0% found this document useful (0 votes)
75 views1 page

Mock Up Sample Request For Backer Rod

The document is a mock-up/sample request form from a contractor called Shapoorji Pallonji Mideast for a sample board of a Technal CW profile facade component for the Exit.10 Development project. It details the request date and references, and provides spaces for approval signatures from representatives of the contractor, WME consulting engineers, EllisDon, and SEVEN. The purpose is to get approval on the sample board before full fabrication and installation of the facade component.

Uploaded by

iamsundark
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views1 page

Mock Up Sample Request For Backer Rod

The document is a mock-up/sample request form from a contractor called Shapoorji Pallonji Mideast for a sample board of a Technal CW profile facade component for the Exit.10 Development project. It details the request date and references, and provides spaces for approval signatures from representatives of the contractor, WME consulting engineers, EllisDon, and SEVEN. The purpose is to get approval on the sample board before full fabrication and installation of the facade component.

Uploaded by

iamsundark
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT NAME: EXIT.

10 DEVELOPMENT
MOCK-UP / SAMPLE REQUEST
CONTRACTOR :Shapoorji Pallonji Mideast DATE
:
19-Nov-23

AREA / LOCATION : See below M/S Request Ref.


:
Document Reference No. 1HMRA10-RUHH-08-SPM-FC-MAS-00009-01 Discipline
:
Façade

Description of Mock-UP / Sample to be Inspected Date & Time


REQUEST Date : 18-Nov-23
REQUEST Time :

SAMPLE BOARD FOR TECHNAL CW PROFILE

Contractor Project Manager : Received By WME:

Signature: Signature / Date :

WME Comments :

Approved Approved As Noted Revise and Resubmit Rejected


WME Engineer Name : Signature : Date :

Project Director Signature : Date :

EllisDon Comments :

Approved Approved As Noted Revise and Resubmit Rejected


EllisDON Engineer Name : Signature : Date :

SEVEN Comments :

Approved Approved As Noted Revise and Resubmit Rejected


SEVEN Engineer Name : Signature : Date :

Distribution: