MANPOWER
MANPOWER
3.10 Reinforcing Steel Bar 1,580,502.00 kgs 25 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 25 25.00
#REF!
3.20 Formworks 31,158.00 m² 25 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 30 30.00
#REF!
3.30 Concrete 6,528.00 m³ 10 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00
4.0 Masonry Works
4.10 Chb Laying 14,769.00 m² 27 27.00 27 27.00 27 27.00 27 27.00 27 27.00 27 27.00 27 27.00
4.20 Plastering 40,068.00 m² 70 70.00 70 70.00 70 70.00 70 70.00 70 70.00 70 70.00
4.30 Sealant and Backer Rod 4,486.00 lm
#REF! 5 5.00 5 5.00 5 5.00 5 5.00 5 5.00
4.40 Zocalo for T& B's 265.00 lm
#REF! 2 2.00 2 2.00 2 2.00 2 2.00
5.0 Metal Works #REF!
5.10 Fire Exit, Balcony and Loft Stair Railings 1,665.00 lm 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00
#REF!
5.20 Bridgeway 18.00 sets
#REF! 8 8.00 8 8.00 8 8.00 8 8.00 8 8.00
5.30 Perimeter Railing at 1st Floor 80.00 lm 3 3.00
5.40 Main Entrance Stair Railing at Lower to Upper Grnd. 40.00 lm 3 3.00
5.50 Trench Grating Cover 79.00 lm 3 3.00
5.60 Ship Ladder and Run Ladder 1.00 lot
#REF! 3 3.00
5.70 Elevator Shaft Embed 117.00 pcs 2 2.00 2 2.00 2 2.00
#REF!
5.80 Manhole Cover 2.00 sets 2 2.00 2 2.00 2 2.00
5.90 Ladder Rungs 18.00 pcs 2 2.00 2 2.00 2 2.00
6.0 Roof Framing Works 1.00 lot 10 10.00 20 20.00 20 20.00 20 20.00
LABOR DAYS 40 42 119 125 119 117 109 136 209 232 244 260 232 182
MANPOWER SCHEDULE
OWNER: PROJECT MANAGER: ARCHITECT: PROJECT: CONTRACTOR: Name: LI MING Sheet No.:
AMALGAMATED PROJECT DANILO C. IBAY ARCHITECTS Designation: PROJECT MANAGER
华友建设发展菲律宾有限公司 MP-1.00
TAGAYTAY GRASSLAND, INC. MANAGEMENT SERVICES. INC THE PEAK AT CANYON HUAYOU CONSTRUCTION DEVELOPMENT PHILIPPINES CORPORATION
Signature:
U/L2 BLK2, TAGAYTAY CITY, CAVITE Stamp: