MANPOWER

This document appears to be a progress report for a construction project showing work completed each month from March 2010 to April 2011. It includes details of various project components (general conditions, earthworks, structural works, masonry works, metal works etc) showing the quantity of work and rate of progress over the project period. Key milestones included project commencement in March 2010, topping off in April 2011 and target completion in April 2011. The report provides a breakdown of work quantities, units and progress over 24 months for various elements of the main contract works.

Uploaded by

jtuquero.chcc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views

MANPOWER

This document appears to be a progress report for a construction project showing work completed each month from March 2010 to April 2011. It includes details of various project components (general conditions, earthworks, structural works, masonry works, metal works etc) showing the quantity of work and rate of progress over the project period. Key milestones included project commencement in March 2010, topping off in April 2011 and target completion in April 2011. The report provides a breakdown of work quantities, units and progress over 24 months for various elements of the main contract works.

Uploaded by

jtuquero.chcc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Item 2010 2011

Description Quantity Unit Remarks


No. Mar Apr May June July Aug Sept Oct Nov Dec Jan Feb Mar Apr
A. MAIN CONTRACT WORKS
1.0 General Conditions & Preliminaries
1.10 Mobilization 1.00 lot 5 5.00 5 5.00
1.20 Project Supervision 1.00 lot 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00 17 17.00
1.30 Temporary Facilities 1.00 lot - 10 10.00 10 10.00
1.40 Miscellaneous Works 1.00 lot 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00 2 2.00
1.50 Demobilization 1.00 lot 5
5.00
2.0 Earthworks -
2.10 Clearing and Grubbing 2,123.00 m²
#REF! 2 2.00

Topping-off (07 April 2011)


2.20 Excavation and Disposal 7,110.00 m³ 4 4.00 4 4.00 4 4.00
#REF!
2.30 Gravel Bedding 147.00 m³ 2 2.00 2 2.00 2 2.00
#REF!
2.40 Backfilling and Compaction 1,969.00 m³
#REF! 8 8.00 8 8.00 8 8
2.50 Soil Poisoning 2,238.00 m²
#REF! 2 2.00 2 2.00 2 2.00
2.60 Vapor Barrier 1,778.00 m² 2 2.00 2 2
2.70 Water Stop 286.00 lm 2 2.00 2 2.00
3.0 Structural Works

Target Completion (30 April 2011)


Project Commencement (01 March 2010)

3.10 Reinforcing Steel Bar 1,580,502.00 kgs 25 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 25 25.00
#REF!
3.20 Formworks 31,158.00 m² 25 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 40 40.00 30 30.00
#REF!
3.30 Concrete 6,528.00 m³ 10 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00
4.0 Masonry Works
4.10 Chb Laying 14,769.00 m² 27 27.00 27 27.00 27 27.00 27 27.00 27 27.00 27 27.00 27 27.00
4.20 Plastering 40,068.00 m² 70 70.00 70 70.00 70 70.00 70 70.00 70 70.00 70 70.00
4.30 Sealant and Backer Rod 4,486.00 lm
#REF! 5 5.00 5 5.00 5 5.00 5 5.00 5 5.00
4.40 Zocalo for T& B's 265.00 lm
#REF! 2 2.00 2 2.00 2 2.00 2 2.00
5.0 Metal Works #REF!
5.10 Fire Exit, Balcony and Loft Stair Railings 1,665.00 lm 10 10.00 10 10.00 10 10.00 10 10.00 10 10.00
#REF!
5.20 Bridgeway 18.00 sets
#REF! 8 8.00 8 8.00 8 8.00 8 8.00 8 8.00
5.30 Perimeter Railing at 1st Floor 80.00 lm 3 3.00
5.40 Main Entrance Stair Railing at Lower to Upper Grnd. 40.00 lm 3 3.00
5.50 Trench Grating Cover 79.00 lm 3 3.00
5.60 Ship Ladder and Run Ladder 1.00 lot
#REF! 3 3.00
5.70 Elevator Shaft Embed 117.00 pcs 2 2.00 2 2.00 2 2.00
#REF!
5.80 Manhole Cover 2.00 sets 2 2.00 2 2.00 2 2.00
5.90 Ladder Rungs 18.00 pcs 2 2.00 2 2.00 2 2.00
6.0 Roof Framing Works 1.00 lot 10 10.00 20 20.00 20 20.00 20 20.00
LABOR DAYS 40 42 119 125 119 117 109 136 209 232 244 260 232 182

MANPOWER SCHEDULE
OWNER: PROJECT MANAGER: ARCHITECT: PROJECT: CONTRACTOR: Name: LI MING Sheet No.:
AMALGAMATED PROJECT DANILO C. IBAY ARCHITECTS Designation: PROJECT MANAGER
华友建设发展菲律宾有限公司 MP-1.00
TAGAYTAY GRASSLAND, INC. MANAGEMENT SERVICES. INC THE PEAK AT CANYON HUAYOU CONSTRUCTION DEVELOPMENT PHILIPPINES CORPORATION
Signature:
U/L2 BLK2, TAGAYTAY CITY, CAVITE Stamp: