Scheduling Methods (Lec 4)
Scheduling Methods (Lec 4)
[HE 304]
Lecture 4
Scheduling Methods
There are many types of time scheduling, the most commonly used methods
are:
Using these values, CPM calculates the longest path of planned activities to
logical end points or to the end of the project, and the earliest and latest that
each activity can start and finish without making the project longer. This
process determines which activities are "critical" (i.e., on the longest path) and
which have "total float" (i.e., can be delayed without making the project longer).
In project management, a critical path is the sequence of project network
activities which add up to the longest overall duration, regardless if that longest
duration has float or not. This determines the shortest time possible to complete
the project. There can be 'total float' (unused time) within the critical path. In
other words, individual tasks on the critical path prior to the constraint might be
able to be delayed without elongating the critical path; this is the 'total float' of
that task. However, the time added to the project duration by the constraint
is actually critical path drag, the amount by which the project's duration is
extended by each critical path activity and constraint.
For Example; CPM chart for a project with five milestones (10 through 50) and
six activities (A through F). The project has two critical paths: activities B and
C, or A, D, and F – giving a minimum project time of 7 months with fast
tracking. Activity E is sub-critical, and has a float of 1 month.
H.W