47 5.14
4
10 11.42 11.5 0.53 0.07 1747.8 196.47 5.14
4
APPENDIX 3
DESIGN CALCULATION
(TEMPORARY EARTH
DRAIN)
UP SUMP DOWN SUMP GROUND LEVEL,m INVERT LEVEL,m SUMP INVERT LEVEL,m DEPTH,m DRAIN TYPE GRADIENT(1/X) LENGTH,m
1 2 11.5 3.50 3.35 1.135 trapezoid 1/200 34.23
2 3 11.5 3.53 3.22 1.135 trapezoid 1/200 168.24
3 4 11.5 3.53 3.20 1.135 trapezoid 1/200 17.24
4 5 11.5 3.53 3.15 1.135 trapezoid 1/200 14.96
5 6 11.5 3.45 3.10 1.135 trapezoid 1/200 82.40
6 7 11.5 3.40 2.95 1.135 trapezoid 1/200 37.14
7 8 11.5 3.35 2.90 1.135 trapezoid 1/200 76.11
8 9 11.5 3.30 2.85 1.135 trapezoid 1/200 19.64
9 10 11.5 3.25 2.80 1.135 trapezoid 1/200 97.37
10 11 11.5 3.20 2.75 1.135 trapezoid 1/200 7.85
Up sump Down sump Depth,m Bottom width,b(m) Side Slope,z Top width,B(m) Area,A(m2) Wet Perimeter,P(m) Hydraulic Radius,R(m) Velocity,V(m/s) Discharge,Q(m3/s)
1 2 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
2 3 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
3 4 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
4 5 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
5 6 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
6 7 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
7 8 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
8 9 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
9 10 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
10 11 1.135 0.5 2 1.25 3.07645 5.575874309 0.551743068 1.729724349 5.321410472 OK!
CA = CAprev + CAcur
0+1.05
1.05
Qreq = CA * I/360
1.05 * 170.064/360
0.49602
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 2-3
2
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 168.24 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.551750421 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 22.41 119.6740526
22.41 min
td=L/V
168.24/1.729724348
3 97.26405262
Drain Type = Trapezoid
tc = to + td
Drain Length = 17.24 m 119.6740526
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.551750421 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
1.05+1.05
2.1
Qreq = CA * I/360
2.10 * 170.064/360
0.99204
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 3-4
3
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 17.24 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.551750421 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 =10.48 20.44690601
10.48 min
td=L/V
17.24/1.729724348
4 9.96690601
Drain Type = Trapezoid
tc = to + td
Drain Length = 14.96 m 20.44690601
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.551750421 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
2.10+1.05
3.15
Qreq = CA * I/360
3.15 * 170.064/360
1.48806
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 4-5
4
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 14.96 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.551750421 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 10.00444587 18.65553529
10.00444587 min
td=L/V
14.964/1.729724348
5 8.651089416
Drain Type = Trapezoid
tc = to + td
Drain Length = 82.40 m 18.65553529
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.551750421 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
3.15+1.05
4.2
Qreq = CA * I/360
4.2 * 170.064/360
1.98408
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 5-6
5
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 82.4 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.55175 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 17.66652448 65.3041727
17.66652448 min
td=L/V
82.40/1.729724348
6 47.63764822
Drain Type = Trapezoid
tc = to + td
Drain Length = 37.14 m 65.3041727
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.55175 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
4.2+1.05
5.25
Qreq = CA * I/360
5.25 * 170.064/360
2.4801
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 6-7
6
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 37.14 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.55175 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 13.54586353 35.01749283
13.54586353 min
td=L/V
37.14/1.729724348
7 21.4716293
Drain Type = Trapezoid
tc = to + td
Drain Length = 76.11 m 35.01749283
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.55175 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
5.25+1.05
6.3
Qreq = CA * I/360
6.3 * 170.064/360
2.97612
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 7-8
7
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 76.11 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.55175 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 17.20542168 61.20665233
17.20542168 min
td=L/V
76.11/1.729724348
8 44.00123065
Drain Type = Trapezoid
tc = to + td
Drain Length = 19.64 m 61.20665233
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.55175 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
6.3+1.05
7.35
Qreq = CA * I/360
7.35 * 170.064/360
3.47214
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 8-9
8
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 19.64 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.55175 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 10.95436265 22.30877298
10.95436265 min
td=L/V
19.64/1.729724348
9 11.35441033
Drain Type = Trapezoid
tc = to + td
Drain Length = 97.37 m 22.30877298
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.55175 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
7.35+1.05
8.4
Qreq = CA * I/360
8.4 * 170.064/360
3.96816
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 9-10
9
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 97.37 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.55175 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 18.6774411 74.96964749
18.6774411 min
td=L/V
97.37/1.729724348
10 56.29220639
Drain Type = Trapezoid
tc = to + td
Drain Length = 7.85 m 74.96964749
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.55175 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
8.4+1.05
9.45
Qreq = CA * I/360
9.45 * 170.064/360
4.46418
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS
From 10-11
10
Drain Type = Trapezoid Reference calculation output
Gradient Friction slope of Drainage = 1/200 1/200
Drain Length = 7.849 m
Cross-sectional area of flow (A) = 3.07645 m Frictional slope of Drainage is satisfactory
Wetted Perimeter = 5.5758 m
Hydraulic Radius = 0.55175 Velocity(V) Formula 1.729724348
1/n*R^(2/3)*s(1/2) m/s
(1/0.0275)*((0.551743068^(2/3))*(1/200)^(1/2))
1.729724348
drainage h = 1.135 The drain velocity is OK
z = 2.0
b= 0.5 Capacity (Q) V*A 5.32141047
5.32141047 m3/s
Area ((0.5+(1.135*2)*1.135))
3.07645 Time of Concentration t0 = 8.068297722 12.60601497
8.068297722 min
td=L/V
7.85/1.729724348
11 4.537717243
Drain Type = Trapezoid
tc = to + td
Drain Length = 7.85 m 12.60601497
Cross-sectional area of flow (A) = 3.07645 m
Wetted Perimeter = 5.5758 m Rainfall Intensity From table 13.A1, the fitting coefficients for (location), 2Years ARI are: 170.0642402
Hydraulic Radius = 0.55175 λ = 64.504 mm/hr
ĸ = 0.196
θ = 0.149
ƞ = 0.723
drainage h = 1.135
z=2 Rainfall intensity is calculated from empirical Equation 2.2:
b= 0.5 i = λTK /(d + θ)ƞ
64.504 x 2^(0.196)/(0.1667 + 0.149)^(0.723)
Area ((0.5+(1.135*2)*1.135)) 170.0642402
3.07645 170.064 mm/hr
CA = CAprev + CAcur
9.45+1.05
10.5
Qreq = CA * I/360
10.5 * 170.064/360
4.9602
Qprov =5.3214 m3 /s
Qprov > Qreq, drain dimension is satisfactory
PASS