Analysis & Rates
Analysis & Rates
The capacity of doing work by an artisan or skilled labour in the form of quantity of work
task work or out turn of the labour.
The out-turn of work per artisan varies to some extent according to the nature, size, height,
In bigger cities where specialized and experienced labour is available the out-turn is
country sides. In well organized work less labour is required.
The following may be taken as the approximate quantity of work or out turn or task for an average artisan
26. Flag store floor laying with lime or cement mortar 10.00sqm
excluding LC
27. Brick on edge in floor lime or cement mortar excluding 7.00sqm
LC
28. Brick bat floor as in above 8.00sqm
Mix 3.00cum
Items 46,47 and 48 are based on the committee report on rates and cost government of India.
Extracts from the report on productivity projects in building industries issued by National
given below:-
laying cement concrete – 2 beldars, 3 mazdoors, ¾ bhisti and ¼ mason, can do 2.83 cum (100 cuft) per day.
c) R C C work:-
1) Laying reinforced concrete – 3 beldars, 3 mazdoors, 1½ Bhisti and ½ mason can do 2.83 cum (100cuft) per day.
2) Centering and shuttering for flat surfaces – 4 beldars and 4 carpenters (II class) can do 9.6sqm(96sqft) per day.
3)Reinforcement work for R C C –1 blacksmith or fitter and 1 beldar can bend and place in position 1 quintal (2 cwt) of ste
Random rubble masonry with blue stone in foundations-3 masons, 3 beldars, 2 mazdoors and 1/4bhisti
per day
First class brick work in 1:4 cement mortar in superstructure partition walls, junctions of roof, parapet
2½masons,4½ mazdoors and 1/2 bhisti can do 2.83 cum (100cuft) per day.
F) Wood work :-
1) For the frames of doors and windows –2 carpenters and 1 beldar can work 0.18 cum (6.40cuft)
7.5cm x 10m of 1.2m x 2.1m (3’x4’of 3’x11’x7’)size per day.
2) For paneled, glazed, etc, shutters-15 carpenters and 4 beldars can make and fix 4 shutters 40 mm
½ thick of size of 6’-9x 3’-9’) per day. Quantity of wood per shutter – 0.075 cum, ie2.66 cuft.
g) Iron work :-
1) Fixing 40mm x 3mm=38cm(1 ½ “ x ½ ‘x 15”0 flat iron holdfasts-1 blacksmith (II class), I mason
per day.
2) Fixing 16mm dia. 5/3” dia) M S rods –1 blacksmith (II class), 2 carpenters (II class) and 3 mazdoors can fix 16.5m (54
h) Flooring: -
4cm thick (1 1/2 “)thick cement concrete flooring of 40sqm (400sqft) require 5 masons, 4 beldars, 3
mixing laying and finishing.
I) Finishing :-
1) Plastering with any mortar 12mm (5”) thick – 3 masons, 3 mazdoors and 1 bhisti can plaster 40sqm (400a ft) per day.
2)White washing or colour washing (3 coats) – 1 white washer and 1 mazdoor can do 60sqm (600sqft) per day.
3) Painting two coats such as chocolate, red, grey, etc on wood are steel –3
Painters and 2 mazdoors can paint 10sqm (100sqft) per day.
Quantity or Number
Sl# Particulars of materials On Rough Road
1. Brick 19 cm x 9cm x 9cm 275nos
8. Cement 15bags
Note; A bullock ……..carry about one tonne load. The average speed for a bullock cart may be taken
and ¾ hour may be allowed for loading and unloading. Taking 8 hours working per day, the
calculated.