Project Management 2023
Project Management 2023
PROJECT
MANAGEMENT
COURSE FOR ROLE BASED CERTIFICATION FOR SBI
ENGINEERS AND FIRE OFFICERS
What is Project Management? also try to find out if changes in the project
environment had required us to change our
Project Management is often described as the objectives and whether we had reacted to this
process of planning and directing a project from promptly and wisely. Thus we see that good
its inception to its completion and in a given time project management requires alternatives in
at a given cost for a given product. This simplistic detecting unexpected situations, ability to find
definition ignores a few very important points. good solutions to problems that have occurred,
The following paragraphs explain why. and foresight to re-plan under the changed
circumstances.
First of all the time and cost estimates of a
project are based on assumptions taken at the So far we have been talking about processes
time of making the estimates. The actual time (ways of doing things), technical problems, and
schedule and the costs incurred will always vary how to solve them. A project also requires human
from forecast values. It is, therefore, unrealistic to inputs and has human problems, and these
expect a project to be completed exactly as problems may be even more difficult to solve
planned. Time, cost, the project scope and than technical ones. No project can be successful
project objectives may frequently be traded off without the people motivated to work towards its
against each other. For example, time and cost objectives. Project Management must, therefore,
may be saved at the expense of the quality and be able to realise and understand the motives
scope of the project, or, if the latter remains and behaviour of all those who have an input to
unchanged, time may be reduced at the expense the project, it must steer the project to its desired
of cost, and vice versa. Thus it is almost objective amidst often conflicting gaols of the
inevitable that the cost, time, quality and scope of various parties involved.
the completed project will differ somewhat from
original estimates. It is also possible that the Having described in general what is required of
original estimates themselves are biased to start project management, we may now try to define
with, thus providing an erroneous base for project management by outlining more
comparison. specifically what it is supposed to do.
If completion time, cost and quality of the end In broad terms project management plans and
product are not reliable measures themselves for directs the process of development of a project to
gauging the efficiency of project management, enable it to reach in the best possible way and
we may ask ourselves how else this can be done. with the best possible result, the intended
The answer to this question will bring us a little objective of the project.
closer to the understanding of what project
management is about. To assess how well a Specific activities of project management as
project has been managed we have to examine outlined in the following chart will show that these
the course of a project's development to find out activities form the dynamic cycle of planning
if we could have detected early any situation, that direction of work according to plan, monitoring
had made us deviate from our original plan, and if achievement and detecting changes in the
we could have come up with solutions that would environment, and feedback for re-planning.
have led us to a better end position. We might
PLANNING
Set Objective
Survey Resources
Formulate Strategy
CONTROL EXECUTION
Measure Achievement Allocate Resource
Compare with Goal Guide Execution
Report, Resolve Co-ordinate Efforts
Problems Motivate Staff
When Is Project Management Needed? It must be emphasized, that the nature of the
work involved in project management can be
If project management is intended to serve the vastly different from that of functional operations,
above purposes, it becomes apparent that it will and it is not often possible to find someone who
be needed from the time when the project is first is well versed in both types of work. Thus
conceived. At this point one might question if assigning the responsibility of project
there is a real need to give to a person entrusted management to a functional "operations"
with the management of a project, the title of manager may often backfire. Table on next
Project Manager. The Project Manager is actually paragraph shows some of the difference between
the person in charge of the project management, the nature of the two types of work. Even when a
and as long as he does this he is the project suitable candidate is available he may not be
manager, no matter what his official title may be. able to find sufficient time for his additional
However, it is necessary to ensure that duties, and the performance of one duty may
everybody concerned with the project, including have to be sacrificed for that of the other.
the individual himself, knows that he has the It is usual, however, to assign some of the duties
responsibility and authority to manage the of project management to functional manager
project, and sometimes bestowing a title such as during the early stages of a project (usually the
project manager, project co-ordinator, or project planning stage) when the demand on time for
director helps. project management is not too severe, and the
In many organisations, individuals who have future of the project is less certain. As the project
other functional duties in the organisation develops, appointment of a full time project
manage projects, particularly in the early stages. manager is often justified. The time when this
There is no strict rule against this practice, stage is reached depends on the size and
provided that the candidate: complexity of the project. Such an arrangement
1. knows how to manage the project, and may cause some inconvenience and loss of
2. has sufficient time and energy to manage the efficiency during the changeover period. In
project, while taking care of his other duties. addition, there is the danger that the incumbent
project manager (and his organisation) would fail Any savings from the late hiring of a full time
or refuse to recognise the limit of his capacity and project manager should therefore, be carefully
cause such delay in the changeover as to be weighed against possible losses to the project
detrimental to the project and the organisation. due to lack of proper project management.
running the project management process), the • He wants to be on top of every detail of the
project manager often has no direct authority project;
over those who work on the project. In addition, • He secretly wishes to manage the project
he has to deal with people who do not work himself because of the challenge it offers.
directly on the project but whose support and
sometimes-input are vital to the success of the
project. CONCEPTS OF PROJECT MANAGEMENT
SPECIAL FEATURES OF PROJECT At this stage, since we may know the precise
MANAGEMENT financial implication of the project, only an
administrative approval is obtained from the top
Modern concept of Project Management imposes level management. That is, rough estimates
a logical discipline upon decision making. based on past norms and estimates along-with
Therefore it enables the management to feasibility reports are submitted for approval.
programme the various activities logically and While a project is in this phase it should have a
control them effectively. At the planning stage the high degree of flexibility in case of major works
project is broken down into its component so that alternate designs
activities in order to establish the logical of equipments can be introduced to achieve
sequence in which they must be carried out and better economy and performance efficiency.
their interrelationships. By estimating the duration
of each activity the project duration is Definition Phase
determined. This also identifies the critical and
non-critical activities and thus enables the After the conception of the project, the various
Management to decide about the degree of component activities take a definite shape in this
control to be exercised for various activities phase. The same group of people, who worked
during execution. The demand for resources is on the conceptual phase should also work on this
predicted period by period. This helps in the phase for all projects.
better deployment and utilization of resources.
During the execution stage a continuous Objectives of this phase are
comparison is made between what was planned • Finalisation of design of equipment after
and what is happening and corrective actions are detailed consideration.
immediately taken so that the completion date of • Thorough analysis and assessment of
the project is not affected. After the project is financial implications.
completed a review is made to assess the extent • Preparation of Cost Estimates
of deviation from the planning duration and cost • Precise assessment of manpower
and the reasons thereof. These are classified as requirements
controllable and uncontrollable. Therefore, the • Preparation of a detailed plan for the
experience and knowledge thus gained is built up execution of the project (e.g. PERT ing of the
so that it may be used in similar projects to be project).
taken up in future. • The scheme proposals, accompanied by the
PERT NETWORK of the project is submitted
PHASES IN PROJECT MANAGEMENT to the top level management for obtaining
financial sanction. This marks the culmination
Conceptual Phase of the definitive phase.
PROJECT MANAGEMENT
CONTROL
MONITORING
ORGANISING
PHASE
Project identification Identify opportunities for new ventures, Estimate other resources
and definition diversification or expansion of existing
activities Evaluate current assets,
Initially define purpose, objective and resource commitments and
scope of the project. magnitude of external financing.
Establish need for justification for the Identify potential sources of
the project funding
Determine potential profits, returns or Obtain preliminary assessment of
benefits technical & managerial feasibility.
Estimate "order of magnitude" costs Consider appropriate alternative
locations.
Project formulation, Define project objectives and targets Analyse technical, commercial,
preparation and Define Project components and elements economic, financial, locational and
feasibility managerial feasibility
Perform market or demand studies Obtain preliminary review by
Prepare project justification potential funding sources, govt.
Prepare cost, return, borrowing estimates agencies or other sponsors
and preliminary financial plan.
Project Design Identify specific activities, tasks to be Prepare initial production resource
performed input and distribution plans.
Select site for project location Determine labour, managerial and
personal needs.
Prepare blueprints and specifications for Analyse alternative, organisational
equipments and facilities. Arrangements for implementation.
Prepare operating plans, work schedules, Prepare formal operations plans.
life of the project budget
Estimate technological requirements and
make plans for technology acquisition.
Appraisal, selection, Establish credit worthiness Secure govt. clearance & licences,
negotiation & approval Negotiate, Sign loan agreements.
Project activation Establish or define project management Requests bids and tender contracts
and organisation and organisation plans for construction and other work
Clear import licences & export requirements
Recruit and train personnel Set up management production
Arrange for procurement of facilities Establish Marketing & distribution
equipment , supplies and materials channels
Implementation Procure resources, raw materials Establish accounting disbursement
operation and and supplies and payment procedure
control Test and adapt technologies and Create monitoring inventory, control
managerial arrangements programming procedures
Adjust production and distribution Establish repair and maintenance
procedures. procedures.
Completion output Plan for transition to full scale. Establish arrangements for loan
diffusion, transition Production loan close out. repayment
to normal Initiate loan close out. Train & redeploy project personnel.
administration Begin transfer of excess
personnel assets to services users
Project Evaluation Perform audits & post assessments Activate organisation for full scale
and follow up production
ANNEXURE
CHOICE OF SOURCES OF FUNDS
The basic objective in arriving at a financing plan is to minimise the cost of capital to the company. Of the
several factors influencing the cost of the capital tax factor is the most important one. The fact that the
interest paid on borrowed capital is a deductible expense for tax purposes makes debt a cheaper source of
finance. The following example illustrates the relative profitability of the same project under three alternative
schemes of financing
SCHEME A B C
(Rs. in Lakhs)
Debt (Rate of interest at 10%) 30.00 70.00
Equity 100.00 70.00 30.00
Total Investment 100.00 100.00 100.00
Estimated profit (before interest and tax) 15.00 15.00 15.00
Less Interest on debt - 3.00 7.00
Profit before tax 15.00 12.00 8.00
Less tax at say 50% 7.50 6.00 4.00
7.50 6.00 4.00
Return on equity(item 8 as percentage of item 2) 7.5% 8.6% 13.3%
The return on equity increases from 7.5 % under scheme 'A' to 13.3 % under scheme "C" for two reasons: (i)
tax outgo is less by Rs.3.5 lakhs and (ii) profit after tax is earned on a very narrow equity base of Rs.30
lakhs as against Rs.100 lakhs under scheme 'A'.
It would appear from the above that the best way to maximise return on equity is to finance the scheme
predominantly through debt. However, the major drawback of doing this would be the fact that interest on
debt is a fixed cost based on time rather than earnings. The project under scheme 'C' for instance, would
have to pay Rs.7.00 lacs as interest whether the profit is Rs 15 lacs or Rs 4 lacs in the latter case, the
shareholders would suffer a loss.
vary from period to period as well as cash flow product drops below, or the amount of fixed costs
profiles with more than one change in the sign. exceed, a certain level, which are called the
break-even market share or break-even fixed
Decision Criteria cost, the company starts losing money on the
Based on the DCF analysis of project proposals, project. The concept of financial break-even or
the decision criterion that follows is relatively investment projects is therefore looking at where
straightforward. Assuming that the company the project recovers its opportunity cost as
operates in a capital market environment where opposed to accounting break-even analysis,
access to capital is not limited, the management which focuses on historical costs.
should accept all projects with positive net
present values and thereby maximise the Scenario Analysis
company's value. The previous two project analysis tools are
concerned with only one underlying factor at a
Project Analysis time, thereby treating them as non-interrelated.
Project analysis tools are widely used methods However, companies often find that certain
developed to provide managers with a deeper market events would result in a change of several
insight and better understanding of the financial underlying variables at the same time. If, for
aspects of investment projects, as well as to shed example, there is a threat of a new competitor
some light on the assumptions behind expected entering an existing market then the market
cash flow forecasts. They can enhance the share of the company as well as the product
confidence of managers in the DCF analysis and price is expected drop. Scenario analysis allows
point-out major risk factors that can potentially management to investigate the effect of potential
jeopardise the expected outcome of the future scenarios of events, which are translated
investment. into the CDF valuation model as consistent
changes of various combinations of the
Sensitivity Analysis underlying variables.
Sensitivity analysis is a very useful tool to identify
key variables or value drivers of projects and Alternative decision criteria
focus managerial attention on the most important
components of forecasts that are underlying the Companies of all sizes and sectors have long
expected incremental project cash flows. The been using a number of other decision criteria to
analysis is carried out by measuring the change evaluate their capital investment projects either
in the value of the project after shifting the value as a supplement to, or worse, as a substitute for
of one underlying variable up or down, the NPV rule. Let us briefly summarise how some
corresponding to a more optimistic or pessimistic of these criteria work and compare them with
forecast. The magnitude of the change in the net NPV.
present value shows the sensitivity of the project
to that particular underlying variable. Payback and discounted payback
If, for example, the NPV proves more sensitive to The simple payback period of a project is defined
the market share of the company and to the as the expected number of years it takes for the
amount of fixed costs than to the price of the company to recover its initial investment outlay
product, then management should focus on the by implementing the project. The decision
reliability of market share estimates and fixed criterion is then given as a maximum number of
cost forecasts, as well as concentrate efforts years, or cut-off period, above which capital
during the implementation to improve these investment proposals should be rejected. this
factors. implies that the shorter the payback period, the
better the project is. However, there are two
Break-even Analysis major short comings to this rule. First, it fails to
Break-even analysis goes one step further. It recognise the time value of money. No investors
points out the critical value of each underlying would be satisfied by investing Rs.100 today and
variable at which the project's NPV is zero. receiving exactly the same amount a year from
Referring back to the previous example, it would now and nothing
tell management that if the market share of the
afterwards, even though the investment has a money. This method involves the calculation of
one year payback period. Second, the rule the payback period in terms of the present value
disregards expected cash flows from the project of future cash flows generated by the project.
after the cutoff period. It prefers projects with However, the rule still does not give any weight to
large payoffs in the early years and perhaps cash flows after the arbitrary cut off date.
nothing later to long term projects with gradually Therefore, its use should be restricted to
increasing positive cash flows. comparing projects with very similar even cash
Companies often use the discounted payback flow profiles. One example could be parts of the
rule to correct for disregarding the time value of property sector, where a number of investments
are expected to produce long term evenly Expanding the frontiers of Capital
distributed rental income. Budgeting Criteria
As mentioned earlier, however, the assumptions
Internal rate of Return underlying the DCF analysis represent a static
The internal rate of return IIRR) of a project is approach to decision making, and can be very
defined as the discount rate that makes the restrictive in some case. the replacement of
project's NPV=0, thus obtained by solving the uncertain future cash flows by their expected
following equation for r: value and the use of a single discount rate ignore
the possibility of active managerial actions over
O = Co + C1 + C2 +.+ Cn the lifetime of the project. For example,
(1+r) (1+r)2 (1+r)n managers take actions aimed at cutting the
losses due to unfavourable market events and
For most projects the IRR rule gives an identical retaining or improving profits following favourable
answer to the question whether it should be changes. This can change the risk profile of the
accepted or rejected. However, for some others, project. Also, the standard DCF analysis works in
the use of IRR is not appropriate, or needs to be terms of making a decision now or never. It
used with great care. these exemptions include ignores the opportunity managers may take to
projects where, instead of an initial investment, delay some strategic decisions pending the
the cash flow of the project changes sign more outcome of future events.
than once over the forecasting period or when To overcome these drawbacks, various attempts
the company is ranking mutually exclusive
have been made to develop more sophisticated
projects either because of technical or capital
constraints. decision criteria and investment analysis
methods. these include decision tree analysis,
Profitability Index the use of certainty equivalent cash flows and the
The profitability index (PI) of a project is defined application of option pricing theory in the
as the ratio between the present value of future valuation of real assets. The application of these
cash flows from the project and the initial
methods have proved to be helpful complements
investment (where Co is assumed to be
negative). to DCF analysis.
n
I+1 C1 THE MERITS OF PROJECT
PI = (1+r)n = PV FINANCE
-Co -Co
In the usual case, lenders to a company have
The rule says that all projects with a profitability collectively a claim on its cash flows as a whole,
index higher than 1 should be accepted, which is except for lenders to a subsidiary where there is
identical to the outcome of applying the NPV rule, no explicit or implicit guarantee (in the form of a
since if PI>I it means that PV> -Co, and thus "letter of comfort", for example) by the parent
NPV > O. However, the profitability index is not company. It is also from the company as a whole
useful when applied to ranking mutually exclusive that the dividends are paid.
projects since it captures the profitability, but not In the case of project finance, on the other hand,
the scale, of projects. both lenders and equity investors look only to the
cash flows of the project concerned (often a
Accounting Measures large-scale undertaking such as oil exploration or
development or tunnel building) for their returns.
There are a number of accounting measures This, too, differs from the case with a normal
used in the process of investment decision subsidiary, the operations of which are rarely
making, such as the return on investment (ROI) confined to a single identifiable project. Where
or average book return on investment. The major such a project is being initiated or spun off by a
problem with these measures in general is that "parent" company, the suppliers of finance to the
they are based on book values that are often project have no recourse, in the classic version of
liable to arbitrary selection of accounting policies project financing, to the "parent" company. Hence
(for example on depreciation schedules). In the American term "non-recourse financing" for
addition, book values and book income do not this situation. But hybrids have also been
reflect the time value of money, therefore various developed where the "parent" company or
adjustments are needed to arrive at meaningful sponsoring organisation offers some form of
results. This means the DCF analysis is clearly minimum guarantee.
preferable to accounting measures in setting
investment decision criteria.
subjecting their cash flow forecasts to a range of by identifying the so-called critical variables
assumptions concerning pre-production delays, involved and then by deciding how uncertainity
capital and operating costs, volumes and prices, as to their values might best be dealt with.
Project financing has taken many forms. There simple terminable partnership formed for a
have been projects initiated by a single company, specific venture inadequate.
as in the case of BP's North Sea oil fields Over the past 20 years, however, there has been
(involving a syndicate of 66 banks) and various a revival of project financing in order to undertake
mining projects, those organized by a non
very large projects (the Channel Tunnel is one
operating sponsor or group of sponsors, joint
ventures and forms of partnership. example) and to finance other joint ventures and
The oldest examples of project financing go back co-operative arrangements in which companies
to medieval times, when Italian bankers would can pool resources and yet each make their
finance mining and other ventures. The most distinctive contribution. Other examples include
common form of early project, however, was the oil fields, pipeline projects, a variety of power
overseas trading venture on a voyage basis,
generation projects in the US in particular, and
using the finite-life partnership as its legal form.
This was superseded by the joint stock form of joint research and development projects. In most
continuing organisation when the necessities of such cases debt finance is provided by a group of
scale, complexity and continuity rendered the banks.
The basic concept of PERT is to calculate the network by specified target dates having regard
probabilities of reaching particular events in the
to the possible variations in the activities times. • What other activity(ies) can be taken up
PERT is based on probabilistic estimate of time while this activity is being done.
duration of various activities. The system is (Subsequent).
predominantly concerned with events and is It is to be noted that concurrence is only a
therefore, an event oriented system. PERT has relationship of logic, not of time. Duration of each
its applications in those projects in which there is activity does not come into picture at this stage,
some uncertainty about the activities but the but only the logical sequence of the individual
necessary resources including money are always activities. The network diagram is a graphical
available as required. representation of the inter-dependency of all the
CPM In contrast to the inherent uncertainties activities of a project.
surrounding the activities of the development
project like Polaris Project, the times required for Time Estimation
the tasks or activities for construction project are Estimates of the time required to perform each of
reasonably amicable to estimation within the network activities are made, these estimates
acceptable limits of accuracy by the use of are based upon manpower and equipment
appropriate techniques. CPM is based on availability and certain assumptions that may
deterministic estimate of time duration for each have been made in planning the project in step-I.
activity. The basic concept of CPM is to calculate
the project duration which will result in the Critical Path Analysis
minimum overall project cost assuming that there This involves the computations of the earliest and
is an approximately linear and measurable the latest allowable start and finish times for each
relationship between the time and direct cost of activity in order to identify the critical path through
each activity. The system is predominantly the network and indicate the amount of slack time
concerned with activities and is therefore, an associated with the critical paths.
activity oriented system.
CPM has its application in projects where the Resource Allocation and Levelling
activities are definable and measurable and After determining the critical path, the resources
minimum overall cost is of utmost importance. namely manpower and equipment are allocated
to the various activities. these resources are
Basic Steps involved in the application of levelled out as far as possible through out the
PERT for Project Management. project in order to achieve optimum utilisation of
the resources. This provides the basis for
Project Planning determination of the initial scheduled completion
The activities making up the project are defined of the project.
and their dependency upon one another is shown
explicitly in the form of a network diagram. PERT Cost and Crashing
Whether a certain project will have two hundred If the scheduled completion time of the project as
activities or two thousand activities depends upon determined in step 4 is satisfactory, the final
the degree of detail desired by the management. project planning and scheduling for the execution
The rule to follow is that an activity should may be prepared.
represent the smallest unit over which control is However, in case it is found necessary or
desired. Hence, a thorough knowledge of the considered desirable to reduce the project
project in hand is essential to breakdown the completion time, the crashing of the activities on
whole project into a number of activities. All the critical path and their associated cost of
these activities are inter-related. In order to crashing are considered, this could enable the
determine the inter-dependency relationship, determination of the optimum time and cost of the
each activity is examined in relation to other project. A final schedule for the execution of the
activity in the light of the following questions. project is then worked out.
• whether other activity(ies) must be
completed before this activity can start Project Control
(Precedence). When the network plan and schedule have been
developed to a satisfactory extent, they are
National Productivity Council 22
Network Techniques
prepared to a final form for use in the field. The manpower, equipment etc. and analysing the
project is controlled by checking progress against efforts of delays. Whenever major changes are
the schedule, assigning and scheduling the
made in the schedule, the network is, revised complete building acquire land, cut over of an
accordingly and new schedule is computed. exchange are events.
3. The beginning of the activity is a tail event that the job began at event 'i' is completed at
while the completion of an activity is a head event 'j'.
event. These are respectively called the 'i' and 'j'
events. 6. Network may have only one initial event and
only one terminal event.
4. No activity may be shown more than once in
the network. 7. Representation of inter-dependency of the
activities should be clearly indicated. Some
5. While drawing network, it is assumed that examples are given below
a) time flows from left to right and
b) head events always have a number higher
than that of the tail i.e. the activity 'i-j' will
always mean
REPRESENTATION INTERPRETATION
2 3 3
1 4 2
1 4
WRONG RIGHT
5
5
1 2 3 1 2 4
4 3
WRONG RIGHT
2 5 3
1 4 6 5
2
3
1 4 6
7
WRONG RIGHT
8. Keep left to right component in each arrow i.e. always draw event 'j' to the right of event 'i'. This
follows from the fact that events are points in time and once an event (point in time) has been passed it is
impossible to return to it as time itself is unidirectional.
3 3
1 2 1 2
WRONG RIGHT
3
6 1 6
4
1
2 4 2 5
WRONG RIGHT
10. The error of 'dangling' any activity in the network construction should be avoided.
1 2 3
4
Dangling is shown by activity (2-4) which produces no results as regards the entirety of the project. To avoid
dangling the following rule must be followed.
"All events, except at the starting and completion of the whole project must have at least one activity
entering and one activity leaving them. "
B C 2 5
A D 1 6
E F 3 4
A is an initial event. Hence it is numbered as 1. Connected to A are the events B & E. Delete the arrows
outgoing from A. This results in B & E. Delete the arrows outgoing from B & E (now made 2 & 3) only F
becomes a new initial event as FC arrow is still acting on to event C. Hence number 4 is assigned to F.
Delete arrows FC & CD. C becomes an initial event. Hence C is marked 5. Cancel DF when D becomes the
final event 6.
If there is a series of activities depending on each other in many paths in a network, the paths are taken one
by one and all events are numbered till the merge event as shown below:
4 5 6 7 8
1 3 11 12 13 25 26
2 21 22 23 24
National Productivity Council 26
Network Techniques
A C (Activity C depends on A)
B D
B C
A D
O P
N P
O Q
P R
Q R
A C C F
B C D E
A H F E
B H H I
C D G I
C G I E
7. Activities R, S and T can start immediately. Activity R must be completed before U and W can start.
Activity V must follow S and precede W. Activities U, W and X must all be completed before Z can start.
A 4 H
B 6 H
C 3 H
D 7 B
E 8 B
F 5 B
G 2 C
H 1 NIL(initial activity)
I 5 A,D
J 6 A,D
K 6 F,G
L 7 I,J
M 4 E,F,G,J
N 3 K
O 1 L,M,N
CRITICAL PATH ANALYSIS is known as the earliest event time. Earliest event
time for initial or start event is obviously zero.
For calculating earliest event times for
Objective subsequent events we must begin from initial
event and must end in final event following the
After the arrow diagram has been drawn and the arrow paths. All the activities, one or more,
duration of each activity has been estimated shown terminating at the event must be
either deterministic or probabilistic it is possible to completed before the event occurs and as such
analyse a network. This analysis consists of: the,
1. Calculating the earliest possible and the latest Earliest Event Time = Max of (Earliest Finish
permissible times for each event, assuming that Times for each Activity terminating at that
the time estimates are correct. event)
2. Finding the critical path, which may be defined or, in other words, for calculating the earliest
as the sequence of activities from project start to event time of an event (merge event) at which
project finish that occupies the longest time. two or more activities terminate, find the earliest
In addition to above, the network analysis also finish time for each activity and compare them.
consists of determining various types of floats of The longest time is the earliest time.
spare time available for activities not on critical
path and preparation of working schedule. These, There are a number of ways of recording the
however, will not be discussed in this topic. results, one which is adopted here is to insert the
earliest event time in the left compartment of the
Earliest Event Times two sides of the compartments made in the circle
enclosing event number. Right side of this
The earliest time at which an event can occur (if compartment will be used for recording latest
the estimated duration of each activity is correct) event times
.
Calculation
2 3 3
1 2 5 6
1 9 2
8 4 0
Figure-I
Taking example of the network in Fig.I we can calculate earliest event times for various events starting from
initial event No.1 to the end event No.6 following the arrow path as shown below:
1 0
2 0+1=1
3 1+2=3
4 1+8=9
5 Max. of (3 + 3, 1+9,9+0) = 10
6 10 + 2 = 12
Earliest event times for all those events are shown in Fig. 2 The total project completion time is 12 units of
time and is presented in the form given below:
3
3
1 2 5 6
0 1 10 12
4
9
This technique of determining the earliest event times is known as the 'method of forward pass.' In forward
pass, calculations must begin from the initial event and must end at the terminal or last event.
Latest event time = minimum of Latest event time for minus Intervening
succeeding event activity duration
Calculations
For the network shown in Fig. 1, the latest event times are:
6 12
5 12 - 2 = 10
4 10 - 0 = 10
3 10 - 3 = 7
2 Min. of
(7-2,10-9,10-8) =1
1 1 - 1 =0
The latest event time for all the events are shown in Fig. 3.
3
7
2 3
1 2 5 6
0 1 1 9 10 2 12
8 4 0
10
Figure-3
Critical Path
An examination of network shown in Fig. 4 indicating both earliest and latest event times reveals that for
certain events earliest and latest events time are the same while for the remaining events they are unequal.
3
3 7
1 2 5 6
0 0 1 1 10 10 12 12
4
10 10
Events having the same earliest and latest network event 3 and 4 are non - critical events.
events times are called critical events. In the Difference between latest and earliest event
above network events 1, 2, 5 and 6 are critical times is termed as event floats. For the network
events. Events having unequal earliest and latest shown in Figure 4. floats are indicated in the
event times, are non-critical events. In the above following tabular form.
The critical path lies along those sequential between paths 2-5 and this path is quite
activities joining all the critical events of a considerable viz. 4, sub-critical paths have
network. The sequence of activities from project considerable significance at the time of crashing
start to project finish that occupies the longest of networks. Every network has a minimum of
time is called the critical path. one critical path. In certain networks, along part
An examination of the above table will indicate or all of its length, a critical path may split into two
that 1-2, 2-5, and 5-6 constitute the critical path or more paths and there is no reason why
for the network. dummy activities should not form part of the
Activities lying in the critical path are called critical path. Suppose that in the network shown
'critical activities'. The sum of the durations of all in Fig. 4, by allocating extra resources to activity
the critical activities will be the project time. Any 2-3, its duration could be reduced to 8. Then
delay in any of the critical activities will naturally there would be one more part of critical path viz.
result in a consequential delay in the completion 2-4-5 through a dummy activity 4-5 converting
of the entire project. sub-critical path 2-4-5 into critical path.
Referring to Fig 4, three separate paths connect Identification of the critical path is an important
the events 2 and 5. The direct path 2-5 has first step in the planning and management of a
duration of 9 while the other path viz. 2-4-5 has a project. It will immediately draw the attention of
duration of 8 and path 2-3-5 has duration of 5. the management to these activities which govern
The difference between duration of path 2-5, 2-4- the date of completion of the project. Critical path
5 is very small viz. only 1 and hence this path is has two principle features. First, if the project
called sub-critical path. The path 2-3-5 is not time is to be shortened, one or more of the
called sub-critical path because the difference activities on this longest (time) path must be
shortened. The application of additional effort if the time required for the actual completion of
anywhere else in the network will be useless any activity on the critical path varies from the
unless the critical path is shortened first, second, calculated expected time, this variation will be
reflected in a one-to-one fashion in the
completion of all subsequent events on the
critical path i) All activities in the network under one
item must fall within a work package.
ii) All work packages must be capable of
summarization to an end item sub-division.
PERT COST AND CRASHING
iii) It should be limited to maximum period
of 2 or 3 months.
Introduction
iv) Work package must be built around
continuous path so as to get the maximum
The extension of PERT concept to include cost
coupling benefits.
considerations was a natural one. It is not only
v) A unit or an individual should be given
enough to complete a project on time but this
the responsibility for carrying out the work
must be achieved with optimum cost. The
package.
amount of priority that should be given to the
The normal activity cost is equal to the absolute
achievement of a certain project by a certain date
minimum of direct costs required to perform the
depends on its cost consideration. It could be
activity, and the corresponding activity duration is
worthwhile to advance the completion of the
called the normal time. It is the normal time that
project by certain amount of time if the resultant
is used in the basic CPM/PERT planning and
savings are considerable. Conversely one might
scheduling and the normal cost is the one usually
like to slip a particular project by certain amount
supplied if the activity is being sub-contracted.
of time, if it helps in the completion of a priority
The normal time is actually the shortest time
project and thereby could also help in the
required to perform the activity under the
reduction in the project cost of the project.
minimum direct cost constraint. Ordinarily a
project would not be scheduled for a longer
Time - Cost Relationship
duration then the normal duration time. However,
for various reasons one may be interested in
Activity direct costs include the costs of the
replanning and scheduling the project for a
material, equipment and direct labour required to
shorter duration time. Selection of a certain
perform the activity in question. If the activity is
schedule for a project generally involves a
being performed in its entirety by a subcontractor
comparison of a number of alternatives, each
then the activity direct cost is equal to the price of
with a different relationship between cost and the
the subcontract. Project indirect costs may
time of completion of the activity. A certain
include in addition to supervision and other
activity could be shortened by incurring extra
customary overhead costs, interest charges,
cost in the form of assigning more personnel or
loss of revenue for completing the project after a
scheduling overtime for that activity. When an
specified date etc. Besides there are other
activity is completed in normal schedule time, the
intangible costs like loss of goodwill and public
associated minimum cost could be called 'normal
image apart from depriving the public from the
cost'. When an activity is completed in minimum
benefit accruable as a result of the completion of
possible time, the associated time could be called
the project.
Crash Time and the cost Crash Cost. An activity
could be scheduled for any time between these
Work Break Down: (Work Packages)
normal and crash times. Actual cost-time
relationship curve could be of any shape, but
Since it would not be possible to estimate the
mostly they are linear. However, for optimisation
cost of each activity, therefore, approach used in
problems, we would assume the relationship to
PERT cost is to aggregate a group of activities
be linear with a constant cost slope.
within a network into a cost work package.
Important points to be considered in making the
cost work packages are:
CRASH POINT
Cd
C
O
S
T
NORMAL POINT
Cd
TIME
Project Duration Reduction at Minimum Cost the minimum cost of expediting if first shortened
is determined.
The Normal cost for a project could be obtained The cost slope has to be found by taking the
simply by summing the normal cost of all the differences between normal cost and Crash Cost
activities of the network. In order to shorten the and divide it by the difference between normal
project duration with minimum extra cost, the time and crash time as given below:
critical path is first examined and the activity with
As the total critical path duration is shortened gradually other paths in turn might become critical and they
too have to be examined. Sufficient points could be plotted in this way to show the variation of direct project
costs with time (project duration). Addition of the indirect cost patterns to this curve would give all the
information, a manager requires to select the project schedule balancing the cost and time objectives.
TOTAL COST
C
O INDIRECT COST
S
T
DIRECT COST
reports, organised by time period, are as of The PERT/cost procedure requires an input cost
responsibility, and technical sub divisions of the data in addition to the time data required by basic
project. PERT. This cost data is generally collected for
The efficiency of system is also a problem small groups of related activities called work
because the level of detail is simultaneously a packages rather than for single activities, so as
promise as well as an interest hazard. A network not to impose an undue accounting burden. Cost
cost control system can easily require routine estimates are obtained only after a satisfactory
input data in quantities and frequency that project schedule has been developed since any
personnel find extremely burdensome. Unless schedule change will normally affect cost. As the
the requirements are reduced and procedures project progresses, actual accrued costs are
simplified, the system will come to an early end. gathered for each cost collection point and
revised
Estimates are submitted as required. costs of activities not completed, the following
computations may be made:
A number of useful and informative reports can i) Summation of all actual costs.
be generated from this data. the basic output is a ii) Summation of budgeted costs of this
status report, which combines time and cost data point in time.
for each cost collection point. This enables the iii) Summation of budgeted costs for all
manager to identify activity groups which are activities completed and proportional costs of
contributing to actual or potential schedule activities partially completed. This figure is called
slippages or cost over-runs and also to compare 'planned cost of work completed 'or' value of
the time and the cost status of any given activity work'.
group. In addition to the output obtained from a iv) Computation of difference in actual
time - oriented network, this report shows the costs and planned cost of work completed;
original cost estimate, the actual costs incurred, computation of both money value and percentage
revised estimates, if any, and the anticipated of planned cost of work completed.
under-run or over-run. v) Computation of a projection of ultimate
Provision is made for summarization of the time costs of the total project.
and cost data at various level of management so The sum of actual and latest revised estimated
that each level of management is presented with of future costs may then be compared with the
only that amount of detail with which it is directly contracted total cost for the project, to indicate
concerned. Upon receipt of all input data on the the amount of the expected over-run or under-
progress and expenditure as of the reporting run.
data, and any revised estimates of duration or
Example
Consider the following network. The cost data and the possibility of crashing the various activities is given in
Table-I. Determine the optimum time for completion of the project:
B1 E H
B 3 4 6 8
4 7 12 5
1 I K
A F 15 14 6
D G J
8 2 6 5 7 7 8 9
Keeping in view the above, the first alternative of For further crashing, we noticed that B1 cannot
crashing A by 4 Weeks only is most favourable. be further crashed. This, therefore should be
This leads to the reduction of float for B to zero circled indicating that no further crashing of B1 is
and any further crashing on a would also require possible. Therefore, alternatives 3 i x iii, 4 i x ii, 5
crashing of B and this cost Rs. 1600 per week. iii and iv mentioned in Table II only are available
This cost is higher than the cost of other available for crashing at the cost indicated therein. In
alternatives, second preference will be for addition one more alternative of crashing B & A
crashing D & B1 at a cost of Rs.750 week for 2 with a cost/week of Rs.1600 (3iii) would reduce
weeks as B could be crashed only by two weeks. the project duration. Accordingly the selection of
Third would be for K for 2 weeks at a cost of alternatives will be in the order of B & A, E & D
Rs900/week. and E, F & I respectively.
16 17250
As is evident from above discussion, the crashing of the project as listed above has been keeping in view
the addl. cost for each stage of crashing. Therefore, in case we wish to complete the project in 3-4 weeks,
we could stop at sl. no. 3 for crashing. This would ensure the minimum addl. cost of crashing the project by
7 weeks which is this works out to only 3000 as compared to addl. cost of Rs. 17250 for crashing the project
by 16 weeks.
The crashing of the project completion time could also be attempted using the squared network as shown in
Annexure-I.
The overall cost of the project for various project duration is shown below in the table.
From the table given above, it could be seen that optimum project duration for this case is 30 weeks. These
figures have been plotted on a curve, shown in annexure-II.
Further it may be seen that at a point in the project duration where the direct cost of crashing exceed the
saving in the indirect cost, that indicates that further crashing would not be useful.
SQUARED NETWORK
ANNEXURE-I
B D E
4 3 5 11 8
F H O
A C G I K
4 3 421 10 84
J
8 11 9
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
i) Determine project duration from the critical path of the network diagram, and select the suitable scale.
ii) Draw the critical path in the center of the graph sheet in a straight line against the time scale as far as
possible
iii) Develop non-critical or secondary paths above and below the critical path, showing constraints as
vertical.
iv) Show direction of dummies correctly by an arrow with dotted lines.
v) Make the bars proportional in length to their activity duration on the time scale.
129000
128500
128000
127500
127000
126500
126000
125500
125000
124500 C
O
124000 S
T
123500
I
123000 N
122500 Rs.
26 28 30 32 34 36 38 40 42 44
Duration
RESOURCE LEVELLING
PROCEDURE
Proper allocation of existing resource is an particular resource is scarce or very costly. For a
eternal problem posed to the management. The project, the ultimate cost will depend upon the
problem demands more attention when the utilisation of resources and thereby dependent on
National Productivity Council 40
PERT Applications
simultaneously. Stop when the trigger level of additional peaks are generated, apply the
any shop (call its) is exceeded. procedure of (4) If all the jobs are successfully
Step-4 scheduled then lower the trigger levels of all
Examine the jobs that are active on the peak day shops one more unit and return to 3). As soon as
in shops. Compile a list of jobs which have no further reduction in trigger level is possible,
sufficient slack to move them beyond the peak then print out the schedule.
day without delaying the due date, and arrange
them in descending order to their total slack. Pick Step-6
one of these jobs (by a selection process that Repeat the above process (as many times as is
favour the jobs highest on the list), and move it to computationally feasible). Because of the random
right on the schedule chart a random number of elements in the programme it is likely that
days between the minimum move necessary to different schedules will result from each
push the job past the peak day and the maximum application of the program. Select as the final
move necessary to push the job past the peak schedule the one having the lowest manpower
day and the maximum move allowed by its total costs which are assumed to be proportional to
slack. the trigger levels i.e. sufficient men are hired to
Step-5 meet peak loads and are paid whether ideal or
Continue with the scheduling of other jobs and active on all days.
plotting of the manpower loading chart. If
1 4 2
2 2 2 6 6
6
0 2 3 5 4 4 5 4 8
00 2 2 7 8 12 12 16 16
1 8
6 3 7 5
1 7 10 10
Fig. 1
Scheduling
The activities of the project network are In large projects it may be advisable to use
scheduled, that is the starting and completion 'project calendar’ for ease of computation and to
time of each activity is decided after drawing the facilitate all project personnel understanding the
network. The scheduling of individual activity are activity times in the same way. The project
guided and restricted by the following calendar is developed by numbering the calendar
consideration: months serially starting from the month of which
the project is started. For example in a project
a) Project duration (critical path) where the work was started on August 79, the
b) Resources allocation (availability) project calendar would be as under:
c) Resources levelling (administrative
convenience) August 79 - 1 January 80 - 6
d) Weather line and other constraints Sept. 79 - 2 January 81 -18
e) Desired mile stone events Oct. 79 - 3 January 82 -30
f) Project funding.
All schedules, computation of project times etc.
will then be made with the project calendar only.
The main advantages would be that the unit of
National Productivity Council 42
PERT Applications
reference for all divisions of the project would be October 81 (27th month and requires 17 months
same and the case of computations like finding to complete (27 plus 17 = 44th month).
the completion time of an activity which starts on The net work times computed are than referred in
this project calendar base (or usual calendar).
This is done by substituting the calendar dates on d) lead time required for remedial actions
network timings of start and finish times of etc.
activities. This becomes the chronological
schedule for the activities and events. For this, TIME
separate instructions can be extracted and
issued to the concerned divisions as to when The time aspect of the project is monitored by
each activity should be started and completed obtaining Activity Status report which gives the
etc. information about the following:
- The list of activities completed
Review of Monitoring - the activities under progress and time
During the implementation (operation stage) the required to complete them and the forecast about
Time, cost and performance aspects of the the duration etc. of the future activities.The
project are periodically monitored to know the activity status is incorporated on the network to
status of the project and to plan remedial actions enumerate the project duration and use of float.
if necessary. The frequency of monitoring is Changes required in future work to maintain the
decided based on the following considerations. project duration are planned and new schedule is
a) variations (fluctuations) of the above prepared. Care is taken to follow activities in
aspects critical path and also the near critical activities
b) criticality of changes (with less float) closely.
c) sensitivity of the changes on the total
project expectations
money required to complete them. It can then be
COST plotted against planned cost to see the under-run
or over-run of expenditure as on date and also a
Cash/expenditure budgets are prepared on the forecast of total project cost variation.
basis of the activity schedule. An interesting Separate proforma have to be used to evaluate
feature of the budget is that for desired project the project cost for (i) work done through
duration the cumulative cost or expenditure curve contractors and (ii) work done departmentally.
can be drawn (within limits) for the entire project The report apart from showing the actual cash
duration. Since the critical activities are fixed, outflow, includes the cost of work completed but
one curve can be drawn by scheduling all non- not paid yet (liability) etc.
critical activities to start on their earliest start Apart from controlling the total project cost it is
dates and another curve by scheduling them to also necessary to generate information about
start on their latest start dates. In both cases the high cost activities (may not be in critical path)
curves are drawn by identifying the number of and control them to ensure effective cost control.
activities to be carried out in the month, the total The high cost activities are identified through
expenditure for the month and accumulating this ABC analysis of individual activity costs.
monthly expenditure for the subsequent months.
The monthly cumulative expenditure when PERFORMANCE
plotted on a graph against time in X-axis takes
the form of an Hysterisis Loop The comparison of planned cost and actual cost
allows the project leader to know only the
Whatever may be the schedule of the non critical consumption pattern of money and other
activities, the project cumulative cost will fall resources. It does not provide any knowledge of
within these curves only. Use of this curve performance of the project; the value of work
permits adoption of control by exception principle. completed. To get a clear picture which could
The cost control system necessitates an activity- lead to meaningful decisions, the cost curves
wise expenditure booking and reporting system. should always be seen along with the
The report should indicate the amount already performance curve or the 'value of work'
spent on each activity and a forecast of balance curve/report.
National Productivity Council 43
PERT Applications
The performance curve is prepared on the basis on the basis of percentage of work completed
of the periodical performance sent from field. The (and not just the payment made).
field reports give the quantum of work completed
UPDATING
The standard reductionist approach to project project's life: Business redesign, process
complexity is not conducive to economic break redesign and engineering redesign.
through thinking. Project team structures • Business redesign
encourage independent thinking by breaking the Building a brilliant business case: Business
overall design into pieces that can be assigned to redesign is about superior strategy. The
individuals. Many project engineers have learnt to objectives are to
be comfortable with this way of working. They 1 Craft a value creating link between target
then find it frustrating to have their judgement markets and resources and
challenged and to be required to explicitly 2 Optimise an internally consistent set of major
evaluate the risks associated with ideas. Lots of commercial decisions
opportunities to improve a project's economics
are foregone as a result. To put it simply, Business redesign is about
Project teams tend to suffer from having a single, devising a superior strategy. The business case
technically oriented frame or reference or is subjected to intense scrutiny by senior
'literacy'. This is not surprising, since most team management before the project team is allowed
members have a very similar engineering- to indulge in working on the assets. By
intensive background. The net effect though, is multiplying and accelerating the iterations
that any project engineers are far more between the broad room and project team room,
comfortable with mass-flow balances then with senior management can put a lot of emphasis on
NPV trade-offs. In addition, they often resent the key levers of value creation. In some cases,
having commercial people question the economic this might mean not owing, not even building, any
consequences of engineering decisions since the assets.
'bean-counters' don't understand the technical • In process redesign
implications of design choices. A sound The challenge is to match the project scope
engineering or technical 'literacy' is an absolute tightly with the optimised business case. The size
pre-requisite for success; it is not sufficient, and nature of the project's major component
however, to create great new business. pieces are redefined in the light of a more
• But there's hope round the corner. Insufficient focused strategy. In addition, interface
top-management input and inappropriate inefficiencies are eliminated.
functioning of project teams can be • Engineering Redesign
addressed with a systematic rethink of what a Ensures that the third and final phases of the
company is planning to build and why. The project's life is highly structured commercial, as
aim of Clean Sheet Capital redesign is well as technical, review of every aspect of the
simple: to extract maximum returns from a project. Here, the objective is to relentlessly
given project. Starting with a clean sheet, tighten the screws on the unnecessary costs that
management can focus the project team on all too often creep in during the detailed
the major value levers, rather than simply engineering work.
trying to fine-tune what has been presented to
them. Fundamental redesign, however, A major project like Australia’s North West Shelf
requires fundamental shifts in project Gas Project which cost the partners A$12 billion -
management processes. Enhanced project is a strategic conduit linking an uncertain
management processes are necessary: resource to uncertain resource to uncertain
Most companies recognise three broad phases in markets. The market for LNG in Asia is uncertain
a project's life prior to construction. An initial because economic growth rates are
business concept phase is followed by a period unpredictable; nations adjust their preferred mix
during which the project scope is tightly defined. of imported fuels from time to time; and a pan-
Once the scope is finalised, detailed engineering Asian network of gas pipelines remains a
is carried out. The Clean Sheet Capital Redesign possibility. The resource is inherently uncertain
methodology seeks to dramatically improve the because reserves are never really fully known;
effectiveness - measured in terms of shareholder geological anomalies may make extraction more
wealth creation - of these phases. Thus, CSCR is difficult and more expensive than expected; and
a suite of mutually reinforcing management adjacent deposits may be discovered. Getting the
processes that apply at different stages of a assets in between right is no mean feat,
especially when they cost billion of dollars.
The selection of a site for a major new plant about limiting the proliferation of ugly steel
illustrates the challenge of optimising an structures across the country.
internally consistent set of major commercial In most cases, of course, fixed assets will be
decisions. One site may be optimal from a cost of necessary to create a new business. Explains
energy standpoint. Another may offer an Carter, However, there is still considerable
attractive cogeneration opportunity or provide benefit to be derived from challenging the
access to cheaper raw materials. Yet another timings, volume and sequencing of market entry."
may beat them all because of infrastructure Players in the pulp and paper industry have long
support and tax regime that the host government suffered from lemming-like capacity additions as
is willing to provide. Too often, project teams are prices rise in the business cycle. One company
in a hurry to choose a site so that they can get on which out-poerforms the pack of capital
with the engineering. However, early commitment productivity has bucked the trend by making
to a location substantially weakens the project counter cyclical investments in capacity and by
owner's negotiating position with other requiring that assets earn satisfactory returns
stakeholders. Such uncertainties confronted the under the most adverse business circumstances.
project teams considering the timber plant, the A telecommunications project team developing a
mines, the refinery and even the broad-based network discovered that the
telecommunications network. Insufficient senior revenue potential for different nodes varied by a
management attention meant that some of the factor of two while the construction costs varied
most critical trade-off decisions in the life of the by a factor of five. This insight caused a complete
project were being resolved at the wrong level in rethink of the sequence in which the nodes were
the organisation. Conversely, bringing the built across the country.
respective companies' best intellect to bear at Each of these changes to the business case was
this stage yielded superior strategies. worth many tens of millions of dollars to the
project owners. All of them originated from a
The key to major improvements were fundamental shift in mind-shift from 'we build big
• Challenging the need for assets to create a projects' to 'create great business'.
business
• Streamlining business systems for selected Streamline the business system for
customers selected customers
• Extracting full value from flexibility
There is a tendency for project teams to think of
Think business, not assets the plant's output as a commodity that cannot be
differentiated. As a result, too little attention is
A project team almost invariably starts work devoted to customer selection and to tailoring the
thinking about the assets. What are we going to business system. The designers of an Australian
build, and how big will it be. An examination of medium density fibreboard (MDF) plant
the business case underlying project proposals, concluded initially that they should focus on the
however will question whether the assets should local market because MDF exporters were
even be built. Sometimes there is a better getting poor margins. Then they found one
alternative to capital investment as a means of competitor - a Japanese timber and housing
market entry. construction company - doing much better. This
company has recognised the needs of Japanese
The project team at the telecommunications households for compact furniture and fittings. The
company began questioning whether it really business system has been configured
needed to build an entire new mobile phone accordingly, all the way back to forests in New
network. Could it not share at least share part of Zealand. Forestry practices are designed to
a competitor's infrastructure. The apparent deliver the right density of wood. Plant
obstacles were the need to differentiate service configuration is optimised to Japanese building
to customers, competitor's unwillingness to co- sizes. Logistics strategies aim to minimise
operate and regulatory objections. On transport and handling costs, and end-market
investigation, however, none of these obstacles distribution avoids the traditional Japanese
proved insurmountable. Service differentiation did intermediaries. A 30 per cent reduction in
not depend on building a separate network and delivered costs has resulted from this meticulous
one competitor actually welcomed the prospect of attention to detail. In addition, a price premium is
earning extra revenue from renting out spare achieved as a reward for consistency of product
capacity on less used parts of its network. For its quality.
part, the regulator understood that competition Application of these concepts fundamentally
did not depend on each player owning its own enhanced the Australian MDF plant's economics.
network in totality and was much more concerned
Streamline the industry chain "The CSCR approach places a lot of emphasis
on hunting out lazy capital and optimising across
Coal is typically viewed as a pure commodity, interfaces. CSCR also seeks to identify low cost
with little opportunity for tailoring products to solutions to managing risk. Finally, it requires that
individual customers. Received wisdom in the competitiveness be proven, rather than assumed,
company developing a coal deposit in Indonesia before an activity is set up inhouse.
was that no power station would be willing to
enter into a sole supplier relationship. Capacity is a major driver of capital cost. This
Nevertheless, the project team recognised that means capital spend can be reduced by avoiding
this type of relationship was the key to unlocking bottle-necks wherever possible and using
the economic benefits of low ash fuel. The theory capacity to full. It is unrealistic, of course, to
is quite simple. A new power station that uses a imagine that a plant will never suffer from bottle-
single source of low ash coal can avoid a lot of necks; capacity expansions, technological
expensive handling and particulate removal developments and unexpected production
equipment. The lower ash handling and waste challenges are bound to throw the system out of
disposal load also reduces operating costs while balance at some stage during the life of plant.
availability is improved because slagging Nevertheless, due attention to lazy capital during
decreases. the process redesign phase will pay dividends in
three important ways. First, it will minimise the
Extract full value from flexibility amount of capital that is planned lazy. After 10
years on the drawing board, the technical experts
Left to its own devices, a project team is likely to were convinced that the main circuit in the
deal with the uncertainty at each end of the chemicals plant had been optimised. Undaunted,
strategic conduit by building more flexibility into the project team used a dynamic model to
the project design. This added flexibility is likely stimulate operations over several years,
to be expensive and occasionally it misses the incorporating uncertainties such as unplanned
mark. Senior management input on what really maintenance. A wide range of capacity, spring
matters and clever use of information technology surge and maintenance schedule combinations
can often allow more value to be extracted from were investigated. Many size adjustments
an asset. resulted - most of them downwards - and a
number of unnecessary surge items were
A timber project team, realised that profitability eliminated. The base case design was improved
would be enhanced if the traditional emphasis on by $ 40 million (Australian) without any operating
throughput was shifted to maximising the return risk.
from each processed log. Accordingly, they
developed a simple optimisation tool that Anticipating future expansions is a second major
combines information from three sources - log source of lazy capital. In one, situation, the
availability by grade, spot prices for final design team had to work out how to cope with a
products, and customer order status. This allows doubling of volume through the pipeline linking
instant decisions on optimal log and cutting the plant to its shipping port, three of four years
pattern selection. It also provides critical input to into the project's life. The conventional response
felling and pruning decisions in the forest. Some would be to increase the diameter of the pipe.
minor capital savings were made in equipment However, the CSCR philosophy resents waste
selection and plant layout. More importantly, and team members were concerned about the
though, all key aspects of managing the business pipeline working at half capacity in its first few
can now be adapted constantly to changing years. The sequential introduction of viscosity
market conditions allowing higher profits to be modifiers and higher-pressure pumps minimised
generated. lazy capital and improved project NPV by 10
million dollars.
HUNTING OUT LAZY CAPITAL Fibre trunk routes in a typical broadband network
carry telephone traffic and video signals from the
During the second phase of CSCR, process telephone switch and the cable head-end out to
redesign, the challenge is to match the project nodes for local distribution. To provide basic
scope tightly with the optimised business case. services such as multi-channel TV and standard
The changes to the business case almost telephony these trunk route require only limited
invariably require a serious rethink of the bandwidth (500 Mhz analogue for TV and 0.5 -
proposed flow sheet. This starts with a review of 1.0 Gbit/sec) for telephony. However, in a future
each of the major component pieces and world of true video-on-demand, 500 times more
progresses to the task of optimising the entire capacity would be needed. For this reason,
system. In an interview with The Strategist, network designers like to include a spare section
McKinsey principal Jeremy Carter, one of the of plastic duct in each trunk route to allow for
initiators of the CSCR methodology, explained, future capacity requirements. This is costly,
especially when the extra space required to costs, lower plant utilisation and a serious
house more than a single duct forces reduction in control over the quality of the
construction beyond the pavement and into the product. Today, the mine operates with a larger
street. number of smaller trucks than originally
envisaged. The project's owners are better off to
More often than not the capacity precaution is the tune of about 50 million dollars. The timber
completely unnecessary, In a dedicated 10 plant team realised it should hold inventory in
Mbit/sec path between the head-end and every partly processed form as 'master batches' in the
home passed by the network. This is enough centre of the plant rather than as a finished
fibre to meet expected future needs. For those product. As a result, predicted inventory stocks
who are concerned about future needs that have were slashed by 60 per cent, a six million dollar
not been thought of, developments in warehouse was eliminated and customer service
multiplexing telephony traffic (wave division is improved with much faster lead times.
multiplexing and synchronous digital hierarchy)
promise to make efficient use of basic fibre MANAGE RATHER THAN SUBMIT TO
capacity. The latest research on pure optical RISK
amplifier suggest that the ultimate capacity of a
single fibre could be 1,000 times greater than the As project firms upend the team gets a clearer
1 Gbit/sec available today. picture of the assets that will be put on the
Project start-up, a notoriously difficult period of ground, the tension builds up to `sign off on the
some new operations, is a third major source of scope'. Unfortunately, some of the uncertainties
'lazy' capital. Past experience of problems at this persist. All too often, the way that a team deals
stage often leads companies to allow for them in with these residual risks is to throw money at
both their schedule and economic projections, so them. Alternatively, plants may be designed to
that a lengthy startup period becomes a self- meet a single set of projections about demand
fulfilling prophecy. In semiconductors or zinc and product specification. This leads to a fixed
mining, to cite two examples, plants can take cost components that cannot be tailored to
several years to reach full capacity - which is variations in demand, and highly specialised
plenty of time to have a major impact on the process and equipment which are difficult to
project's economics. The problem is that the best adapt if customers' need change. Both of these
practice is poorly documented, which means approaches to risk are sub-optimal. Getting a
operators of each new plant have to reinvent the better answer depends on improving the dialogue
wheel. Yet with the benefit of hindsight, many between management and project engineers.
start-up problems anew quite avoidable. Poor This generally requires two changes in
circuit designs can be identified with system management's approach as illustrated by one
dynamics models of material flow; construction mining project team. First, engage the the project
contract specifications can prevent the use of team in discussing options rather than
inferior components; specialist start-up managers recommendations. Second, concentrate the
and a few additional employees can overcome team's effort on reducing the risks associated
specialist staff and skill shortages during a start- with low-cost options.
up up period. Even a modest improvement to the
proposed learning curve was worth $ 60 million to STEP 1
the owners of a metallic concentrate project.
Learning while a plant is up and running is The initial plant design submitted to management
unnecessarily expensive ! had a conventional flow sheet with three distinct
crushing stages. This was characterised by the
OPTIMISE ACROSS INTERFACES project team as `low cost low risk'.... and
management was left wondering whether there
Taking a total system perspective, a mining were no better alternatives. There were, but
project team changed its initial decision to management needed to ask to disuss the other
purchase, a mining project team changed its options that had been considered and discarded.
initial decision to purchase 240 tonne haulage In particular, advances in crusher technology and
trucks. The original recommendations recognised the relatively friable ore in the deposit indicated
the superior economics of the largest trucks in that two crushers should suffice.
the world in transporting ore from the pit to the
processing plant. However, the very large haul STEP 2
loads required the plant being designed as a
batch rather than continuous process. The knock On paper, the two crusher option was clearly
on effects were both insidious and severe. The more attractive for shareholders. Yet doubts
most obvious interface problem was a 15 million remained as to whether product quality would be
dollar intermediate stockpile. Beyond this, acceptable to customers. Management broke the
however, were higher operating and maintenance
deadlock by encouraging the project team to design the plant's layout to allow the third
crusher to be retro-fitted if it were needed The and process redesign phases will make a lot of
cost to the project of buying the option was half a them redundant. It is only in this third and final
million dollars. The original design, complete with stage of CSCR that the project team is finally
three crushers, would have cost an extra $10 allowed to turn its attention to the nitty-gritty. The
million in front capital. By the way, the mine is engineering redesign process challenges the
now operating and the two crushers do the job project team to submit every component to a
just fine. rigorous fit-for-purpose test. It also seeks to
establish a set of fresh activity-based bench
OUTSOURCE NON-CORE ACTIVITIES marks so that designs keep abreast of best
practice.
The conventional approach to big projects,
especially in remote areas, is for the project Design fit-for-purpose components
owner to build, own and operate the whole box
and dice. Though out sourcing has become It is very easy to be glib about the concept of fit-
common practice in some industries, the owners for purpose. Most people assume that their
of heavy plant underestimate its value. Mining designs already match this description.
companies, for example, have long been Unfortunately, their confidence is often misplaced
accustomed to owning, driving and maintaining either because of a tendency to allow a bit extra
haulage trucks as an integral part of their into the design to 'just to be sure', or because this
business. The weight of evidence, however, design is based on ill founded assumptions or
suggests that specialist contractors can be unquestioning of historical practice. Why, for
leaner, hungrier and more cost effective in example, build a railway line that can withstand a
carrying out this set of activities. Since the ore is once-in- 100 year flood when the plant's life is
moved but not transformed during the process, only 15 years and a rapid response capability can
the mining company losses none of its distinctive be counted on. Why waste time incorporating
knowledge provided it retains control of day-to- extra functions in a control dependent that
day mine planning. At one new mine, the NPV operators have no intention using? Why build
benefit of outsourcing the hauling function was walkways on both sides of a conveyor belt if a
estimated at $ 20 million. In our chemicals single walk way is safe and functional?
example, the initial capital estimate included $ 30
million for a lime calcination facility. Sourcing the Benchmark the way things get done
lime from a producer that could achieve
economies of scale represented an attractive The march of time can play tricks on the most
deal for both parties. The chemicals company experienced and capable of project designers.
was able to deter expenditure and improve NPV Major projects are relatively infrequent events so
by $ 10 million. it is not uncommon for people remember a
Systematically examining outsourcing options decision but forget the detailed assumptions
invariably results in a project that is more which under-pinned it. The initial design that a
competitive in the long run - whether or not a thrown together quickly in a pre-feasibility study
specific function wins up in-house. More is far more likely to reflect earlier assets than
importantly, perhaps, outsourcing frees up capital earlier thought processes. Since the technical
and management attention to focus on what the and managerial disciplines advance rapidly all
company is good at and can make money from. the time, relying on what you did last time rather
One major energy company systematically sells than why you did is fraught with danger.
down its equity in established power stations so
that it can invest the capital in the early stages of NOT A PANACEA
new projects.
CSCR is not a quick fix for a project that is
ENGINEERING REDESIGN; TIGHTEN THE struggling to get the board's approval. It is a
SCREWS ON UNNECESSARY COSTS methodology that allows management to begin a
revolution in the way organisations think about
The third phase of CSCR, engineering redesign, their capital spending. This revolution requires
is a highly structured commercial, as well as project teams to embrace radically different
technical review of every aspect of the project. norms of performance, which in turn requires
Here, the objective is to relentlessly tighten the intense attention and consistent support from
screws on the unnecessary costs that all too senior management. Throughout, the team's
often creep in during the detailed engineering attention has to be focussed on making money
work, when the team is under pressure to make for shareholders, and tight management systems
sure the plant works and the project stays on will be required to capture, manage and
schedule. Detailed drawings should be avoided implement ideas for improvement.
up until this point because work in the business
National Productivity Council 51
CSCR
Embarking on a CSCR effort is therefore not a capital project to life is a people intensive
proposition for the faint-hearted. Bringing a big
process. Accepting the CSCR challenge is, in intensive industries, CSCR could be the single
effect, to embrace a major change program. Our most important lever for increasing shareholder
case studies suggest, however, that the prize will value.
be well worth the effort. For many firms in capital
ZOPP OBJECTIVES
ZOPP APPLICATION
FEATURES OF ZOPP
1. Gradual procedure through a sequence of successive planning steps
2. Permanent visualization and documentation of all planning steps
3 Team approach
1. Steps of Analysis
* Participation Analysis
* Problem Analysis
* Objectives Analysis
* Alternatives Analysis
* Objectives/Activities
* Important Assumptions
* Objectively Verifiable Indicators
* Means of Verification
PARTICIPATION ANALYSIS
• Gives an overview of all persons, groups, organisations and institutions connected with the
project in any way
• Incorporates the interests and expectations of persons and groups significant to the project
HOW TO DO IT
a) Write down all persons and groups connected with or influenced by the project
b) Categorize them (e.g. beneficiaries, target-groups, actors etc.)
c) Characterize and analyse
d) Identify consequences for the project work (e.g. reactions of project)
Potentials:
PROBLEM ANALYSIS
Is a set of techniques to
- analyse the existing situation surrounding a given problem condition
- identify the major problems in this context
- define the core problem of a situation
- visualize the cause-effect relationships in a diagram (problem tree)
Step 1 Identify major problems existing within the stated problem situation (brain-storming)
Step 2 Write up short statement of the core problem
Step 3 Write up the cause of the core problem
Step 4 Write up the effects caused by the core problem
Step 5 Form a diagram showing the cause and effect relationship in the form of a problem tree
Step 6 Review diagram as a whole and verify its validity and completeness.
Note:
1. Word problems as negative conditions
2. One problem per card
3. Identify existing problems, not possible, imagined or future ones
4. A problem is not the absence of a solution, but an existing negative state.
5. The position on the problem tree does not indicate the importance of a problem.
OBJECTIVES ANALYSIS
Is a set of techniques to:
- describe the future situation that will be achieved by solving the problems
- identify potential alternatives for the project.
Step 1 Restate all negative conditions of the problem tree into positive conditions that are:
- desirable and realistically achievable
Step 2 Examine the "means-ends" relationships thus derived to assure validity and
completeness of your diagram
Step 3 If necessary:
- revise statements
- add new objectives if these appear to be relevant and necessary to achieve the stated
objective at the next higher level
- delete objectives which do not seem to be expedient or necessary.
ALTERNATIVES ANALYSIS
Is a set of techniques to
- identify alternative solutions which could be project strategies
- select one or more potential project strategy
- decide upon one strategy to be adopted by the project
Project
Purpose
Results/
Outputs
Activities
ASSUMPTIONS
Definition:
Conditions that must exist if the project is to succeed but which are not under the direct control of
the project:
ASSESSMENT OF ASSUMPTIONS
No
Don't include this one
Yes
3rd Question: "Can the project strategy be (re-)designed to make this assumption
superfluous?"
No Killer assumption!
Warn decision makers!
Stop!
Yes
Redesign project!
Plan activities to influence assumptions or make them superfluous
OVI's - Steps
Objective: Agricultural production increased
COMBINE: 10,000 small holders in Umbia province (owning 3 acres or less) increase their rice
yield by 50 % between October 1984 and October 1985, maintaining the same quality of harvest
as 1983 crops.
National Productivity Council 58
Theory of Constraints
Tell Us:
• Where we get the evidence that the objectives have been met
• Where we can find the data necessary to verify the indicator
• Some important questions:
• Are the MOVs available from normal sources? (statistics, observation, records)
• How reliable are the sources?
• Is special data-gathering is required?
• If so, what will it cost?
• Has a new source to be created
If we cannot find an MOV, the indicator has to be changed!
THEORY OF CONSTRAINTS
Q: How does Goldratt define a Jonah is someone who has completed the
"throughput"? Goldratt Institute's two-week Jonah course,
A: In "The Goal", Jonah defines Throughput during which the Jonah learns how to apply
as the rate at which a system generates the five thinking process tools and the
money through sales. As Jonah points out categories of legitimate reservations. A
here, it is critical that we distinguish sales Jonah also applies those tools with at least
from production: While manufacturing some regularity.
operations traditionally measured production
at each stage of production, the only Q: What is "The Goal"?
Throughput that counts is that which comes A: In a concrete sense, it is the title of Dr.
off the end of the line to be sold. Why? -- Goldratt's first book on the Theory of
this serves the goal (see above). Constraints. In that book, the narrator -- Alex
Mathematically, we express Throughput as Rogo -- defines the goal of his
Sales minus the raw material inventory manufacturing company as making money.
content of the sales. In generic terms, Working with an accountant, he settles on
Throughput is a quantitative measure of the three measures for this goal: net profit, ROI,
entity that the organisation seeks to and cash flow. More recently, the goal for a
maximise. Another way of defining profit-making business has been defined as
Throughput as, "The rate at which the making more money both now and in the
organisation creates added value to its future. Also, we have recognised that cash
owners".However, added value is flow is not a measure of the goal but is a
sometimes limited by the global interests of necessary condition. This is something that
the owners. This is the case for any you want in certain limits, not too low, not
department within an organisation that does too high, like blood pressure -- a measure of
not contain any global constraint. One may the goal you want always to increase if you
still attempt to produce better quality and can. Achieving as much as possible from an
faster response - but even here the added entity while minimising the cost to produce
value is restricted by the overall quality and the throughput.
responsiveness of the global system. What
is left is to try and do the same with less Q: How does the Theory of Constraints
expenses. For reasons outlined below, define "Inventory" and "Operating
"Throughput" is one of the most critical Expense"?
elements of TOC. A: Inventory is defined as all funds that the
system has invested in purchasing things
Q: Who or what is a Jonah? that it intends to sell. In other words,
A: Jonah is the name of the physicist that Inventory is the current value of all the
advises Alex Rogo, the narrator of Dr. things that the organisation owns and uses
Goldratt's book, "The Goal", as he attempts to create its product or to deliver its service
to identify and solve the problems plaguing to the market.
his manufacturing plant. In a general sense,
Operating expense is defined as all funds
the system spends in order to turn inventory
into throughput.
National Productivity Council 61
Theory of Constraints
3. SUBORDINATE everything else to the clouds, are often indistinct (i.e., people are
above decisions. This is the means by which unable to articulate the real reasons for the
the rest of the organisation is synchronised conflict). The "evaporating" part refers to the
with the capabilities of the constraint and the tool's ability to dissipate the confusion
decisions made regarding how to best utilise surrounding the conflict, clearly identify the
it. For instance, if the constraint is a machine key elements, and provide a means for
on the line, you might establish buffers to resolving the conflict.
protect its ability to produce and base the
release of materials into the plant on the Q: How does the Evaporating Cloud
schedule for that constraint and the amount methodology work?
of buffer time that has been established. A: The method makes more sense when it
This is where most of our common is diagrammed visually through example, but
measures in the plant must be changed. By Mr. Dettmer summarises it as follows:
default, every single resource that is NOT Identify FIVE elements of every conflict
the constraint will do severe damage to the (right-to-left): The 2 Prerequisites that
organisation if they strive for 100% directly conflict with one another, the
utilisation. However, that is exactly how they Requirement each Prerequisite is trying to
are measured! satisfy, and the Objective each Requirement
4. ELEVATE the system's constraint. In is necessary to achieve. Diagram looks like
previous steps, you ensure that the "home plate" lying on its side, pointing left.
organisation is optimised via nothing more Unspoken Assumptions are identified
than policy changes. In this step, you are relating to the arrows connecting each
actually altering the constraint. For instance, element of the EC. Solutions are proposed
when the constraint has been a machine in that replace invalid assumptions.
the plant, this is the step in which you will
add physical capacity. You may do this Q: What is a Reality Tree?
through, - reducing set-up and process A: A Reality Tree is a cause-and-effect tree
times - investing in other process (current or future), construction of which is
improvements - overtime - hiring more staff - governed by rigorous rules of logic (eight of
buying another machine or any other action them). It starts with "roots" in a cause of
that removes the constraint. some kind, develops upward through a
5. Don't let INERTIA become the system's "trunk" and "branches" of several layers of
constraint. Once you have "broken" a
intermediate effects, to the "leaves", which
constraint, go back to Step One! This is a
reminder that all of the policies you have are the ultimate effects. In a Current Reality
established in the organisation based on Tree, the "leaves" are undesirable effects,
one con- straint will likely not apply once the and the "roots" are the core problem or root
constraint lies elsewhere!
causes of the Undesirable Effects. Root
Causes constitute " what needs changing".
Q: What is an Evaporating Cloud?
A Future Reality Tree starts with a pro-
A: This is a term used to describe a
posed solution to a core problem at the
methodology developed by Goldratt to
"root", builds upward through intermediate
resolve conflicts in a "win-win" manner.
effects (the "trunk" and "branches") to
Name relates to the idea that conflicts, like
Desired Effects (the "leaves").
National Productivity Council 63
Theory of Constraints
cost for producing a little more product than are we going to do then, hire more people?
our customers are buying right now?" "I told Won't that increase our operating
you what our product cost was. Are you expenses?" he asked. "That's the whole
deaf?" interrupted the CFO. The marketing point, you stupid *** !" nearly responded the
director tried hard to not react to the CFO's marketing director before catching himself. It
verbal assault, but his patience was wearing took enormous effort to maintain his control
very thin. "That's not the real cost of as he spoke. "The market is our constraint
producing the extra products that we're right now," he said in an obviously controlled
giving away as free samples," responded tone. "We want to give away free samples to
the marketing director. "If we don't produce potential new customers, so that our orders
the samples, then our operating expenses will pick up. When they do, we'll stop making
are x dollars per month. If we do produce the free samples, and we'll make only the
the samples, then our operating expenses products that we sell for a profit," said the
are still x dollars per month. The only marketing director. "Bill, now you calm
additional cost that we incur by producing down, please!" pleaded Henry, who had
the samples is the cost of the additional raw heard the strain in the marketing director's
material that we use in the samples. That's voice. "I think I understand," he continued.
all," he declared. "What's the raw material "So long as we're not interfering with
content of our product?" he asked of the customer orders, we can use any excess
CFO. The CFO paused briefly, trying to capacity that we have to produce samples
recall the information. "Most of our product for the sales people to give away. I can see
cost is labour," he responded. "We don't why this won't increase our operating
have much raw material content in the expenses," added Henry. "But what
product. It's about$1.50," said the CFO. happens if our current customers find out
"Then we're giving away $1.50 every time that we're giving away product? What's to
that we give away a free sample. We're not prevent them from asking for free samples
giving away $12.50, which is what you said too?" worried Henry. "That could happen,"
earlier," reminded the marketing director. admitted the marketing director. "If our sales
"Bill, I'm a little confused," said Henry as he people gave samples away to everybody, or
requested clarity. "We have a high labour at random, then some of our current
content in our product. Yet you're telling me customers might ask for them regularly,
that we're giving away only the raw material forcing us effectively to offer discounts. But
cost with every sample. Aren't we paying for I've issued clear instructions to avoid this.
labour?" "Of course we are," agreed the The samples are to be given only to
marketing director. "That's precisely the prospective new customers. I've also
point. We're paying for some labour and for required that we track who gets the
some resources that are not producing samples. That way we can keep the free
product for our current customers. That samples program from corrupting our
labour and those resources and the current markets. The idea is to develop new
operating expense that they represent are markets, not to offer discounts within our
with us no matter what. We're paying for current markets, "explained the marketing
them if they produce the samples, and we're director. "Good!" exclaimed Henry. "I like it.
paying for them if they don't produce the Let me know how it works," he said to his
samples. That's why we're not driving costs director. "Now let's break for lunch while the
through the roof. That's also why we're not cafeteria is still open," he suggested. As the
giving away the equivalent of the fully three of them left the executive wing, Henry
allocated product cost with every sample," turned to the CFO. "So tell me, John," he
explained the marketing director. "The said. "Why haven't we heard about this
incremental cost of making the samples is Goldridge guy before?" "Goldratt!"
only the cost of the additional raw material exclaimed the marketing director. "His name
that we use," he continued. "Well, what if our is Eli Goldratt. He's really a nice guy. You
orders pick up, and we have people making should meet him.
your free samples?" asked the CFO. "What